Central Coast Council has settled the current EIS concept for a Toukley desalination plant: the seawater pump station stays beside the existing sewage treatment plant, a 2.4 km microtunnel reaches an intake about 1 km off Jenny Dixon Beach, and a short connection sends brine through the existing Norah Head ocean outfall. NSW lists the project at Prepare EIS. Council has neither decided to build nor funded construction.
Project signal
Planning in Australia
Current statusPrepare EIS; the current concept fixes a 2.4 km intake tunnel and existing-outfall connection, but no construction decision or funding is publicSource confidenceConfirmed
Location
Australia / Asia Pacific
Segment
Marine utilities
Status
Prepare EIS; the current concept fixes a 2.4 km intake tunnel and existing-outfall connection, but no construction decision or funding is public / Confirmed
Last checked
20 July 2026
Coverage
Related sectors
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Central Coast Council Water and Sewer
Delivery parties
GHD - concept design and statutory approvals support, Construction and marine contractors - not appointed in the cited public record
Contract route
Council appointed GHD to support concept design and statutory approvals. The public record does not identify a funded detailed-design, tunnelling, intake-caisson, process-plant or construction contract. Any later procurement remains conditional on approvals, water-security triggers, funding and a Council decision to proceed.
Execution window
Council is seeking a plan-ready approval rather than an immediate build. The EPBC referral uses 2036 as a conservative planning assumption, says construction could take about 36 months and says the plant may be needed in the early 2040s if drought triggers do not bring it forward. Council's March FAQ uses a broader three-to-four-year construction estimate. Neither is a committed start or completion date.
Works package
The current proposal allows an initial 30 ML/d reverse-osmosis plant and an assessment envelope up to 40 ML/d. Its marine scope includes a roughly 2.4 km, 2.5 m diameter microtunnel from the plant through an intermediate shaft to an intake about 1 km offshore; a roughly 12 m diameter intake tower with concrete caisson rings, a steel support frame, GRP dome, removable grills and rockfill scour protection; and a roughly 180 m brine connection to the Toukley sewage treatment plant outfall tank. A separate 1.4 km, 600 mm treated-water pipeline connects to the potable network.
Marine interfaces
Moving the pump station to the plant site removes the permanent beach pump-station option but concentrates delivery risk in the long microtunnel, the Jenny Dixon Beach construction and maintenance shaft, offshore caisson installation and tunnel-to-intake connection. Brine is proposed to co-mingle with treated effluent through the existing Norah Head ocean outfall, with no physical change to that outfall. Hydraulic capacity, near-field mixing, far-field plume behaviour and discharge approval therefore remain system-level gates rather than assumed benefits of an existing asset.
Commercial evidence boundary
There is no current marine construction opportunity supported by an owner tender or award. The next market evidence would be an exhibited EIS, approved project description, funded detailed design, geotechnical and marine survey packages, tunnelling or shaft procurement, intake-caisson fabrication and installation, or owner-issued process and integration packages. GHD's planning role should not be read as an EPC or construction award.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The Commonwealth referral described the offshore intake and existing-outfall connection
EPBC 2026/10457 documented the 2.4 km microtunnel, intake about 1 km offshore, caisson concept and 180 m brine connection. The portal currently records Assessment Approach Determined, not final approval.
Council fixed the current pump-station and intake-route concept
The preferred concept moved the pump station to the plant site and retained only a construction and maintenance shaft near Jenny Dixon Beach. It defines the EIS basis but does not authorise construction.
Council opened the next planning and consultation stage
The owner began route and intake option work to make the scheme plan ready for a future drought response. That planning start was not a construction commitment.