Location
Spain / Europe
Project record
Valencia's North Terminal has moved from design publication and open procurement into a EUR 489.18 million marine-civil contract. About two kilometres of main quay, ancillary quays, reclamation, basin deepening, and demolition must be accepted before TIL's separate automated-terminal systems can enter commissioning.
Spain / Europe
Port infrastructure
Main quay works under construction after the Q4 2024 start / Confirmed
16 July 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe Port Authority's reformulated 2024 accounts confirm that the awarded works began executing in the final quarter of 2024 and describe the pace as adequate. Physical construction had started, while quay, dredging, reclamation, demolition, civil handover, terminal systems and operations remained incomplete.
SourceThe concession assigns TIL construction and operation of the future terminal and records EUR 1.098237 billion of proposed private investment outside Port Authority works. The private-investment figure is separate from the EUR 489.18 million marine-civil contract and provides no evidence of installed automation or operating readiness.
SourceThe Board selected the ACCIONA-Jan De Nul-Grupo Bertolin joint venture. The Port Authority's annual accounts later state EUR 489.18 million excluding VAT; the award fixes contractor and value, while mobilisation, production, accepted depth and handover remain open.
SourceFour submissions moved the container-quay procurement into evaluation. Bid receipt did not establish a selected contractor, contract value, concession award, or physical start.
SourceThe Port Authority approved an open procedure and EUR 545.78 million excluding VAT of expenditure. This procurement ceiling is distinct from the later EUR 489.18 million award and from TIL's private concession investment.
SourceThe then non-final design carried an estimated EUR 448 million including VAT and 58-month period, plus technical prescriptions for caissons, consolidation, dredged-material characterization, and operability. Those planning figures were superseded by the later procurement and award evidence.
SourceEvidence gap