Project record
Budimex; exact Baltic Hub T3 terminal during the 2025 delivery period
Baltic Hub completed Poland's 36-hectare T3 deep-water terminal on an artificial platform at the Port of Gdansk. The Budimex-DEME consortium delivered the marine and civil works; DEME identifies dredging and reclamation as its scope, while Haskoning records engineering, investigations, tender support, construction supervision and project management. The 717-metre quay, 17.5-metre water depth, seven STS cranes and 20 remotely operated aRMG cranes add 1.5 million TEU of annual capacity. The terminal became fully operational in October 2025, although 2026 crane relocation and yard-line commissioning show that automation optimisation continued after marine completion.
Poland / Europe
Deep-water ports and container terminals
Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation / Confirmed
1 August 2026
Coverage
Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe operator opened storage blocks X7 and Y7 after the aRMG relocation sequence, adding evidence of continuing automation ramp-up without changing the completed marine-works status.
SourceBaltic Hub's annual review separates the June inauguration from the point at which the complete terminal entered operation and ties T3 to record 2025 throughput.
SourceThe owner confirmed the last yard-use permit and final four aRMG cranes in operation, closing the core construction programme.
SourceThe inauguration placed the new quay and part of the terminal into commercial use while full yard completion and commissioning continued into the second half of 2025.
SourceEvidence gap