Drain and bank works reported in execution in January 2026; Samatay-Hamoul evaluation complete with award order in preparation in September, followed by an October procurement review
Vietnam / Asia Pacific / Riverbank embankment and urban flood outfall works
Not assessed
Recorded status
June 2026 government account reports embankment work and drainage-package mobilisation; subsequent reach acceptance and programme updates remain to be checked
Nigeria / Africa / Earth dam, spillway, intake and scour-outlet rehabilitation
Not assessed
Recorded status
IUFMP records commissioning on 29 May 2020; the World Bank's 2023 implementation report confirms completed rehabilitation; its 2025 review records the dam-maintenance assignment as pending
Vietnam / Asia Pacific / Container berth and ancillary barge/tug wharves
Not assessed
Recorded status
Berth 4 and ancillary wharves opened in April 2025; an August 2025 owner account reports conditional approval in principle for larger partially laden ships; HTIT records an October 2026 service launch
The Harbour Master's 22 June 2026 report confirms Van Oord completed dredging at Batson, Lincombe and Kingsbridge, with pontoons reopened by April; published draft meeting minutes record subsequent receipt of the post-dredge survey
award / Last checked
Latest material change / Harbour Board records completed dredging and survey receipt / 5 recorded changes
Confirmed
ASIPONA records dredger arrival for third-phase stage 1 on 26 October 2026; estimated stage scope 3,076,370 m3. The July north-platform tender remains a separate historical procurement record.
construction / Last checked
Latest material change / Dredger arrives for third-phase stage 1 / 9 recorded changes
Confirmed
October marine assessment adopts the existing SEPCO intake and a revised canyon outfall; financing approvals recorded, construction release unconfirmed
financing / Last checked
Latest material change / October addendum changes the intake and outfall construction basis / 9 recorded changes
Confirmed
India / Asia Pacific / Deep-water ports, dredging and reclamation
Not assessed
Recorded status
Afcons disclosed receipt of VPPL's Letter of Award on 9 June 2026 for the 10.14 km offshore breakwater, valued at INR 53.01 billion excluding GST. The nearshore EPC award is separate; the offshore HAM procurement outcome and current field progress require their own records.
award / Last checked
Latest material change / Owner opened a Daman marine-sand investigation tender / 7 recorded changes
Confirmed
UK6 notice 097475-2026 names Chunnel Plant Hire and Contractors Limited for the six-unit repair at GBP 169,187.49 excluding VAT; signature is scheduled for 19 October 2026, with reinstatement and acceptance unconfirmed
award / Last checked
Latest material change / Council publishes repair award naming Chunnel / 3 recorded changes
Confirmed
Malaga Port Authority declared Quay 4 procedure 26exma-033 unsuccessful on 7 September 2026 after receiving no bids; the 15 September notice retains the seven-zone repair design and EUR 78,739.06 excluding-VAT tender budget, with no works award under this procedure
tender / Last checked
Latest material change / PLACSP published the unsuccessful-procedure outcome / 4 recorded changes
Confirmed
CanadaBuys' 13 October data records the CAD 948,750 tax-inclusive Le Goulet contract CW2466490 awarded to Les Entreprises P E C inc on 10 September 2026; mobilisation, plant, dredged quantities and acceptance remain unreported
award / Last checked
Latest material change / CanadaBuys records the original award to Les Entreprises P E C inc / 3 recorded changes
Confirmed
East Devon's 28 September UK7 notice records a Boskalis Westminster contract signed on 14 September 2026 at GBP 18,911,242.18 excluding VAT, with a 15 September 2026 to 29 March 2030 contract period; Stage 2 instruction and physical mobilisation remain unconfirmed
award / Last checked
Latest material change / UK7 recorded the signed Boskalis contract / 6 recorded changes
Confirmed
ECEPP marks the berth first-stage and supervision invitations closed; the supervision page lists 10 September 2026 as its final deadline; later-stage and other-package participation remain unverified
tender / Last checked
Latest material change / Aktau opened the supervision and implementation-support tender / 4 recorded changes
Confirmed
Three-year Boskalis award covers annual 2026-2028 campaigns; dated navigation notices add operational evidence, with 2026 contractual acceptance unconfirmed in the appointment and navigation notices
award / Last checked
Latest material change / The dated index retained the depth notice and cancelled the campaign notice / 4 recorded changes
Confirmed
ABP selected Boskalis Westminster on 11 August 2026; the UK6 award remains pending and signature is unconfirmed. MMO case MLA/2026/00178 shows Submitted / (In progress) / [On Hold], with no current consultation, as reviewed on 15 October
award / Last checked
Latest material change / ABP published the Boskalis selection / 5 recorded changes
Confirmed
PQQ closed on 1 May 2026; subsequent invitation to tender and supplier appointment remain unconfirmed in the reviewed notice
prequalification / Last checked
Latest material change / Ardersier opened prequalification for the Phase 2 dredging package / 3 recorded changes
Confirmed
Bullo holds the signed GBP 392,500 excluding-VAT contract; July and August navigation windows are historical, with the post-term instruction and accepted output unconfirmed
award / Last checked
Latest material change / October notice listing omits historical August dredging windows / 4 recorded changes
Confirmed
Find a Tender records an active award to ZPMC for four STS cranes at GBP 43.594 million excluding VAT; actual contract signature, manufacture, shipment, commissioning and acceptance remain unconfirmed
award / Last checked
Latest material change / ZPMC selected for the four-crane package / 3 recorded changes
Confirmed
National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT; the contract period ran from 13 August to 12 September 2025, but no dated completion, acceptance or final-account record has been located
award / Last checked
Latest material change / NOC signed the quayside repair contract / 2 recorded changes
Confirmed
Swansea signed the GBP 411,775.70 excluding-VAT two-pontoon contract on 15 July; the August amendment revised its start to 5 August, retaining a 2 October end, with site completion and acceptance unconfirmed
award / Last checked
Latest material change / Contract amendment revised the administrative start date / 5 recorded changes
Confirmed
Carmarthenshire County Council signed a GBP 425,000 excluding VAT emergency dredging contract with Kaymac Marine & Civil Engineering on 29 June 2026 for a 13 July to 31 October delivery window; the council has published no mobilisation, dredger, production, survey, completion or acceptance update
award / Last checked
Latest material change / Find a Tender published Kaymac's emergency dredging contract details / 5 recorded changes
Confirmed
HHA confirmed Suffolk Dredging LLP's five-year maintenance award in July; the March procurement family was withdrawn for a scope-description correction, with current value and exact commencement unconfirmed
award / Last checked
Latest material change / HHA confirmed the five-year maintenance award / 7 recorded changes
Confirmed
Chunnel holds the signed beach-management contract; the March campaign and April order are historical programme evidence, with autumn activity and accepted output unconfirmed
delivery / Last checked
Latest material change / Council purchase order names Chunnel on the active programme / 6 recorded changes
Confirmed
Jan De Nul was selected at GBP 57 million excluding VAT under the 18 December 2025 decision; the UK6 award remains pending for signature and C2526 field execution is unconfirmed
award / Last checked
Latest material change / Latest award notice retained Jan De Nul and GBP 57 million / 3 recorded changes
Confirmed
CW02 prequalification applications closed on 30 September 2026; bidding invitations expected in December 2026
prequalification / Last checked
Latest material change / CW02 deadline extended to 30 September; bidding invitations expected in December / 8 recorded changes
Confirmed
United States / Americas / Navigation channel maintenance dredging
Not assessed
Recorded status
USACE awarded the USD 2.852 million contract to American Construction on 24 September 2026; dredging is scheduled no sooner than 1 December and mobilisation remains unreported
award / Last checked
Latest material change / Seattle District published the field and placement plan / 2 recorded changes
Confirmed
United States / Americas / Navigation channel maintenance dredging
Not assessed
Recorded status
USACE scheduled Morrish-Wallace's 109,000-cubic-yard campaign to start on 6 October 2026 and finish by 1 November; actual mobilisation remains unverified
Owner reports realization has begun with the lake-side foreshore; conventional dike work planned from early 2027, quantities and acceptance unconfirmed
Wheeler and Glenn Edwards operations scheduled from approximately 4 September with different end dates; actual vessel mobilisation and accepted output unconfirmed
United States / Americas / Capital dredging and navigation-channel deepening
Not assessed
Recorded status
USACE lists Phase 2 in construction with new-work dredging continuing toward an FY2026 scheduled completion; final accepted depth, certified quantity and contract completion are unpublished
delivery / Last checked
Latest material change / The federal award record reached USD 109.240 million in obligations / 3 recorded changes
Confirmed
Greece / Europe / Commercial-port shore power and electrical utility integration
Not assessed
Recorded status
HEDNO signed the EUR 6.82 million turnkey contract with Paralos on 11 February 2026 for two 3 MVA OPS positions and one 0.5 MVA position. TED names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors; mobilisation, installation, energisation, vessel connection and acceptance remain unconfirmed
award / Last checked
Latest material change / Paralos confirms the Igoumenitsa turnkey award / 4 recorded changes
Confirmed
Italy / Europe / Sheet-pile rehabilitation and port-yard conversion
Not assessed
Recorded status
TED notice 514687-2026 records a EUR 8,295,571.84 contract concluded on 23 July 2026 with the Rossi Renzo Costruzioni-led four-member RTI; notice to proceed, mobilisation, named subcontractors and installed work remain unverified
award / Last checked
Latest material change / TED publishes the Phase B award / 4 recorded changes
Confirmed
Kerr Limited's CAD 18.86 million contract reached its amended 31 December 2025 expiry after 11 amendments; no cited owner record confirms accepted completion, final dredged quantities or reopening
delivery / Last checked
Latest material change / The amended contract term expired / 4 recorded changes
Confirmed
Terelian and SDI/DEME are constructing the 1,800 metre protection dike; HAROPA reported nearly 800,000 m3 of foundation material placed by 1 June 2026 after a 760,000 m3 weak-silt purge, while channel dredging, dike tie-ins, completion and operating release remain pending
construction / Last checked
Latest material change / Environmental compensation moved into monitored operation / 4 recorded changes
Confirmed
Democratic Republic of the Congo / Africa / Deep-water ports and container terminals
Not assessed
Recorded status
Phase-one contract announced with an estimated 24-month term; no current cited record confirms accepted marine works, terminal commissioning, or commercial opening
construction / Last checked
Latest material change / Council of Ministers kept the Banana corridor on the national modernisation agenda / 6 recorded changes
Confirmed
United States / Americas / Marinas, pontoons and berthing infrastructure
Not assessed
Recorded status
New York City's 22 January 2026 award notice names Empire Construction and Property Management Group at USD 4,583,648 for X310-117M; the city hazard plan identifies bulkhead, dock and electrical reconstruction, but no cited record establishes contract signing, notice to proceed, mobilisation or completion
award / Last checked
Latest material change / NYC published the USD 4.58 million construction award / 3 recorded changes
Confirmed
Australia / Asia Pacific / Public boat-launch infrastructure, maintenance dredging and fixed access
Not assessed
Recorded status
Northern Territory Tenders Online records T25-1462 as a 12-month awarded period contract to Polaris Marine Constructions at AUD 676,047.56 on an estimated-unit-rate basis
award / Last checked
Latest material change / Official tender page records the 12-month award to Polaris / 3 recorded changes
Confirmed
Democratic Republic of the Congo / Africa / Port infrastructure
Not assessed
Recorded status
PFCIGL reported that GETRA-AXOR remobilized from 15 June 2026 and that Kalundu works were progressively resuming; activity then remained at site installation and ground preparation before effective rehabilitation works
construction / Last checked
Latest material change / Published completion baseline became stale / 5 recorded changes
Confirmed
Morocco / Africa / Deep-water ports and energy terminals
Not assessed
Recorded status
Basic port infrastructure reported complete; access-control, port-management, systems, staffing, and service preparations remain active ahead of the East terminal's Q4 2026 commissioning target, while the West terminal follows from 2027
commissioning / Last checked
Latest material change / Access and operating-transition work remained in procurement / 7 recorded changes
Confirmed
Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access
construction / Last checked
Latest material change / Owner scheduled a three-day quay-wall sheet-pile delivery window / 5 recorded changes
Confirmed
CHEC EPC delivery and live-berth works reported by two current staff profiles; owner releases confirm the AED 84 million programme but do not name the contractor
construction / Last checked
Latest material change / AD Ports Group and EGA agreed an AED 84 million Newcastlemax berth upgrade / 5 recorded changes
Confirmed
Australia / Asia Pacific / Maintenance dredging, approach-channel access and beach placement
Not assessed
Recorded status
Buying for Victoria records Birdon Pty Ltd on a current AUD 31.9 million contract starting 1 November 2021; Birdon describes a 2021-2030 term and names dredge Ballina with support craft Willie Tell and Bella, while site-level quantities and owner acceptance remain campaign-specific
delivery / Last checked
Latest material change / Parks Victoria confirmed another depth-triggered Portarlington campaign / 4 recorded changes
Confirmed
Mozambique / Africa / Water intake and treatment works
Not assessed
Recorded status
Jiangxi Water and Hydropower Construction Group signed the USD 17.985 million W-15/23 contract on 10 January 2024; ARA Norte documented work at the treatment, pumping and elevated-storage sites in September 2025, and no package completion or acceptance record follows the cited April 2026 target
construction / Last checked
Latest material change / The cited continuation target passed without package closeout evidence / 5 recorded changes
Confirmed
Senegal / Africa / Deep-water ports and container terminals
Not assessed
Recorded status
DP World reports the major dredging works complete 13 months ahead of schedule; quay and other marine and civil works remain active, while 2028 is a target rather than an accepted opening date
construction / Last checked
Latest material change / DP World reported major dredging complete 13 months early / 7 recorded changes
Confirmed
Phase 2 reclamation stood at 79.5% in December 2025 and its planned six-berth handover remains unverified; the wider Tuas Port passed 25 million TEU in August 2026, but that operating total began with Phase 1
delivery / Last checked
Latest material change / PSA reported 25 million TEU handled across the wider Tuas Port / 10 recorded changes
Confirmed
Granite Management received DFO contract 4500013526 on 23 December 2021 for a two-site floating-dock package; the 2021-22 Public Accounts mark the contract completed, while physical acceptance records remain unpublished
completed / Last checked
Latest material change / Public Accounts marked the contract completed / 3 recorded changes
Confirmed
Canada / Americas / Remote fishing-harbour timber crib wharf and floating offloading dock
Not assessed
Recorded status
Fisheries and Oceans Canada awarded ZheMaak Inc. contract 4500091055 for CAD 220,542 on 8 August 2025; the published seven-month term ended on 27 March 2026, but the reviewed federal record does not publish physical completion, accepted quantities, owner handover or a final account
delivery / Last checked
Latest material change / The published contract term ended / 3 recorded changes
Confirmed
Maher's Contracting received F6140-210731/001/PWD on 15 November 2021; CanadaBuys records a CAD 1,763,368 cumulative contract after amendments, and the 2022-23 Public Accounts mark the Port de Grave contract completed
completed / Last checked
Latest material change / Public Accounts marked the Port de Grave contract completed / 4 recorded changes
Confirmed
Canada / Americas / Capital and maintenance dredging for a remote ferry, cargo and fishing port
Not assessed
Recorded status
PSPC awarded contract CW2402077 to Dragage Ocean DS on 1 September 2025; a CNESST filing places the contractor at the Cap-aux-Meules dredging site from a planned 13 October to 12 November 2025, while a 13 May 2026 amendment lifted the published contract total to CAD 6,724,266.72 without disclosing its scope
construction / Last checked
Latest material change / Contract total increased by CAD 3.235 million / 4 recorded changes
Confirmed
Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed
completed / Last checked
Latest material change / Public Accounts marked the Winterton contract completed / 4 recorded changes
Confirmed
Australia / Asia Pacific / Port revetment repair and armour-rock placement
Not assessed
Recorded status
Queensland Transport and Main Roads disclosed Contract MSQ25017 with Hunter Contractors Pty Ltd at AUD 1,981,207 on 10 July 2025, and Maritime Safety Queensland announced a 2 September 2025 construction start; no cited official source confirms installed quantities, completion, acceptance or final account
construction / Last checked
Latest material change / Owner announced shoreline works start / 3 recorded changes
Confirmed
Oman / Middle East / Deep-water ports and energy terminals
Not assessed
Recorded status
Phase 1 plant construction and CBM equipment delivery are active. Masirah Marine is the reported installation lead; its contract, vessel allocation and ASD-tug support remain undisclosed
construction / Last checked
Latest material change / Fleet review exposed a separate ASD-tug subcontract gap / 16 recorded changes
Confirmed
Czechia / Europe / Inland marina quay edges, floating fingers, bank protection and utilities
Not assessed
Recorded status
The Czech Waterways Directorate opened 30 new public berths in August 2025 and the Transport Ministry reports the expanded marina operating with capacity for 66 boats in the 2026 season; IDS holds the phase-one works contract, with the highest reviewed official modification snapshot at CZK 86,312,219.98
completed / Last checked
Latest material change / Modification series exposes the phase-one risk and cost chain / 4 recorded changes
Confirmed
United States / Americas / Marina electrical infrastructure, waterfront site preparation and public realm
Not assessed
Recorded status
The Port of Edmonds Commission unanimously authorized a contract with TRICO Companies LLC on 8 June 2026; the current owner page marks Phase II in progress and estimates work will begin late in 2026
award / Last checked
Latest material change / Owner page carries Phase II as in progress / 3 recorded changes
Confirmed
Kildare Construction Ltd. received CAD 1.10 million contract 4500013345 on 23 December 2021 for structure 401; the 15 June 2022 target date is published, but completion and owner acceptance remain unverified
award / Last checked
Latest material change / Kildare Construction received the wharf 401 award / 3 recorded changes
Confirmed
Christian Larocque Services LTEE received the CAD 347,878.45 construction contract in November 2021; Harbourside Engineering reports the rebuilt dredge-spoil containment cell completed in March 2022
completed / Last checked
Latest material change / ASDR Canada received a separate four-channel dredging award / 4 recorded changes
Confirmed
United States / Americas / Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities
Not assessed
Recorded status
Port reporting confirms key dock and stormwater upgrades were completed in 2025 and navigation and environmental work advanced; Washington L&I records American Construction's contractor-reported 8 April 2026 work-completed date, but no filed Notice of Completion, owner acceptance, final hydrographic survey, final dredged quantity or final account is evidenced
delivery / Last checked
Latest material change / American Construction affidavit enters the L&I record / 4 recorded changes
Confirmed
United States / Americas / Wharf maintenance, fender piles and marine asset renewal
Not assessed
Recorded status
The San Francisco Port Commission adopted Resolution 25-25 on 13 May 2025, authorizing award of Contract 2871 to Manson Construction Co. for USD 5,518,500 plus a USD 551,850 contingency; the cited official record does not confirm the planned notice to proceed, physical progress, substantial completion or acceptance
award / Last checked
Latest material change / Port Commission authorized award to Manson / 3 recorded changes
Confirmed
Spain / Europe / Urban wastewater treatment, tertiary reuse and flood resilience
Not assessed
Recorded status
CHJ currently lists the Torrent adaptation works in execution under the Global Omnium Medioambiente-CICLAGUA-BECSA UTE; its 2025 delivery report fixes the site-start baseline at 19 September 2023 and records separate certified amounts for modification 1 and the post-DANA emergency workfront, while PLACSP's 10 August 2026 modification record adds zero price and zero duration
construction / Last checked
Latest material change / PLACSP publishes modification 1 / 4 recorded changes
Confirmed
ADB records the three-outfall civil package completed in August 2018, testing and commissioning in Q2 2019, the wider project physically completed on 31 December 2019, and the financing operation closed
completed / Last checked
Latest material change / Independent validation rated the completed project less than successful / 5 recorded changes
Confirmed
Phase A tug quay delivered; the same consortium has started Phase B, including 1.4 million m3 of sand dredging; Phase C remains a post-2028 package
construction / Last checked
Latest material change / Phase A delivered and the same consortium started quantified Phase B works / 7 recorded changes
Confirmed
Construction contract awarded; site preparations commenced
construction / Last checked
Latest material change / Maraen awarded the construction contract and began site preparations / 4 recorded changes
Confirmed
South Africa / Africa / Port revetment repair and armour-rock placement
Not assessed
Recorded status
South Africa's official procurement release records an active ZAR 5,466,159 award to KATLANTIC for the Port of Durban North Bank revetment repairs; the public record does not provide an award date, executed contract, notice to proceed, physical progress or completion
award / Last checked
Latest material change / The tender closed after its compulsory briefing / 2 recorded changes
Confirmed
United States / Americas / Inland navigation lock rehabilitation and hydraulic steel structures
Not assessed
Recorded status
USACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublished
completed / Last checked
Latest material change / USACE reports four-gate installation complete / 3 recorded changes
Confirmed
Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate
construction / Last checked
Latest material change / Breakwater becomes the July 2027 critical path / 4 recorded changes
Confirmed
United States / North America / MOTEMS wharf replacement, dolphins, fenders and maintenance dredging
Not assessed
Recorded status
The Port of Los Angeles January 2026 CIP report classifies the project in construction and, using actuals through November 2025, records 22% construction completion, a 31 March 2027 forecast finish, USD 39,288,466 projected project cost and USD 6,315,074 spent to date
construction / Last checked
Latest material change / Port publishes project-level construction progress / 3 recorded changes
Confirmed
Spain / Europe / Urban wastewater treatment, tertiary reuse and renewable-energy integration
Not assessed
Recorded status
ACUAES selected the Aquambiente-COPASA-PESA consortium on 30 July 2026 at EUR 61,784,295.49 excluding VAT; the award notice was published on 4 August, while contract signature, notice to proceed and mobilisation remain unconfirmed
award / Last checked
Latest material change / ACUAES publishes the works award notice / 3 recorded changes
Confirmed
Bahrain / Middle East / Liquid-cargo terminal maintenance
Not assessed
Recorded status
Bahrain Tender Board's May 2026 report records a BHD 340,000 extension under tender T17600(65), following the May 2021 BHD 2,489,690 five-year award to Bahrain Maintenance and Diving Services; the extension duration and work orders remain undisclosed
award / Last checked
Latest material change / Monthly report observes a BHD 340,000 extension / 2 recorded changes
Confirmed
USACE records the FY2025 campaign complete after Dutra's USD 6.272 million dredging award; three reported subawards expose placement fees, DQM and survey support, tug setup and crew boats, while the final accepted quantity and account remain unpublished
completed / Last checked
Latest material change / USACE completed a post-campaign condition survey / 5 recorded changes
Confirmed
Madagascar / Africa / Inland river-port station and passenger-cargo terminal rehabilitation
Not assessed
Recorded status
ECH BTP signed the USD 1,272,815.07 works contract on 28 November 2025; public records also name the design and supervision consultant, but no notice to proceed, mobilisation, measured progress, completion or acceptance has been located
award / Last checked
Latest material change / World Bank record stores a post-review no-objection date / 3 recorded changes
Confirmed
Mali / Africa / Inland river-port quay and bank rehabilitation
Not assessed
Recorded status
Two works lots under ML-UGP-PRTD-477915-CW-RFB were signed in December 2025; the April 2026 procurement plan marks the package under implementation, but no lot-specific mobilisation, progress, completion or acceptance record has been published
award / Last checked
Latest material change / Latest procurement plan retained the Dioro package under implementation / 3 recorded changes
Confirmed
Australia / Oceania / Urban ferry terminal, floating platform and passenger gangway
Not assessed
Recorded status
Maritime Constructions holds the AUD 1,756,143 fixed-price design-and-construct award; Tenders WA does not publish a start date, expiry date, mobilisation or completion milestone
award / Last checked
Latest material change / Maritime Constructions awarded the Elizabeth Quay package / 2 recorded changes
Confirmed
Australia / Asia Pacific / Urban waterway maintenance dredging, navigation access and in-river material placement
Not assessed
Recorded status
Buying for Victoria records Australasian Marine Associates on a current AUD 1.93985 million contract starting 8 September 2021; Parks Victoria confirms AMA delivered Campaign C in 2024, while the owner programme was reported complete and the next funding cycle remained open
delivery / Last checked
Latest material change / Annual report separated completed programme from ongoing need / 4 recorded changes
Confirmed
Norfolk Island / Global islands / Pier remediation and island freight access
Not assessed
Recorded status
GP Services' AUD 183,041 emergency-remediation period has elapsed without accepted completion evidence; the separate AUD 10 million apron project is in detailed design with Consult Marine, with no construction award or mobilisation published
award / Last checked
Latest material change / Draft ports strategy defined the apron Stage 2 scope and planning sequence / 4 recorded changes
Confirmed
EWEC lists Taweelah RO as an existing 909,000 m3/day facility and records 297.16 million m3 of 2024 production; final as-built intake and outfall geometry is not publicly disclosed
completed / Last checked
Latest material change / EWEC publishes a full-year operating baseline / 5 recorded changes
Confirmed
TerraMarine is preferred proponent; contract negotiations, an in-progress Fisheries Act authorization and development work precede any target-price design-build agreement, financial close or mobilisation
design / Last checked
Latest material change / Current federal dashboard keeps the Fisheries Act authorization open / 5 recorded changes
Confirmed
Construction active; common marine, tunnelling, and electrical systems remain on the path to the February 2027 first-phase target
construction / Last checked
Latest material change / Q1 construction activity identified Casablanca as a Water delivery driver / 7 recorded changes
Confirmed
Teignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmed
construction / Last checked
Latest material change / Temporary pontoon and bridge commissioned / 5 recorded changes
Confirmed
India / Asia Pacific / Inland-waterway floating jetties, gangways and passenger facilities
Not assessed
Recorded status
Cleghorn Mfg. Co. signed the six-location bundled supply and installation contract on 24 April 2025; public evidence does not confirm final sites, fabrication, installation, commissioning or acceptance
India / Asia Pacific / Inland-waterway floating jetties, gangways and passenger facilities
Not assessed
Recorded status
Nalanda Engineering Enterprise signed the seven-location bundled supply and installation contract on 3 April 2025; public evidence does not confirm fabrication, installation, commissioning or acceptance
United States / Asia Pacific / Naval and civil seaport wharf, breakwater and harbor-dredging design
Not assessed
Recorded status
MDPAC JV holds a USD 12.616m architect-engineer task order through 31 December 2026 for P-940 wharf improvements, P-1001 breakwater restoration and P-1002 harbor dredging and Finger Pier A removal; 13 named design-chain subaward records total USD 4.055m, while no construction award or mobilisation is evidenced
design / Last checked
Latest material change / Port reopened for daylight operations after Super Typhoon Bavi / 5 recorded changes
Confirmed
Canada / North America / Small-craft-harbour marginal wharf and channel-wall renewal
Not assessed
Recorded status
DFO-SCH's 2026 proposal remains in federal assessment after the public-comment period ended on 22 June 2026; no environmental determination, procurement, award, contractor, mobilisation or construction is evidenced
approval / Last checked
Latest material change / Federal public-comment period closed / 3 recorded changes
Confirmed
Canada / North America / Small-craft-harbour entrance dredging and breakwater works
Not assessed
Recorded status
Marine Contractors' CAD 1.499m entrance-improvement contract and R.J.G Construction's separate CAD 1.133m channel re-dredging contract have both reached their published administrative end dates, but no completion certificate, accepted hydrography, final dredged quantity or causal link between the packages is public
delivery / Last checked
Latest material change / Separate channel-wall proposal closed its public-comment period / 5 recorded changes
Confirmed
United States / Asia Pacific / Naval-wharf and inner-harbor dredging design
Not assessed
Recorded status
MDPAC JV holds the USD 3.335m P-835 design task order, expanded in August 2025 from DD1391 and 15% design into a design-bid-build package and extended in March 2026 to September 2028; no construction award or physical dredging is evidenced
design / Last checked
Latest material change / Task order extended to September 2028 / 4 recorded changes
Confirmed
Superior Contracting's CAD 1.264 million contract ran from 14 October 2022 to 31 March 2023 for an integrated timber-wharf, dredging, breakwater, floating-dock and electrical package; the reviewed federal record does not publish accepted completion, measured quantities or final account
delivery / Last checked
Latest material change / The published contract term expired / 2 recorded changes
Confirmed
Tunisia / Africa / Fishing-port expansion, dredging, breakwater, quay and coastal esplanade
Not assessed
Recorded status
ETEP signed the TND 20,018,762.19 works contract on 28 April 2025, but Tunisia's parliament still described the port and esplanade project as delayed during a February 2026 site visit; physical start, achieved quantities and supervision award remain unverified
award / Last checked
Latest material change / Parliamentary site visit records continued delay / 5 recorded changes
Confirmed
France / Europe / Commercial-port shore power and electrical utility integration
Not assessed
Recorded status
BOAMP notice 25-50611 records a EUR 5,436,212 contract issued on 3 April 2025 to the SPIE CityNetworks-led consortium with Nidec ASI and T.A.E.H., plus subcontractor Guintoli. A 24 March 2026 Department presentation classifies the work as in progress; energisation, vessel connection, commissioning, acceptance and completion remain unconfirmed
construction / Last checked
Latest material change / Department classifies electrification as works in progress / 4 recorded changes
Confirmed
United States / North America / Cruise berth rehabilitation, shore power and marine piling
Not assessed
Recorded status
Los Angeles Harbor Commission Resolution 26-10665 approved Shimmick's USD 61,290,400 bid on 6 January 2026, and RAMP records the award on 26 January; the owner's award presentation estimated a March 2026 notice to proceed and January 2029 completion, while the actual NTP, site mobilisation and installed work remain unconfirmed through 8 August 2026
award / Last checked
Latest material change / RAMP records the construction award / 4 recorded changes
Confirmed
Australia / Asia Pacific / Marinas, pontoons and berthing infrastructure
Not assessed
Recorded status
Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract
completed / Last checked
Latest material change / Hillarys final jetty-replacement stage completed / 4 recorded changes
Confirmed
Australia / Asia Pacific / Marinas, pontoons and berthing infrastructure
Not assessed
Recorded status
Transport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade Sales
completed / Last checked
Latest material change / Transport WA publishes the Jetty 3 project cost / 5 recorded changes
Confirmed
Bahrain / Middle East / Liquid-cargo terminal berth enhancement
Not assessed
Recorded status
Bahrain Tender Board's March 2026 monthly report records a BHD 10,987,831 award to NASS Contracting for Sitra Wharf tender T78534; no award date, contract signature, mobilisation or installed work is published
award / Last checked
Latest material change / Monthly report observes the NASS award / 2 recorded changes
Confirmed
Netherlands / Europe / Quay-wall replacement and waterfront public-realm renewal
Not assessed
Recorded status
TED notice 542353-2026 records a EUR 7,887,000 contract with De Vries Werkendam B.V. concluded on 4 August 2026; the owner plans physical works from 5 October 2026 to 21 July 2028 and publishes no current mobilisation evidence
award / Last checked
Latest material change / TED publishes the M2 award / 3 recorded changes
Confirmed
Australia / Asia Pacific / Harbour seawall renewal and coastal asset protection
Not assessed
Recorded status
Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation
award / Last checked
Latest material change / State contract period begins in the award record / 2 recorded changes
Confirmed
Senegal / Africa / Fish landing quay and fisheries value-chain infrastructure
Not assessed
Recorded status
FIDELE SARL's rehabilitation contract was signed 5 February 2025 for an operating export-approved landing facility; no controlled site start, temporary operating setup or physical progress evidence through 8 August 2026
Senegal / Africa / Fish landing quay and fisheries value-chain infrastructure
Not assessed
Recorded status
KELIMANE ENTREPRISE's Lot 01 contract was signed 5 February 2025, while a separate replacement relocation-site package remained awaiting execution in the current plan; no controlled main-works start evidence through 8 August 2026
Senegal / Africa / Fish landing quay and fisheries value-chain infrastructure
Not assessed
Recorded status
Official works launch held 24 July 2025 after ETIC's Lot 02 contract was signed 15 January 2025; no controlled later completion or commissioning evidence through 8 August 2026
Oman / Middle East / Fishing-port concession, commercial waterfront and operating PPP
Not assessed
Recorded status
Liwa remained in Oman's 2024 PPP and fisheries-investment pipeline after 2021 and 2023 market approaches; a selected developer and financial close remain undisclosed through 8 August 2026
Oman / Middle East / Operating fishing-port maintenance dredging
Not assessed
Recorded status
Oman eTender 441/2023/MAFWR/HQ-36 reached financial evaluation in Q3 2023, then a Recall-1 procedure closed on 19 December 2023; an awardee, value and mobilisation remain undisclosed
Oman / Middle East / Fishing-port breakwaters, dredging, quay and marine infrastructure
Not assessed
Recorded status
Liwa harbour was operating by 2023 after the original Galfar award and 2015-2017 downstream marine works; formal completion, acceptance and final-account records remain unrecovered
Oman / Middle East / Fishing-port maintenance, rehabilitation and dredging
Not assessed
Recorded status
Masirah Island International identifies active harbour maintenance, rehabilitation and dredging; a 2025 Oman News Agency owner-side report says the port remained under maintenance, with no public completion or acceptance record
South Africa / Africa / Wastewater pump stations, rising mains and treatment-plant tie-ins
Not assessed
Recorded status
City of Cape Town tender 32Q/2026/27 is open for a new 1,100 L/s Rietvlei sewage pump station, twin 1,980 m DN710 HDPE rising mains and Bellville WWTW tie-in works; bids close at 10:00 local time on 2 November 2026 and no contractor is appointed
Dexter holds CAD 4.29 million CW2462474 for floating-dock and pipe-pile replacement, while Connors Diving holds CAD 1.27 million 4500109325 for Wharf 403 pile jackets and concrete repairs; both awards are active but mobilisation and progress are unverified
award / Last checked
Latest material change / Dexter received the floating-wharf package / 3 recorded changes
Confirmed
Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified
award / Last checked
Latest material change / Zutphen received the D1-D11 reconstruction award / 2 recorded changes
Confirmed
Italy / Europe / Container and multipurpose terminal quay extension
Not assessed
Recorded status
TED notice 521188-2026 records a 23 July 2026 works contract with a planned RTI led by Dott. Carlo Agnese at EUR 10,868,519.12 for 419 days; notice to proceed, mobilisation, installed quantities and named subcontractors remain unverified
award / Last checked
Latest material change / TED publishes the Lot I award / 3 recorded changes
Confirmed
Zutphen Contractors holds active CAD 2.75 million contract CW2455209 through 27 November 2026 for rubble-mound breakwater construction at Larrys River; award and scope are confirmed but mobilisation and physical progress are not
delivery / Last checked
Latest material change / Zutphen Contractors received the breakwater award / 2 recorded changes
Confirmed
Les Entreprises P E C inc holds active CAD 862,270 contract CW2452382 through 31 December 2026 for barge-excavator dredging and containment-cell reconfiguration; earliest site start was 6 July and field progress remains unverified
delivery / Last checked
Latest material change / The earliest authorized field-start date arrived / 2 recorded changes
Confirmed
L Breau and Sons Ltd holds active CAD 8.75 million contract CW2440554 through 24 August 2027 for structure 401 wharf reconstruction and a new breakwater; mobilisation, measured work and acceptance remain unconfirmed
delivery / Last checked
Latest material change / L Breau and Sons received the structure 401 award / 2 recorded changes
Confirmed
Sri Lanka / Asia Pacific / Deep-water port expansion, breakwaters and reclaimed logistics land
Not assessed
Recorded status
Dohwa-led detailed-design contract awarded in April 2025; SLPA's May 2026 planning document confirms the engineering study but leaves financing, construction procurement and field start open
design / Last checked
Latest material change / SLPA kept financing and project launch outside the design award / 4 recorded changes
Confirmed
France / Europe / Breakwater and reinforced-concrete marine-structure rehabilitation
Not assessed
Recorded status
The owner-confirmed nine-month repair started on 25 August 2025; its planned end-May 2026 acceptance window has passed without a published completion certificate, handover or final account
construction / Last checked
Latest material change / Planned acceptance remains unconfirmed in the current owner archive / 6 recorded changes
Confirmed
Netherlands / Europe / Beach and foreshore nourishment
Not assessed
Recorded status
Van den Herik signed the EUR 16.302 million contract on 10 March 2026; Rijkswaterstaat schedules Maasvlakte 2 nourishment for September and names Van den Herik with Van der Kamp there, while mobilisation and the parties' commercial relationship remain unverified
award / Last checked
Latest material change / Owner schedule names two Maasvlakte 2 execution participants / 2 recorded changes
Confirmed
Netherlands / Europe / Beach and foreshore nourishment
Not assessed
Recorded status
Fa. Gebr. Van der Lee signed the EUR 8.199 million contract on 31 March 2026; the contract is live through 2027, while no public evidence of physical mobilisation, vessel assignment or accepted production was identified by the 7 August 2026 review
award / Last checked
Latest material change / TenderNed published the 31205036 award / 2 recorded changes
Confirmed
Netherlands / Europe / Beach and foreshore nourishment
Not assessed
Recorded status
Boskalis signed the EUR 26.098 million contract on 12 May 2026; Rijkswaterstaat announced Den Helder tidal-channel nourishment from 14 July to mid-October and Julianadorp sinker-pipe removal from 20 July, while measured production and acceptance remain unpublished
construction / Last checked
Latest material change / Rijkswaterstaat announced the Den Helder execution window / 2 recorded changes
Confirmed
Malta / Europe / Cargo-port quay, land reclamation, piling and utilities
Not assessed
Recorded status
Infrastructure Malta is taking replacement works tender IMT008/2025 to 1 October 2026 after terminating predecessor contract IM027/2020; the replacement works package remains unawarded
tender / Last checked
Latest material change / Latest TED notice retains the 1 October tender deadline / 5 recorded changes
Confirmed
India / Asia Pacific / Inland-waterway floating jetties, gangways and passenger facilities
Not assessed
Recorded status
IWAI signed the five-site Lot A contract with West Coast Marine Yacht Services on 18 March 2026; the procurement plan lists the package under implementation, but fabrication, installation and site acceptance remain publicly unconfirmed
award / Last checked
Latest material change / IWAI signed the five-site Lot A contract / 2 recorded changes
Confirmed
Two Soubise works lots were signed on 27 April 2026 for a combined USD 5.747 million; Marquis Lot 3, notice to proceed, mobilisation and physical works remain publicly unconfirmed
award / Last checked
Latest material change / World Bank data reports no-objection for both signed Soubise contracts / 4 recorded changes
Confirmed
C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished
construction / Last checked
Latest material change / World Bank award data confirmed C. O. Williams and USD 8.482 million / 7 recorded changes
Confirmed
Netherlands / Europe / LNG jetty, combi-wall, mooring structures, dredging and shore works
Not assessed
Recorded status
Gate took FID in January 2026, Port of Rotterdam signed the Hakkers Waterbouw-De Klerk combination on 6 February, and April works notices support early construction; start-up is planned around the end of 2028
construction / Last checked
Latest material change / Harbour marking changed for Yukonhaven construction / 5 recorded changes
Confirmed
Colombia / Americas / Capital dredging and navigation-channel deepening
Not assessed
Recorded status
SECOP II records contract GN2862-2026 signed with Consorcio Puerto Tumaco II for COP 26.826 billion and eight months, but the public ledger has no start date, invoicing or payment and the separate supervision procurement remains unawarded
award / Last checked
Latest material change / Phase I works contract signed at COP 26.826 billion / 4 recorded changes
Confirmed
SECOP II shows contract 0-525-2024 modified to COP 241.685 billion and 31 December 2026 after a 365-day extension; Cormagdalena reported 80.7% execution at 31 March before the later ledger update, while completion and acceptance remain unconfirmed
delivery / Last checked
Latest material change / SECOP ledger carries the modified contract to COP 241.685 billion and year-end / 5 recorded changes
Confirmed
Landco Construction's CAD 3.08 million contract ran from 2 November 2023 to 4 July 2024 for a Berlin-wall marginal wharf, harbour dredging and electrical reinstatement; CanadaBuys does not publish accepted completion or final quantities
delivery / Last checked
Latest material change / The recorded eight-month contract term expired / 2 recorded changes
Confirmed
Bulldog Contracting received the CAD 7.05 million award on 1 April 2022 for timber-crib wharf, finger-pier, dredging and utility works; the reviewed federal record does not establish the delivery end date, accepted completion or final account
delivery / Last checked
Latest material change / Bulldog received the integrated reconstruction award / 2 recorded changes
Confirmed
Brian MacGillivary Construction's CAD 516,100 contract ran from 22 November 2023 to 29 March 2024; CanadaBuys confirms the award and amended term but publishes no accepted dredging quantity, dock handover or completion certificate
delivery / Last checked
Latest material change / The amended four-month contract term ended / 2 recorded changes
Confirmed
India / Asia Pacific / Inland-waterway floating jetties, gangways and passenger facilities
Not assessed
Recorded status
World Bank data identifies 21 direct works contracts across the 29-jetty Phase I and 16-jetty Phase II programme; the June 2026 ISR says 44 of 45 locations are complete with Metiabruze under implementation, while its results table says all 45 are complete
Australia / Asia Pacific / Wharf maintenance, fender piles and marine asset renewal
Not assessed
Recorded status
Queensland TMR awarded MSQ26005 to Pacific Marine Group on 11 May 2026 for AUD 423,687; no public milestone establishes mobilisation, pile quantities, installation method, completion or acceptance
Tanzania / Africa / Capital dredging, berth reconstruction and concrete remediation
Not assessed
Recorded status
Channel and berth civil packages were reported complete in 2024 and the port publishes operational depths; CHEC's separate USD 15.70 million 2025 concrete-repair contract has no cited completion or acceptance evidence
construction / Last checked
Latest material change / TPA signed a separate concrete-repair contract with CHEC / 3 recorded changes
Confirmed
United States / Americas / Maintenance dredging and operating-port access
Not assessed
Recorded status
Great Lakes' Padre Island campaign was publicly scheduled from 20 October to 16 November 2024; an April 2025 final-quantity modification reduced the current federal obligation from USD 8.799 million to USD 7.456 million, while accepted quantities and formal closeout remain unpublished
delivery / Last checked
Latest material change / USACE records the final quantity adjustment / 6 recorded changes
Confirmed
Great Lakes holds the USD 219.108 million Contract 6 obligation; its USD 235.423 million potential value, April 2027 owner finish, production, assigned fleet and lower tiers remain to be confirmed
delivery / Last checked
Latest material change / SNND schedules Contract 6 in the second four-foot cut / 4 recorded changes
Confirmed
France / Europe / Inland-port basin excavation, sheet-pile quays, pile-supported jetties and multimodal access
Not assessed
Recorded status
HAROPA PORT reports phase-one construction in execution: earthworks, a retaining wall and conveyor loading were active in summer 2026, South Quay sheet-pile installation had started, and piling for the west then east jetties was scheduled from the week of 6 July
construction / Last checked
Latest material change / HAROPA updated the summer marine-works sequence / 5 recorded changes
Confirmed
Australia / Asia Pacific / Public boat-launch infrastructure, capital dredging and fixed access
Not assessed
Recorded status
Australian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026
construction / Last checked
Latest material change / MSQ established a starboard lateral beacon in Poona Creek / 5 recorded changes
Confirmed
Australia / Asia Pacific / Public boat-launch infrastructure, capital dredging and fixed access
Not assessed
Recorded status
Queensland TMR completed the upgraded all-tide facility in May 2022 after Australian Marine & Civil delivered the main works under CN-17011; the published contract disclosure rose from AUD 2,560,154 to AUD 2,603,835 after a variation
completed / Last checked
Latest material change / Completed facility opened to users / 4 recorded changes
Confirmed
World Bank contract record 1881500 names C. O. Williams Construction Limited at USD 3.338 million, but the public procurement chronology does not reconcile and no dated mobilisation, progress or completion record has been located
award / Last checked
Latest material change / World Bank contract record carries a later no-objection date / 3 recorded changes
Confirmed
China Jiangsu International holds the signed USD 4.803 million MOI-WK2-13 award; notice to proceed, mobilisation and physical works remain publicly unconfirmed
award / Last checked
Latest material change / The Ministry sought a dedicated construction-supervision team / 4 recorded changes
Confirmed
Region Hauts-de-France concluded contract 202613951 with SODRANORD on 24 February 2026 for a purchase-order maintenance dredging framework; the EUR 23 million figure is the four-year maximum ceiling, while the first call-off, 2026 quantity and mobilisation remain unconfirmed
award / Last checked
Latest material change / BOAMP published the SODRANORD award / 3 recorded changes
Confirmed
Taing Cheng Oing Construction & Import Export signed package SCMFP FiA/CW-03 on 9 March 2026; ADB reports a financed amount of 472,336.05 without currency or full contract value, and mobilisation or physical start is not independently confirmed
award / Last checked
Latest material change / Taing Cheng Oing Construction signed CW-03 / 3 recorded changes
Confirmed
Peru / Americas / Maintenance dredging and operating-port access
Not assessed
Recorded status
APN started the access-channel and inner-roadstead campaign on 20 December 2025; a Jan De Nul post-dredging environmental report covers January 2026 monitoring, while owner acceptance, as-built hydrography and final account remain unverified
commissioning / Last checked
Latest material change / APN published the pre- and post-dredging environmental reports / 3 recorded changes
Confirmed
Zanzibar Marine and Diving Services signed the USD 266,878 supply-and-installation contract on 12 March 2026; the procurement plan's 24 May 2026 completion target has passed without cited installation or acceptance evidence
delivery / Last checked
Latest material change / Planned completion date passed without acceptance evidence / 2 recorded changes
Confirmed
Tuvalu / Global islands / Ports and coastal protection
Not assessed
Recorded status
Hall Civil Contracting signed the USD 62.552 million design-build contract on 21 July 2025; the latest cited mission set August 2027 and January 2028 completion targets for Nanumaga and Nanumea, but no cited source confirms physical mobilisation or current progress
award / Last checked
Latest material change / Hall Civil signed the two-island design-build contract / 2 recorded changes
Confirmed
World Bank contract data records a USD 26.453 million EPC works contract signed with China Civil Engineering Construction Corporation on 27 July 2026; no cited source confirms notice to proceed, mobilisation or physical construction
award / Last checked
Latest material change / CCECC signed the Rumonge Port EPC works contract / 2 recorded changes
Confirmed
Spain / Europe / Piled fishing-quay concrete rehabilitation and metal fender renewal
Not assessed
Recorded status
Cantabria formalized the EUR 2,486,545.15 excluding-VAT works contract with the Cuevas Gestión de Obras-COMSA UTE on 9 July 2026; the signed contract requires a viable setting-out check before the 24-month execution period starts, while the setting-out act, site mobilisation, monthly production and lower-tier appointments remain unpublished
award / Last checked
Latest material change / Works contract formally executed / 4 recorded changes
Confirmed
United States / Americas / Breakwater armour repair, access dredging and nearshore placement
Not assessed
Recorded status
Ahtna Infrastructure & Technologies held the USD 16,037,425 current-obligation contract for Moss Landing Harbor dredging and jetty repair; the US Coast Guard published 2025 field-work windows and USACE published August-September post-dredge surveys, but the 23 January 2026 contract end does not establish final quantity, jetty acceptance, completion or final account
construction / Last checked
Latest material change / Published contract and navigation-notice window ended / 5 recorded changes
Confirmed
Australia / Asia Pacific / Foreshore seawall and rip-rap protection
Not assessed
Recorded status
Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence
construction / Last checked
Latest material change / NSW Planning confirmed construction underway / 4 recorded changes
Confirmed
Mali / Africa / Inland river-port access dredging and sediment clearance
Not assessed
Recorded status
The package was officially launched on 13 February 2025 and a project team inspected progress on 6 March 2025; the latest disclosed procurement plan, dated 13 April 2026, still records the contract only as signed, and no official completion, accepted bathymetry or operating release has been published
construction / Last checked
Latest material change / Latest disclosed procurement plan still records the works contract as signed / 5 recorded changes
Confirmed
Finland / Europe / Ferry-terminal piers, passenger bridges and port-yard renewal
Not assessed
Recorded status
Pier S1 was handed over on 15 June 2026 but will not enter service until March 2027; the joint terminal, passenger bridges and 11-hectare field works remain under construction, while Quay S2 is targeted for 2028
construction / Last checked
Latest material change / Terramare handed Pier S1 over to Port of Turku / 7 recorded changes
Confirmed
India / Asia Pacific / Inland-waterway floating jetties, gangways and passenger facilities
Not assessed
Recorded status
Two lots were signed on 16 August 2024 for Tamlipara, Chinsurah, Metiabruze and Pujali; the June 2026 World Bank ISR says Metiabruze remains under implementation but its results table says all 45 project jetties are complete
construction / Last checked
Latest material change / Latest procurement plan still lists the two-lot package as Signed / 3 recorded changes
Confirmed
Ireland / Europe / Fishery harbour piling, civil works and marine utilities
Not assessed
Recorded status
TED published the EUR 1.2498795 million Sorensen award on 5 August 2026 and records contract conclusion on 22 June; no project-specific mobilisation, commencement or subcontractor notice has been published
award / Last checked
Latest material change / TED published the Sorensen award / 4 recorded changes
Confirmed
France / Europe / Marinas, pontoons and berthing infrastructure
Not assessed
Recorded status
SPAD concluded three separate Grand Large marina works contracts on 30 June 2026 with Eiffage Travaux Maritimes et Fluviaux, Atlantic Marine and Ramery Travaux Publics; each lot carries a 24-month planned period, but no dated notice to proceed or field mobilisation has been located
award / Last checked
Latest material change / The three-lot award notice was published / 3 recorded changes
Confirmed
France / Europe / Ro-Ro berth and island freight access
Not assessed
Recorded status
Métropole Toulon Provence Méditerranée concluded contract 98RL25 with Océlian and TP Spada at EUR 2,104,311.99 on 20 August 2025 after an earlier procedure ended without an award; no dated mobilisation or completion record has been located
award / Last checked
Latest material change / The relaunched contract was concluded / 3 recorded changes
Confirmed
Mskikue'j Enterprises holds the CAD 5.09 million wharf and shore-protection contract through March 2027; the separate 2025 dredging and containment-cell contract reached its stated expiry without a public completion or measured-quantity record
award / Last checked
Latest material change / Mskikue'j received the structural marine award / 4 recorded changes
Confirmed
Advanteering Civil Engineers has completed detailed design and started early off-site construction under DOT413022; on-site work is planned from spring 2026 but no dated mobilisation evidence has been published
construction / Last checked
Latest material change / Owner confirmed design completion and off-site start / 3 recorded changes
Confirmed
Australia / Asia Pacific / Marinas, pontoons and berthing infrastructure
Not assessed
Recorded status
Jetty and Marine Constructions holds one design-and-construct contract covering the Woodman Point western boat ramp and Fremantle Fishing Boat Harbour Jetty 1; Woodman Point field works began under a 27 July 2026 closure, while a dated Fremantle mobilisation record has not been published
construction / Last checked
Latest material change / Woodman Point field work window opened / 3 recorded changes
Confirmed
France / Europe / Coastal protection and dredged-sand reuse
Not assessed
Recorded status
Baggerbedrijf de Boer holds the EUR 1.720365 million replacement contract concluded on 13 January 2025; the planned 31 May 2025 in-service deadline has passed, while physical completion, acceptance and downstream packages remain unverified
award / Last checked
Latest material change / Award result published after contract conclusion / 4 recorded changes
Confirmed
Western Broadside Wharf, adjacent seawall and access-pontoon repairs are underway under two NSW contracts through August and September 2026; the published notices name Polaris Marine Constructions and Clement Marine Constructions but do not disclose their exact package split
construction / Last checked
Latest material change / Clement marine-repair contract published / 3 recorded changes
Confirmed
United States / North America / Port infrastructure
Not assessed
Recorded status
Oceanetics holds the USD 1.378 million Navy task order through 11 September 2026; two reported subawards identify charter support and Ocean Guard buoy supply, while field installation and acceptance remain unverified
award / Last checked
Latest material change / Healy Tibbitts charter agreement reported / 3 recorded changes
Confirmed
Tanzania / Africa / Port berth electrical systems and commissioning
Not assessed
Recorded status
DERM Group signed the USD 20.16 million berth electrical-power works contract in October 2024; the planned June 2026 end has passed without public completion or acceptance evidence
construction / Last checked
Latest material change / World Bank reported electrical installation under way / 3 recorded changes
Confirmed
Oman / Middle East / Small-port commercial activation, maintenance, dredging and berth readiness
Not assessed
Recorded status
A three-year development, management and operation framework was signed with Abu Sultan Enterprises in December 2025; the planned handover for maintenance and simple operations, physical marine works, capital programme and current operating state are not publicly confirmed
planning / Last checked
Latest material change / Guard-room furnishing tender appears after the planned handover window / 5 recorded changes
Confirmed
United States / North America / Breakwater armour repair, access dredging and nearshore placement
Not assessed
Recorded status
Curtin Maritime holds the USD 4.89 million USACE award for breakwater repair and approximately 45,000 yd3 of access dredging; owner and award sources reviewed do not confirm mobilisation or construction progress
award / Last checked
Latest material change / USACE awarded the breakwater repair contract / 2 recorded changes
Confirmed
Australia / Asia Pacific / Recreational harbour, breakwaters, dredging and boat-launch infrastructure
Not assessed
Recorded status
The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works
completed / Last checked
Latest material change / Queensland opened the completed boating facility / 2 recorded changes
Confirmed
Canada / North America / Fishing harbour timber-wharf reconstruction
Not assessed
Recorded status
R.J.G. Construction holds the CAD 3.02 million wharf-reconstruction contract; the stated contract period ended in April 2026, but completion and acceptance are not publicly confirmed
construction / Last checked
Latest material change / The stated federal contract period reached expiry / 2 recorded changes
Confirmed
Jersey / Europe / Ferry-terminal marine works, dredging and demolition
Not assessed
Recorded status
Final design and planning-condition discharge are evidenced; construction was scheduled for autumn 2026, while Stage Two authorization, dredger or piling mobilisation and physical works start remain unpublished
design / Last checked
Latest material change / Ports of Jersey named the Portside delivery team / 3 recorded changes
Confirmed
Oman / Middle East / Fishing-port dredging, breakwater, groyne, quay and reclamation
Not assessed
Recorded status
The Ministry reported 100% completion in May 2026 after an 81% owner update in January; final hydrography, formal acceptance, operating release and most downstream marine packages remain undisclosed
completed / Last checked
Latest material change / Owner-side report states 100% completion / 5 recorded changes
Confirmed
Four-year framework awarded to Boskalis Westminster, Dutch Dredging and Van den Herik; the first mini-competition, call-off, assigned vessel, dredged quantity and acceptance remain unconfirmed
award / Last checked
Latest material change / Award notice appointed three framework suppliers / 3 recorded changes
Confirmed
Lesotho / Africa / Water intake and treatment works
Not assessed
Recorded status
The official LLWDP dashboard currently displays 85% overall progress under a malformed update date; the last fully dated World Bank restructuring paper recorded 65% physical completion after a 24 February 2026 flood compromised the temporary river diversion and cofferdam, delaying intake works
construction / Last checked
Latest material change / Owner dashboard shows a newer but internally inconsistent progress signal / 4 recorded changes
Confirmed
World Bank completion reporting confirms three fish landing stations and two fish markets completed by project close on 28 November 2025; five other sites in the original 10-site package could not start because of land-tenure disputes
completed / Last checked
Latest material change / World Bank completion report confirms five completed assets / 3 recorded changes
Confirmed
Pristim Supply received the USD 1.355m contract on 11 June 2024; KEMFSED recorded the October 2024 construction launch and published a dated active-workfront photograph, but no completion evidence
construction / Last checked
Latest material change / KEMFSED formally launched Kidongo construction / 2 recorded changes
Confirmed
Procost Ideas holds the USD 2.128m contract signed on 11 June 2024; an official November 2024 mission inspected the workfront and reported landing-site works advancing, without a site-specific percentage or completion record
construction / Last checked
Latest material change / World Bank mission inspected the Kilifi Central workfront / 2 recorded changes
Confirmed
Gesken Enterprises holds the USD 1.852m contract signed on 11 June 2024; public sources define a jetty and land-reclamation workfront but do not confirm site-specific mobilisation, completion or acceptance
award / Last checked
Latest material change / Mokowe ESIA defined the jetty and reclamation workfront / 2 recorded changes
Confirmed
Toddy Civil Engineering received the USD 1.174m works contract on 11 June 2024 and KEMFSED recorded the October 2024 groundbreaking; no later completion or acceptance evidence has been published
construction / Last checked
Latest material change / KEMFSED recorded the Kipini groundbreaking / 2 recorded changes
Confirmed
Serka-MSF completed the commercial-terminal fit-out in December 2020; the port is operational, while AIIB's 2025 review says throughput and revenue remain below original forecasts
completed / Last checked
Latest material change / AIIB published an independent post-completion review / 4 recorded changes
Confirmed
Pilitak Enterprises holds the CAD 77.04m construction contract through 7 May 2030; DFO plans construction activity in 2026-27, while current public sources provide no marine mobilisation evidence
construction / Last checked
Latest material change / Pilitak completed the related Clyde River harbour / 3 recorded changes
Confirmed
Jersey / Europe / Marinas, pontoons and berthing infrastructure
Not assessed
Recorded status
Albert Pier's final berthing stage was complete by 6 April 2022 and St Helier Marina's refurbishment by May 2022; Ports of Jersey subsequently confirmed the marina works were on schedule and the combined capacity benefits were in use
completed / Last checked
Latest material change / Ports of Jersey confirmed the combined capacity benefits / 4 recorded changes
Confirmed
China / Asia Pacific / Inland-waterway green-port programme, open-piled bulk and general-cargo berths
Not assessed
Recorded status
Daorenji's main marine structure was reported complete in July 2026 with equipment installation and commissioning next; Songyanghu III moved from 1,556 precast deck panels into field installation in January 2026; no current Phase II construction evidence has been found for Songmu. AIIB still lists the proposed sovereign financing as Proposed
construction / Last checked
Latest material change / Daorenji's main marine structure reached physical completion / 8 recorded changes
Confirmed
France / Europe / Historic rubble-mound breakwater rehabilitation and island-port protection
Not assessed
Recorded status
Contract Z250608F00 was concluded on 2 February 2026 with an Océlian-led five-company group for EUR 19.589919 million; the owner reports that the overall rehabilitation programme continues in 2026, while main-contract mobilisation, placed rock, accepted sections and downstream subcontract awards remain unpublished
award / Last checked
Latest material change / Owner financial report kept the programme active in 2026 / 4 recorded changes
Confirmed
France / Europe / Maintenance dredging and operating-port access
Not assessed
Recorded status
Eight call-off lots were concluded on 12 November 2025 for a four-year maximum framework beginning in 2026; the award chain is confirmed, while the first 2026 call-off, vessel mobilisation, measured quantity and port acceptance remain unpublished
award / Last checked
Latest material change / TED published the eight-lot award result / 4 recorded changes
Confirmed
Croatia / Europe / Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems
Not assessed
Recorded status
Civil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacity
completed / Last checked
Latest material change / Operator documented the terminal as an operating sustainability asset / 7 recorded changes
Confirmed
Poland / Europe / Caisson breakwaters and port access infrastructure
Not assessed
Recorded status
The May 2026 building permit has moved the design-build contract into principal in-water works; the first reinforced-concrete caisson was launched and towed toward its placement position in July 2026, with the remaining 48 caissons and breakwater systems still to be delivered
construction / Last checked
Latest material change / First reinforced-concrete caisson entered the waterborne installation sequence / 4 recorded changes
Confirmed
Morocco / Africa / Multipurpose berth extension, block quay, mooring dolphin, access bridge and terminal equipment modernisation
Not assessed
Recorded status
Marsa Maroc says the berth-front extension was launched and remained part of its active 2025 investment programme. Execution-design evidence identifies two quay extensions and a mooring dolphin; no owner acceptance or completed operating release has been published
construction / Last checked
Latest material change / Execution-design chain became publicly attributable / 3 recorded changes
Confirmed
Morocco / Africa / Brownfield quay strengthening, retaining structure, micropiles, scour protection and capital dredging
Not assessed
Recorded status
Works started on 1 October 2024. Marsa Maroc reported a first 230-metre section commissioned at -12 m, while the published delivery programme continues toward 530 metres of deepened quay plus transition zones by 2028; the civil-works award is confirmed but the contractor remains publicly unnamed
construction / Last checked
Latest material change / First 230-metre quay section entered service / 3 recorded changes
Confirmed
Georgia / Europe / Container berth rehabilitation, dredging, quay-top renewal and terminal equipment
Not assessed
Recorded status
EBRD lists Phase 1 as Completed, and a TRACECA technical record says Berth 14 was rehabilitated in 2009 for 1,000-TEU feeder vessels; the exact acceptance date, as-built dredging quantity and depth, delivery contractor and final account remain publicly unresolved
completed / Last checked
Latest material change / A.P. Moller-Maersk acquired Poti Sea Port Corporation / 2 recorded changes
Confirmed
Caribbean Netherlands / Americas / Hurricane-resilient harbor, breakwater, dredging, quay and marina works
Not assessed
Recorded status
Public Entity Saba reported steady construction progress on 10 May 2026, including breakwater works and Xbloc arrivals, with additional units being produced in Sint Eustatius. Dredging and excavation were active in March 2026, but marine completion, harbor handover, Fort Bay close-out and operational opening remain unconfirmed.
construction / Last checked
Latest material change / Owner confirmed active breakwater and Xbloc delivery / 3 recorded changes
Confirmed
Norway / Europe / Deep-water quay, fairway dredging, contaminated-sediment containment and navigation works
Not assessed
Recorded status
Kystverket reported the Langneset quay in its finishing phase on 29 June 2026, with concrete works nearing completion and technical installations scheduled through summer and autumn; completion and an official opening are planned for autumn 2026, but handover, acceptance and operation remain unconfirmed
construction / Last checked
Latest material change / Kystverket placed the quay in its finishing phase / 3 recorded changes
Confirmed
Romania / Europe / Inland-port quay, dredging, basin infill and intermodal berth works
Not assessed
Recorded status
TED published a further contract modification on 27 May 2026, extending the recorded execution duration by 4 months and 23 days and reducing the stated contract value by RON 1,270.26; the latest owner progress figure located is 62.04% at 30 June 2025, and no completion or acceptance record has been published
construction / Last checked
Latest material change / Latest TED notice extended the recorded execution duration again / 3 recorded changes
Confirmed
Malta / Europe / Fishing-port fairway dredging and beneficial reuse
Not assessed
Recorded status
Transport Malta described the Marsaxlokk works as ongoing on 26 June 2026; the original navigation notice ran to 31 July, but no public final hydrographic survey, accepted quantity, completion certificate or final account was located by 2 August
construction / Last checked
Latest material change / Transport Malta still described the dredging as ongoing / 3 recorded changes
Confirmed
France / Europe / Ferry-terminal marine works, dredging and demolition
Not assessed
Recorded status
Région Bretagne reported one of the two old lock-guide structures under demolition on 1 April 2026 after the 270-tonne Ro-Ro ramp was removed in December 2025; the new reinforced-concrete guide caissons and maintenance dredging remain inside the two-year Lot 2 mission, with no owner acceptance published
construction / Last checked
Latest material change / Owner documented active lock-guide demolition / 3 recorded changes
Confirmed
Iceland / Europe / Maintenance dredging and operating-port access
Not assessed
Recorded status
Jan De Nul confirms that trailing suction hopper dredger Tristão da Cunha deepened the Höfn access channel between January and February 2025; the measured quantity and post-dredge acceptance remain unpublished, and a separate Boskalis contract now covers 2026-2028
completed / Last checked
Latest material change / Boskalis signed a separate three-year successor contract / 3 recorded changes
Confirmed
Ireland / Europe / Fishery harbour berthing, marine piling and shore power
Not assessed
Recorded status
Sorensen reported all 24 dolphin piles installed in August 2025; the government project page published the following month still described the works as ongoing with substantial completion due in Q3 2025, and DAFM has not published a later handover record
construction / Last checked
Latest material change / Government project page kept the works open / 4 recorded changes
Confirmed
Porto Ingles marine works were inaugurated on 7 September 2022 and later received a final price-revision authorization; Palmeira's landside package was awarded to GRINER / Armando Cunha Cabo Verde in July 2024, with no public completion or acceptance record identified by 2 August 2026
construction / Last checked
Latest material change / Palmeira supervision consortium and value became public / 5 recorded changes
Confirmed
Single-party framework active with Murphy International; Berth 29 was handed over in 2024, Murphy reports 21 call-offs delivered during 2025, and owner confirmation of the contractor-stated July 2026 completion target for Berths 30/31 and McCairns Yard has not been identified
construction / Last checked
Latest material change / Late award notice exposed the framework ceiling and contractor / 5 recorded changes
Confirmed
Kystverket's latest dated update records blasting complete and about 26,000 solid cubic metres of clean material dredged by 21 April 2026; the owner page says work remains in progress toward December 2026 completion
construction / Last checked
Latest material change / Blasting completed and clean dredging reached 26,000 fm³ / 3 recorded changes
Confirmed
The construction contract started on 24 September 2025 and Marine Notice 23/2026 records Ward & Burke commencing the two-year marine works; no later completed work package has been published
construction / Last checked
Latest material change / Marine Notice records the works commencing / 3 recorded changes
Confirmed
Quay construction and the four-hectare yard remain the latest official delivery state; handover to operator AMLP was targeted for the second half of 2026 but has not been published
construction / Last checked
Latest material change / The port logged an advanced quay workfront / 3 recorded changes
Confirmed
Denmark / Germany / Europe / Immersed tunnels and marine crossings
Not assessed
Recorded status
Third tunnel element immersed and connected on 1 August 2026; protection, serial immersion, systems integration, and a two-stage road-then-rail opening remain active
construction / Last checked
Latest material change / Third standard element immersed and connected / 6 recorded changes
Confirmed
South Korea / Asia Pacific / Deep-water ports and automated container terminals
Not assessed
Recorded status
BPA completed the 23-caisson substructure in August 2024 and is advancing superstructure and automated-equipment packages toward an October 2027 completion and second-half 2027 opening target
construction / Last checked
Latest material change / BPA held a construction-site emergency drill / 5 recorded changes
Confirmed
Greece / Europe / Container terminal expansion, quay construction and dredging
Not assessed
Recorded status
ThPA signed the EUR 195.6 million METKA-TEKAL construction contract in November 2025 and installed the first of 21 quay caissons in July 2026; the second caisson was under construction at publication
construction / Last checked
Latest material change / The first of 21 caissons was installed / 3 recorded changes
Confirmed
Norway / Europe / Multipurpose quays, dredging and carbon-logistics infrastructure
Not assessed
Recorded status
Repstad Anlegg began works in August 2025; demolition, dredging and subsea blasting preceded a 99-pile quay-foundation programme scheduled from March to July 2026
construction / Last checked
Latest material change / The quay moved into its 99-pile foundation stage / 3 recorded changes
Confirmed
United Kingdom / Europe / Deep-water ports and automated container terminals
Not assessed
Recorded status
Port of London Authority reported the 430-metre Berth 5 quay extension complete by 1 August 2026 while further retaining-wall piling continued toward the Berth 6 interface; the separately contracted ten-module automated yard remains on a contractor-reported programme to March 2027
construction / Last checked
Latest material change / The 430-metre Berth 5 extension was reported complete / 3 recorded changes
Confirmed
Malaysia / Asia Pacific / Deep-water ports and container terminals
Not assessed
Recorded status
Malaysia Marine Department notices documented Package 1 and Package 2 work vessels on site from January 2026; PTP is delivering a 360-metre berth, dredging, reclamation, yard works and four quay cranes toward commissioning by 2028
construction / Last checked
Latest material change / PTP linked Berth Zero to its 16 million TEU capacity target / 3 recorded changes
Confirmed
Republic of the Congo / Africa / Deep-water ports and container terminals
Not assessed
Recorded status
AD Ports Group awarded two marine and topside contracts to the MAR Contracting-MBTP joint venture and a crane contract to ZPMC on 18 May 2026; the 420-metre terminal is expected to be built over approximately two years
award / Last checked
Latest material change / Three terminal contracts were awarded / 3 recorded changes
Confirmed
Republic of the Congo / Africa / Deep-water ports, dredging and multipurpose terminals
Not assessed
Recorded status
Congo Terminal reported 400 metres of the planned 750-metre quay complete by 6 July 2026 after all 558 steel piles were driven; dredging and electric-terminal integration remain active toward the 2027 delivery target
construction / Last checked
Latest material change / The owner positioned the project as an all-electric terminal platform / 4 recorded changes
Confirmed
Ghana / Africa / Deep-water ports and container terminals
Not assessed
Recorded status
Eiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021
completed / Last checked
Latest material change / Eiffage completed the 27-hectare platform / 4 recorded changes
Confirmed
Sri Lanka / Asia Pacific / Deep-water ports and automated container terminals
Not assessed
Recorded status
Phase 1 has operated since April 2025 and handled one million TEU in its first year; the 1,400-metre quay was complete by March 2026 while Phase 2 crane deployment and full-terminal construction continue
construction / Last checked
Latest material change / Phase 2 crane deployment began / 4 recorded changes
Confirmed
Colombia / Americas / Deep-water ports, dredging and multipurpose terminals
Not assessed
Recorded status
Commercial operations began on 5 February 2026 after four controlled vessel trials; the operator's current port-status ledger shows repeat container, breakbulk and refrigerated calls through July 2026
completed / Last checked
Latest material change / The live port ledger showed repeat commercial services / 4 recorded changes
Confirmed
Chile / Americas / Deep-water ports, dredging and reclamation
Not assessed
Recorded status
Environmental approval was granted on 26 May 2026; six bidders or consortia are prequalified for the common marine-works tender, but no construction award has been announced
tender / Last checked
Latest material change / CAF and Puerto San Antonio signed an initial USD 50 million credit / 4 recorded changes
Confirmed
Poland / Europe / Deep-water ports and container terminals
Not assessed
Recorded status
Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation
completed / Last checked
Latest material change / Baltic Hub released T3 yard line 7 for operations / 4 recorded changes
Confirmed
Saudi Arabia / Middle East / Deep-water ports and energy terminals
Not assessed
Recorded status
Overall complex above 90% complete; energization and commissioning started, with jetty VTS radar commissioned but first ammonia transfer not confirmed
commissioning / Last checked
Latest material change / Air Products reported final completion and energization-led commissioning / 5 recorded changes
Confirmed
TOA's Package 1 is in construction; KPA reports confirm quay and trestle foundation dredging, while channel, basin, jacket installation and accepted quantities remain open
construction / Last checked
Latest material change / KPA published the first DK1 monthly monitoring set and current field gallery / 3 recorded changes
Confirmed
DPA is assessing berth-wide repair, strengthening or replacement for an intended EPC package; no expanded-consultant award, EPC tender or works contractor is verified
design / Last checked
Latest material change / DPA reopened the programme as a berth-wide structural and EPC consultancy / 3 recorded changes
Confirmed
Technical audit and detailed engineering are commissioned through 31 December 2027; no construction tender, award or works contractor is verified
design / Last checked
Latest material change / IIT Madras listed the 19A audit and detailed-engineering assignment as ongoing / 2 recorded changes
Confirmed
NZD 8 million of government co-funding confirmed; designer, shipyard, build contract and first port assignment not disclosed
planning / Last checked
Latest material change / Government placed the barge within its six coastal-shipping investments / 2 recorded changes
Confirmed
Prepare EIS; the current concept fixes a 2.4 km intake tunnel and existing-outfall connection, but no construction decision or funding is public
planning / Last checked
Latest material change / The Commonwealth referral described the offshore intake and existing-outfall connection / 3 recorded changes
Confirmed
Three sub-seabed utility lines remain under an active harbour construction notice; the CDO and desalination pipe-pull notices have closed
construction / Last checked
Latest material change / The general construction notice remains active after two pipe-pull notices closed / 4 recorded changes
Confirmed
UAE / Middle East / Deep-water ports and energy terminals
Not assessed
Recorded status
Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published
construction / Last checked
Latest material change / ADNOC kept the 2028 commercial target and reported 90% of capacity committed / 3 recorded changes
Confirmed
Egypt / Africa / Deep-water ports and container terminals
Not assessed
Recorded status
Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity
commissioning / Last checked
Latest material change / Damietta CT2 entered commercial operation / 3 recorded changes
Confirmed
Vietnam / Asia Pacific / Deep-water ports and container terminals
Not assessed
Recorded status
Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced
approval / Last checked
Latest material change / Ho Chi Minh City selected the investor consortium / 3 recorded changes
Confirmed
Under construction; Nama PWP targets commercial operation in Q1 2027
construction / Last checked
Latest material change / GS Inima reported four million work hours without a lost-time injury / 4 recorded changes
Confirmed
Solomon Islands / Global islands / Marine utilities
Not assessed
Recorded status
ADB still lists bid-document preparation for the new marine works; Solomon Water's public plan carries competing three-outfall, two-new-outfall and NRH/Ranadi package definitions, with no works award disclosed
tender / Last checked
Latest material change / ADB still lists the new outfall works at bid-document stage / 4 recorded changes
Confirmed
Callan Marine dredging has reached the Gulf Intracoastal Waterway junction; the Navigation District says the next work front is the harbor and turning basin
construction / Last checked
Latest material change / Dredging reached the GIWW junction / 3 recorded changes
Confirmed
ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items
construction / Last checked
Latest material change / ADB grant data still shows an active project / 4 recorded changes
Confirmed
Phase 1-1 is completed and partly operating; Package 5 car-terminal and Package 6 container-terminal works remained active through June 2025; Package 7 construction lacks a current owner or contractor mobilisation date
construction / Last checked
Latest material change / JICA monitoring kept both expansion packages in active marine construction / 8 recorded changes
Confirmed
Two bids were opened for Hawar's separate offshore intake and outfall EPC package on 25 December 2025; EWA still lists the wider desalination scheme as a future project and no award is published
tender / Last checked
Latest material change / EWA retained Hawar SWRO in its future-project portfolio / 4 recorded changes
Confirmed
The Government of India reports Phase VI complete and Kamarajar operating at 18.0 metres draft; the post-dredge survey sheet and a first fully laden Capesize call are not published
completed / Last checked
Latest material change / Government announced Phase VI complete / 6 recorded changes
Confirmed
Marine construction is active; the 2026 harbour notice keeps the buoyed work zone in place through January 2027, while berth acceptance and service release remain open
construction / Last checked
Latest material change / TED published the contract result / 4 recorded changes
Confirmed
Sharakat is qualifying developers across five planned seawater reverse-osmosis projects; no individual RFP, award or project-specific marine package is public
prequalification / Last checked
Latest material change / Current portfolio confirms the five-project capacity list / 2 recorded changes
Confirmed
The West Point revetment has an approved ESIA and March 2026 environmental permit; construction award, notice to proceed and physical start are not established
approval / Last checked
Latest material change / Liberia issued the West Point environmental permit / 2 recorded changes
Confirmed
Nearshore outfall and Contract 1A permanent works were substantially completed on 14 August 2023; wider DTSS2 and Tuas WRP completion, commissioning and discharge acceptance remain open
construction / Last checked
Latest material change / PUB current programme retains phased commissioning from 2027 / 6 recorded changes
Confirmed
Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed
construction / Last checked
Latest material change / World Bank paper reset the completion boundary and sought additional credit / 5 recorded changes
Confirmed
AIIB loan approved; three terminal programmes active on separate schedules
construction / Last checked
Latest material change / ICTSI assigned the corporate loan to three Philippine terminal lanes / 10 recorded changes
Confirmed
Project agreements, the L&T-Lantania EPC award and December 2025 financial close are evidenced, and ACWA's 3 March 2026 year-end report classifies the full 300,000 m3/day capacity as under construction; offshore mobilisation, installed intake or outfall geometry, first water and accepted production are not dated
construction / Last checked
Latest material change / ACWA classified the full design capacity as under construction / 4 recorded changes
Confirmed
Core marine assets built; terminal, tunnel, and commercial-operating interfaces remain under verification
construction / Last checked
Latest material change / The 62 km connecting road received GCPI's final Performance Certificate / 8 recorded changes
Confirmed
construction / Last checked
Latest material change / Ashghal reported 98% with remaining works and readiness planning still open / 5 recorded changes
Confirmed
101,642 estimated unique leads across 41 official channels; 3,922 multilateral project families are directly searchable; 250 leads already resolve to public project records.
The tracker follows marine and water infrastructure from planning and procurement through award, construction,
commissioning and completion, with named parties and package scope shown where sources support them.
Last checked gives the most recent source review date. The CSV provides 34 fields per public project,
including sector, delivery phase, current status, named parties, contract evidence, material developments
and every source date and URL in the record.