Performance evidence after handover.

A handover certificate can close construction without showing whether a harbour stays usable, an outfall remains within limits or a terminal can turn ships. A performance conclusion needs an accepted baseline, a defined service, a stated observation period and records of failure, maintenance and recovery.

Updated 75 tracked projects 99 publications

How a milestone becomes a performance record

The four levels are cumulative. A later level relies on the earlier one, but it answers a different question.

01 Dated event

Identify the asset, source, date and verb: handed over, first water, civil works complete, commissioned, trialled or opened.

02 Accepted scope

Record the certificate, survey, tested capacity, released depth, closed defects and exact package boundary accepted by the owner.

03 Operating series

Use repeated observations for availability, outages, quality, throughput, usable depth, maintenance, incidents and environmental limits.

04 Measured outcome

Connect reliable operation to user access, service continuity, lifecycle cost, environmental performance, recovery after events or capacity delivered.

Baseline and denominator

Fix what was accepted and what was expected to operate

Performance begins with two records that are often missing from public announcements. The acceptance baseline states the asset configuration handed to the operator. The operating denominator states when, at what capacity and for which users that asset was expected to be available. Without both, a percentage can look precise while measuring the wrong system.

Accepted configuration

Record as-built geometry, tested capacity, released depth, installed equipment, permit conditions, unresolved defects and temporary restrictions. Keep partial handover, sectional completion and whole-system acceptance separate.

Service denominator

Define scheduled hours, navigation season, tide or weather envelope, vessel class, treatment block, flow range and demand basis. State whether availability is measured against calendar time, planned service time or actual demand.

Exclusions and changes

Separate planned maintenance, owner shutdowns, force majeure, demand curtailment and third-party outages. Preserve changes to operating limits, design capacity or permit thresholds so later results remain comparable.

Three evidence layers

Condition, function and service answer different questions

PIANC's lifecycle-management guidance for port structures connects inspection, condition assessment, maintenance planning and intervention over the asset life. The 2024 ISO 55000 series also strengthens decision-making around value, risk, data and lifecycle operation. Neither framework supports treating a new asset's appearance as proof of dependable service.

Condition

Inspections, bathymetry, corrosion readings, settlement, cracking, scour, wear and component tests describe physical state. A defect count is useful only when severity, location, trend and response are recorded.

Function

Depth, flow, pressure, transfer rate, berth load, wave attenuation or power availability show whether the asset can perform its intended technical function under a stated test envelope.

Service

Availability, vessel access, throughput, water delivered, safe transfers, cancellations and user delay show whether the technical function becomes a dependable operating service.

See the ISO technical committee's 2024 ISO 55000 and 55001 release note for the current lifecycle, value, risk and data-management emphasis.

Availability and failure

Availability is meaningful only after the service level is defined

IALA Standard S1010 links marine aids to navigation to service objectives, availability categories and risk management. The IALA NAVGUIDE explains that long-term outage and repair records are needed to represent availability. The principle extends beyond navigation aids: the metric must preserve what failed, when the service clock was running and how quickly full function returned.

Start and stop the clock

Timestamp detection, service loss, temporary restoration and full repair. Distinguish complete outage, degraded mode, capacity reduction and a redundant component failure with no user impact.

Classify the cause

Separate design, installation, material, control-system, environmental, vessel-impact, maintenance and external-supply causes. A generic fault total cannot identify where risk is accumulating.

Measure the response

Track detection time, access delay, mobilisation, repair duration, spares constraint, repeated failure and deferred work. Report both individual critical events and the observation-period series.

Test to operation

A passed test is one point on the operating curve

Performance test

State the test duration, loading, boundary conditions, instruments, tolerances and exclusions. A successful test demonstrates the specified point or envelope, not future availability.

Reliability run

Record continuous or cumulative operation, interruptions, resets, operator interventions, quality compliance and rectification during the contractual reliability period.

Operating series

Compare repeated periods using the same denominator. Explain material changes in demand, asset configuration, maintenance policy, environmental conditions and reporting method.

Four milestones that need four different follow-up records

These cases show why the same word, such as commissioned or complete, cannot carry the same operating conclusion across marine utilities, ports and island harbours.

First water / Reported

SADDN reached Radomiro Tomic during progressive validation

The June milestone shows a connected treatment and high-head conveyance route. The next record needs accepted continuous flow at the initial 840 l/s design capacity, product-water quality, intake and return-system availability, marine monitoring and commercial-operation certification.

Phased commissioning / Corroborated

Hassyan commissioned the first 60 MIGD block

Block A establishes entry into service for one third of Phase 1. A performance conclusion still depends on representative uptime, outage history, product-water compliance, diffuser monitoring, intake-outfall acceptance and commissioning of the remaining 120 MIGD.

Marine civil completion / Corroborated

Nador West Med completed its basic marine footprint

The owner and dredging contractor support a bounded civil-completion finding. As-built bathymetry, berth release, aids and harbour systems, tug and pilot readiness, first commercial service and recurring throughput belong to the operating record.

Harbour handover / Corroborated

Nui and Niutao moved into the service-and-maintenance phase

The named channels, basins, wharves, ramps and passenger facilities are documented as complete. Usable-depth surveys, navigation-aid uptime, workboat calls, weather cancellations, incident records, maintenance response and post-storm condition will show how the harbours perform.

The minimum useful operating dataset

A single update can establish a milestone. Performance needs a series with a stated denominator and owner or operator context.

Availability

State the observation period, planned and unplanned downtime, service cancellations, outage cause, recovery time and the asset or block included.

Condition and geometry

Use hydrographic surveys, structural inspections, defect logs, sediment change, fender and bollard condition, aid availability and repair close-out.

Quality and environment

Track accepted water quality, discharge or diffuser results, turbidity, incidents, permit limits, monitoring frequency and any corrective action.

Service and users

Measure vessel calls, throughput, passenger or cargo movements, transfer safety, dependable access, queue time and service continuity after severe weather.

Milestones and operating evidence answer different questions

Each public performance record separates the dated milestone from the accepted scope, observation period, available measurements and unresolved operating outcome.

Open performance records Read the milestone evidence method Read the port opening evidence chain

Operating records

Review dated milestone, accepted scope, observation period, available metrics and unresolved operating evidence for each published case.

Open performance records

Evidence standards

Inspect the distinction between source-reported milestones, corroborated acceptance and measured operating results before comparing assets.

Open methodology

Submit operating evidence

Provide the asset boundary, service denominator, observation period, source records and submitter relationship for review.

Submit evidence

Reports and data

Project records and references

These reports, datasets and source links preserve project dates, quantities, methods and the distinction between award, construction, acceptance and observed performance.

Reports

MENA Marine Works Monitor: July 2026 PDF

Designed open-access edition with executive findings, calculated figures, the fixed 34-project evidence table, method, limitations, and source register.

Data exports

Performance records CSV

Structured export of asset-specific commissioning and operating evidence, including the measurement basis, confirmed evidence and unresolved operating outcomes.

Templates

Performance note template

Structured form for asset-specific commissioning and operating evidence, including measures, periods, outcomes and source documents.

Source references

Source register

Primary owner, authority, lender, contractor and technical references cited by IMWO records, with last checked dates and direct source routes.

Current evidence

Performance evidence collection

Performance evidence starts from an accepted asset baseline and tests condition, function and service against a stated operating denominator, failure record, maintenance response, environmental result and user outcome.

Publications
99
Projects
75
Confirmed
75
Regions
7
Change histories
74
Updated
16 August 2026

Engineering frame

Technical scope

Accepted baseline
Anchor the record to a dated, project-specific milestone and state what was formally accepted.
Delivered output
Measure achieved depth, capacity, flow, access, protection or service against the stated design basis.
Operating reliability
Look for sustained operation, utilisation, downtime, maintenance demand and repeat service after commissioning.
Outcome and limits
Separate verified environmental, user and economic outcomes from claims that remain unmeasured or unavailable.
99 publications / 75 projects
Record type

Current analysis and reports

Brief / Confirmed

Skinners Pond wharf 401 carries two official scope baselines

DFO's August 2021 environmental assessment described an approximately 50-metre same-footprint copewall with no excavation. The September tender and July IFC drawings instead include dredging and excavation, a pile-in-place reinforced-concrete copewall and an approximately 65.93-metre rehabilitated wall. Kildare Construction later received the CAD 1,099,800 award, but the public record located does not explain the scope difference or confirm close-out.

12 August 2026 / 4 sources
Brief / Confirmed

Bristol's field notices outlast the original dredging contract window

Find a Tender fixes Bullo Limited's original GBP 392,500 contract through 26 June. Bristol Harbour Authority later scheduled Baltic Wharf dredging in late July and again from 10 to 17 August, with a floating pipeline and Bullo call sign. The public chain shows a live delivery question, not a proven extension or completion.

16 August 2026 / 6 sources
Brief / Confirmed

Hague Basin's named dredging spread still lacks completion evidence

Breakwater Marine's USD 12,984,450 Hague Basin contract has moved beyond award evidence: the Coast Guard names a 60-by-155-foot dredge, ten scows, a pushboat and work skiff. USACE still records construction ongoing, while accepted depth, final quantity and completion remain unpublished.

16 August 2026 / 7 sources
Brief / Confirmed

Tumaco deepening contract awaits supervision and mobilisation records

Gobernacion de Narino signed Tumaco Phase I access-channel deepening contract GN2862-2026 with Consorcio Puerto Tumaco II for COP 26.826 billion on 22 July. SECOP confirms the 75/15/10 legal member chain, but the contract has no public start date, invoice or payment and the COP 999.999 million independent-supervision process remains unawarded. The evidence supports award, not mobilisation or dredging progress.

6 August 2026 / 6 sources
Brief / Confirmed

Barranquilla's COP 150.97bn award is now a COP 241.68bn live contract

SECOP II records a COP 150.967 billion initial award for Barranquilla's access-channel maintenance dredging and a later modified contract value of COP 241.685 billion with a 31 December 2026 current end date. The selected consortium is legally split 70% Caribbean Region Water Conservancy Engineering SAS, 20% Panamerican Dredging and 10% CFD Ingenieria SAS. Cormagdalena documented active dredging and 80.7% execution at 31 March; accepted quantities, completion and final cost remain unpublished.

6 August 2026 / 6 sources
Brief / Confirmed

Centreville contract expired without published acceptance records

Centreville's integrated wharf, dredging and breakwater contract moved from an 84-week requirement ending 31 August 2024 to a 31 December 2025 expiry. CanadaBuys reports CAD 18,864,176.72 after 11 amendments, while Public Accounts publishes different fiscal snapshots. None of the cited records supplies the physical and commercial close-out evidence needed to call the harbour work complete.

16 August 2026 / 4 sources
Brief / Confirmed

Cheticamp's CAD 1.264m award lacks public handover evidence

CanadaBuys confirms Superior Contracting Ltd. at CAD 1,264,230 for the Cheticamp Jobs Wharf package. The tender joins timber-pile wharf demolition, harbour-bottom dredging, designated disposal, breakwater raising and repair, upland grading, floating docks, strongarms, gangways, concrete works and electrical reinstatement. Its published contract window ended on 31 March 2023; federal public records supply no accepted quantities, commissioning certificate, owner handover or final account.

9 August 2026 / 5 sources
Brief / Confirmed

Pugwash's floating-dock award closes price, not harbour acceptance

CanadaBuys confirms that Fisheries and Oceans Canada awarded Brian MacGillivary Construction CAD 516,100 for an integrated Pugwash package spanning harbour-bottom dredging, containment in an existing berm, floating docks, strongarms, gangways, a concrete retaining wall and berm reinstatement. The amended four-month term ended on 29 March 2024, while accepted quantities, commissioning and a completion certificate remain unpublished.

6 August 2026 / 4 sources
Brief / Confirmed

Harbour Grace award covers timber cribwork, dredging and utilities

Public Services and Procurement Canada awarded Bulldog Contracting Ltd. CAD 7,045,871.75 for Harbour Grace demolition, treated-timber crib reconstruction, a reinforced-concrete deck and finger pier, local dredging to -3.0 metres, retaining works and water and electrical reinstatement. The official pages confirm the 1 April 2022 award but do not establish a reliable delivery end date or accepted completion.

6 August 2026 / 4 sources
Brief / Confirmed

Petit-Cap's Berlin-wall contract still lacks acceptance evidence

CanadaBuys records Landco Construction Ltd. under CAD 3,083,763.87 contract CW2335551 for Petit-Cap structure 403. The package partially demolishes the timber-crib marginal wharf, dredges the harbour basin, builds a new Berlin-wall marginal wharf, reinstates electrical services and manages cofferdam and environmental controls. The eight-month contract ended on 4 July 2024, while accepted completion and final quantities remain unpublished.

6 August 2026 / 4 sources
Brief / Confirmed

Three Atlantic Canada wharf awards expose the same close-out blind spot

Three federal awards place very different Atlantic fishing-harbour packages under named primes: Brian MacGillivary Construction at Pugwash, Bulldog Contracting at Harbour Grace and Landco Construction at Petit-Cap. Together they cover floating access, timber cribwork, Berlin-wall construction, dredging, concrete, armour stone and utilities. Their official procurement records are strong on award facts but weak on accepted quantities, lower tiers, final accounts and return to service.

6 August 2026 / 6 sources
Brief / Confirmed

Three 2026 Atlantic Canada awards split wharf, dredging and breakwater markets

Three active 2026 CanadaBuys awards place CAD 12,360,523.57 of Atlantic harbour work under named primes: L Breau and Sons at Sainte-Marie-Sur-Mer, Les Entreprises P E C at Grande-Anse and Zutphen Contractors at Larrys River. The packages are not interchangeable. One joins a Berlin-wall wharf to a title-level new breakwater, one specifies barge-excavator and scow dredging with a containment cell, and one reconstructs a rubble-mound breakwater inside a core fishing harbour.

7 August 2026 / 5 sources
Brief / Confirmed

L Breau holds the 79-week structure 401 contract

L Breau and Sons Ltd holds CAD 8,745,856.95 contract CW2440554 for Sainte-Marie-Sur-Mer structure 401 through 24 August 2027. CanadaBuys describes a 79-week replacement of the timber-crib wharf with a Berlin-wall structure, while the procurement title also includes a new breakwater whose dimensions and quantities remain unpublished.

7 August 2026 / 3 sources
Brief / Confirmed

Grande-Anse dredging carries a pre-start bird survey

Les Entreprises P E C inc holds CAD 862,270 contract CW2452382 for Grande-Anse harbour-basin dredging through 31 December 2026. The specified method uses a barge-mounted excavator and scow with containment-cell reconfiguration. Site work could begin from 6 July only after a bird survey, with a species-at-risk finding able to defer activity to mid-September.

7 August 2026 / 3 sources
Brief / Confirmed

Zutphen holds Larrys River's 25-week breakwater contract

Zutphen Contractors holds CAD 2,752,396.62 contract CW2455209 for rubble-mound breakwater construction at Larrys River Small Craft Harbour through 27 November 2026. The 25-week requirement includes delineating the construction zone from the operating facility, but published records give no breakwater dimensions, rock quantities, quarry source or first-placement date.

7 August 2026 / 3 sources
Article / Published analysis

Island marine delivery depends on logistics, interfaces and operations

Thirteen public island records, current to 14 August 2026, show why contract status alone is a poor proxy for usability: remote supply, live-port constraints, package interfaces, accepted works and operating evidence close on different records.

16 August 2026 / 20 sources
Brief / Confirmed

Hamad Port food-security terminal reaches 98% implementation

Hamad Port's QAR 1.6 billion food-security terminal received two Liebherr LHM 280 mobile harbour cranes by vessel in August 2022. Ashghal then reported 98% implementation in June 2026 and continued to describe remaining stages and operational-readiness planning. Whole-system handover and sustained food-cargo service are still outstanding.

15 July 2026 / 5 sources
Brief / Confirmed

Yangtzekanaal starts 1.4 million m3 Phase B dredging after tug-quay delivery

Rotterdam has delivered the 500-metre tug quay with 12 berths and shore power, and Hakkers, De Klerk and Van Oord have started the 1,450-metre second phase. The owner now defines 20 new inland-shipping berths, NAP -6.80 metre maintained berth depth, 1.4 million cubic metres of sand dredging and reuse on Maasvlakte 2, a heavy-load zone and about 10,000 cubic metres of geopolymer concrete.

12 August 2026 / 9 sources
Brief / Confirmed

WACA's six country programmes are approaching close-out at different speeds

WACA ResIP 1 is nearing its final phase across six West African countries. Its lagoon, shoreline, quay, dike, drainage and community packages run under different contracts and timetables, while Senegal is seeking a later closing date. A single regional completion figure would mask the sites still controlling delivery.

16 July 2026 / 6 sources
Brief / Confirmed

Eiffage records a 340 m intake drive at Mamelles

Eiffage recorded a 340 m seawater-intake microtunnel at Dakar's Mamelles desalination plant in July 2025. A February 2026 supervision visit still described the plant as under construction and expected commissioning later in the year. Final brine-discharge installation and marine acceptance remain unpublished.

19 July 2026 / 6 sources
Brief / Confirmed

One World Bank report counts both 44 and 45 completed Hooghly jetties

World Bank award data close the prime-contractor gap for four Hooghly passenger-jetty locations: P.G. Enterprise holds Lot 1 and Patra Shipping Private Limited holds Lot 2. Delivery is less clear. The June 2026 implementation report says 44 of 45 project jetties were complete and names Metiabruze as still under implementation, then says all 45 were complete in its results table.

5 August 2026 / 5 sources
Brief / Confirmed

West Bengal's 21 jetty contracts leave Metiabruze acceptance unresolved

World Bank supplier data now identify every direct works award used to map West Bengal's 29 Phase I and 16 Phase II floating passenger jetties. The 21 contracts carry USD 24,836,527.26 in reported supplier commitments across eight contractor groups. Prime-contract identification is complete, while the latest implementation report still says both 44 and 45 locations are complete.

6 August 2026 / 6 sources
Brief / Confirmed

Turku S1 handover opens the system-commissioning phase

Terramare handed the new S1 pier to Port of Turku in June 2026, completing the first construction contract in the Ferry Terminal Turku programme. The berth remains outside passenger service until March 2027 because the terminal, passenger gangway, three boarding bridges, traffic systems, field circulation and operating interfaces must still converge. The nine-month interval separates marine-civil handover, system commissioning and first service.

5 August 2026 / 7 sources
Article / Published analysis

Beach nourishment closes through quantity, profile, demobilization and response

Ocean City has a mobilized 1.6-million-cubic-yard contract, Carolina and Kure beaches have nearly 2 million cubic yards placed, and St. Joseph is monitoring nearshore movement. Each sits at a different point between planned quantity and an accepted coastal outcome.

23 July 2026 / 9 sources
Article / Published analysis

Where USACE dredging records actually appear

USACE dredging records are split between SAM.gov, the Navigation and Civil Works Decision Support Center, district engineering pages, DQM and local sponsor files. A solicitation, bid abstract, award, plant trace, hydrographic survey and acceptance record answer different questions.

20 July 2026 / 11 sources
Article / Published analysis

Rabigh 4 completes 600,000 m3/day EPC performance test

SEPCOIII reports that Rabigh 4 completed its EPC performance test at 600,000 m3/day on 19 February 2026, with power use of 2.712 kWh/m3 before photovoltaic offset. SWPC has not published commercial-operation acceptance, and the marine close-out file remains unavailable.

16 August 2026 / 12 sources
Article / Published analysis

For coastal revetments, the quarry is part of the job

Ebeye, Goree and West Point all depend on armourstone, but their routes from quarry approval to accepted shoreline protection sit at very different stages.

17 July 2026 / 7 sources
Article / Published analysis

The final mile from port construction to commercial service

Breakwaters, quays, channels, equipment and first vessel calls close different parts of a port programme. Nador West Med, Grand Faw, Hamad, Tartous, Ndayane and Banana remain at different points between completed marine assets and repeat commercial service.

11 August 2026 / 16 sources
Article / Published analysis

First water, commissioning, completion, and opening are four different claims

SADDN has produced first water, Hassyan is commissioning in blocks, Tuvalu has handed over named harbour assets, and Nador West Med has completed basic port infrastructure. None of those milestones closes every marine, terminal or operating interface.

15 August 2026 / 12 sources
Brief / Confirmed

Ras Mohaisen sources give 2028, Q4 2029 and 2030 production milestones

Ras Mohaisen has a dated chain from project-agreement signing through EPC award, financial close and ACWA's under-construction classification, but Sharakat's 2028 partial-production and 2030 full-production sequence, ACWA's Q4 2029 PCOD and Lantania's 2025-2029 execution period are not the same milestone. The 3-kilometre offshore scope still needs evidence from marine design through first water and sustained production.

15 July 2026 / 6 sources
Brief / Confirmed

Banana's 24-month contract leaves a longer route to first service

Banana Port has a public chain from the final agreement and first-stone ceremony through minority investment and the phase-one contract. An April 2026 Council of Ministers record still described rapid modernisation of the Banana-Boma-Matadi-Kinshasa corridor as necessary. The designed quay, depth, yard and capacity still require dated evidence from marine acceptance through terminal commissioning and repeat commercial service.

16 August 2026 / 6 sources
Brief / Confirmed

Ndayane's completed dredging shifts risk to quay and terminal integration

DP World reports Ndayane's major dredging works complete 13 months ahead of schedule: a 5-kilometre channel dredged to 20 metres, a 600-metre turning basin and an 875-metre berth pocket. More than 95% of the material was rock and the hardest cited formations exceeded 100 MPa, yet the work was completed without blasting. The critical path now runs through dredging acceptance, reclaimed-ground release, quay and terminal delivery, harbour services and operating trials ahead of the 2028 target.

16 August 2026 / 12 sources
Article / Published analysis

From dredging award to usable port capacity

A signed contract, marine plant on site, dredged volume, a completed quay and commercial vessel access mark different points in a port programme. Six current cases trace the remaining work between a package award and capacity an operator can actually use.

15 July 2026 / 11 sources
Brief / Confirmed

Nador West Med moves from marine completion into port opening preparations

Morocco reports Nador West Med's 5.4 kilometres of breakwaters and 4 kilometres of quays complete and targets an operational launch in Q4 2026. Current authority notices cover an access-control building and maritime-zone gantry, a main access building, and external quality control for building works. Recruitment is also active for port-flow, port-officer, and IT roles. The port is therefore past its main marine works but still assembling the access, control, systems, and staffing needed for service.

15 August 2026 / 9 sources
Evidence record / Corroborated

Nador West Med basic marine infrastructure completion evidence

By the 15 July 2026 cutoff, the Royal Office had reported completion of all basic port infrastructure and published breakwater and quay totals. Jan De Nul had separately closed its dredging account, while dated programmes described terminal and towage readiness. No reviewed source provides as-built hydrographic acceptance, berth handover certificates, terminal-equipment acceptance, harbour-control readiness, first commercial service, recurring throughput or lifecycle performance.

15 July 2026 / 7 sources
Evidence record / Reported

SADDN first-water delivery to Radomiro Tomic evidence

The file reviewed through 15 July 2026 establishes Codelco's BOOT authorization, Aguas Horizonte's developer role and Techint's EPC mandate. It defines the submarine system, auxiliary pier, coastal sump, trench blasting, intake and brine-return pipes, coastal energization, intake-tower installation, high-head conveyance, reservoir and independent commissioning assurance. Techint's 23 June account confirms first water at Radomiro Tomic during hydraulic tests and progressive validation. Still absent are accepted continuous flow, representative water-quality results, intake availability, brine-dispersion monitoring, power and pumping reliability, service to the other two mining divisions, final completion and commercial-operation certification.

15 July 2026 / 9 sources
Evidence record / Corroborated

Tuvalu Nui and Niutao harbour handover evidence

Records reviewed through 15 July 2026 document the February completion announcement for Nui and Niutao, the Niutao opening and the June 2024 Nui handover. They also identify the marine and landside assets and ADB's operation-and-maintenance capacity objective. Missing from the public file are current as-built surveys, service logs, weather cancellations, aid uptime, maintenance response, post-storm asset condition and independently measured user outcomes.

15 July 2026 / 7 sources
Brief / Confirmed

Fehmarnbelt's third immersion extends the repeat cycle

FLC connected Fehmarnbelt's third 217-metre, more-than-73,500-tonne standard element on 1 August after a five-tug tow and Friday immersion. Three of 89 elements are now in place. The owner has not published a new installed-length total, accepted protection quantity, mature series rate or replacement opening date.

16 August 2026 / 7 sources
Evidence record / Corroborated

Hassyan IWP Block A marine-system commissioning evidence

Owner statements available on 13 July 2026 confirm Block A commissioning and the published delivery schedule. The project structure and ESIA also define the marine design basis. No independent records establish uptime, product-water compliance, outfall performance, environmental monitoring results, final completion or acceptance of the remaining blocks.

13 July 2026 / 5 sources
Brief / Confirmed

Hassyan's six-pipe marine corridor enters operating proof

DEWA commissioned Hassyan Block A, 60 MIGD, by the end of March 2026. The wider marine installation is already sized for the planned 240 MIGD complex: eight intake risers feed four 3 m pipes, while two 3 m outfalls discharge through modelled diffusers outside the Ramsar boundary. Blocks B and C still have to turn that EPC configuration into sustained plant and receiving-water performance.

13 August 2026 / 6 sources
Brief / Confirmed

USACE starts 83,000 yd³ St. Joseph dredging with monitored nearshore placement

USACE Detroit District's July 2026 St. Joseph Harbor operation moves beyond a routine Great Lakes maintenance item: Viking Marine Construction will hydraulically dredge roughly 83,000 cubic yards from the federal channel while ERDC monitors a perpendicular shoreline placement to understand sediment movement under Lake Michigan wave action.

21 July 2026 / 5 sources
Brief / Confirmed

Niagara fish passage closes construction, not monitoring

USACE has completed the USD 13.4 million, 778-foot Emerald Shiner Fish Passage along Freedom Park's Niagara River seawall. Field measurements reportedly kept velocity below the shiner swimming threshold, while observed fish use remains an early result rather than a seasonal performance record.

23 July 2026 / 3 sources
Evidence record / Reported

Niagara River Emerald Shiner Fish Passage early performance evidence

The 23 July 2026 USACE completion release confirms the combined 778-foot structure, May construction finish, measured velocities below the emerald shiner swimming threshold and observations of shiners using the passage. Earlier USACE releases establish the demonstration design, full-phase wall repairs and concrete-filled baffles. The reviewed sources do not publish raw hydraulic measurements, a completion certificate, independent fish counts, a representative monitoring period or post-winter condition evidence.

23 July 2026 / 5 sources
Brief / Confirmed

Akita offshore wind links certified design to an active base-port workfront

The 315 MW Oga-Katagami-Akita project now connects certified 15MW-class foundation design to a visible Iijima Wharf workfront: a 2,500-tonne crawler crane and multi-axle transporters are on site, named contractors cover unloading and tower pre-assembly, and dedicated vessels are assigned for foundation and turbine installation.

28 July 2026 / 7 sources
Article / Published analysis

Akita offshore wind puts base-port readiness on the installation critical path

Akita Port now has direct field evidence of heavy-component logistics for the 315 MW Oga-Katagami-Akita project: a 2,500-tonne crawler crane, multi-axle transporters, named handling contractors and a defined delivery and storage area. Component arrival, offshore mobilisation and navigation controls remain open before the June 2028 operating target.

15 August 2026 / 11 sources
Report / Version 3.20

MENA Marine Works Monitor: July 2026

Thirty-four Middle East records span fishing ports, commercial terminals, naval fleet-support infrastructure, energy-terminal access and export systems, desalination marine works and a five-plant seawater pipeline at developer qualification. Hassyan's first 60 MIGD block is operating, while acceptance of the full six-pipe marine corridor and receiving-water performance remains to be demonstrated as Blocks B and C enter service.

13 August 2026 / 119 sources
Brief / Confirmed

Queen Salote stayed open through a two-stage rebuild

Tonga completed Queen Salote International Wharf's marine and civil upgrade in November 2025 after rebuilding Wharf 1, repairing Wharves 2 to 4, extending Wharf 2 by 50 metres and installing four new berthing or mooring dolphins around a live cargo gateway.

21 July 2026 / 6 sources
Brief / Confirmed

Aiwo wharf enters service while wider port works continue

Cargo vessels are using Aiwo's new wharf and fuel line. ADB's latest monitoring report puts dredging at 78% and the northern-yard interim apron at 97% by June 2025, with all buildings handed over; the current project page still carries a broader unfinished-work list.

3 August 2026 / 7 sources
Brief / Confirmed

Damietta CT2 begins vessel operations before full 3.3m TEU ramp-up

Damietta Alliance Container Terminals started commercial operations on 14 February 2026. The opening configuration has 1,670 metres of quay at 18 metres depth, 12 ship-to-shore cranes, 40 yard cranes and two operational rail lanes. The 3.3 million TEU figure remains the terminal's capacity after the final construction phase, not measured throughput.

20 July 2026 / 7 sources
Brief / Confirmed

Ruwais LNG channel dredging reached round-the-clock operations

NMDC Group's Ruwais LNG marine package covers about 15 million cubic metres of dredging along a 5-kilometre, 245-metre-wide access channel and new navigation aids. A February 2025 ADNOC port notice shows that phased dredging had entered 24-hour execution, with two offshore disposal sites, environmental buoys and a silt curtain. The disclosed trail ends before final hydrographic acceptance and marine handover.

20 July 2026 / 6 sources
Brief / Confirmed

Cotonou Terminal 5 owner page reports 69% physical progress

Port Autonome de Cotonou's live Terminal 5 page reports 69% physical progress and 72% overall progress. The same page still gives a 2021-2024 delivery period, so the percentages show unfinished construction but do not supply a current finish date. CHEC's marine scope includes a 350-metre breakwater extension and an 891-metre revetment protected by ACCROPODE II units.

21 July 2026 / 6 sources
Brief / Confirmed

Rabigh 4 completes 600,000 m3/day performance test

SEPCOIII reports that Rabigh 4 completed its EPC performance test on 19 February 2026 at the 600,000 m3/day design capacity. Power use was 2.712 kWh/m3, falling to 2.659 kWh/m3 after photovoltaic generation. SWPC has not published commercial-operation acceptance.

20 July 2026 / 6 sources
Brief / Confirmed

Ghubrah III construction targets Q1 2027 operation

Nama PWP still targets Q1 2027 commercial operation for Oman's 300,000 m3/day Ghubrah III plant. The four-line marine system is well defined on paper, but current public updates do not say how much of the intake and outfall network has been installed or accepted.

20 July 2026 / 7 sources
Brief / Confirmed

Nui and Niutao boat harbours complete after channel and shore works

The Nui and Niutao boat harbours are complete. Both include channel and shore-side work, but the completion notices do not report channel condition, navigation-aid serviceability, facility availability or workboat reliability after handover.

21 July 2026 / 6 sources
Brief / Confirmed

SADDN delivers first desalinated water to Radomiro Tomic

SADDN has moved from its 2022 BOOT award through a defined 1.3 km submarine system, coastal energization, intake-tower installation and high-head conveyance to first desalinated water at Radomiro Tomic. The complete route is connected, while accepted 840 l/s service, marine reliability and supply to all three divisions remain unverified.

15 July 2026 / 14 sources
Brief / Confirmed

Paranaguá channel concession starts from a 13.3-metre operating draft

Paranaguá's planned 1 August transfer changes the operator and tariff counterparty for the access system. The concessionaire portal publishes a 13.3-metre operating draft against a 15.5-metre target. Baseline bathymetry and the first concession-period dredging will establish how progress is measured.

16 July 2026 / 8 sources
Brief / Confirmed

Baltic Hub T3 separates marine completion from automation ramp-up

Baltic Hub's 717-metre T3 quay and 36-hectare reclaimed platform were completed in 2025, and the operator says the terminal became fully operational in October. A later 2026 sequence relocated aRMG cranes and released additional yard lines. That is not a contradiction: the marine asset and base terminal were delivered, while automated-yard configuration continued to mature in live service.

1 August 2026 / 6 sources
Brief / Confirmed

Ploce needed four completion dates before the terminal truly operated

Ploce's New Bulk Cargo Terminal is a clean example of why a single completion label fails. Public infrastructure was physically complete in June 2016. CNBM equipment arrived in October 2017. Integrated trial operation started in March 2019. Regular service began with the Orient Cavalier call in February 2021. The delivery chain also separates the Port Authority's CYES-Viadukt civil contract from Luka Ploce's concessionaire-funded CNBM handling system.

2 August 2026 / 8 sources
Brief / Confirmed

Lesotho W03A's 85% signal leaves intake and subcontractor gaps open

World Bank evidence identifies China International Water & Electric Corp. as the USD 42.553 million W03A design-build contractor and Zutari Lesotho as a separate USD 1.014 million construction-supervision consultant. A March 2026 restructuring paper recorded 65% physical completion after flood damage to the temporary river diversion and cofferdam. The LLWDP dashboard now displays 85%, but its date is malformed and a 23% treatment-works subtask appears on the same page.

3 August 2026 / 6 sources
Brief / Confirmed

Braek's replacement pipeline is contracted but not publicly handed over

Grand Port Maritime de Dunkerque concluded a EUR 1,720,365 excluding-VAT contract with Baggerbedrijf de Boer B.V. to remove and replace the submerged sand-discharge line in front of the Braek dike. The tender required service by 31 May 2025, while public project records publish no physical completion or acceptance milestone. A 2018 predecessor award shows the same contractor installed a 1.5 km line intended to support annual nourishment of 0.5 million to 2 million m3.

5 August 2026 / 6 sources
Brief / Confirmed

Harwich's GBP 100m dredging award still needs a contract-details notice

Harwich Haven Authority named Suffolk Dredging LLP on a GBP 100 million excluding-VAT maintenance-dredging award covering Tiamat, conventional dredging, coastal beneficial use and early contractor involvement. The award scheduled signature for 17 April 2026, but the Find a Tender process page still has no contract-details notice and does not attribute later 2026 fleet activity to the LLP.

5 August 2026 / 8 sources
Brief / Confirmed

Mopti dredging activity leaves acceptance unverified

Mopti's boat-quay access dredging moved from a signed USD 3.28 million contract to an official February 2025 launch and a March field inspection. Those milestones establish mobilisation and visible activity, but not an accepted navigation route. The latest procurement plan still records only a signed contract, leaving post-dredge bathymetry, final quantities, sediment destination, commercial closeout and operating release unverified.

5 August 2026 / 6 sources
Brief / Confirmed

Warrawong's live seawall contract still needs a completion record

Warrawong Parklands has moved from a failed timber seawall and open tender into a live AUD 3.814 million construction contract with Civil Constructions. NSW Planning reports work underway and targets completion by year end. The public record still does not provide the installed rip-rap quantity, habitat-feature acceptance, final value, practical completion or reopening evidence needed to close the project.

5 August 2026 / 4 sources
Brief / Confirmed

Moss Landing has post-dredge surveys, not a full closeout

Moss Landing Harbor now has a traceable award, physical work windows, named dredging fleet and published post-dredge surveys. Ahtna's current official obligation is USD 16.037 million and the contract period ended on 23 January 2026. The public chain still stops before final dredged quantity, accepted jetty repairs, practical completion and certified final value.

5 August 2026 / 7 sources
Brief / Confirmed

Santoña has a signed repair contract, not proven mobilisation

Cantabria signed the north-basin fishing-quay repair contract with a Cuevas-COMSA UTE on 9 July 2026 for EUR 2.486 million excluding VAT. The contract and 848-page technical package define a sophisticated staged repair of an ageing piled quay. The viable setting-out act, first work section, lower-tier contractors, monthly certified quantities and acceptance remain unpublished.

5 August 2026 / 5 sources
Brief / Confirmed

CCECC signed Rumonge's USD 26.453 million EPC contract

Burundi's implementing agency signed the Rumonge Port design-and-build contract with China Civil Engineering Construction Corporation on 27 July 2026 for USD 26.453 million. Contract 1893998 establishes the prime EPC relationship and procurement identity. Notice to proceed, site possession, approved design programme, supervision appointment, mobilised marine plant and first physical works remain unpublished.

5 August 2026 / 4 sources
Brief / Confirmed

Kalundu moved from suspension into site remobilization

PFCIGL's owner-side record changes the reading of Kalundu's schedule. After the USD 21.156 million GETRA-AXOR contract was suspended, the project unit and parties reviewed restart prerequisites on 4 June 2026. Contractors remobilized from 15 June, with Kalundu limited to site installation and ground preparation before effective rehabilitation works. The steering committee recorded progressive resumption on 24 June. The procurement plan's 2 July completion entry is therefore a stale baseline, not evidence that a completed package merely awaits closeout.

15 August 2026 / 7 sources
Brief / Confirmed

Nanumaga and Nanumea share one contract, not one delivery status

Hall Civil Contracting signed one USD 62.552 million design-build contract for small-boat harbors at Nanumaga and Nanumea on 21 July 2025. A June 2025 mission set August 2027 and January 2028 target completion dates for the two islands. Public evidence reviewed does not establish approved design, mobilisation, current field progress or an island-level value split after signature.

5 August 2026 / 4 sources
Brief / Confirmed

Five conservation areas need five buoy-acceptance records

Zanzibar Marine and Diving Services signed the USD 266,877.81 supply-and-installation contract for demarcation, mooring and marker buoys across five marine conservation areas on 12 March 2026. The procurement plan carries a 24 May 2026 planned completion and still marks the package Signed. No cited source provides buoy counts, component specifications, installation records, tests or location-level acceptance.

5 August 2026 / 3 sources
Brief / Confirmed

Callao reached post-dredging monitoring, not final closeout

APN announced maintenance dredging in Callao's access channel and inner roadstead from 20 December 2025, targeting safe depths up to -16.50 m. Its 31 March 2026 publication includes Jan De Nul's post-dredging environmental report based on January monitoring. That is strong physical-execution evidence, but the public chain still lacks final measured quantities, accepted bathymetry, owner completion and final account.

5 August 2026 / 4 sources
Brief / Confirmed

Nacala's April completion target now needs an actual acceptance record

Jiangxi Water and Hydropower Construction Group signed W-15/23 for Nacala's intake, treatment, transmission and pumping works in January 2024. ARA Norte documented the contractor team and treatment, pumping and elevated-storage construction sites in September 2025. The World Bank's completion report says two Nacala contracts remained incomplete at project closing and were expected to finish with Netherlands financing in April 2026. No cited package completion or acceptance followed that forecast date.

16 August 2026 / 5 sources
Brief / Confirmed

Libertad dredging is reported complete without published package closeout

Rayman Builders signed the USD 1.071 million Libertad Outfall dredging contract on 6 October 2023. The Philippines Commission on Audit identifies the same package as DPWH contract 22Z00033, records a PHP 60.833 million contract cost and lists PHP 60.665 million in construction in progress at 31 December 2024. A November-December 2025 World Bank mission reports that all eight DPWH dredging contracts were completed. That supports completed contract status for the group that includes Libertad, but it does not publish this package's measured volume, sediment destination, as-built geometry, hydraulic clearance or DPWH acceptance.

16 August 2026 / 5 sources
Brief / Confirmed

Preah Sihanouk's inspectorate jetty has an award, not a mobilisation record

Taing Cheng Oing Construction & Import Export signed SCMFP FiA/CW-03 on 9 March 2026. The approved design defines a 2,226.71 m2 reinforced-concrete boat-mooring and landing platform, 3.5-4.0 m wide, within the existing Preah Sihanouk fisheries inspectorate. ADB reports a financed amount of 472,336.05 but not its currency or the full contract value, and no cited source proves mobilisation.

5 August 2026 / 4 sources
Brief / Confirmed

Salcombe's signed dredging contract still lacks a completion record

South Hams District Council signed Van Oord UK Limited on 11 March 2026 for GBP 101,600 excluding VAT, with an estimated contract period ending 11 May. The earlier tender expected water injection dredging at Batson Creek, Lincombe and Kingsbridge. Public records confirm the award and tendered scope, but not mobilisation, the plant used, measured quantities, post-dredge levels, navigation release or owner acceptance.

6 August 2026 / 6 sources
Brief / Confirmed

Menzel Abderrahmane's ETEP award still lacks a verified works start

TED confirms that ETEP signed the combined fishing-port and coastal-esplanade contract for TND 20,018,762.19 on 28 April 2025, with a stated 28-month duration. The EIA exposes a substantial marine package, including a 493 m breakwater and 5,400 m3 of planned dredging. Yet the public delivery chain stops short of technical works: July 2025 reporting described site-facility locations and pending administration, and parliament still described the project as delayed in February 2026.

9 August 2026 / 5 sources
Brief / Confirmed

Newell Beach physical completion lacks a published final account

TMR confirms that Newell Beach's ramp, fixed walkway, fishing platform, rock wall and dredged all-tide access were complete in May 2022. The commercial record is less closed: CN-17011 rose from AUD 2,560,154 to AUD 2,603,835 after a disclosed variation; RECS held a separate AUD 44,000 inspection contract; and completion reporting used an AUD 3.5 million whole-facility figure. None is a public final account.

6 August 2026 / 6 sources
Brief / Confirmed

Poona's January target passed before access dredging began

TMR expected Poona's full boat-ramp package to finish by January 2026. MSQ then scheduled approach dredging and foreshore nourishment for 9-27 February and closed the ramp from 16 February while upgrade works continued. The contract disclosure rose from AUD 2,041,001 to AUD 2,448,002, but the variation scope and final account remain unpublished.

6 August 2026 / 8 sources
Brief / Confirmed

Burry Port's GBP 425,000 emergency dredge still needs field evidence

Carmarthenshire County Council signed Kaymac Marine & Civil Engineering for emergency sand dredging of Burry Port's outer harbour and approach channel, with placement on East Beach. The GBP 425,000 excluding VAT contract runs on paper from 13 July to 31 October 2026. In parallel, Anthony D. Bates advises on mechanical and water-injection options and a 5-10 year maintenance strategy. Neither contract notice proves field delivery.

6 August 2026 / 6 sources
Brief / Confirmed

TDG Lot I has a lead RTI, not a named subcontract chain

Terminal del Golfo has concluded a EUR 10,868,519.12 first-lot works contract with a planned RTI of Dott. Carlo Agnese, SET and Ferraloro. TED identifies Carlo Agnese as group leader and a 419-day duration, but publishes no start date or named subcontractor. Its 48.67% and EUR 6.073 million subcontract fields do not reconcile exactly to the award or reported tender-base denominators.

7 August 2026 / 6 sources
Brief / Confirmed

Atlantic Canada adds CAD 14.45m across three wharf systems

Three confirmed base contracts place CAD 14,454,531.96 of Nova Scotia fishing-harbour work under named primes. Zutphen Contractors holds Glace Bay's D1-D11 demolition and steel H-pile marginal-wharf package. Dexter Construction holds Meteghan's floating-dock and pipe-pile replacement. Connors Diving holds Meteghan's separate Wharf 403 concrete-repair and FRP pile-jacket package. The exact sum defines current award scale, while the three contracts retain different methods, terms, work fronts and acceptance records.

8 August 2026 / 6 sources
Brief / Confirmed

Glace Bay puts D1-D11 under a CAD 8.90m prime contract

A CAD 8,896,913.40 federal award places demolition and reconstruction of Glace Bay wharf structures D1 through D11 with Zutphen Contractors under CW2454987. The replacement changes the structural system from mainly timber cribs to a steel H-pile-supported marginal wharf. The federal contract page fixes the prime, amount and 2 June 2026 to 31 March 2027 period; DFO's earlier navigation filing fixes the Renwick Brook worksite. Neither source establishes site possession, first demolition or first pile.

8 August 2026 / 3 sources
Brief / Confirmed

Meteghan splits floating access from pile rehabilitation

Two separate contracts now govern Meteghan Small Craft Harbour. Dexter Construction holds CAD 4,292,100.00 CW2462474 through 30 November 2026 to replace three floating-dock systems and associated pipe piles, except the middle set replaced in 2018. Connors Diving holds CAD 1,265,518.56 contract 4500109325 through 31 March 2027 for Wharf 403 concrete removal, repairs and FRP pile jackets. Shared geography does not create a prime-subcontract relationship or a common acceptance record.

8 August 2026 / 4 sources
Brief / Confirmed

Fremantle-Hillarys contract records AUD 14.448m expenditure

Tenders WA records AUD 15.582 million original estimate, AUD 14.464 million revised estimate and AUD 14.448 million actual contract expenditure for DOT409421RFT. Its eleven published variation amounts net to minus AUD 1,117,808, exactly reconciling the original and revised estimates; actual expenditure is another AUD 16,122 lower. The owner separately described Fremantle Jetty 3 as an AUD 4.6 million project and Hillarys as an AUD 10 million project.

8 August 2026 / 7 sources
Brief / Confirmed

Fremantle Jetty 3 records AUD 4.6m project cost

Transport WA records Fremantle Fishing Boat Harbour Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost. The replacement delivered 45 floating berths after demolition and new-pile installation photographed in October 2022. Its design-and-construct award sits inside DOT409421RFT, a common contract covering both Fremantle and Hillarys.

8 August 2026 / 5 sources
Brief / Confirmed

Hillarys five-jetty replacement completes at AUD 10m

Transport WA records the final Hillarys Boat Harbour replacement stage completed in April 2024 as an AUD 10 million project. Five floating jetties and a realigned 3.5-metre central walkway now serve 115 pens. The annual report also publishes major installed quantities, Western Australian manufacturing outcomes and an 84% metropolitan-WA spend share.

8 August 2026 / 5 sources
Brief / Confirmed

Fox Island River has three package clocks, not one

Fox Island River's current public chain contains a 2023 entrance-improvement award, a separate 2024 channel re-dredging award and a 2026 marginal-wharf proposal still in assessment. Each package has a different supplier or open supplier gate, scope and evidence clock.

9 August 2026 / 6 sources
Brief / Confirmed

Fox Island River wharf remains a pre-award workfront

Fox Island River's 2026 channel-wall proposal is still an assessment-stage project. Its disclosed work covers marginal-wharf demolition and replacement, steel sheet piling, reinforced concrete, shoreline reinstatement, parking, a jib crane, lighting and an electrical shed, while procurement and delivery parties remain open.

9 August 2026 / 4 sources
Brief / Confirmed

NOC's GBP 88,800 wall repair contract still needs handback evidence

National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT. The contract covered quayside wall and pontoon repairs at NOC Southampton and ran from 13 August to 12 September 2025. Mobilisation, repair quantities, handback, acceptance and final payment remain unconfirmed in public sources.

9 August 2026 / 3 sources
Brief / Confirmed

Ringvaart routes 86,500 m3 away from the canal

The signed Ringvaart 2 contract gives Van der Lee an estimated 108,000 cubic metres of canal material to manage across two distinct routes: about 86,500 cubic metres to an approved processor and 21,500 cubic metres to a local grassland depot.

9 August 2026 / 4 sources
Brief / Confirmed

Burry Port's GBP 72.6k float award does not prove installation

A direct goods award to Solent Marine Ltd covers replacement floats for Burry Port Harbour's pontoons. The contract is GBP 72,600 excluding VAT and runs from 16 March 2026 to 31 March 2029. Solent Marine is the confirmed supplier, while float quantity, installation responsibility and accepted replacement work remain unpublished.

9 August 2026 / 5 sources
Brief / Confirmed

Lower Yarra's completed programme does not close AMA's current contract

AMA is the named supplier on a current AUD 1.93985 million Lower Yarra contract and the named Campaign C contractor. A separate annual report says the 2022-24 programme finished in 2024; that does not prove contract closeout, accepted quantities or final depth.

16 August 2026 / 6 sources
Brief / Confirmed

Manson's Berths 238-239 award resolves 12 subcontract packages

Los Angeles RAMP displays the USD 27,414,900 opportunity amount on 13 award-participant rows, but the Port of Los Angeles contractor attachment resolves the structure: Manson is the prime and 12 named subcontractors carry bid-stage packages totaling USD 3,331,945, or 12.15% of the bid. Johnson-Peltier's USD 1,530,000 electrical package is the largest lower-tier line. The Port's January 2026 capital report separately records the owner project at 22% construction completion through November 2025.

16 August 2026 / 5 sources
Brief / Confirmed

Apia's 100-metre breakwater moves to the July 2027 critical path

Samoa Ports Authority's July-December 2024 monitoring report placed CHEC's Section 3 breakwater and whole-project completion in December 2026. The later implementation baseline moves the 100-metre breakwater works to mid-July 2027, followed by a one-year defects period. Sections 1 and 2 had June 2026 close-out and handover expectations, but no later signed acceptance certificate was published.

16 August 2026 / 5 sources
Brief / Confirmed

Lock and Dam 9 separates G&G fabrication from USACE installation

USACE's 11 August completion account resolves the most important delivery-chain question at Lock and Dam 9. G&G Steel fabricated the four replacement miter-gate leaves in Alabama over about two years, but it did not perform the reported field installation. St. Paul and Rock Island District maintenance and repair crews completed that work over four July closure days with Rock Island's 500-ton heavy-lift crane The Quad Cities.

16 August 2026 / 3 sources
Brief / Confirmed

Bellingham's USD 22.47m marine contract exposes a 30-company downstream chain

American Construction's USD 22,472,328.83 award covers contaminated-sediment dredging, a new heavy-lift wharf, terminal repairs and utilities at Bellingham Shipping Terminal. Washington L&I identifies 30 unique downstream companies through 37 intent filings and 35 affidavit filings, but the statutory chain is not a substitute for executed-scope, quantity or acceptance evidence.

12 August 2026 / 8 sources
Brief / Confirmed

Winterton wharf contract is marked complete in Public Accounts

Maher's Contracting's Winterton award grew from CAD 2,616,163.75 to CAD 2,759,914 in CanadaBuys. The federal Public Accounts separately present CAD 2,399,925 as amount contracted, mark the contract completed in 2023-24 and report CAD 2,399,651 spent to date. The exact 1.15 ratio is consistent with HST treatment; the values describe one contract, not two funding streams.

13 August 2026 / 6 sources
Brief / Confirmed

Wesleyville-Brookfield dock contract is marked complete

Granite Management's ten-week DFO contract combined Wesleyville floating-dock removal and boardwalk repair with a new Brookfield access, crib, dredging, gangway and two-dock system. Public Accounts mark the contract completed at CAD 393,285, but do not close the physical asset or supply-chain record.

13 August 2026 / 6 sources
Brief / Confirmed

Port de Grave wharf contract is marked complete in Public Accounts

Maher's Contracting's Port de Grave award grew from CAD 1,547,256 to CAD 1,763,368 through two published monetary amendments. Public Accounts separately present CAD 1,533,364 as both amount contracted and expenditure to date and mark the contract completed in 2022-23.

13 August 2026 / 6 sources
Brief / Confirmed

Veseli marina opens while its modification record exposes brownfield risk

Veseli nad Moravou's phase-one marina expansion is operating with 66 spaces after IDS delivered fixed quay edges, floating fingers, bank protection, access and utility systems. Official modification notices show how buried structures, timber piles, weak foundations, unsuitable soil, sediment and a damaged pipe changed delivery.

12 August 2026 / 6 sources

Related project records

Canada / Confirmed

Skinners Pond wharf 401 copewall rehabilitation

Fishing harbour wharf, dredging and shore protection / Kildare Construction Ltd. received CAD 1.10 million contract 4500013345 on 23 December 2021 for structure 401; the 15 June 2022 target date is published, but completion and owner acceptance remain unverified

Last checked 12 August 2026 / 5 sources
United Kingdom / Confirmed

Bristol Floating Harbour 2026 maintenance dredging

Maintenance dredging, floating-harbour navigation and marina access / Bullo Limited holds the GBP 392,500 contract; Bristol notice 36/26 schedules a 10-17 August Baltic Wharf work window beyond the original 26 June contract end

Last checked 10 August 2026 / 8 sources
Colombia / Confirmed

Tumaco port access-channel deepening, Phase I

Capital dredging and navigation-channel deepening / SECOP II records contract GN2862-2026 signed with Consorcio Puerto Tumaco II for COP 26.826 billion and eight months, but the public ledger has no start date, invoicing or payment and the separate supervision procurement remains unawarded

Last checked 6 August 2026 / 9 sources
Colombia / Confirmed

Barranquilla access-channel maintenance dredging

Navigation channel maintenance dredging / SECOP II shows contract 0-525-2024 modified to COP 241.685 billion and 31 December 2026 after a 365-day extension; Cormagdalena reported 80.7% execution at 31 March before the later ledger update, while completion and acceptance remain unconfirmed

Last checked 6 August 2026 / 7 sources
India / Confirmed

Hooghly four-location floating passenger-jetties package

Inland-waterway floating jetties, gangways and passenger facilities / Two lots were signed on 16 August 2024 for Tamlipara, Chinsurah, Metiabruze and Pujali; the June 2026 World Bank ISR says Metiabruze remains under implementation but its results table says all 45 project jetties are complete

Last checked 5 August 2026 / 7 sources
India / Confirmed

West Bengal 45-jetty contract ledger

Inland-waterway floating jetties, gangways and passenger facilities / World Bank data identifies 21 direct works contracts across the 29-jetty Phase I and 16-jetty Phase II programme; the June 2026 ISR says 44 of 45 locations are complete with Metiabruze under implementation, while its results table says all 45 are complete

Last checked 6 August 2026 / 8 sources
Finland / Confirmed

Ferry Terminal Turku marine and landside works

Ferry-terminal piers, passenger bridges and port-yard renewal / Pier S1 was handed over on 15 June 2026 but will not enter service until March 2027; the joint terminal, passenger bridges and 11-hectare field works remain under construction, while Quay S2 is targeted for 2028

Last checked 5 August 2026 / 11 sources
Canada / Confirmed

Centreville small craft harbour wharf reconstruction

Fishing harbour wharf, dredging and shore protection / Kerr Limited's CAD 18.86 million contract reached its amended 31 December 2025 expiry after 11 amendments; no cited owner record confirms accepted completion, final dredged quantities or reopening

Last checked 16 August 2026 / 6 sources
Canada / Confirmed

Cheticamp Jobs Wharf floating-dock reconstruction

Fishing harbour wharf, dredging and shore protection / Superior Contracting's CAD 1.264 million contract ran from 14 October 2022 to 31 March 2023 for an integrated timber-wharf, dredging, breakwater, floating-dock and electrical package; the reviewed federal record does not publish accepted completion, measured quantities or final account

Last checked 9 August 2026 / 5 sources
Canada / Confirmed

Pugwash small craft harbour floating-dock works

Fishing harbour wharf, dredging and shore protection / Brian MacGillivary Construction's CAD 516,100 contract ran from 22 November 2023 to 29 March 2024; CanadaBuys confirms the award and amended term but publishes no accepted dredging quantity, dock handover or completion certificate

Last checked 6 August 2026 / 5 sources
Canada / Confirmed

Harbour Grace small craft harbour wharf reconstruction

Fishing harbour wharf, dredging and shore protection / Bulldog Contracting received the CAD 7.05 million award on 1 April 2022 for timber-crib wharf, finger-pier, dredging and utility works; the reviewed federal record does not establish the delivery end date, accepted completion or final account

Last checked 6 August 2026 / 5 sources
Canada / Confirmed

Petit-Cap structure 403 wharf reconstruction

Fishing harbour wharf, dredging and shore protection / Landco Construction's CAD 3.08 million contract ran from 2 November 2023 to 4 July 2024 for a Berlin-wall marginal wharf, harbour dredging and electrical reinstatement; CanadaBuys does not publish accepted completion or final quantities

Last checked 6 August 2026 / 4 sources
Canada / Confirmed

Sainte-Marie-Sur-Mer structure 401 wharf and breakwater works

Fishing harbour wharf, dredging and shore protection / L Breau and Sons Ltd holds active CAD 8.75 million contract CW2440554 through 24 August 2027 for structure 401 wharf reconstruction and a new breakwater; mobilisation, measured work and acceptance remain unconfirmed

Last checked 7 August 2026 / 4 sources
Canada / Confirmed

Grande-Anse harbour-basin dredging and containment-cell works

Fishing harbour wharf, dredging and shore protection / Les Entreprises P E C inc holds active CAD 862,270 contract CW2452382 through 31 December 2026 for barge-excavator dredging and containment-cell reconfiguration; earliest site start was 6 July and field progress remains unverified

Last checked 7 August 2026 / 4 sources
Canada / Confirmed

Larrys River small craft harbour breakwater reconstruction

Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds active CAD 2.75 million contract CW2455209 through 27 November 2026 for rubble-mound breakwater construction at Larrys River; award and scope are confirmed but mobilisation and physical progress are not

Last checked 7 August 2026 / 4 sources
Netherlands / Confirmed

Port of Rotterdam Yangtzekanaal widening and quay programme

Port infrastructure / Phase A tug quay delivered; the same consortium has started Phase B, including 1.4 million m3 of sand dredging; Phase C remains a post-2028 package

Last checked 12 August 2026 / 9 sources
Senegal / Confirmed

Dakar Mamelles desalination intake and brine discharge

Marine utilities / Plant remained under construction in February 2026; commissioning was expected later in 2026, while final marine handover evidence remains unpublished

Last checked 19 July 2026 / 6 sources
Saudi Arabia / Confirmed

Ras Mohaisen Independent Water Project and Marine Intake/Outfall

Marine utilities / Project agreements, the L&T-Lantania EPC award and December 2025 financial close are evidenced, and ACWA's 3 March 2026 year-end report classifies the full 300,000 m3/day capacity as under construction; offshore mobilisation, installed intake or outfall geometry, first water and accepted production are not dated

Last checked 15 July 2026 / 8 sources
Democratic Republic of the Congo / Confirmed

Banana Deep-water Port Phase One

Deep-water ports and container terminals / Phase-one contract announced with an estimated 24-month term; no current cited record confirms accepted marine works, terminal commissioning, or commercial opening

Last checked 16 August 2026 / 7 sources
Senegal / Confirmed

Port of Ndayane Deep-water Port and Container Terminal

Deep-water ports and container terminals / DP World reports the major dredging works complete 13 months ahead of schedule; quay and other marine and civil works remain active, while 2028 is a target rather than an accepted opening date

Last checked 14 August 2026 / 16 sources
Morocco / Confirmed

Nador West Med Deep-water Port

Deep-water ports and energy terminals / Basic port infrastructure reported complete; access-control, port-management, systems, staffing, and service preparations remain active ahead of the East terminal's Q4 2026 commissioning target, while the West terminal follows from 2027

Last checked 15 August 2026 / 12 sources
Brazil / Confirmed

Paranaguá access channel dredging concession

Dredging / Concession signed; 1 August operating transition remains scheduled, with the 13.3-metre baseline still controlling

Last checked 16 July 2026 / 8 sources
United States / Confirmed

Niagara River Emerald Shiner Fish Passage

Coastal infrastructure / USACE reports the 700-foot full phase completed in May 2026 and the combined 778-foot fish passage opened with a ribbon-cutting on 23 July 2026

Last checked 23 July 2026 / 5 sources
Nauru / Confirmed

Nauru Aiwo Port climate-resilient redevelopment

Port infrastructure / ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items

Last checked 19 July 2026 / 9 sources
Egypt / Confirmed

Damietta Alliance Container Terminal (Tahya Misr 1)

Deep-water ports and container terminals / Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity

Last checked 20 July 2026 / 7 sources
UAE / Confirmed

Ruwais LNG marine access and export terminal

Deep-water ports and energy terminals / Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published

Last checked 20 July 2026 / 7 sources
Benin / Confirmed

Port of Cotonou Terminal 5 bulk terminal

Port infrastructure / The port authority reports 69% physical progress and 72% overall progress, while its published 2021-2024 delivery period is no longer current

Last checked 20 July 2026 / 6 sources
Saudi Arabia / Confirmed

Rabigh 4 IWP intake, outfall and storage system

Marine utilities / EPC performance test completed on 19 February 2026; SWPC commercial-operation confirmation remains unpublished

Last checked 14 August 2026 / 7 sources
Denmark / Germany / Confirmed

Fehmarnbelt Fixed Link Immersed Tunnel

Immersed tunnels and marine crossings / Third tunnel element immersed and connected on 1 August 2026; protection, serial immersion, systems integration, and a two-stage road-then-rail opening remain active

Last checked 2 August 2026 / 11 sources
Benin / Côte d'Ivoire / Mauritania / São Tomé and Príncipe / Senegal / Togo / Confirmed

WACA ResIP 1 coastal protection works programme

Coastal infrastructure / ResIP 1 in finalisation; country work fronts and closing dates remain separate

Last checked 17 July 2026 / 5 sources
Poland / Confirmed

Baltic Hub T3 deep-water container terminal

Deep-water ports and container terminals / Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation

Last checked 1 August 2026 / 8 sources
Croatia / Confirmed

Ploce New Bulk Cargo Terminal

Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems / Civil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacity

Last checked 2 August 2026 / 10 sources
Lesotho / Confirmed

Lesotho Ha Setene W03A Intake and Water Treatment Works

Water intake and treatment works / The official LLWDP dashboard currently displays 85% overall progress under a malformed update date; the last fully dated World Bank restructuring paper recorded 65% physical completion after a 24 February 2026 flood compromised the temporary river diversion and cofferdam, delaying intake works

Last checked 3 August 2026 / 10 sources
France / Confirmed

Dunkirk Braek submerged sand-discharge pipeline replacement

Coastal protection and dredged-sand reuse / Baggerbedrijf de Boer holds the EUR 1.720365 million replacement contract concluded on 13 January 2025; the planned 31 May 2025 in-service deadline has passed, while physical completion, acceptance and downstream packages remain unverified

Last checked 5 August 2026 / 8 sources
United Kingdom / Confirmed

Harwich Haven maintenance dredging 2026-2031

Maintenance dredging, beneficial use and dredging technology / GBP 100m award notice names Suffolk Dredging LLP for a five-year base term; a contract-details notice, reconciled extension limit and attribution of 2026 field activity remain unconfirmed

Last checked 5 August 2026 / 12 sources
Mali / Confirmed

Mopti boat-quay access dredging and sediment clearance

Inland river-port access dredging and sediment clearance / The package was officially launched on 13 February 2025 and a project team inspected progress on 6 March 2025; the latest disclosed procurement plan, dated 13 April 2026, still records the contract only as signed, and no official completion, accepted bathymetry or operating release has been published

Last checked 5 August 2026 / 9 sources
Australia / Confirmed

Warrawong Parklands Kully Bay seawall reconstruction

Foreshore seawall and rip-rap protection / Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence

Last checked 5 August 2026 / 5 sources
United States / Confirmed

Moss Landing Harbor jetty repair and maintenance dredging

Breakwater armour repair, access dredging and nearshore placement / Ahtna Infrastructure & Technologies held the USD 16,037,425 current-obligation contract for Moss Landing Harbor dredging and jetty repair; the US Coast Guard published 2025 field-work windows and USACE published August-September post-dredge surveys, but the 23 January 2026 contract end does not establish final quantity, jetty acceptance, completion or final account

Last checked 5 August 2026 / 7 sources
Spain / Confirmed

Santoña North Basin fishing-quay structural repair

Piled fishing-quay concrete rehabilitation and metal fender renewal / Cantabria formalized the EUR 2,486,545.15 excluding-VAT works contract with the Cuevas Gestión de Obras-COMSA UTE on 9 July 2026; the signed contract requires a viable setting-out check before the 24-month execution period starts, while the setting-out act, site mobilisation, monthly production and lower-tier appointments remain unpublished

Last checked 5 August 2026 / 5 sources
Peru / Confirmed

Callao access-channel and inner-roadstead maintenance dredging

Maintenance dredging and operating-port access / APN started the access-channel and inner-roadstead campaign on 20 December 2025; a Jan De Nul post-dredging environmental report covers January 2026 monitoring, while owner acceptance, as-built hydrography and final account remain unverified

Last checked 5 August 2026 / 5 sources
Mozambique / Confirmed

Nacala intake, water-treatment, transmission and pumping works

Water intake and treatment works / Jiangxi Water and Hydropower Construction Group signed the USD 17.985 million W-15/23 contract on 10 January 2024; ARA Norte documented work at the treatment, pumping and elevated-storage sites in September 2025, and no package completion or acceptance record follows the cited April 2026 target

Last checked 14 August 2026 / 7 sources
Philippines / Confirmed

Libertad Outfall dredging works

Dredging / Group completion reported; Libertad closeout remains unpublished.

Last checked 14 August 2026 / 7 sources
Cambodia / Confirmed

Preah Sihanouk Marine Fisheries Inspectorate boat mooring and jetty

Marine infrastructure / Taing Cheng Oing Construction & Import Export signed package SCMFP FiA/CW-03 on 9 March 2026; ADB reports a financed amount of 472,336.05 without currency or full contract value, and mobilisation or physical start is not independently confirmed

Last checked 5 August 2026 / 4 sources
United Kingdom / Confirmed

Salcombe-Kingsbridge estuary 2026 maintenance dredging

Maintenance dredging and operating-port access / South Hams District Council signed Van Oord UK Limited on 11 March 2026 for GBP 101,600 excluding VAT; water injection dredging was the tendered expectation for Batson Creek, Lincombe and Kingsbridge, but no public mobilisation, post-dredge survey or acceptance record has been located

Last checked 6 August 2026 / 8 sources
Tunisia / Confirmed

Menzel Abderrahmane fishing-port extension and coastal esplanade

Fishing-port expansion, dredging, breakwater, quay and coastal esplanade / ETEP signed the TND 20,018,762.19 works contract on 28 April 2025, but Tunisia's parliament still described the port and esplanade project as delayed during a February 2026 site visit; physical start, achieved quantities and supervision award remain unverified

Last checked 9 August 2026 / 8 sources
Australia / Confirmed

Newell Beach all-tide boat ramp upgrade

Public boat-launch infrastructure, capital dredging and fixed access / Queensland TMR completed the upgraded all-tide facility in May 2022 after Australian Marine & Civil delivered the main works under CN-17011; the published contract disclosure rose from AUD 2,560,154 to AUD 2,603,835 after a variation

Last checked 6 August 2026 / 10 sources
Australia / Confirmed

Poona boat ramp and access-channel upgrade

Public boat-launch infrastructure, capital dredging and fixed access / Australian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026

Last checked 6 August 2026 / 10 sources
United Kingdom / Confirmed

Burry Port Harbour emergency sand dredging

Maintenance dredging, approach-channel access and beach placement / Carmarthenshire County Council signed a GBP 425,000 excluding VAT emergency dredging contract with Kaymac Marine & Civil Engineering on 29 June 2026 for a 13 July to 31 October delivery window; the council has published no mobilisation, dredger, production, survey, completion or acceptance update

Last checked 6 August 2026 / 8 sources
Italy / Confirmed

La Spezia Terminal del Golfo expansion and redevelopment Lot I

Container and multipurpose terminal quay extension / TED notice 521188-2026 records a 23 July 2026 works contract with a planned RTI led by Dott. Carlo Agnese at EUR 10,868,519.12 for 419 days; notice to proceed, mobilisation, installed quantities and named subcontractors remain unverified

Last checked 7 August 2026 / 7 sources
Canada / Confirmed

Glace Bay small craft harbour wharf reconstruction

Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified

Last checked 8 August 2026 / 4 sources
Canada / Confirmed

Meteghan floating wharf and pile rehabilitation

Fishing harbour wharf, dredging and shore protection / Dexter holds CAD 4.29 million CW2462474 for floating-dock and pipe-pile replacement, while Connors Diving holds CAD 1.27 million 4500109325 for Wharf 403 pile jackets and concrete repairs; both awards are active but mobilisation and progress are unverified

Last checked 8 August 2026 / 5 sources
Australia / Confirmed

Fremantle Fishing Boat Harbour Jetty 3 replacement

Marinas, pontoons and berthing infrastructure / Transport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade Sales

Last checked 8 August 2026 / 6 sources
Australia / Confirmed

Hillarys Boat Harbour jetties A, F, G, H and J replacement

Marinas, pontoons and berthing infrastructure / Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract

Last checked 8 August 2026 / 5 sources
Canada / Confirmed

Fox Island River harbour entrance improvement and re-dredging

Small-craft-harbour entrance dredging and breakwater works / Marine Contractors' CAD 1.499m entrance-improvement contract and R.J.G Construction's separate CAD 1.133m channel re-dredging contract have both reached their published administrative end dates, but no completion certificate, accepted hydrography, final dredged quantity or causal link between the packages is public

Last checked 9 August 2026 / 7 sources
United Kingdom / Confirmed

NOC Southampton quayside wall and pontoon repairs

Seawall, quayside and pontoon repair / National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT; the contract period ran from 13 August to 12 September 2025, but no dated completion, acceptance or final-account record has been located

Last checked 9 August 2026 / 4 sources
Netherlands / Confirmed

Ringvaart 2 dredging

Dredging / Award signed; start unverified.

Last checked 9 August 2026 / 4 sources
United Kingdom / Confirmed

Burry Port pontoon floats

Marinas, pontoons and berthing infrastructure / Solent Marine holds a GBP 72,600 float award.

Last checked 9 August 2026 / 6 sources
Australia / Confirmed

Lower Yarra River Maintenance Dredging Program

Urban waterway maintenance dredging, navigation access and in-river material placement / Buying for Victoria records Australasian Marine Associates on a current AUD 1.93985 million contract starting 8 September 2021; Parks Victoria confirms AMA delivered Campaign C in 2024, while the owner programme was reported complete and the next funding cycle remained open

Last checked 10 August 2026 / 7 sources
United States / Confirmed

Los Angeles Berths 238-239 Marine Oil Terminal Improvements

MOTEMS wharf replacement, dolphins, fenders and maintenance dredging / The Port of Los Angeles January 2026 CIP report classifies the project in construction and, using actuals through November 2025, records 22% construction completion, a 31 March 2027 forecast finish, USD 39,288,466 projected project cost and USD 6,315,074 spent to date

Last checked 11 August 2026 / 9 sources
Samoa / Confirmed

Apia Port climate-resilient breakwater and terminal upgrade

Port infrastructure / Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate

Last checked 11 August 2026 / 8 sources
United States / Confirmed

Upper Mississippi Lock and Dam 9 miter-gate replacement

Inland navigation lock rehabilitation and hydraulic steel structures / USACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublished

Last checked 11 August 2026 / 4 sources
United States / Confirmed

Bellingham Shipping Terminal marine infrastructure and dredging

Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities / Port reporting confirms key dock and stormwater upgrades were completed in 2025 and navigation and environmental work advanced; Washington L&I records American Construction's contractor-reported 8 April 2026 work-completed date, but no filed Notice of Completion, owner acceptance, final hydrographic survey, final dredged quantity or final account is evidenced

Last checked 12 August 2026 / 12 sources
Canada / Confirmed

Winterton small craft harbour wharf reconstruction

Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed

Last checked 13 August 2026 / 7 sources
Canada / Confirmed

Wesleyville and Brookfield floating-dock reconstruction

Fishing harbour wharf, dredging and shore protection / Granite Management received DFO contract 4500013526 on 23 December 2021 for a two-site floating-dock package; the 2021-22 Public Accounts mark the contract completed, while physical acceptance records remain unpublished

Last checked 13 August 2026 / 6 sources
Canada / Confirmed

Port de Grave marginal wharf reconstruction

Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210731/001/PWD on 15 November 2021; CanadaBuys records a CAD 1,763,368 cumulative contract after amendments, and the 2022-23 Public Accounts mark the Port de Grave contract completed

Last checked 13 August 2026 / 7 sources
Czechia / Confirmed

Veseli nad Moravou marina phase-one expansion

Inland marina quay edges, floating fingers, bank protection and utilities / The Czech Waterways Directorate opened 30 new public berths in August 2025 and the Transport Ministry reports the expanded marina operating with capacity for 66 boats in the 2026 season; IDS holds the phase-one works contract, with the highest reviewed official modification snapshot at CZK 86,312,219.98

Last checked 12 August 2026 / 8 sources

Scope and corrections

This general technical reference is not project-specific design advice. Project status is dated and linked to its public sources; corrections can be submitted with the relevant acceptance, inspection, maintenance, operating or service record.

Read featured analysis Open knowledge centre Submit a correction