Sector intelligence

Marine utilities and infrastructure intelligence

Seawater intakes and outfalls, marine pipelines, treatment-plant interfaces, island access, harbour facilities, and industrial coastal enabling works.

Projects retain their detailed work segment and may appear in more than one sector when the scope crosses delivery disciplines.

Latest item update 152 public projects 182 related publications 108 connected organizations
On this page

Coverage focus

Water, wastewater, power-water and island-access interfaces

Tracker coverage

152 project records connected to this sector.

Publication coverage

182 current analyses and briefs connect through governed project relationships.

Organization coverage

108 public profiles connect through documented project roles.

Project coverage

All current Marine utilities and infrastructure project records

152 records
Confirmed

Gulfport Harbor deep-draft navigation improvements

United States / Navigation-channel deepening and sedimentation basin / Signed Chief's recommendation dated 23 June 2026; Gulfport included in the House-passed September WRDA bill

planning / Last checked
Confirmed

Sizewell C Marine Bulk Import Facility

United Kingdom / Bulk-import jetty, conveyor and berthing pocket / Owner reports offshore construction progress and expects bulk-import operation in Q2 2027

construction / Last checked
Confirmed

Davis station seawater-intake and reverse-osmosis renewal

Australian Antarctic Territory / Seawater intake, water production and station services / Water-system modules dispatched in October 2026; V1 schedule plans Davis over-ice resupply for 4-13 November

mobilisation / Last checked
Confirmed

Marsa LNG Sohar jetty and marine access

Oman / Deep-water ports and energy terminals / Access-channel dredging completed; LNG jetty, shore protection and drainage under construction

construction / Last checked
Confirmed

Lower Molonglo membrane-bioreactor renewal

Australia / Wastewater bioreactor foundations and commissioning / Excavation completed in June; August owner plan schedules foundation pours in October, November and December 2026

construction / Last checked
Confirmed

Aqaba New Oil Terminal marine EPC package

Jordan / Liquid-cargo terminal berth enhancement / December bids advertised; document requests closed 28 October and access needs ADC confirmation

tender / Last checked
Confirmed

Holt Lock permanent monolith repair

United States / Inland navigation lock rehabilitation and hydraulic steel structures / Permanent monolith repairs with revised navigation closures

construction / Last checked
Confirmed

Port Ellen ferry terminal marine redevelopment

United Kingdom / Marine infrastructure / Marine construction programme; owner 9 October steel-pile import and local-transfer plan, with actual receipts to confirm.

construction / Last checked
Confirmed

King Abdulaziz Naval Base MMSC IOC facilities

Saudi Arabia / Naval base wharf and fleet-support facilities / USAspending records USD 400,172,871.91 obligated and exercised across 28 transactions through 7 July 2026; current performance end 8 March 2027

construction / Last checked
Confirmed

Aqaba-Amman National Water Carrier marine works

Jordan / Marine utilities / October marine assessment adopts the existing SEPCO intake and a revised canyon outfall; financing approvals recorded, construction release unconfirmed

financing / Last checked
Confirmed

Ebeye Coastal Protection Works

Marshall Islands / Coastal infrastructure / Completed seawall and footpath handed over on 17 September 2026; final account and post-storm performance unverified

completed / Last checked
Confirmed

Ocean City and Peck Beach 2026 Periodic Nourishment

United States / Coastal infrastructure / USACE records September 7 completion; the city reports 1.6 million cubic yards placed; New Jersey requested storm-repair assistance on October 16

completed / Last checked
Confirmed

Mermaid Beach breakwater walkway-unit recovery and repair

United Kingdom / Coastal infrastructure / UK6 notice 097475-2026 names Chunnel Plant Hire and Contractors Limited for the six-unit repair at GBP 169,187.49 excluding VAT; signature is scheduled for 19 October 2026, with reinstatement and acceptance unconfirmed

award / Last checked
Confirmed

Fort George North Glacis sea-wall underpinning

United Kingdom / Coastal infrastructure / Recorded tender deadline passed on 4 November 2026 at 17:00 GMT; advertised duration 28 working days

tender / Last checked
Confirmed

Dunkirk port mechanical preventive-maintenance framework

France / Port structures and mechanical installations maintenance / BOAMP extended submissions to 28 September 2026; that date has passed and the latest buyer-profile result remains unverified

tender / Last checked
Confirmed

Sidmouth and East Beach coastal defence scheme

United Kingdom / Two-stage coastal flood and erosion defence, beach recharge and offshore rock works / East Devon's 28 September UK7 notice records a Boskalis Westminster contract signed on 14 September 2026 at GBP 18,911,242.18 excluding VAT, with a 15 September 2026 to 29 March 2030 contract period; Stage 2 instruction and physical mobilisation remain unconfirmed

award / Last checked
Confirmed

Burry Port pontoon floats

United Kingdom / Marinas, pontoons and berthing infrastructure / Solent Marine holds a GBP 72,600 float award.

award / Last checked
Confirmed

Swansea Morfa Quay and New Cut Road pontoons

United Kingdom / Marinas, pontoons and berthing infrastructure / Swansea signed the GBP 411,775.70 excluding-VAT two-pontoon contract on 15 July; the August amendment revised its start to 5 August, retaining a 2 October end, with site completion and acceptance unconfirmed

award / Last checked
Confirmed

Langstone Coastal Defence Scheme

United Kingdom / Continuous tidal flood and coastal erosion defence with early contractor involvement / Jackson is appointed; April 2027 main construction is planned, with the programme under refinement and signed terms and consent documents outstanding

award / Last checked
Confirmed

IJsselmeerdijk foreshore and conventional dike reinforcement

Netherlands / Coastal infrastructure / Owner reports realization has begun with the lake-side foreshore; conventional dike work planned from early 2027, quantities and acceptance unconfirmed

construction / Last checked
Confirmed

Igoumenitsa Port three-berth OPS shore-power systems

Greece / Commercial-port shore power and electrical utility integration / HEDNO signed the EUR 6.82 million turnkey contract with Paralos on 11 February 2026 for two 3 MVA OPS positions and one 0.5 MVA position. TED names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors; mobilisation, installation, energisation, vessel connection and acceptance remain unconfirmed

award / Last checked
Confirmed

Molo Sali Phase B sheet-pile restoration and quay completion

Italy / Sheet-pile rehabilitation and port-yard conversion / TED notice 514687-2026 records a EUR 8,295,571.84 contract concluded on 23 July 2026 with the Rossi Renzo Costruzioni-led four-member RTI; notice to proceed, mobilisation, named subcontractors and installed work remain unverified

award / Last checked
Confirmed

Mus seawall at Car Nicobar

India / Coastal infrastructure / Recall tender is in post-bid evaluation; no public AOC or named EPC contractor

tender / Last checked
Confirmed

Banana Deep-water Port Phase One

Democratic Republic of the Congo / Deep-water ports and container terminals / Phase-one contract announced with an estimated 24-month term; no current cited record confirms accepted marine works, terminal commissioning, or commercial opening

construction / Last checked
Confirmed

Hammond Cove Marina reconstruction

United States / Marinas, pontoons and berthing infrastructure / New York City's 22 January 2026 award notice names Empire Construction and Property Management Group at USD 4,583,648 for X310-117M; the city hazard plan identifies bulkhead, dock and electrical reconstruction, but no cited record establishes contract signing, notice to proceed, mobilisation or completion

award / Last checked
Confirmed

Dundee Beach boat-ramp maintenance

Australia / Public boat-launch infrastructure, maintenance dredging and fixed access / Northern Territory Tenders Online records T25-1462 as a 12-month awarded period contract to Polaris Marine Constructions at AUD 676,047.56 on an estimated-unit-rate basis

award / Last checked
Confirmed

Nador West Med Deep-water Port

Morocco / Deep-water ports and energy terminals / Basic port infrastructure reported complete; access-control, port-management, systems, staffing, and service preparations remain active ahead of the East terminal's Q4 2026 commissioning target, while the West terminal follows from 2027

commissioning / Last checked
Confirmed

Rabigh 4 IWP intake, outfall and storage system

Saudi Arabia / Marine utilities / EPC performance test completed on 19 February 2026; SWPC commercial-operation confirmation remains unpublished

commissioning / Last checked
Confirmed

Port of Ndayane Deep-water Port and Container Terminal

Senegal / Deep-water ports and container terminals / DP World reports the major dredging works complete 13 months ahead of schedule; quay and other marine and civil works remain active, while 2028 is a target rather than an accepted opening date

construction / Last checked
Confirmed

South Moose Lake 2025 harbour improvements

Canada / Remote fishing-harbour timber crib wharf and floating offloading dock / Fisheries and Oceans Canada awarded ZheMaak Inc. contract 4500091055 for CAD 220,542 on 8 August 2025; the published seven-month term ended on 27 March 2026, but the reviewed federal record does not publish physical completion, accepted quantities, owner handover or a final account

delivery / Last checked
Confirmed

ACME Duqm green-ammonia CBM export terminal

Oman / Deep-water ports and energy terminals / Phase 1 plant construction and CBM equipment delivery are active. Masirah Marine is the reported installation lead; its contract, vessel allocation and ASD-tug support remain undisclosed

construction / Last checked
Confirmed

Edmonds North Portwalk Phase II electrification

United States / Marina electrical infrastructure, waterfront site preparation and public realm / The Port of Edmonds Commission unanimously authorized a contract with TRICO Companies LLC on 8 June 2026; the current owner page marks Phase II in progress and estimates work will begin late in 2026

award / Last checked
Confirmed

Torrent wastewater treatment plant adaptation

Spain / Urban wastewater treatment, tertiary reuse and flood resilience / CHJ currently lists the Torrent adaptation works in execution under the Global Omnium Medioambiente-CICLAGUA-BECSA UTE; its 2025 delivery report fixes the site-start baseline at 19 September 2023 and records separate certified amounts for modification 1 and the post-DANA emergency workfront, while PLACSP's 10 August 2026 modification record adds zero price and zero duration

construction / Last checked
Confirmed

Kuwait Mubarak Al-Kabeer Port Phase I completion

Kuwait / Deep-water ports and container terminals / Phase I EPC signed with CCCC; government follow-up continues, while mobilisation and marine construction remain unverified

award / Last checked
Confirmed

South Tarawa sanitation and three-ocean-outfall rehabilitation

Kiribati / Marine utilities / ADB records the three-outfall civil package completed in August 2018, testing and commissioning in Q2 2019, the wider project physically completed on 31 December 2019, and the financing operation closed

completed / Last checked
Confirmed

Upper Mississippi Lock and Dam 9 miter-gate replacement

United States / Inland navigation lock rehabilitation and hydraulic steel structures / USACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublished

completed / Last checked
Confirmed

Cáceres El Marco wastewater treatment plant

Spain / Urban wastewater treatment, tertiary reuse and renewable-energy integration / ACUAES selected the Aquambiente-COPASA-PESA consortium on 30 July 2026 at EUR 61,784,295.49 excluding VAT; the award notice was published on 4 August, while contract signature, notice to proceed and mobilisation remain unconfirmed

award / Last checked
Confirmed

Bapco wharf and pipeline repair term services

Bahrain / Liquid-cargo terminal maintenance / Bahrain Tender Board's May 2026 report records a BHD 340,000 extension under tender T17600(65), following the May 2021 BHD 2,489,690 five-year award to Bahrain Maintenance and Diving Services; the extension duration and work orders remain undisclosed

award / Last checked
Confirmed

Manangareza river-port station rehabilitation

Madagascar / Inland river-port station and passenger-cargo terminal rehabilitation / ECH BTP signed the USD 1,272,815.07 works contract on 28 November 2025; public records also name the design and supervision consultant, but no notice to proceed, mobilisation, measured progress, completion or acceptance has been located

award / Last checked
Confirmed

Dioro riverbank and port-quay rehabilitation

Mali / Inland river-port quay and bank rehabilitation / Two works lots under ML-UGP-PRTD-477915-CW-RFB were signed in December 2025; the April 2026 procurement plan marks the package under implementation, but no lot-specific mobilisation, progress, completion or acceptance record has been published

award / Last checked
Confirmed

Elizabeth Quay ferry platform and gangway additions

Australia / Urban ferry terminal, floating platform and passenger gangway / Maritime Constructions holds the AUD 1,756,143 fixed-price design-and-construct award; Tenders WA does not publish a start date, expiry date, mobilisation or completion milestone

award / Last checked
Confirmed

Taweelah RO desalination intake and outfall system

UAE / Marine utilities / EWEC lists Taweelah RO as an existing 909,000 m3/day facility and records 297.16 million m3 of 2024 production; final as-built intake and outfall geometry is not publicly disclosed

completed / Last checked
Confirmed

Plymouth Mount Batten pontoon replacement

United Kingdom / Marinas, pontoons and berthing infrastructure / Teignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmed

construction / Last checked
Confirmed

NW-1 Bihar-West Bengal: six steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Cleghorn Mfg. Co. signed the six-location bundled supply and installation contract on 24 April 2025; public evidence does not confirm final sites, fabrication, installation, commissioning or acceptance

award / Last checked
Confirmed

NW-1 West Bengal: seven 30 m steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Nalanda Engineering Enterprise signed the seven-location bundled supply and installation contract on 3 April 2025; public evidence does not confirm fabrication, installation, commissioning or acceptance

award / Last checked
Confirmed

Fox Island River channel-wall and marginal-wharf reconstruction

Canada / Small-craft-harbour marginal wharf and channel-wall renewal / DFO-SCH's 2026 proposal remains in federal assessment after the public-comment period ended on 22 June 2026; no environmental determination, procurement, award, contractor, mobilisation or construction is evidenced

approval / Last checked
Confirmed

Tarifa fishing-wharf electrical utility upgrade

Spain / Fishing-wharf electrical distribution and utility connection / APBA awarded the EUR 273,030 works to VES Renewable; contract formalization and setting-out remain unpublished

award / Last checked
Confirmed

La Pozona harbour upgrade

Spain / Dredging, pontoons, piles and utilities / Cantabria awarded the EUR 2.647m works to a three-member UTE; contract and mobilisation remain unpublished

award / Last checked
Confirmed

Port-Vendres Quai Dezoums shore-power electrification

France / Commercial-port shore power and electrical utility integration / BOAMP notice 25-50611 records a EUR 5,436,212 contract issued on 3 April 2025 to the SPIE CityNetworks-led consortium with Nidec ASI and T.A.E.H., plus subcontractor Guintoli. A 24 March 2026 Department presentation classifies the work as in progress; energisation, vessel connection, commissioning, acceptance and completion remain unconfirmed

construction / Last checked
Confirmed

Los Angeles Berths 49-51 Outer Harbor Cruise Terminal Development

United States / Cruise berth rehabilitation, shore power and marine piling / Los Angeles Harbor Commission Resolution 26-10665 approved Shimmick's USD 61,290,400 bid on 6 January 2026, and RAMP records the award on 26 January; the owner's award presentation estimated a March 2026 notice to proceed and January 2029 completion, while the actual NTP, site mobilisation and installed work remain unconfirmed through 8 August 2026

award / Last checked
Confirmed

Hillarys Boat Harbour jetties A, F, G, H and J replacement

Australia / Marinas, pontoons and berthing infrastructure / Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract

completed / Last checked
Confirmed

Fremantle Fishing Boat Harbour Jetty 3 replacement

Australia / Marinas, pontoons and berthing infrastructure / Transport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade Sales

completed / Last checked
Confirmed

Sitra Wharf Berths 5 and 6 liquid-cargo enhancement

Bahrain / Liquid-cargo terminal berth enhancement / Bahrain Tender Board's March 2026 monthly report records a BHD 10,987,831 award to NASS Contracting for Sitra Wharf tender T78534; no award date, contract signature, mobilisation or installed work is published

award / Last checked
Confirmed

Ouakam fishing-quay rehabilitation

Senegal / Fish landing quay and fisheries value-chain infrastructure / FIDELE SARL's rehabilitation contract was signed 5 February 2025 for an operating export-approved landing facility; no controlled site start, temporary operating setup or physical progress evidence through 8 August 2026

award / Last checked
Confirmed

Fass Boye modern fishing quay

Senegal / Fish landing quay and fisheries value-chain infrastructure / KELIMANE ENTREPRISE's Lot 01 contract was signed 5 February 2025, while a separate replacement relocation-site package remained awaiting execution in the current plan; no controlled main-works start evidence through 8 August 2026

award / Last checked
Confirmed

Cap Skirring modern fishing quay

Senegal / Fish landing quay and fisheries value-chain infrastructure / Official works launch held 24 July 2025 after ETIC's Lot 02 contract was signed 15 January 2025; no controlled later completion or commissioning evidence through 8 August 2026

construction / Last checked
Confirmed

Liwa Fishery Harbour development, management and operation PPP

Oman / Fishing-port concession, commercial waterfront and operating PPP / Liwa remained in Oman's 2024 PPP and fisheries-investment pipeline after 2021 and 2023 market approaches; a selected developer and financial close remain undisclosed through 8 August 2026

tender / Last checked
Confirmed

Rietvlei sewage pump station and Bellville WWTW tie-in works

South Africa / Wastewater pump stations, rising mains and treatment-plant tie-ins / City of Cape Town tender 32Q/2026/27 is open for a new 1,100 L/s Rietvlei sewage pump station, twin 1,980 m DN710 HDPE rising mains and Bellville WWTW tie-in works; bids close at 10:00 local time on 2 November 2026 and no contractor is appointed

tender / Last checked
Confirmed

La Spezia Terminal del Golfo expansion and redevelopment Lot I

Italy / Container and multipurpose terminal quay extension / TED notice 521188-2026 records a 23 July 2026 works contract with a planned RTI led by Dott. Carlo Agnese at EUR 10,868,519.12 for 419 days; notice to proceed, mobilisation, installed quantities and named subcontractors remain unverified

award / Last checked
Confirmed

Colombo West Container Terminal II Western Breakwater Extension Design

Sri Lanka / Deep-water port expansion, breakwaters and reclaimed logistics land / Dohwa-led detailed-design contract awarded in April 2025; SLPA's May 2026 planning document confirms the engineering study but leaves financing, construction procurement and field start open

design / Last checked
Confirmed

Ras Hanzir replacement cargo facility

Malta / Cargo-port quay, land reclamation, piling and utilities / Infrastructure Malta is taking replacement works tender IMT008/2025 to 1 October 2026 after terminating predecessor contract IM027/2020; the replacement works package remains unawarded

tender / Last checked
Confirmed

NW-1 Bihar: ten steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Signed with Merolyn on 11 November 2025; procurement is under implementation, while physical delivery is unverified

award / Last checked
Confirmed

NW-1 West Bengal Lot A: five concrete floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / IWAI signed the five-site Lot A contract with West Coast Marine Yacht Services on 18 March 2026; the procurement plan lists the package under implementation, but fabrication, installation and site acceptance remain publicly unconfirmed

award / Last checked
Confirmed

Soubise/Marquis coastal protection: Soubise Lots 1 and 2

Grenada / Coastal infrastructure / Two Soubise works lots were signed on 27 April 2026 for a combined USD 5.747 million; Marquis Lot 3, notice to proceed, mobilisation and physical works remain publicly unconfirmed

award / Last checked
Confirmed

Bridgetown Fisheries Complex breakwater repair

Barbados / Coastal infrastructure / C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished

construction / Last checked
Confirmed

Yukonhaven Jetty 4 LNG bunker-loading berth

Netherlands / LNG jetty, combi-wall, mooring structures, dredging and shore works / Gate took FID in January 2026, Port of Rotterdam signed the Hakkers Waterbouw-De Klerk combination on 6 February, and April works notices support early construction; start-up is planned around the end of 2028

construction / Last checked
Confirmed

West Bengal 45-jetty contract ledger

India / Inland-waterway floating jetties, gangways and passenger facilities / World Bank data identifies 21 direct works contracts across the 29-jetty Phase I and 16-jetty Phase II programme; the June 2026 ISR says 44 of 45 locations are complete with Metiabruze under implementation, while its results table says all 45 are complete

construction / Last checked
Confirmed

Port Seine-Metropole Ouest phase-one river-port construction

France / Inland-port basin excavation, sheet-pile quays, pile-supported jetties and multimodal access / HAROPA PORT reports phase-one construction in execution: earthworks, a retaining wall and conveyor loading were active in summer 2026, South Quay sheet-pile installation had started, and piling for the west then east jetties was scheduled from the week of 6 July

construction / Last checked
Confirmed

Poona boat ramp and access-channel upgrade

Australia / Public boat-launch infrastructure, capital dredging and fixed access / Australian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026

construction / Last checked
Confirmed

Newell Beach all-tide boat ramp upgrade

Australia / Public boat-launch infrastructure, capital dredging and fixed access / Queensland TMR completed the upgraded all-tide facility in May 2022 after Australian Marine & Civil delivered the main works under CN-17011; the published contract disclosure rose from AUD 2,560,154 to AUD 2,603,835 after a variation

completed / Last checked
Confirmed

Preah Sihanouk Marine Fisheries Inspectorate boat mooring and jetty

Cambodia / Marine infrastructure / Taing Cheng Oing Construction & Import Export signed package SCMFP FiA/CW-03 on 9 March 2026; ADB reports a financed amount of 472,336.05 without currency or full contract value, and mobilisation or physical start is not independently confirmed

award / Last checked
Confirmed

Warrawong Parklands Kully Bay seawall reconstruction

Australia / Foreshore seawall and rip-rap protection / Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence

construction / Last checked
Confirmed

Mopti boat-quay access dredging and sediment clearance

Mali / Inland river-port access dredging and sediment clearance / The package was officially launched on 13 February 2025 and a project team inspected progress on 6 March 2025; the latest disclosed procurement plan, dated 13 April 2026, still records the contract only as signed, and no official completion, accepted bathymetry or operating release has been published

construction / Last checked
Confirmed

Ferry Terminal Turku marine and landside works

Finland / Ferry-terminal piers, passenger bridges and port-yard renewal / Pier S1 was handed over on 15 June 2026 but will not enter service until March 2027; the joint terminal, passenger bridges and 11-hectare field works remain under construction, while Quay S2 is targeted for 2028

construction / Last checked
Confirmed

Hooghly four-location floating passenger-jetties package

India / Inland-waterway floating jetties, gangways and passenger facilities / Two lots were signed on 16 August 2024 for Tamlipara, Chinsurah, Metiabruze and Pujali; the June 2026 World Bank ISR says Metiabruze remains under implementation but its results table says all 45 project jetties are complete

construction / Last checked
Confirmed

Castletownbere small craft harbour piling and utilities

Ireland / Fishery harbour piling, civil works and marine utilities / TED published the EUR 1.2498795 million Sorensen award on 5 August 2026 and records contract conclusion on 22 June; no project-specific mobilisation, commencement or subcontractor notice has been published

award / Last checked
Confirmed

Port de Plaisance du Grand Large marine works

France / Marinas, pontoons and berthing infrastructure / SPAD concluded three separate Grand Large marina works contracts on 30 June 2026 with Eiffage Travaux Maritimes et Fluviaux, Atlantic Marine and Ramery Travaux Publics; each lot carries a 24-month planned period, but no dated notice to proceed or field mobilisation has been located

award / Last checked
Confirmed

Port de l'Ayguade du Levant Ro-Ro quay

France / Ro-Ro berth and island freight access / Métropole Toulon Provence Méditerranée concluded contract 98RL25 with Océlian and TP Spada at EUR 2,104,311.99 on 20 August 2025 after an earlier procedure ended without an award; no dated mobilisation or completion record has been located

award / Last checked
Confirmed

New Woodman Point Ammo Jetty

Australia / Marine infrastructure / Advanteering Civil Engineers has completed detailed design and started early off-site construction under DOT413022; on-site work is planned from spring 2026 but no dated mobilisation evidence has been published

construction / Last checked
Confirmed

Woodman Point western boat ramp and Fremantle Jetty 1 renewals

Australia / Marinas, pontoons and berthing infrastructure / Jetty and Marine Constructions holds one design-and-construct contract covering the Woodman Point western boat ramp and Fremantle Fishing Boat Harbour Jetty 1; Woodman Point field works began under a 27 July 2026 closure, while a dated Fremantle mobilisation record has not been published

construction / Last checked
Confirmed

Dar es Salaam berths 1-7 and RoRo electrical-power package

Tanzania / Port berth electrical systems and commissioning / DERM Group signed the USD 20.16 million berth electrical-power works contract in October 2024; the planned June 2026 end has passed without public completion or acceptance evidence

construction / Last checked
Confirmed

Yorkeys Knob boating facility

Australia / Recreational harbour, breakwaters, dredging and boat-launch infrastructure / The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works

completed / Last checked
Confirmed

St. Lawrence fishing harbour wharf reconstruction

Canada / Fishing harbour timber-wharf reconstruction / R.J.G. Construction holds the CAD 3.02 million wharf-reconstruction contract; the stated contract period ended in April 2026, but completion and acceptance are not publicly confirmed

construction / Last checked
Confirmed

Albert Pier and St Helier Marina berthing upgrades

Jersey / Marinas, pontoons and berthing infrastructure / Albert Pier's final berthing stage was complete by 6 April 2022 and St Helier Marina's refurbishment by May 2022; Ports of Jersey subsequently confirmed the marina works were on schedule and the combined capacity benefits were in use

completed / Last checked
Confirmed

Hunan Inland Waterway Green Port programme: Daorenji, Songyanghu III and Songmu II

China / Inland-waterway green-port programme, open-piled bulk and general-cargo berths / Daorenji's main marine structure was reported complete in July 2026 with equipment installation and commissioning next; Songyanghu III moved from 1,556 precast deck panels into field installation in January 2026; no current Phase II construction evidence has been found for Songmu. AIIB still lists the proposed sovereign financing as Proposed

construction / Last checked
Confirmed

Ploce New Bulk Cargo Terminal

Croatia / Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems / Civil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacity

completed / Last checked
Confirmed

Jorf Lasfar Multipurpose Terminal Quay Extension

Morocco / Multipurpose berth extension, block quay, mooring dolphin, access bridge and terminal equipment modernisation / Marsa Maroc says the berth-front extension was launched and remained part of its active 2025 investment programme. Execution-design evidence identifies two quay extensions and a mooring dolphin; no owner acceptance or completed operating release has been published

construction / Last checked
Confirmed

Casablanca Multipurpose Terminal Quay Deepening

Morocco / Brownfield quay strengthening, retaining structure, micropiles, scour protection and capital dredging / Works started on 1 October 2024. Marsa Maroc reported a first 230-metre section commissioned at -12 m, while the published delivery programme continues toward 530 metres of deepened quay plus transition zones by 2028; the civil-works award is confirmed but the contractor remains publicly unnamed

construction / Last checked
Confirmed

Poti Sea Port Berth 14 Rehabilitation

Georgia / Container berth rehabilitation, dredging, quay-top renewal and terminal equipment / EBRD lists Phase 1 as Completed, and a TRACECA technical record says Berth 14 was rehabilitated in 2009 for 1,000-TEU feeder vessels; the exact acceptance date, as-built dredging quantity and depth, delivery contractor and final account remain publicly unresolved

completed / Last checked
Confirmed

Saba Black Rocks Harbor and Fort Bay improvement works

Caribbean Netherlands / Hurricane-resilient harbor, breakwater, dredging, quay and marina works / Public Entity Saba reported steady construction progress on 10 May 2026, including breakwater works and Xbloc arrivals, with additional units being produced in Sint Eustatius. Dredging and excavation were active in March 2026, but marine completion, harbor handover, Fort Bay close-out and operational opening remain unconfirmed.

construction / Last checked
Confirmed

Mo i Rana entrance and Langneset deep-water quay

Norway / Deep-water quay, fairway dredging, contaminated-sediment containment and navigation works / Kystverket reported the Langneset quay in its finishing phase on 29 June 2026, with concrete works nearing completion and technical installations scheduled through summer and autumn; completion and an official opening are planned for autumn 2026, but handover, acceptance and operation remain unconfirmed

construction / Last checked
Confirmed

Galati Multimodal Platform Stage I quay works

Romania / Inland-port quay, dredging, basin infill and intermodal berth works / TED published a further contract modification on 27 May 2026, extending the recorded execution duration by 4 months and 23 days and reducing the stated contract value by RON 1,270.26; the latest owner progress figure located is 62.04% at 30 June 2025, and no completion or acceptance record has been published

construction / Last checked
Confirmed

Killybegs Smooth Point breasting dolphins and shore power

Ireland / Fishery harbour berthing, marine piling and shore power / Sorensen reported all 24 dolphin piles installed in August 2025; the government project page published the following month still described the works as ongoing with substantial completion due in Q3 2025, and DAFM has not published a later handover record

construction / Last checked
Confirmed

Fehmarnbelt Fixed Link Immersed Tunnel

Denmark / Germany / Immersed tunnels and marine crossings / Third tunnel element immersed and connected on 1 August 2026; protection, serial immersion, systems integration, and a two-stage road-then-rail opening remain active

construction / Last checked
Confirmed

Busan New Port West Container Terminal Phase 2-6

South Korea / Deep-water ports and automated container terminals / BPA completed the 23-caisson substructure in August 2024 and is advancing superstructure and automated-equipment packages toward an October 2027 completion and second-half 2027 opening target

construction / Last checked
Confirmed

Thessaloniki Port Pier 6 expansion

Greece / Container terminal expansion, quay construction and dredging / ThPA signed the EUR 195.6 million METKA-TEKAL construction contract in November 2025 and installed the first of 21 quay caissons in July 2026; the second caisson was under construction at publication

construction / Last checked
Confirmed

London Gateway Berth 5 quay and automated yard

United Kingdom / Deep-water ports and automated container terminals / Port of London Authority reported the 430-metre Berth 5 quay extension complete by 1 August 2026 while further retaining-wall piling continued toward the Berth 6 interface; the separately contracted ten-module automated yard remains on a contractor-reported programme to March 2027

construction / Last checked
Confirmed

Port of Tanjung Pelepas Berth Zero

Malaysia / Deep-water ports and container terminals / Malaysia Marine Department notices documented Package 1 and Package 2 work vessels on site from January 2026; PTP is delivering a 360-metre berth, dredging, reclamation, yard works and four quay cranes toward commissioning by 2028

construction / Last checked
Confirmed

Noatum Ports Pointe-Noire Terminal

Republic of the Congo / Deep-water ports and container terminals / AD Ports Group awarded two marine and topside contracts to the MAR Contracting-MBTP joint venture and a crane contract to ZPMC on 18 May 2026; the 420-metre terminal is expected to be built over approximately two years

award / Last checked
Confirmed

Tema Port Terminal 3 Phase 2 expansion

Ghana / Deep-water ports and container terminals / Eiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021

completed / Last checked
Confirmed

Colombo West International Terminal

Sri Lanka / Deep-water ports and automated container terminals / Phase 1 has operated since April 2025 and handled one million TEU in its first year; the 1,400-metre quay was complete by March 2026 while Phase 2 crane deployment and full-terminal construction continue

construction / Last checked
Confirmed

Baltic Hub T3 deep-water container terminal

Poland / Deep-water ports and container terminals / Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation

completed / Last checked
Confirmed

NEOM green-ammonia export jetty

Saudi Arabia / Deep-water ports and energy terminals / Overall complex above 90% complete; energization and commissioning started, with jetty VTS radar commissioned but first ammonia transfer not confirmed

commissioning / Last checked
Confirmed

Luderitz renewable-energy SWRO and marine studies

Namibia / Marine utilities / Toyota Tsusho feasibility study active; marine-site consultant, selected site and delivery awards remain unconfirmed

feasibility / Last checked
Confirmed

Niagara River Emerald Shiner Fish Passage

United States / Coastal infrastructure / USACE reports the 700-foot full phase completed in May 2026 and the combined 778-foot fish passage opened with a ribbon-cutting on 23 July 2026

completed / Last checked
Confirmed

Snow's Cut AIWW shoreline stabilization

United States / Coastal infrastructure / USD 7.016 million contract awarded; mobilization and the awarded reach split remain unpublished

award / Last checked
Confirmed

Zeevonk phase 1 foundation installation

Netherlands / Offshore wind foundations / DEME holds the transport and installation contract for 69 monopile foundations; offshore mobilisation has not been announced

award / Last checked
Confirmed

Ruwais LNG marine access and export terminal

UAE / Deep-water ports and energy terminals / Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published

construction / Last checked
Confirmed

Damietta Alliance Container Terminal (Tahya Misr 1)

Egypt / Deep-water ports and container terminals / Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity

commissioning / Last checked
Confirmed

Can Gio International Transshipment Port

Vietnam / Deep-water ports and container terminals / Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced

approval / Last checked
Confirmed

Dakar Mamelles desalination intake and brine discharge

Senegal / Marine utilities / Plant remained under construction in February 2026; commissioning was expected later in 2026, while final marine handover evidence remains unpublished

construction / Last checked
Confirmed

Honiara wastewater mains and two deep-sea outfalls

Solomon Islands / Marine utilities / ADB still lists bid-document preparation for the new marine works; Solomon Water's public plan carries competing three-outfall, two-new-outfall and NRH/Ranadi package definitions, with no works award disclosed

tender / Last checked
Confirmed

Hawar SWRO offshore intake and outfall tender

Bahrain / Marine utilities / Two bids were opened for Hawar's separate offshore intake and outfall EPC package on 25 December 2025; EWA still lists the wider desalination scheme as a future project and no award is published

tender / Last checked
Confirmed

Rosarito 2,200 l/s desalination procurement

Mexico / Marine utilities / Compras MX lists the invitation as current, with proposal opening deferred to 24 July 2026 and the ruling moved to 29 July; no award is published

tender / Last checked
Confirmed

Nigeria Snake Island Container Terminal concession and EPC

Nigeria / Deep-water ports and container terminals / MSC signed a 45-year sub-concession and finalized the ITB/DEME EPC on 11 March 2026; the reviewed project sources do not record mobilisation

award / Last checked
Confirmed

Algarve seawater desalination intake and outfall system

Portugal / Marine utilities / Construction was released on 22 April 2026 and the site milestone was held on 8 July; offshore intake and outfall execution remains unverified

construction / Last checked
Confirmed

Saudi Arabia five-IWP developer qualification programme

Saudi Arabia / Marine utilities / Sharakat is qualifying developers across five planned seawater reverse-osmosis projects; no individual RFP, award or project-specific marine package is public

prequalification / Last checked
Confirmed

Gopalpur Industrial Park 100 MLD desalination PPP

India / Marine utilities / Four IFC advisory procurements define transaction preparation; the 100 MLD PPP, marine site, concession and works remain unawarded

planning / Last checked
Confirmed

Isle of Palms Breach Inlet beneficial-use dredging

United States / Coastal infrastructure / Two dredging packages completed on 27 February 2026; clay cleanup followed in April and staging was cleared in May

completed / Last checked
Confirmed

West Point Coastal Defence Revetment

Liberia / Coastal infrastructure / The West Point revetment has an approved ESIA and March 2026 environmental permit; construction award, notice to proceed and physical start are not established

approval / Last checked
Confirmed

WACA ResIP 1 coastal protection works programme

Benin / Côte d'Ivoire / Mauritania / São Tomé and Príncipe / Senegal / Togo / Coastal infrastructure / ResIP 1 in finalisation; country work fronts and closing dates remain separate

construction / Last checked
Confirmed

Singapore DTSS2 Tuas WRP nearshore outfall

Singapore / Marine utilities / Nearshore outfall and Contract 1A permanent works were substantially completed on 14 August 2023; wider DTSS2 and Tuas WRP completion, commissioning and discharge acceptance remain open

construction / Last checked
Reported

Taweelah C IPP coastal utility interface

UAE / Marine utilities / PPA and EPC signed; cooling-water review and existing-plant tie-ins exposed, marine route unconfirmed

award / Last checked
Confirmed

Ras Mohaisen Independent Water Project and Marine Intake/Outfall

Saudi Arabia / Marine utilities / Project agreements, the L&T-Lantania EPC award and December 2025 financial close are evidenced, and ACWA's 3 March 2026 year-end report classifies the full 300,000 m3/day capacity as under construction; offshore mobilisation, installed intake or outfall geometry, first water and accepted production are not dated

construction / Last checked

Current research

Latest publications connected to this sector

6 shown / 182 current
IVY 1 and IVY 2 supporting a standard Fehmarnbelt tunnel element during mooring trials at Rødbyhavn, in the owner's 2026 image-library record
Brief / Confirmed

Fehmarnbelt: IVY's 1,600-Tonne Load Test

Fehmarnbelt's September load test addressed a change in transport geometry. The first special tunnel element has a basement and must travel higher in the water than a standard element. Raising it reduces buoyancy and transfers more load to the immersion vessel IVY. Sund & Bælt reported on 11 September 2026 that the fourth standard element had been loaded with an additional 1,600 tonnes, distributed between water bags on its roof and tanks inside it, and lifted to the height required for transporting the special element. [1]

Updated
Davis planned over-ice delivery diagram links the Nuyina cargo, module and vehicle configuration, released route, water-system foundations and service connections
Brief / Confirmed

Davis prepares water-plant modules for an over-ice resupply

Australia's Antarctic programme is sending a containerised pump house, a reverse-osmosis plant and earthmoving equipment to Davis for the 2026-27 construction season. Its 20 October departure account puts RSV Nuyina's planned resupply position about one kilometre from station buildings. More than half of the voyage's cargo of over 950 tonnes is assigned to infrastructure renewal. AAD's V1 schedule lists an over-ice resupply at Davis from 4 to 13 November. [1][3]

Updated
Melaka mud-removal diagram shows the four boundary points in Port Circular 52/2026 and the two named anchor-handling tugs and two barges
Brief / Confirmed

Melaka sets a buoyed work area for power-plant mud removal

Malaysia's Marine Department has published a mud-removal work area for the Melaka 2,242 MW combined-cycle power plant, with a stated period from 7 October 2026 to 15 June 2027. Port Circular 52/2026, dated 12 October, identifies four boundary points and names anchor-handling tugs JETTA 35 and JETTA 37 and barges JETTA 39 and LIGHT SABER. It advises other vessels to keep clear of the work area and navigate cautiously nearby. [1]

Updated
Sizewell bulk-import diagram connects the planned Wind jetty-head work and Canti-travel trestle to the berth, conveyor and shore receiving route
Brief / Confirmed

Sizewell targets Q2 2027 bulk imports as jetty works advance offshore

Sizewell C expects its Marine Bulk Import Facility to become operational in the second quarter of 2027. The owner's works tracker reports that construction has advanced from the beach into the sea, with platform works continuing through the end of 2026. The facility will transfer bulk materials from vessels to the main construction site. April's site forum recorded Canti-travel piling in progress; the harbour's subsequent phase-two plan paired offshore jetty-head construction with an approach trestle advancing seaward from the mainland. [1][2][4]

Updated
Gulfport funding diagram separates initial shares, later GNF repayment, local facilities and the estimated $17 million annual federal OMRR&R account, including maintenance dredging
Brief / Confirmed

Gulfport's deepening plan includes a later sponsor payment

Gulfport's recommended navigation improvements carry two different sponsor payments. The signed 23 June 2026 Chief's Report assigns $137.102 million of the $548.216 million initial project cost to the Mississippi State Port Authority. It also estimates an additional General Navigation Features payment at $50.8 million, before eligible credits. Paragraph 9(d) places that additional payment after construction, with interest, over a period of up to 30 years. A sponsor's funding forecast therefore needs a construction contribution and a separate post-completion repayment schedule. Annual federal operation, maintenance, repair, replacement and rehabilitation (OMRR&R) is estimated at $17 million, including anticipated maintenance dredging. [1]

Updated
Northern coastal defences and foreshore at Fort George on 28 June 2016, shown as historical context for the North Glacis package
Brief / Confirmed

Fort George underpinning: recorded tender deadline passed

Historic Environment Scotland's 8 October notice covered concrete underpinning at Fort George North Glacis, near Ardersier: temporary propping, beach-side excavation, secured formwork, mass-concrete fill and beach reinstatement. The recorded PCS Postbox submission deadline of 17:00 GMT on 4 November 2026 has passed; the advertised duration is 28 working days.

Updated

Delivery network

Organizations connected to this collection

6 shown / 108 profiled
Overhead view of four treatment basins and operating equipment at Kinoya wastewater treatment plant in Suva, Fiji
National water and wastewater utility

Water Authority of Fiji

National public water and wastewater utility / Kinoya treatment-plant owner and existing operator / CW02 employer, procuring agency and contract-management counterparty

Last checked
USACE hopper dredge Essayons operating in the Columbia River near Cathlamet, Washington
Federal water-resources agency and navigation-project owner

U.S. Army Corps of Engineers, Civil Works

Federal navigation project owner / Coastal and inland navigation asset manager / Planning, design, construction and operations-and-maintenance authority

Last checked
IMWO illustrated guide to Boskalis' Dredging and Inland Infra, Offshore Energy, and Towage and Salvage businesses, separating corporate capabilities from individual project assignments
Dredging, marine infrastructure and offshore-energy contractor

Boskalis

Capital and maintenance dredging contractor / Port, waterway and reclamation contractor / Coastal defence, riverbank and hydraulic-infrastructure contractor

Corporate facts reviewed Procurement checked
Official execution drawing comparing Tarifa fishing wharf's existing 20 kV route with the proposed 20 kV route to the new transformation centre
Spanish state-port authority and marine-infrastructure owner

Algeciras Bay Port Authority (APBA)

State-port authority / Port infrastructure owner and landlord / Marine and utility works client

Last checked
Aerial view across Igoumenitsa Bay showing ferry berths, Ro-Pax vessels, terminal aprons, breakwaters and the city waterfront
Greek concession port operator and marine-infrastructure owner

Igoumenitsa Port Authority S.A. (IPA S.A.)

Port concession operator / Passenger, vehicle and cargo handler / Vessel-berthing service provider

Last checked

Continue the sector evidence review

Search the public index for this delivery discipline, compare mapped projects, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.

Search Marine utilities and infrastructure Open project tracker Open sector guide Review methodology