Project record

Baltic Hub T3 deep-water container terminal

Aerial view of an MSC container ship alongside the completed Baltic Hub T3 deep-water quay and automated yard in Gdansk

Budimex; exact Baltic Hub T3 terminal during the 2025 delivery period

Baltic Hub completed Poland's 36-hectare T3 deep-water terminal on an artificial platform at the Port of Gdansk. The Budimex-DEME consortium delivered the marine and civil works; DEME identifies dredging and reclamation as its scope, while Haskoning records engineering, investigations, tender support, construction supervision and project management. The 717-metre quay, 17.5-metre water depth, seven STS cranes and 20 remotely operated aRMG cranes add 1.5 million TEU of annual capacity. The terminal became fully operational in October 2025, although 2026 crane relocation and yard-line commissioning show that automation optimisation continued after marine completion.

Project signal

Completed in Poland

Current status Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation Source confidence Confirmed

Location

Poland / Europe

Segment

Deep-water ports and container terminals

Status

Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation / Confirmed

Last checked

1 August 2026

Coverage

Related sectors

Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Baltic Hub Container Terminal Sp. z o.o., owned by PSA International (40%), Polish Development Fund (30%) and IFM Global Infrastructure Fund (30%)
Delivery parties
Budimex-DEME consortium - general contractor for T3, DEME - dredging, land reclamation and geotechnical design for the 36-hectare artificial platform, Budimex - marine civil, quay and terminal-yard construction within the consortium, Haskoning - site investigations, masterplanning, design support, tender management, construction supervision and project management, ZPMC - handling-equipment supplier named in the owner and Port of Gdansk completion chain, Kuenz - handling-equipment supplier named in the owner and Port of Gdansk completion chain, ABB - handling-equipment and automation supplier named in the owner and Port of Gdansk completion chain
Contract route
Baltic Hub appointed the Budimex-DEME consortium as general contractor and issued the order to commence work on 22 September 2022. Haskoning held the client-side engineering, procurement-support and construction-management role. Public completion acknowledgements name ZPMC, Kuenz and ABB in the handling-equipment chain. Contractor disclosures cite an investment of about EUR 450-470 million at different stages; these are project values, not an audited final account or a breakdown of every subcontract.
Execution window
The construction order was issued in September 2022 and site works began in late 2022. Baltic Hub inaugurated T3 on 6 June 2025, reports that it became fully operational at the beginning of October 2025 and declared construction officially complete on 17 November 2025. In June and July 2026 it continued relocating aRMG cranes and opening yard lines, an operating-system optimisation sequence rather than a reopening of the completed marine contract.
Works package
Create a 36-hectare artificial terminal platform through dredging and reclamation; build a 717-metre deep-water quay at 17.5 metres water depth; construct container yards, pavements, drainage, electrical and telecommunication networks, crane rails and support buildings; and install seven STS quay cranes plus 20 remotely operated aRMG yard cranes. Public sources report 4.3-4.37 million cubic metres of sand, more than 17,500 tonnes of steel and about 160,000 cubic metres of concrete.
Marine interfaces
The reclaimed platform, quay wall, fenders and bollards, dredged berth pocket, crane rails, power supply, stormwater systems and navigational access had to reach structural and operational acceptance before deep-sea calls could transition from testing to commercial handling. The 2026 aRMG moves affect yard flow and automated stacking, not the accepted 717-metre marine frontage.
Commercial evidence boundary
The principal chain is unusually transparent at consortium, specialist-dredging, engineer and equipment-supplier level. Remaining gaps are the allocation of individual quay-wall, piling, paving, electrical, rail, automation-software and commissioning subcontracts; the final account; and equipment-by-equipment acceptance dates. Operational evidence now matters more than construction percentage claims.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Baltic Hub released T3 yard line 7 for operations

The operator opened storage blocks X7 and Y7 after the aRMG relocation sequence, adding evidence of continuing automation ramp-up without changing the completed marine-works status.

Source

Operator confirmed full T3 operation from October 2025

Baltic Hub's annual review separates the June inauguration from the point at which the complete terminal entered operation and ties T3 to record 2025 throughput.

Source

T3 construction was officially completed

The owner confirmed the last yard-use permit and final four aRMG cranes in operation, closing the core construction programme.

Source

Baltic Hub inaugurated the new terminal

The inauguration placed the new quay and part of the terminal into commercial use while full yard completion and commissioning continued into the second half of 2025.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Final aRMG relocation and acceptance by yard line
  • Automated-yard availability and remote-operator performance
  • T3 berth moves per hour and vessel turnaround performance
  • Quay, pavement and settlement performance on the reclaimed platform
  • Rail and gate throughput after full T3 ramp-up
  • Final construction account and unresolved subcontract allocations
  • Any defects-liability or remediation works separated from operating maintenance

Reporting status

Completed, confirmed confidence

Last checked 1 August 2026 across 8 cited sources. The dated timeline above carries the project events.

Last checked 1 August 2026 Cited sources 8