Location
Spain / Europe
Project record
Valencia's North Terminal has moved from design publication and open procurement into a EUR 489.18 million marine-civil contract. About two kilometres of main quay, ancillary quays, reclamation, basin deepening, and demolition must be accepted before TIL's separate automated-terminal systems can enter commissioning.
Spain / Europe
Port infrastructure
Main quay works under construction after the Q4 2024 start / Confirmed
16 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The Port Authority's reformulated 2024 accounts confirm that the awarded works began executing in the final quarter of 2024 and describe the pace as adequate. Physical construction had started, while quay, dredging, reclamation, demolition, civil handover, terminal systems and operations remained incomplete.
Read controlling sourceThe concession assigns TIL construction and operation of the future terminal and records EUR 1.098237 billion of proposed private investment outside Port Authority works. The private-investment figure is separate from the EUR 489.18 million marine-civil contract and provides no evidence of installed automation or operating readiness.
Read controlling sourceThe Board selected the ACCIONA-Jan De Nul-Grupo Bertolin joint venture. The Port Authority's annual accounts later state EUR 489.18 million excluding VAT; the award fixes contractor and value, while mobilisation, production, accepted depth and handover remain open.
Read controlling sourceFour submissions moved the container-quay procurement into evaluation. Bid receipt did not establish a selected contractor, contract value, concession award, or physical start.
Read controlling sourceThe Port Authority approved an open procedure and EUR 545.78 million excluding VAT of expenditure. This procurement ceiling is distinct from the later EUR 489.18 million award and from TIL's private concession investment.
Read controlling sourceThe then non-final design carried an estimated EUR 448 million including VAT and 58-month period, plus technical prescriptions for caissons, consolidation, dredged-material characterization, and operability. Those planning figures were superseded by the later procurement and award evidence.
Read controlling sourceDelivery watch
A dated owner or contractor progress record for quay-caisson production, dredging and material placement, reclamation settlement, demolition, or civil handover
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerValenciaport published a non-final construction project in April 2022 with an estimated EUR 448 million including VAT and a 58-month design period; those figures are planning history, not the later contract. The Port Authority's signed 2024 annual accounts say its Board initiated the open procedure on 22 December 2023 with EUR 545.78 million excluding VAT approved expenditure, received four bids in April 2024, awarded the main works on 1 July 2024 for EUR 489.18 million excluding VAT, and saw physical execution begin in Q4 2024. EIB project 20240513 defines about 2 km of main quay, 700 m of ancillary quays, 137 ha of reclamation, basin deepening, and dismantling interfaces. ACCIONA describes 126 ha of paved terminal areas and use of dredged material from Valencia and Sagunto, while Jan De Nul describes about 25 million m3 of dredged material for reuse where feasible. Valenciaport's September 2024 grant to TIL is a separate 50-year concession with EUR 1.098237 billion of proposed private investment; it does not prove marine-civil acceptance, installed automation, terminal commissioning, or commercial operation.
Phase: construction. Evidence reviewed: 16 July 2026.