Identifiable marine works, with scope and evidence attached.
The public tracker follows named projects from finance and procurement through award, mobilisation, and delivery.
Records without a project-specific owner, location, marine scope, and source basis stay outside the public dataset.
Evidence reviewed 109 public projects108 with change history6 regions13 marine works segments
IFB W912DS26BA027 open; 237,945 CY in the base dredging CLINs; bids due 31 July 2026; no award or mobilisation recorded / tender / Evidence reviewed
Latest material change / USACE issued the sealed-bid solicitation / 2 recorded changes
Confirmed
Prepare EIS; the current concept fixes a 2.4 km intake tunnel and existing-outfall connection, but no construction decision or funding is public / planning / Evidence reviewed
Latest material change / The Commonwealth referral described the offshore intake and existing-outfall connection / 3 recorded changes
Confirmed
World Bank's revised procurement plan marks MOI-WK2-13 under implementation; contractor, contract value, notice to proceed and site mobilisation remain publicly unconfirmed / award / Evidence reviewed
Latest material change / The Ministry sought a dedicated construction-supervision team / 3 recorded changes
Confirmed
Sand reclamation is active behind the new quay line; phased terminal delivery runs through 2028 / construction / Evidence reviewed
Latest material change / Meuse River began active reclamation work / 3 recorded changes
Confirmed
DEME holds the transport and installation contract for 69 monopile foundations; offshore mobilisation has not been announced / award / Evidence reviewed
Latest material change / DEME won the 69-foundation transport and installation package / 3 recorded changes
Confirmed
Three sub-seabed utility lines remain under an active harbour construction notice; the CDO and desalination pipe-pull notices have closed / construction / Evidence reviewed
Latest material change / The general construction notice remains active after two pipe-pull notices closed / 4 recorded changes
Confirmed
EPC agreement signed on 7 May 2026; no notice to proceed or marine mobilisation is published / award / Evidence reviewed
Latest material change / EtihadWE signed the AED 1.046 billion EPC agreement / 2 recorded changes
Confirmed
EPC performance test completed on 19 February 2026; SWPC commercial-operation confirmation remains unpublished / commissioning / Evidence reviewed
Latest material change / The EPC consortium completed the performance test / 2 recorded changes
Confirmed
The port authority reports 69% physical progress and 72% overall progress, while its published 2021-2024 delivery period is no longer current / construction / Evidence reviewed
Latest material change / PAC continued the owner-representative assignment / 2 recorded changes
Confirmed
UAE / Middle East / Deep-water ports and energy terminals
Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published / construction / Evidence reviewed
Latest material change / ADNOC kept the 2028 commercial target and reported 90% of capacity committed / 3 recorded changes
Confirmed
Egypt / Africa / Deep-water ports and container terminals
Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity / commissioning / Evidence reviewed
Latest material change / Damietta CT2 entered commercial operation / 3 recorded changes
Confirmed
Vietnam / Asia Pacific / Deep-water ports and container terminals
Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced / approval / Evidence reviewed
Latest material change / Ho Chi Minh City selected the investor consortium / 3 recorded changes
Confirmed
Arm and head rebuilt; formal completion and owner acceptance not published / construction / Evidence reviewed
Latest material change / Fisheries reported operational-readiness use at the complex / 6 recorded changes
Confirmed
Under construction; Nama PWP targets commercial operation in Q1 2027 / construction / Evidence reviewed
Latest material change / GS Inima reported four million work hours without a lost-time injury / 4 recorded changes
Confirmed
PIDG capital committed; financial close and construction start still to be confirmed / financing / Evidence reviewed
Latest material change / PIDG joined the capital stack and described a path to financial close / 4 recorded changes
Confirmed
Owner reports Phase 2 reclamation at 79.5% as of December 2025; its March 2026 target for handing six completed berths to PSA remains unverified, while current marine notices confirm active delivery / delivery / Evidence reviewed
Latest material change / MPA extended Phase 2 bulk-carrier operations through December 2026 / 9 recorded changes
Confirmed
World Bank project is Active and Board Approved; the April 2026 procurement plan omits the Itajaí-Mirim main works package / approval / Evidence reviewed
Latest material change / The World Bank project reached Board Approved status / 3 recorded changes
Confirmed
Plant remained under construction in February 2026; commissioning was expected later in 2026, while final marine handover evidence remains unpublished / construction / Evidence reviewed
Latest material change / The plant remained under construction in its commissioning year / 3 recorded changes
Confirmed
Solomon Islands / Global islands / Marine utilities
ADB still lists bid-document preparation for the new marine works; Solomon Water's public plan carries competing three-outfall, two-new-outfall and NRH/Ranadi package definitions, with no works award disclosed / tender / Evidence reviewed
Latest material change / ADB still lists the new outfall works at bid-document stage / 4 recorded changes
Confirmed
ACWA lists commercial operations from Q1 2024; the 200 MIGD plant is operating, while final as-built intake and outfall geometry is not publicly disclosed / completed / Evidence reviewed
Latest material change / ACWA places commercial operations in Q1 2024 / 4 recorded changes
Confirmed
Three preliminary bids opened for MFP-364.003; evaluation and award remain pending / evaluation / Evidence reviewed
Latest material change / Three bids set the preliminary commercial range / 3 recorded changes
Confirmed
Callan Marine dredging has reached the Gulf Intracoastal Waterway junction; the Navigation District says the next work front is the harbor and turning basin / construction / Evidence reviewed
Latest material change / Dredging reached the GIWW junction / 3 recorded changes
Confirmed
IFB amendment 0007 posted 16 July 2026; bids closed 17 July; no award or notice to proceed posted / tender / Evidence reviewed
Latest material change / The amended IFB closed for bids / 3 recorded changes
Confirmed
Updated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recorded / tender / Evidence reviewed
Latest material change / USACE issued the updated full RFP / 3 recorded changes
Confirmed
Norfolk Island / Global islands / Dredging and waterways
Rock revetment contractor appointed; the separate channel-dredging and pier-repair package was released to tender on 14 May 2026 / tender / Evidence reviewed
Latest material change / Revetment contractor appointed and dredging tender released / 3 recorded changes
Confirmed
IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started / design / Evidence reviewed
Latest material change / Latest implementation report kept physical works at pre-start / 3 recorded changes
Confirmed
Jan De Nul contract signed on 12 June 2026; official mobilisation, production and acceptance evidence remain ahead / award / Evidence reviewed
Latest material change / APS signed the 16-metre deepening contract / 2 recorded changes
Confirmed
Fifteen-year charter awarded on 30 June 2026; construction, delivery, port acceptance and service commencement remain ahead / award / Evidence reviewed
Latest material change / NMPA issued the 15-year charter work order / 2 recorded changes
Confirmed
Owner-defined cutter-suction campaign scheduled from July to October 2026; contractor and mobilisation remain unconfirmed / approval / Evidence reviewed
Latest material change / MSQ published the quantified 2026 delivery plan / 2 recorded changes
Confirmed
ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items / construction / Evidence reviewed
Latest material change / ADB grant data still shows an active project / 4 recorded changes
Confirmed
Phase 1-1 is completed and partly operating; Package 5 car-terminal and Package 6 container-terminal works remained active through June 2025; Package 7 construction lacks a current owner or contractor mobilisation date / construction / Evidence reviewed
Latest material change / JICA monitoring kept both expansion packages in active marine construction / 8 recorded changes
Confirmed
Marine licence MLA/2026/00178 remains submitted and open for consultation; the principal-contractor participation stage closed on 6 February 2026 and no award notice is published in the reviewed procurement family / approval / Evidence reviewed
Latest material change / MMO register kept the application open for consultation / 4 recorded changes
Confirmed
Two bids were opened for Hawar's separate offshore intake and outfall EPC package on 25 December 2025; EWA still lists the wider desalination scheme as a future project and no award is published / tender / Evidence reviewed
Latest material change / EWA retained Hawar SWRO in its future-project portfolio / 4 recorded changes
Confirmed
Compras MX lists the invitation as current, with proposal opening deferred to 24 July 2026 and the ruling moved to 29 July; no award is published / tender / Evidence reviewed
Latest material change / Compras MX deferred the opening and ruling / 5 recorded changes
Confirmed
The Government of India reports Phase VI complete and Kamarajar operating at 18.0 metres draft; the post-dredge survey sheet and a first fully laden Capesize call are not published / completed / Evidence reviewed
Latest material change / Government announced Phase VI complete / 6 recorded changes
Confirmed
Nigeria / Africa / Deep-water ports and container terminals
MSC signed a 45-year sub-concession and finalized the ITB/DEME EPC on 11 March 2026; the reviewed project sources do not record mobilisation / award / Evidence reviewed
Latest material change / MSC signed the sub-concession and finalized the EPC / 3 recorded changes
Confirmed
AIFFP and Ports Authority Tonga confirmed all marine and civil works complete and operational on 5 November 2025 / completed / Evidence reviewed
Latest material change / All marine and civil works declared complete and operational / 3 recorded changes
Confirmed
World Bank and AfDB implementation records confirm works are under way; the contractor's current target is 11 August 2027 / construction / Evidence reviewed
Latest material change / AfDB recorded Boingoma works in progress / 3 recorded changes
Confirmed
The open tender closed on 16 March 2026; no award, work order or mobilisation is identified / tender / Evidence reviewed
Latest material change / The published bid window closed / 2 recorded changes
Confirmed
Marine construction is active; the 2026 harbour notice keeps the buoyed work zone in place through January 2027, while berth acceptance and service release remain open / construction / Evidence reviewed
Latest material change / TED published the contract result / 4 recorded changes
Confirmed
Construction was released on 22 April 2026 and the site milestone was held on 8 July; offshore intake and outfall execution remains unverified / construction / Evidence reviewed
Latest material change / The first brick marked the site start / 5 recorded changes
Confirmed
TerraMarine is preferred proponent; contract negotiations and development work precede any target-price design-build agreement, financial close or mobilisation / design / Evidence reviewed
Latest material change / Canada referred the Port of Vancouver Gateway Strategy to the Major Projects Office / 4 recorded changes
Confirmed
Sharakat is qualifying developers across five planned seawater reverse-osmosis projects; no individual RFP, award or project-specific marine package is public / prequalification / Evidence reviewed
Latest material change / Current portfolio confirms the five-project capacity list / 2 recorded changes
Confirmed
USACE scheduled MURDEN to work through May 2026; measured production and completion remain unpublished / construction / Evidence reviewed
Latest material change / USACE published the May dredging and bypass plan / 3 recorded changes
Confirmed
PQQ closed on 1 May 2026; no shortlist, ITT or award notice is present in the reviewed public chain / prequalification / Evidence reviewed
Latest material change / Ardersier opened prequalification for the Phase 2 dredging package / 3 recorded changes
Confirmed
Curtin Maritime's DB Avalon was operating in the Patapsco River on 16 June 2026 / construction / Evidence reviewed
Latest material change / DB Avalon was operating in the Patapsco River / 3 recorded changes
Confirmed
Mechanical dredging began in late May 2026 and is scheduled to continue through August / construction / Evidence reviewed
Latest material change / USACE recorded mechanical dredging in the channel / 3 recorded changes
Confirmed
USACE reports the first phase nearing completion and a 450-foot second phase continuing through November 2026 / construction / Evidence reviewed
Latest material change / USACE put the remaining 450 feet into a second repair phase / 3 recorded changes
Confirmed
Four IFC advisory procurements define transaction preparation; the 100 MLD PPP, marine site, concession and works remain unawarded / planning / Evidence reviewed
Latest material change / Odisha's PPP register lists the project as Proposed / 5 recorded changes
Confirmed
Two dredging packages completed on 27 February 2026; clay cleanup followed in April and staging was cleared in May / completed / Evidence reviewed
Latest material change / Ahtna cleared the final staging area / 7 recorded changes
Confirmed
USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028 / award / Evidence reviewed
Latest material change / USACE awarded the 732-foot second repair phase / 3 recorded changes
Confirmed
USD 2.3 million Ryba award confirmed; field start scheduled from 18 July 2026 / award / Evidence reviewed
Latest material change / USACE published the 2026 start plan and two-route material split / 3 recorded changes
Confirmed
The West Point revetment has an approved ESIA and March 2026 environmental permit; construction award, notice to proceed and physical start are not established / approval / Evidence reviewed
Latest material change / Liberia issued the West Point environmental permit / 2 recorded changes
Confirmed
Marshall Islands / Global islands / Coastal infrastructure
Marine logistics and construction are established; completion and owner acceptance are not confirmed, while the latest programme update forecasts completion by the end of 2026 / construction / Evidence reviewed
Latest material change / The first armourstone shipment reached the Marshall Islands / 3 recorded changes
Confirmed
Award decision published to Boskalis Westminster; contract signature and start not evidenced / award / Evidence reviewed
Latest material change / The Ministry of Defence published its Boskalis award decision / 4 recorded changes
Confirmed
Outer harbor dredging and ERDC placement monitoring active / construction / Evidence reviewed
Latest material change / USACE announced the 2026 dredging and research campaign / 2 recorded changes
Confirmed
ResIP 1 in finalisation; country work fronts and closing dates remain separate / construction / Evidence reviewed
Latest material change / Senegal sought more time for the Gorée works / 4 recorded changes
Confirmed
Initial state dredging phase completed and a separate private berth stage is active; the federal 40 ha north-platform construction-dredging tender was declared void on 8 July 2026, with no rebid confirmed / tender / Evidence reviewed
Latest material change / Official project database revised the platform package to void / 8 recorded changes
Confirmed
Nearshore outfall and Contract 1A permanent works were substantially completed on 14 August 2023; wider DTSS2 and Tuas WRP completion, commissioning and discharge acceptance remain open / construction / Evidence reviewed
Latest material change / PUB current programme retains phased commissioning from 2027 / 6 recorded changes
Confirmed
ADB records the three-outfall civil package completed in August 2018, testing and commissioning in Q2 2019, the wider project physically completed on 31 December 2019, and the financing operation closed / completed / Evidence reviewed
Latest material change / Independent validation rated the completed project less than successful / 5 recorded changes
Confirmed
Democratic Republic of the Congo / Africa / Dredging
Easydredge 2700XL building contract signed; no yard, trial, delivery, acceptance, or Congo River deployment milestone published / delivery / Evidence reviewed
Latest material change / CVM and Royal IHC signed the customised 2700XL building contract / 3 recorded changes
Confirmed
São Tomé and Príncipe / Africa / Marine infrastructure
AfDB financing signed and three site-level safeguard packages disclosed; design-supervision and works awards remain unverified / financing / Evidence reviewed
Latest material change / AfDB financing agreements were signed / 5 recorded changes
Confirmed
DFBOT proposals due 17 August 2026 / tender / Evidence reviewed
Latest material change / Mandatory site-visit window was scheduled / 5 recorded changes
Confirmed
Concession signed; 1 August operating transition remains scheduled, with the 13.3-metre baseline still controlling / mobilisation / Evidence reviewed
Latest material change / The concessionaire portal exposes the operating baseline and unresolved VTS schedule / 6 recorded changes
Confirmed
Tender E.47/2026 remains open; bids due 23 July 2026 after one corrigendum / tender / Evidence reviewed
Latest material change / Mumbai Port opened the 2026-29 three-cycle tender / 5 recorded changes
Confirmed
USD 11.7 million award confirmed; no 2026 field execution is documented / award / Evidence reviewed
Latest material change / DMYLES received the two-window maintenance award / 6 recorded changes
Confirmed
Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed / award / Evidence reviewed
Latest material change / DEME received the capital-deepening package / 7 recorded changes
Confirmed
Named and launched on 3 October 2025; latest reviewed owner update still described construction as ongoing on 5 March 2026; delivery and service entry remain unconfirmed / delivery / Evidence reviewed
Latest material change / Boskalis still reported SEAWAY under construction / 4 recorded changes
Confirmed
Great Lakes Dredge & Dock's USD 19.5 million nourishment contract is in construction; dredge mobilisation is evidenced, but placed volume, accepted beach template and completion remain open / construction / Evidence reviewed
Latest material change / Dredge Illinois reached the mobilisation gate / 5 recorded changes
Confirmed
Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access / construction / Evidence reviewed
Latest material change / Owner scheduled a three-day quay-wall sheet-pile delivery window / 5 recorded changes
Confirmed
Construction contract awarded; site preparations commenced / construction / Evidence reviewed
Latest material change / Maraen awarded the construction contract and began site preparations / 4 recorded changes
Confirmed
Ongoing at programme level; March 2025 remains the latest quantitative Phase I physical-progress baseline / construction / Evidence reviewed
Latest material change / UNDP presented a climate-resilience engineering study for the port / 7 recorded changes
Confirmed
USD 3.587 million award; July 2026 start expected but mobilisation remains unconfirmed / award / Evidence reviewed
Latest material change / USACE set a July start expectation and public navigation-safety briefing / 4 recorded changes
Confirmed
Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed / construction / Evidence reviewed
Latest material change / World Bank paper reset the completion boundary and sought additional credit / 5 recorded changes
Confirmed
AED 84 million Newcastlemax upgrade agreed; design, package awards and delivery remain open / award / Evidence reviewed
Latest material change / AD Ports Group and EGA agreed an AED 84 million Newcastlemax berth upgrade / 4 recorded changes
Confirmed
Market survey closed; potential public procurement anticipated before end-2026 / planning / Evidence reviewed
Latest material change / Market-survey response window reached its stated close / 6 recorded changes
Confirmed
AIIB loan approved; three terminal programmes active on separate schedules / construction / Evidence reviewed
Latest material change / ICTSI assigned the corporate loan to three Philippine terminal lanes / 10 recorded changes
Confirmed
Operations active; modernisation equipment mobilising / early works / Evidence reviewed
Latest material change / First of three mobile harbour cranes arrived / 4 recorded changes
Reported
PPA and EPC signed; cooling-water review and existing-plant tie-ins exposed, marine route unconfirmed / award / Evidence reviewed
Latest material change / Lead developer recruited for BOP execution and existing-plant tie-ins / 8 recorded changes
Confirmed
Main quay works under construction after the Q4 2024 start / construction / Evidence reviewed
Latest material change / Signed annual accounts confirmed a Q4 2024 physical start / 6 recorded changes
Confirmed
IDA financing signed; marine packages are planned, under review, pending, cancelled, or absent from the reviewed plan / approval / Evidence reviewed
Latest material change / AIIB published the US$100 million co-financing as proposed / 7 recorded changes
Confirmed
Concession signed; operating transfer complete and August maintenance mobilisation remains to be evidenced / mobilisation / Evidence reviewed
Latest material change / Argentina signed the 25-year concession contract / 8 recorded changes
Confirmed
A$50 million dredging contract awarded; federal sea-dumping application remains an open evidence gate before September mobilisation / award / Evidence reviewed
Latest material change / Pilbara Ports awarded the A$50 million dredging contract / 7 recorded changes
Confirmed
Phase A tug quay complete; Phase B inland-shipping quay started; Phase C dredging remains a post-2028 package / construction / Evidence reviewed
Latest material change / Phase A completed and Phase B field construction started / 8 recorded changes
Confirmed
First desalinated water reached Radomiro Tomic during progressive commissioning; rated service and commercial operation remain open / commissioning / Evidence reviewed
Latest material change / Desalinated water reached the Radomiro Tomic reservoir / 10 recorded changes
Confirmed
Dredging contract signed for 2027 start / award / Evidence reviewed
Latest material change / The remaining dredging contract was signed / 8 recorded changes
Confirmed
India / Asia Pacific / Deep-water ports, dredging and reclamation
The approximately 200-hectare nearshore reclamation and shore-protection EPC package is awarded; as of 15 July 2026, the owner tender page lists the offshore dredging, reclamation and protection-bund HAM package closing on 17 July and the Daman marine-sand investigation closing on 15 July, while no award or AOC is published for either package or for the 10.14-kilometre offshore breakwater / tender / Evidence reviewed
Latest material change / Owner opened a Daman marine-sand investigation tender / 6 recorded changes
Confirmed
Project agreements, the L&T-Lantania EPC award and December 2025 financial close are evidenced, and ACWA's 3 March 2026 year-end report classifies the full 300,000 m3/day capacity as under construction; offshore mobilisation, installed intake or outfall geometry, first water and accepted production are not dated / construction / Evidence reviewed
Latest material change / ACWA classified the full design capacity as under construction / 4 recorded changes
Confirmed
Democratic Republic of the Congo / Africa / Deep-water ports and container terminals
Phase-one marine and terminal works are under way; the DRC government was still pressing for acceleration in May 2026, so the previously stated 2026 delivery and first-vessel dates remain targets rather than evidence of accepted operation / construction / Evidence reviewed
Latest material change / Government kept acceleration on the agenda after reported local delays / 8 recorded changes
Confirmed
Senegal / Africa / Deep-water ports and container terminals
Marine works and container-terminal construction are active; the access channel, reclamation, quay and terminal packages remain under delivery, while 2028 is a government operating target rather than an accepted opening date / construction / Evidence reviewed
Latest material change / Senegal set 2028 as a full-operation target / 6 recorded changes
Confirmed
Quay-wall construction and marine works in progress / construction / Evidence reviewed
Latest material change / The port published an updated CO2 quality interface / 7 recorded changes
Confirmed
Denmark / Germany / Europe / Immersed tunnels and marine crossings
Second tunnel element immersed and connected; serial immersion, backfill, systems integration, and a two-stage road-then-rail opening remain active / construction / Evidence reviewed
Latest material change / Second standard element immersed and connected / 5 recorded changes
Confirmed
24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active / construction / Evidence reviewed
Latest material change / Twenty-fourth caisson installed in open sea / 5 recorded changes
Confirmed
Callan Marine 44-foot package awarded; Great Lakes offshore Contract 6 in delivery; final 48-foot inland cut remains separate / construction / Evidence reviewed
Latest material change / SNND awarded the 44-foot inland package to Callan Marine / 5 recorded changes
Confirmed
Intake tunnel and offshore piling complete; outfall tunnel and diffuser installation remained active after the original June 2026 marine-work window / construction / Evidence reviewed
Latest material change / Marine work continued beyond the original June window with diffuser installation still active / 8 recorded changes
Confirmed
Final technical and legal agreement signed; financial close still pending as of 7 July 2026 / financing / Evidence reviewed
Latest material change / The water ministry confirmed financial close was still incomplete / 7 recorded changes
Confirmed
Construction active; common marine, tunnelling, and electrical systems remain on the path to the February 2027 first-phase target / construction / Evidence reviewed
Latest material change / Annual reporting kept Casablanca among ACCIONA's faster-delivering water projects / 6 recorded changes
Confirmed
CW02 international prequalification open; Water Authority of Fiji lists a 28 August 2026 closing date / prequalification / Evidence reviewed
Latest material change / WAF current tender list confirms CW02 open with a 28 August closing date / 7 recorded changes
Confirmed
Core marine assets built; terminal, tunnel, and commercial-operating interfaces remain under verification / construction / Evidence reviewed
Latest material change / The 62 km connecting road received GCPI's final Performance Certificate / 8 recorded changes
Confirmed
Owner reports 98% construction; full-system handover pending / construction / Evidence reviewed
Latest material change / Ashghal reported 98% with remaining works and readiness planning still open / 5 recorded changes
Confirmed
Design certification complete; base-port and offshore installation preparation active / construction / Evidence reviewed
Latest material change / Technical conformity certification completed for the wind facilities / 5 recorded changes
Confirmed
Quay construction active; port-side dredging awarded; optimized national fairway package in procurement for 2027-2028 delivery / construction / Evidence reviewed
Latest material change / Authority reopened an optimized and split fairway procurement / 6 recorded changes
Confirmed
Dredging contract signed; enabling and supervision sequence forming / award / Evidence reviewed
Latest material change / DEME confirmed the contractor scope and three material routes / 4 recorded changes
Confirmed
Morocco / Africa / Deep-water ports and energy terminals
Basic port infrastructure reported complete; East terminal, towage, port systems, staffing, and service activation remain on the Q4 2026 launch path, while the West terminal follows from 2027 / commissioning / Evidence reviewed
Latest material change / WMCT signed long-term East-terminal financing documents / 6 recorded changes
Confirmed
Marine reference design, investigations, environmental-review preparation, and construction planning active; Westport Bill remains before Parliament / design / Evidence reviewed
Latest material change / Westport opened a seagrass-restoration trial RFP / 7 recorded changes
Confirmed
Nui and Niutao harbour works completed and opened; operating performance and maintenance now under review / completed / Evidence reviewed
Latest material change / Nui and Niutao harbour development completed / 2 recorded changes
Confirmed
Block A commissioned; remaining Phase 1 capacity in delivery / commissioning / Evidence reviewed
Latest material change / DEWA confirmed commissioning of Hassyan Block A / 3 recorded changes
Publication boundary and data export
Tracker entries summarize source-reviewed project evidence. They are not tender notices, award notices, bid
invitations, procurement instructions, investment recommendations, or commitments that an opportunity remains open.
Evidence reviewed. The date IMWO last reviewed the public evidence set. It is not an implied
project-event date. The CSV provides 25 fields per public project, including controlled sectors and a source-bound
material change history. The export preserves every source date and URL in the record. A source without a stated
publication date is labelled "Publication date not stated; evidence reviewed [date]".