New Deirout combines seven irrigation outlets with discharge-and-level monitoring. The ministry reports distinct February and March 2026 operating milestones for the barrages and monitoring system.
Irrigation regulators and discharge-monitoring systems
Phase
Commissioning / Confirmed
Last checked
3 November 2026
Coverage
Related sectors
Irrigation regulators and discharge-monitoring systems is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Ministry of Water Resources and Irrigation, Egypt
Delivery parties
Dai Nippon Construction - contractor identified by the water ministry
Contract route
JICA's EG-P35 record identifies a March 2015 loan agreement for JPY 5,854 million. The water ministry identifies Dai Nippon Construction as contractor; the loan amount describes financing.
Execution window
The ministry's March 2026 status reports barrages operation on 28 February, monitoring-system trial operation on 30 March, 99.1% overall progress and commencement of operation-and-maintenance training. Its revised 15 June completion target is a published programme date.
Works package
Bahr Youssef, Ibrahimia, Badraman, Deiroutia and Abu Gabal regulators, Dalgawi and Sahelia intakes, and a discharge/level monitoring system. The ministry lists 38 monitoring stations, a main station at the barrages control building and an Assiut sub-monitoring station.
Marine interfaces
The hydraulic complex distributes irrigation water between seven principal outlets. Operating performance links headworks settings, downstream withdrawals, field measurements and intake/pump interfaces across the canal network.
Commercial evidence boundary
The operating task combines the regulator structures, field sensors, monitoring locations, downstream intake condition and pump-status interfaces. Acceptance and maintenance planning should follow the complete measurement and allocation function.