Project change log

Dated changes across the marine works pipeline.

This log records source-backed events that changed project scope, phase, counterparties, procurement, delivery, completion, commissioning, or acceptance. Event dates do not forecast the next milestone.

Latest change 498 recorded changes 108 projects 6 regions

Showing 24 of 498 source-bound changes

Europe / United Kingdom / Marine utilities / Current phase: construction

Sizewell C temporary desalination intake, outfall and CDO

The general construction notice remains active after two pipe-pull notices closed

The harbour register lists Notice 11 as active and the CDO and desalination pipe-pull notices as inactive. This supports completion of the two discrete pull-in windows, while head structures, testing, plant integration and final acceptance remain open.

Read controlling source

Europe / Netherlands / Offshore wind foundations / Current phase: award

Zeevonk phase 1 foundation installation

DEME won the 69-foundation transport and installation package

The award fixes the principal offshore foundation contractor and includes marshalling, intermediate transport and filter-layer placement. Port, vessel, fabrication and mobilisation details remain unpublished.

Read controlling source

Asia Pacific / India / Marine utilities / Current phase: planning

Gopalpur Industrial Park 100 MLD desalination PPP

Odisha's PPP register lists the project as Proposed

The state database identifies the Industries Department project and an INR 500 crore planning cost. It does not establish budget approval, final capacity, a concession tender, award or construction start.

Read controlling source

Global islands / Solomon Islands / Marine utilities / Current phase: tender

Honiara wastewater mains and two deep-sea outfalls

ADB still lists the new outfall works at bid-document stage

The current record confirms two existing-outfall rehabilitations but does not disclose a construction award for the purpose-built NRH and Ranadi marine lines.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: construction

Port Mansfield Channel 2026 maintenance dredging

Dredging reached the GIWW junction

The Navigation District says Callan Marine has advanced west from the entrance jetties to the channel intersection and will next work into the harbor and turning basin.

Read controlling source

Americas / Mexico / Marine utilities / Current phase: tender

Rosarito 2,200 l/s desalination procurement

Compras MX deferred the opening and ruling

The live procedure detail moved proposal opening from the earlier 21 July programme date to 24 July at 11:00 and lists the ruling for 29 July at 17:00. An annex is identified as the notice deferring the proposal-opening date and time.

Read controlling source

Middle East / Saudi Arabia / Marine utilities / Current phase: prequalification

Saudi Arabia five-IWP developer qualification programme

Current portfolio confirms the five-project capacity list

Sharakat's current portfolio lists Ras Al Khair 2, Ras Al Khair 3, Tabuk 1, Shuqaiq 4 and Jazan 1 at a combined planned capacity of 2.1 million cubic metres per day. The list does not establish individual RFPs, bidders, awards or construction starts.

Read controlling source

Middle East / Saudi Arabia / Marine utilities / Current phase: prequalification

Saudi Arabia five-IWP developer qualification programme

Shared RFQ assigns intake and outfall responsibility

The common qualification document places seawater intake and outfall facilities within each future project company's responsibility. It does not publish the five site-specific alignments, dimensions, permits, marine packages or delivery programmes.

Read controlling source

Europe / United Kingdom / Dredging / Current phase: approval

Southampton Channel Deepening capital dredge

MMO register kept the application open for consultation

The live register showed case MLA/2026/00178 as submitted, with consultation closing on 30 July. That is a consent process, not a licence decision or permission to mobilise.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Buffalo Harbor 2026 dredging and Slip 3 wetland placement

USACE published the 2026 start plan and two-route material split

The release identifies Ryba, a USD 2.3 million award, approximately 190,000 cubic yards, a start as early as 18 July, and separate CDF #4 and Slip 3 quantities. These are contracted and planned values, not measured field results.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: tender

New Haven Harbor improvement dredging

The amended IFB closed for bids

PIEE update 0007 retained the 17 July response deadline. The procurement moved into post-bid review without a public bidder, award, contract value or notice to proceed.

Read controlling source

Africa / Morocco / Marine utilities / Current phase: construction

Casablanca-Settat desalination marine works and common systems

Annual reporting kept Casablanca among ACCIONA's faster-delivering water projects

ACCIONA's 2025 integrated report attributes part of Water's improved performance to faster-than-expected delivery of key projects including Casablanca. This is a current execution signal, not a measured marine-progress percentage, tunnel breakthrough, common-system acceptance, first water, or operating release.

Read controlling source

Americas / Brazil / Dredging / Current phase: mobilisation

Paranaguá access channel dredging concession

The concessionaire portal exposes the operating baseline and unresolved VTS schedule

PPCC publishes a 13.3-metre current operating draft, 15.5-metre target, March 2026 bathymetry, and VTS under implementation. Its year-five VTS label differs from ANTAQ's first-two-year summary, so neither summary page should be promoted into an accepted contract milestone.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: design

Roberts Bank Terminal 2 landmass and wharf

Canada referred the Port of Vancouver Gateway Strategy to the Major Projects Office

The federal record places RBT2 within the wider gateway strategy and describes the project as well advanced in regulatory and project planning. Referral does not replace the target-price agreement, financial close, permits or construction evidence.

Read controlling source

Global islands / Fiji / Marine utilities / Current phase: prequalification

Fiji Kinoya wastewater treatment and Laucala Bay outfall programme

WAF current tender list confirms CW02 open with a 28 August closing date

The live utility list advances Kinoya from approval into active international prequalification for an operate-design-build-operate package. An open process does not prove shortlist, award, notice to proceed, construction, or accepted performance.

Read controlling source

Americas / United States / Port infrastructure / Current phase: tender

Richmond Inner Harbor FY26 maintenance dredging

USACE issued the updated full RFP

The current notice set the 14 August proposal deadline, USD 10 million to USD 25 million estimate, LPTA evaluation, 14-reach scope, -37-foot requirement and Montezuma route without identifying an award or contractor.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: approval

Port Douglas Boat Harbour 2026 maintenance dredging

MSQ published the quantified 2026 delivery plan

The owner defined about 45,000 cubic metres, cutter-suction plant, a temporary pipeline to Killaloe, water-quality monitoring and an October completion target. The page did not confirm contractor appointment or physical mobilisation.

Read controlling source

Europe / Netherlands / Port infrastructure / Current phase: construction

Port of Rotterdam Yangtzekanaal widening and quay programme

Phase A completed and Phase B field construction started

The current owner page advances the programme from Phase A wall installation and Phase B design into a completed 12-berth tug quay and active 1,450-metre inland-shipping quay. Phase B berth, shore-power, heavy-load and operating acceptance remain open, with Phase C dredging scheduled after 2028.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: construction

Port of Montreal Contrecœur Container Terminal

Owner scheduled a three-day quay-wall sheet-pile delivery window

The live works log set 13-15 July for delivery, unloading, and on-site storage of quay-wall sheet piles, advancing the supply sequence without confirming that delivery was completed or that sheet-pile driving and in-water construction had started.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: design

Roberts Bank Terminal 2 landmass and wharf

TerraMarine became preferred proponent for the landmass and wharf package

The selection identifies the construction and design team and starts collaborative planning and negotiations. The authority says the target-price agreement follows sufficient initial work and financial close.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: construction

Ocean City and Peck Beach 2026 Periodic Nourishment

Dredge Illinois reached the mobilisation gate

USACE recorded the dredge Illinois as mobilised and set to begin operations. The statement establishes plant readiness at the workfront, not first production, pumped quantity, placed quantity, compliant geometry, completion or acceptance.

Read controlling source

Americas / Panama / Dredging / Current phase: planning

Panama Canal new TSHD acquisition planning

Market-survey response window reached its stated close

The RFI's submission deadline has passed, closing the stated market-input window. ACP has not publicly identified respondents or issued a formal solicitation, so the opportunity remains at planning rather than tender or award stage.

Read controlling source

Middle East / Jordan / Port infrastructure / Current phase: tender

Aqaba Cement Terminal and Mut'ah berth rehabilitation concession

Mandatory site-visit window was scheduled

ADC scheduled mandatory site visits for 8-9 July after the tender-document request window. The reviewed public pages do not identify attendees, confirm that a visit occurred, disclose observations or provide an asset-condition survey.

Read controlling source

Africa / Morocco / Deep-water ports and energy terminals / Current phase: commissioning

Nador West Med Deep-water Port

WMCT signed long-term East-terminal financing documents

The financing record strengthens the East terminal's separate fourth-quarter 2026 commissioning path; it does not prove equipped-terminal completion, harbour-service readiness, first vessel handling, or recurring throughput.

Read controlling source

Europe / Portugal / Marine utilities / Current phase: construction

Algarve seawater desalination intake and outfall system

The first brick marked the site start

Águas do Algarve and the Portuguese government recorded the on-site ceremony and monitoring committee. The owner calls the event symbolic and does not report offshore plant mobilisation, pipeline installation or first water.

Read controlling source

Middle East / Iraq / Port infrastructure / Current phase: construction

Grand Faw phase-one marine and port-access system

The 62 km connecting road received GCPI's final Performance Certificate

Daewoo E&C reported final completion approval after 45 months of construction and a one-year defects period. The certificate closes the road package, not the immersed-tunnel, terminal, navigation, marine-service, or commercial-operation interfaces.

Read controlling source

Middle East / Jordan / Marine utilities / Current phase: financing

Aqaba-Amman National Water Carrier marine works

The water ministry confirmed financial close was still incomplete

The ministry said it was continuing efforts to complete financial close and that close would pave the way for implementation. This is the latest public gate: it does not prove notice to proceed, marine mobilisation, accepted final design, physical intake or outfall work, or construction commencement.

Read controlling source

Americas / Argentina / Port infrastructure / Current phase: mobilisation

Argentina Vía Navegable Troncal dredging and signaling concession

Argentina signed the 25-year concession contract

Vía Navegable Argentina S.A. completed the administrative transfer steps, asset transfer and worker contracting, while the 13.5% toll reduction took effect. Signature establishes the operator and commercial handover; it does not prove August mobilisation, achieved depth, navigation-aid acceptance or sustained service performance.

Read controlling source

Asia Pacific / India / Dredging / Current phase: completed

Kamarajar Port Capital Dredging Phase VI

Government announced Phase VI complete

The completion release moved the project from construction to completed and stated an 18.0-metre operating draft, with outer and inner channel depths of 23.0 and 22.0 metres respectively.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: construction

Ocean City and Peck Beach 2026 Periodic Nourishment

USACE recorded the current construction start

The project page records construction beginning on 7 July. That milestone advances the package beyond award, while production, beachfill quantity, surveyed template, demobilisation and owner acceptance remain separate gates.

Read controlling source

Americas / Mexico / Marine utilities / Current phase: tender

Rosarito 2,200 l/s desalination procurement

CONAGUA opened a new invitation procedure

The project returned to procurement after the previous public tender was declared void. The new register schedules proposals for 21 July and a ruling for 24 July.

Read controlling source

Middle East / UAE / Deep-water ports and energy terminals / Current phase: construction

Ruwais LNG marine access and export terminal

ADNOC kept the 2028 commercial target and reported 90% of capacity committed

The latest owner update confirms commercial cover and continued development. It does not report access-channel acceptance, navigation-aid commissioning or berth readiness.

Read controlling source

Europe / Belgium / Port infrastructure / Current phase: construction

Antwerp Kanaaldok B2 liquid CO2 export quay

The port published an updated CO2 quality interface

The 21 May specification defines a current vapor-network baseline and supersedes the October 2023 version, but it is explicitly non-binding. Terminal, loading-arm, carrier, liquid-product and storage compatibility remain unconfirmed.

Read controlling source

Global islands / Nauru / Port infrastructure / Current phase: construction

Nauru Aiwo Port climate-resilient redevelopment

ADB grant data still shows an active project

The main grants now close on 31 December 2026. ADB reports the wharf, pipelines, southern yard and reverse-osmosis plant complete, while the northern yard, roads, sheds, buildings and full berth-pocket dredging remain outstanding.

Read controlling source

Americas / Brazil / Dredging and waterways / Current phase: approval

Itajaí-Mirim flood-channel widening and dredging

The World Bank project reached Board Approved status

The portfolio record confirms Active status and a USD 119.2 million current IBRD commitment. The related release ties that milestone to Itajaí-Mirim channel dredging, embankment reinforcement and floodgates without announcing the main works procurement.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: award

Port of Luleå Malmporten fairway and deepwater port works

The remaining dredging contract was signed

The owners moved the main dredging package from conditional award to a signed approximately SEK 5.7 billion contract for about 40 kilometres of fairway, with execution from 2027 and completion by 15 August 2030. Signing does not prove fleet mobilisation, accepted depth, reclaimed land or deepwater-port readiness.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: construction

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

Marine work continued beyond the original June window with diffuser installation still active

Water Corporation's July panel records all intake and outfall piling complete and the final outfall-diffuser installation phase under way. This advances the offshore package but also shows that the annual report's June 2026 marine-construction endpoint was not an acceptance date; diffuser placement, connection, testing and marine demobilisation remained open.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

St. Joseph Harbor 2026 dredging and sediment-placement research

USACE announced the 2026 dredging and research campaign

Viking Marine was due to dredge about 83,000 cubic yards and pump it to a perpendicular nearshore placement south of the harbor. The release set the July-August work plan and monitoring method; final volumes, channel condition, and shoreline response still need field results.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Dunkirk Harbor west breakwater rehabilitation

USACE put the remaining 450 feet into a second repair phase

The district says approximately 1,850 feet are nearing completion and the last 450 feet will run through November 2026. The same release gives two different phase-two cost figures, USD 4.5 million and USD 1.9 million, which remain unresolved.

Read controlling source

Asia Pacific / India / Marine utilities / Current phase: planning

Gopalpur Industrial Park 100 MLD desalination PPP

IFC opened technical and commercial advisory procurements

The two briefs put site investigations, intake and outfall concepts, demand commitments, tariffs, phasing, financial modelling and bankability into the same transaction-preparation sequence. Their 20 July EOI deadline is for advisers, not for a concessionaire or works contractor.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

New Mangalore Port 60T battery-electric tug charter

NMPA issued the 15-year charter work order

The owner named the successful consortium and fixed the award at INR 3.150425 billion excluding GST. Delivery and port acceptance of the new tug remain future gates before service starts.

Read controlling source

Asia Pacific / Japan / Offshore energy / Current phase: construction

Oga-Katagami-Akita offshore wind marine installation programme

Technical conformity certification completed for the wind facilities

The certificate closes the published design and certification process under Japanese technical requirements, while fabrication release, installed foundations, offshore construction, commissioning, and commercial operation remain separate delivery gates.

Read controlling source

Asia Pacific / Japan / Offshore energy / Current phase: construction

Oga-Katagami-Akita offshore wind marine installation programme

First navigation safety committee convened for construction planning

The meeting records formal discussion of project waters, related ports and fishing harbours, marine traffic and navigation safety. Final controls, work windows and permits were not approved by this record.

Read controlling source

Europe / Denmark / Germany / Immersed tunnels and marine crossings / Current phase: construction

Fehmarnbelt Fixed Link Immersed Tunnel

Second standard element immersed and connected

The owner record demonstrates an early repeat of the 73,500-tonne tow, positioning, immersion, and joint sequence and reports more than 500 metres installed; it does not establish mature series cadence, completed protection, or overall tunnel completion.

Read controlling source

Middle East / UAE / Port infrastructure / Current phase: award

Khalifa Port EGA berth enhancement programme

AD Ports Group and EGA agreed an AED 84 million Newcastlemax berth upgrade

The joint investment defines dredging, capping-beam, fender, bollard, crane-foundation, utility and additional-unloader interfaces for planned August 2028 completion and about 8 million tonnes of annual handling. It is a programme agreement, not a design acceptance, construction award, mobilisation notice or completed capacity increase.

Read controlling source

Middle East / Syria / Port infrastructure / Current phase: early works

Port of Tartous modernisation and marine access works

First of three mobile harbour cranes arrived

The first crane reached Tartous and two more were scheduled by August. Arrival proves equipment mobilisation, not commissioning of all three cranes or the expected 40% cargo-capacity increase.

Read controlling source

Africa / Madagascar / Marine infrastructure / Current phase: approval

Madagascar Majunga, Tulear and Pangalanes transport resilience programme

AIIB published the US$100 million co-financing as proposed

AIIB's project page confirms direct co-financing intent, Category A treatment and the same no-port-dredging versus canal-dredging boundary. Proposed status is not financing approval or effectiveness, and the IDA agreement sets 31 March 2027 as the co-financing deadline.

Read controlling source

Africa / Senegal / Coastal infrastructure / Current phase: construction

Gorée Island east and west coastal protection works

World Bank paper reset the completion boundary and sought additional credit

The paper reports 85% completion for protection works and 75% when landscaping is included, then seeks EUR 3.5 million in additional IDA credit and a 30 June 2027 close. It remains a financing proposal and completion plan, not acceptance evidence.

Read controlling source

Middle East / Qatar / Port infrastructure / Current phase: construction

Hamad Port food security terminal and warehouses

Ashghal reported 98% with remaining works and readiness planning still open

The owner-side visit confirmed advanced whole-project construction and technical installation, but also referred to remaining implementation stages and operational-readiness plans. The percentage is not a completion certificate, integrated commissioning record, operator handover or evidence of sustained food-cargo service.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: construction

Port of Montreal Contrecœur Container Terminal

Three-hundred-tonne marine-construction crane assembled on site

The owner reports that the crane was raised and ready for pile and sheet-pile operations after delivery in 13 convoys and a week of assembly. Pile driving, quay progress and dredging remained unreported.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Taweelah C IPP coastal utility interface

Lead developer recruited for BOP execution and existing-plant tie-ins

Al Jomaih's Taweelah C BOP role assigns owner-side oversight of the 2.6 GW EPC, surveys and studies, permits, commissioning and tie-ins to the existing plant. This is an execution-interface and staffing signal, not evidence that a tie-in has occurred or that any intake, outfall, pipeline, dredging or marine package exists.

Read controlling source

Africa / West Africa / Coastal infrastructure / Current phase: construction

WACA ResIP 1 coastal protection works programme

Senegal sought more time for the Gorée works

The additional-financing paper linked the delay to sea conditions, supply constraints, inflation, and heritage-site design changes, then proposed a 30 June 2027 closing date. That date remains a financing proposal, not a completion record for Gorée or the wider programme.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Georgetown Harbor maintenance dredging

USACE set a July start expectation and public navigation-safety briefing

The district said dredging was expected to begin in July and finish in less than three months, with a public meeting covering vessel safety around active equipment. The release establishes an intended window, not contractor disclosure, notice to proceed, mobilisation, or production.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

Desalinated water reached the Radomiro Tomic reservoir

The event advances the record to first water across the integrated coast-to-mine route during progressive commissioning; rated flow, accepted water quality, marine reliability, all-division service, and commercial operation remain separate gates.

Read controlling source

Middle East / Bahrain / Marine utilities / Current phase: tender

Hawar SWRO offshore intake and outfall tender

EWA retained Hawar SWRO in its future-project portfolio

The current owner page confirms a 1 MIGD initial plant and 2 MIG of storage, both extendable, without naming an award or construction start.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Port Hedland Zone 5 Bypass Channel

Pilbara Ports awarded the A$50 million dredging contract

Jan De Nul Australia became the named delivery contractor and the owner stated a September start target. The award left federal permit grant, plant mobilisation, final quantity, completed dredging, accepted geometry and operational release ahead.

Read controlling source

Americas / Argentina / Port infrastructure / Current phase: mobilisation

Argentina Vía Navegable Troncal dredging and signaling concession

Resolución 36/2026 formalized the award

The Boletín Oficial placed Jan De Nul-Servimagnus first, DEME second and rejected DTA Engenharia for the missing bid-maintenance guarantee. The award closed the competition but did not itself transfer operations or start dredging.

Read controlling source

Americas / Mexico / Dredging / Current phase: tender

Port of Progreso expansion dredging and north-platform procurement

State phase closed and separate private berth stage started

Yucatan distinguished the earlier public dredging phase from an SSA Marine Mexico stage that targets 13.3 m depth and a berth extension from 332 m to 450 m. This SSA Marine Mexico stage is separate from the void federal platform package.

Read controlling source

Asia Pacific / India / Dredging / Current phase: tender

Mumbai Port 2026-29 maintenance dredging programme

Mumbai Port opened the 2026-29 three-cycle tender

E.47/2026 packages three annual campaigns at an estimated INR 281.70 crore. The current listing moves bid close to 23 July after one corrigendum; it does not establish bidders, award, mobilisation, quantity, or accepted depth.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Taweelah C IPP coastal utility interface

Energy China reported an EPC execution meeting and contract-signing ceremony

The contractor-side record shows AEW, Sembcorp and Energy China establishing project execution and interface-coordination mechanisms after contract award. This is evidence of contract-performance setup, not site mobilisation, construction commencement, a confirmed cooling-water design, or physical marine works.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Baltimore Harbor 2026 maintenance dredging and Cox Creek routing

DB Avalon was operating in the Patapsco River

USACE field reporting and exact-site photographs confirm active clamshell excavation and scow loading under the current 1.46-million-cubic-yard package. They do not establish final production or accepted channel condition.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

Ramayapatnam Port capital deepening works

DEME received the capital-deepening package

Navayuga awarded DEME capital deepening of the harbour basin, turning circle and four berth pockets, using a cutter suction dredger and onshore pumping for reclamation. The award does not establish mobilisation, dredged quantity, accepted depth or Phase I completion.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Taweelah C IPP coastal utility interface

Siemens Energy identified the generation-equipment supply package

The supplier record defines three gas turbines, two steam turbines, five generators and auxiliary systems for the 2.6 GW plant. It confirms the power-island supply chain but does not define cooling-water intake, outfall, dredging, pipeline, shoreline or marine-civil responsibility.

Read controlling source

Europe / Italy / Ports and coastal protection / Current phase: construction

Genoa New Breakwater

Twenty-fourth caisson installed in open sea

The record advances the repeatable tow-out and controlled-sinking work front to 24 installed units, while foundation completion, caisson-line continuity, filling, armour, superstructure, dredging, and navigation acceptance remain separate gates.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: award

Port of Luleå Malmporten fairway and deepwater port works

Malmporten Dredging Contractors received the main-works award

The owner announced a roughly 14-million-m³ optimized scope and planned contract signing after the review period. The record at that gate established an award decision; the signed contract followed on 2 July.

Read controlling source

Americas / Brazil / Port infrastructure / Current phase: award

Port of Santos 16 m channel deepening

APS signed the 16-metre deepening contract

Jan De Nul became the named contractor for the integrated licensing, design, capital-dredging and two-year maintenance scope. Signature did not establish mobilisation or achieved channel depth.

Read controlling source

Asia Pacific / India / Deep-water ports, dredging and reclamation / Current phase: tender

Vadhvan Greenfield Deep-draft Port

Owner opened a Daman marine-sand investigation tender

The 90-day investigation procurement advances definition of a potential offshore borrow area. Environmental or mining permission, material suitability, a production source, a dredging or reclamation award and accepted fill remain unconfirmed.

Read controlling source

Middle East / Jordan / Port infrastructure / Current phase: tender

Aqaba Cement Terminal and Mut'ah berth rehabilitation concession

ADC published formal Tender 27/A/2026

The owner moved from EOI market sounding to a live 20-year DFBOT competition with a possible five-year extension, a JOD 100,000 bid bond, separate technical and financial submissions, and a 17 August close. Publication is not evidence of bids received, award, financing, mobilisation, rehabilitation, or operation.

Read controlling source

Europe / Italy / Ports and coastal protection / Current phase: construction

Genoa New Breakwater

Breakwater passed one kilometre with the twenty-third caisson

The caisson alignment exceeded one kilometre while seabed consolidation continued. The milestone does not show proportional overall completion, an accepted entrance or an operational navigation route.

Read controlling source

Africa / Madagascar / Marine infrastructure / Current phase: approval

Madagascar Majunga, Tulear and Pangalanes transport resilience programme

Madagascar and IDA signed the US$200 million financing agreement

Credits 8004-MG and 8005-MG moved the World Bank financing from approval into a signed legal framework for a US$305 million project. Signature did not activate unissued marine packages, satisfy co-financing conditions or evidence physical works.

Read controlling source

Americas / Panama / Dredging / Current phase: planning

Panama Canal new TSHD acquisition planning

Revision 3.3 fixed the market-survey vessel envelope

The revised document confirms a 3,500-4,300-cubic-metre hopper, one starboard pipe, 30-metre dredging depth, three discharge routes, dynamic positioning, and a current intended diesel-electric and azimuth-propulsion configuration, while preserving the non-binding procurement boundary.

Read controlling source

Asia Pacific / India / Marine utilities / Current phase: planning

Gopalpur Industrial Park 100 MLD desalination PPP

Environmental and social scoping identified the coastal interfaces

The brief explicitly places the marine intake and outfall in the Coastal Regulation Zone and requires review of marine ecology, brine effects, fishing and coastal livelihoods, tourism, public access and climate risk.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Taweelah C IPP coastal utility interface

Energy China disclosed the USD 1.687 billion EPC contract and 32-month duration

The Hong Kong regulatory filing defines the EPC consortium, price, project-company counterparties and whole-plant design-to-warranty scope. Its broad civil and commissioning language does not identify a separate seawater, cooling-water or marine package, accepted design, permit, or mobilisation date.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Geraldton Port Maximisation marine works

Mid West Ports awarded the surge-protection breakwater

MGN Civil became the named contractor for the first disclosed marine construction package. The announcement did not publish contract value, notice to proceed, rock source or mobilisation evidence.

Read controlling source

Americas / United States / Dredging / Current phase: evaluation

New York and New Jersey marine terminals maintenance dredging

The Port Authority advertised a four-terminal work-order contract

MFP-364.003 packages maintenance dredging, material amendment, transport and disposal across three New Jersey terminal systems and Howland Hook in New York at an advertised USD 50 million to USD 60 million range.

Read controlling source

Europe / United Kingdom / Marine utilities / Current phase: construction

Sizewell C temporary desalination intake, outfall and CDO

Desalination intake and outfall pipe pulls entered the marine work sequence

Notice 24 scheduled approximately 500-metre floating pipes for towage, jack-up-assisted pull-in and diving operations. The notice later moved to the inactive register; it does not certify the complete desalination marine system.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Taweelah C IPP coastal utility interface

EWEC awarded the IPP and signed the power purchase agreement

EWEC confirmed TAQA's 60 per cent project-company stake, the international consortium's 40 per cent stake, a PPA through 2050 and a 2029 commercial-operation forecast. Award and PPA execution establish the development structure; they do not prove financial close, notice to proceed, marine scope or construction progress.

Read controlling source

Africa / Tunisia / Port infrastructure / Current phase: award

Tunisia three-port access and dredged-material programme

DEME confirmed the contractor scope and three material routes

The contractor disclosure defines containment first, TSHD dredging second, and different receiving systems at each port. It does not prove mobilisation, approved material destinations, dredged quantities, production, completion, or acceptance.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: construction

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

The intake tunnel reached its offshore destination while the outfall drive remained incomplete

The owner's June panel records TBM Mary completing the 2.5 km intake drive in 196 days, all offshore piling complete and TBM Karli about 80% through the 4 km outfall drive. Intake-tunnel completion does not prove permanent riser connection, outfall completion, accepted diffuser performance, integrated testing or first water.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Georgetown Harbor maintenance dredging

USACE awarded the USD 3.587 million navigation-recovery contract

The award covers about 390,000 cubic yards in the base and a 170,000-cubic-yard option in the Bypass and Steel Mill channels, or up to about 560,000 cubic yards. The reviewed release does not identify the contractor or establish physical start.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: construction

Ocean City and Peck Beach 2026 Periodic Nourishment

USACE awarded the current periodic-nourishment contract

The USD 19.5 million Great Lakes Dredge & Dock award calls for more than 1.6 million cubic yards from the offshore borrow area and placement from 12th Street to the Seaview Road groin area. The quantity is contractual scope, not measured current-cycle output.

Read controlling source

Americas / Brazil / Dredging / Current phase: mobilisation

Paranaguá access channel dredging concession

The port tariff notice set a planned 1 August handover

Portos do Paraná says Table I will move to PPCC and gives 1 August 2026 as the expected concession start. This is a transition notice, not evidence that handover, tariff collection, or service acceptance has occurred.

Read controlling source

Africa / Ghana / Port infrastructure / Current phase: financing

Takoradi Project Shiprite floating dock and repair yard

PIDG joined the capital stack and described a path to financial close

PIDG committed USD 9.7 million in equity and shareholder lending and said the investment closed a final funding gap. The release says the transaction can proceed to financial close and construction; it does not report close, notice to proceed or site mobilisation.

Read controlling source

Asia Pacific / Japan / Offshore energy / Current phase: construction

Oga-Katagami-Akita offshore wind marine installation programme

Sea Challenger turbine-installation charter contract concluded

The charter fixes the named 1,600-tonne-lift installation vessel and Japan Offshore Marine interface for 21 turbines, without proving mobilisation, component readiness, installation cadence, or offshore completion.

Read controlling source

Americas / Brazil / Port infrastructure / Current phase: award

Port of Santos 16 m channel deepening

APS approved Jan De Nul's Lot 1 offer

The executive board approved RLE 51/2025 and recorded the integrated package boundary and R$619,780,813.76 offer. Later public announcements describe the signed package as R$617.9 million, leaving the executed contract as the controlling commercial document.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Rocky River Harbor 2026 maintenance dredging

USACE recorded mechanical dredging in the channel

Buffalo District video shows an excavator working from a spudded platform and loading dredged sediment into a scow. It confirms field operations but not measured production, final material routing or completion.

Read controlling source

Europe / United Kingdom / Port infrastructure / Current phase: construction

Maraen Port of Nigg Eastern Inner Dock Quay

Maraen awarded the construction contract and began site preparations

The owner named McLaughlin & Harvey for the Eastern Inner Dock Quay and said site preparations had commenced. The award establishes the delivery contractor and an early site state; it does not disclose the construction-contract price or prove retaining-wall installation, quay completion, berth acceptance, or cable load-out readiness.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Rocky River Harbor 2026 maintenance dredging

USACE published the contract and material split

The district reported a USD 1.1 million Geo Gradel contract, approximately 59,000 cubic yards and a planned split of about 50,000 cubic yards nearshore and 9,000 cubic yards to an open-lake area, with work continuing through August.

Read controlling source

Africa / Madagascar / Marine infrastructure / Current phase: approval

Madagascar Majunga, Tulear and Pangalanes transport resilience programme

The revised procurement plan exposed the first marine package states

The plan recorded the US$28 million Majunga works package as pending implementation, the US$6.36 million canal maintenance and dredging-fleet package under review, and a US$1.2 million landing-stage package cancelled. It listed no active main Tulear or canal-dredging works package, and planned dates do not confirm later notices or awards.

Read controlling source

Americas / Barbados / Coastal infrastructure / Current phase: construction

Bridgetown Fisheries Complex breakwater repair

Fisheries reported operational-readiness use at the complex

Operation Tempest involved the Bridgetown Fisheries Complex and its administration in a 34-vessel readiness exercise. This establishes facility use and emergency coordination, not breakwater acceptance or contract close-out.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

ICTSI assigned the corporate loan to three Philippine terminal lanes

ICTSI linked the facility to MICT, SLCT, and MCT and published terminal capacity targets through 2028. The announcement confirms intended use at portfolio level, but it does not identify package allocations, contractors, disbursements, or accepted assets.

Read controlling source

Asia Pacific / India / Marine utilities / Current phase: planning

Gopalpur Industrial Park 100 MLD desalination PPP

Legal advisory procurement set the PPP and approvals workstream

The legal brief covers regulatory due diligence, PPP structure, risk allocation, approvals, transaction documents and bid support for a phased 100 MLD plant and associated intake, outfall and transmission system.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

MPA extended Phase 2 bulk-carrier operations through December 2026

Port Marine Notice 73 set 24-hour operations in two project-area work zones from 20 June to 19 December 2026 and superseded a 2025 notice. It confirms continuing construction logistics, not completed reclamation, accepted wharf geometry, or commercial terminal operation.

Read controlling source

Americas / Brazil / Dredging / Current phase: mobilisation

Paranaguá access channel dredging concession

A separate public maintenance campaign preceded the concession transfer

Portos do Paraná placed Van Oord's Vox Amalia on the 2026 campaign and targeted end-June completion. The campaign belongs to the pre-handover maintenance regime and does not name the concession fleet or prove completion.

Read controlling source

Africa / Tunisia / Port infrastructure / Current phase: award

Tunisia three-port access and dredged-material programme

OMMP opened a separate supervision and technical-assistance tender

The owner created an independent guidance, monitoring, and technical-assistance layer for the same three-port works. The notice is a procurement start, not a supervision award, mobilisation, or approved monitoring plan.

Read controlling source

Europe / Denmark / Germany / Immersed tunnels and marine crossings / Current phase: construction

Fehmarnbelt Fixed Link Immersed Tunnel

Owner adopted separate road-first and rail-later opening paths

The decision changes the operating-release sequence and makes German railway landworks a separate service dependency, while replacement road and rail opening dates, final systems acceptance, and cost effects remain unpublished.

Read controlling source

Global islands / Norfolk Island / Dredging and waterways / Current phase: tender

Norfolk Island Kingston Pier channel and repair works

Revetment contractor appointed and dredging tender released

Land and Marine Ocean Engineering was engaged for the revetment package, while dredging and pier repairs moved into a separate tender with no award recorded.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: commissioning

Hassyan IWP seawater intake and outfall programme

DEWA confirmed commissioning of Hassyan Block A

The first 60 MIGD block entered the installed water-capacity record, moving the project into phased commissioning while the remaining 120 MIGD, full marine-system acceptance, and sustained performance remain separate conclusions.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Port Hedland Zone 5 Bypass Channel

EPA WA decided not to assess the proposal under Part IV

The state referral exited the Part IV assessment pathway after preliminary examination. That decision was not a federal sea-dumping permit, dredging approval, notice to proceed or construction acceptance.

Read controlling source

Europe / Netherlands / Offshore wind foundations / Current phase: award

Zeevonk phase 1 foundation installation

TKF received the phase 1 inter-array cable supply contract

The separate award covers about 162 km of 66 kV cable and accessories. It establishes the cable supply chain but does not identify the offshore installer.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Ocean City Inlet 2026 bypass dredging and navigation programme

USACE published the May dredging and bypass plan

Baltimore District identified approximately 15,000 cubic yards across two shoaling areas, assigned MURDEN and named the authorized offshore Assateague placement route. The release is a work plan and does not publish measured production or completion.

Read controlling source

Europe / Denmark / Germany / Immersed tunnels and marine crossings / Current phase: construction

Fehmarnbelt Fixed Link Immersed Tunnel

First standard element immersed and joined to the Danish portal

The first-of-kind operation proves the initial 217-metre element could be towed, lowered, positioned, laser-confirmed, and hydraulically connected, without proving repeat productivity or acceptance of the remaining 88 elements and systems.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Fujairah I IWP seawater intake and outfall

EtihadWE signed the AED 1.046 billion EPC agreement

The owner confirmed NMDC Infra and Lantania Aguas as the EPC consortium for a 60 MIGD plant and described an approximately 30-month delivery programme. Contract signature establishes delivery responsibility, not notice to proceed, marine mobilisation or construction progress.

Read controlling source

Africa / Tunisia / Port infrastructure / Current phase: award

Tunisia three-port access and dredged-material programme

TAP reported the three-port dredging contract had been signed

The national news agency reported a contract value of about TND 125 million across three port complexes. It gave no exact signing day or evidence of notice to proceed, fleet mobilisation, installed containment or dredging production.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Fujairah I IWP seawater intake and outfall

Lantania defined the intake-outfall scope and NMDC marine role

The contractor record identifies a submarine intake tower, two GRP intake pipelines, a GRP marine outfall and NMDC responsibility for civil and marine works. It does not publish final geometry, installation method, subcontract awards or accepted quantities.

Read controlling source

Middle East / Oman / Marine utilities / Current phase: construction

Ghubrah III IWP desalination marine system

GS Inima reported four million work hours without a lost-time injury

The event brought together more than 1,250 project and subcontractor personnel and confirms a large active construction site. It does not state offshore installation quantities, mechanical completion, first water or owner acceptance.

Read controlling source

Americas / Brazil / Dredging and waterways / Current phase: approval

Itajaí-Mirim flood-channel widening and dredging

Itajaí commissioned a separate executive dredging design

The municipal contract covers surveys, sampling, laboratory work and design for a natural-river reach. It advances preparation but is not the P508221 main works contract.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: construction

Skandia Gateway fairway and quay deepening

Authority reopened an optimized and split fairway procurement

The Swedish Maritime Administration reduced selected fairway and turning-area dredging, retained 16.5 metres as the base depth with 17.5 metres as an option, and separated the port-side and national contracts. The update advances procurement but does not establish the revised total volume, national award, completed geometry, or operating draft.

Read controlling source

Africa / Morocco / Marine utilities / Current phase: construction

Casablanca-Settat desalination marine works and common systems

Q1 construction activity identified Casablanca as a Water delivery driver

ACCIONA's Q1 statement says Water revenue growth and backlog execution were driven in part by construction at Casablanca. It confirms active contractor delivery through 31 March 2026 but does not identify completed marine structures, tunnel advance, wet testing, or owner acceptance.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Geraldton Port Maximisation marine works

Ministerial Statement 1272 allowed the proposal to proceed

The approval set the 258,000 m3 dredging limit, seasonal restriction and environmental-management conditions for the wider project. It did not award the dredging or berth packages.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Oswego Harbor 2026 breakwater repair phases

USACE awarded the 732-foot second repair phase

Dean Marine and Excavating received a USD 14.9 million contract covering 425 feet of East Arrowhead and 307 feet of Outer West. USACE planned a summer 2026 start, but the award does not establish mobilisation or production.

Read controlling source

Africa / Democratic Republic of the Congo / Deep-water ports and container terminals / Current phase: construction

Banana Deep-water Port Phase One

Government kept acceleration on the agenda after reported local delays

The Prime Minister's office recorded political concern about manoeuvres and slowdowns that could delay execution and renewed acceleration as a priority. It did not publish a revised completion date, quantified progress, accepted marine output, terminal readiness or an opening notice.

Read controlling source

Europe / Portugal / Marine utilities / Current phase: construction

Algarve seawater desalination intake and outfall system

The owner signed the construction release

The release followed APA review of pre-start conditions under the DCAPE. It advances the whole contract into construction but leaves the offshore sequence and physical marine progress to later evidence.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: tender

New Haven Harbor improvement dredging

USACE and Connecticut executed the project partnership

The construction phase was formally launched and the owner set a fall 2026 to spring 2028 expectation, without naming a works contractor.

Read controlling source

Middle East / Jordan / Marine utilities / Current phase: financing

Aqaba-Amman National Water Carrier marine works

Jordan signed the final technical and legal agreement

The government marked completion of 16 months of technical, legal and financial negotiation and kept financial close and construction launch as later steps. The agreement advances contractual readiness; it is not financial close, a notice to proceed, marine-package mobilisation or physical construction evidence.

Read controlling source

Europe / Ireland / Port infrastructure / Current phase: construction

Dublin Port MP2 Berths 52 and 53 marine construction

TED published the contract result

The result identifies Wills Bros and €128.7065 million excluding VAT. It also records 25 April 2024 as the contract date, so publication in 2026 is a procurement-disclosure event rather than a new award.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: completed

Isle of Palms Breach Inlet beneficial-use dredging

USACE marked both dredging projects complete

The district reported about 700,000 cubic yards placed below high tide between 2nd and 10th Avenue. The figure covers the combined programme and does not provide a contractor-by-contractor final split.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: construction

Skandia Gateway fairway and quay deepening

Port awarded the quay-adjacent dredging package to Boskalis

The approximately SEK 202 million contract covers blasting and dredging beside the terminal quay during an October 2026 to March 2027 window. The port-side package is separate from the national fairway award; mobilisation, accepted port-reach depth and usable vessel draft remain future evidence.

Read controlling source

Europe / United Kingdom / Marine utilities / Current phase: construction

Sizewell C temporary desalination intake, outfall and CDO

The combined drainage outfall reached pipe pull

Notice 19 scheduled a 48-72 hour harbour closure around the CDO pull-in using NP497 and associated vessels. Its later inactive status supports the end of that operation, not final outfall acceptance.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: construction

Sabine-Neches Waterway Channel Improvement Project

SNND awarded the 44-foot inland package to Callan Marine

The USD 239 million contract covers about 20 million cubic yards, two anchorage basins, and 44 feet of usable draft from Taylor Bayou to Port Arthur and Beaumont by 15 April 2028. Its early-June dredging date was a schedule, not evidence of mobilisation or production.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: completed

Isle of Palms Breach Inlet beneficial-use dredging

A shoreline crew began removing clay pockets

Sewee Construction was brought in under Cottrell to remove concentrated clay and mud at low tide, turning a material-compatibility issue into a defined cleanup task after placement.

Read controlling source

Africa / Madagascar / Marine infrastructure / Current phase: approval

Madagascar Majunga, Tulear and Pangalanes transport resilience programme

The final appraisal fixed the US$102.24 million marine component

The PAD allocated US$30 million to Majunga, US$32 million to Tulear and US$29.94 million to the Pangalanes Canal within an eight-subcomponent port and waterway programme. These are programme allocations, not contract values or awarded amounts.

Read controlling source

Asia Pacific / Vietnam / Deep-water ports and container terminals / Current phase: approval

Can Gio International Transshipment Port

Ho Chi Minh City selected the investor consortium

Decision 2155/QD-UBND approved Vietnam Maritime Corporation, Saigon Port and Terminal Investment Limited Holding as the project investor. The decision establishes the developer group, not a marine construction award.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Cleveland Harbor 2026 maintenance dredging

DMYLES received the two-window maintenance award

USACE awarded DMYLES USD 11.7 million for approximately 250,000 cubic yards from the upper Cuyahoga River, with work planned for 15 May-30 June and 1 October-30 November. Award and planned dates do not establish mobilisation, production, placement, survey acceptance, or completion.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: construction

Port of Montreal Contrecœur Container Terminal

Canada Infrastructure Bank announced a CAD 1.16 billion loan

The loan materially strengthens the financing path for the owner-led terminal programme, but it is neither a disclosed total project cost nor evidence that the marine package, dredging, or vessel-access works have been completed.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: design

Westport Kwinana container port and marine infrastructure

Westport opened a seagrass-restoration trial RFP

The request sought multiple providers for delivery-ready summer-2026 trials and emerging methods for summer 2027. It creates a bounded ecological-restoration procurement signal, not evidence of provider award, trial mobilisation, successful restoration, environmental approval, or capital marine works.

Read controlling source

Europe / Germany / Port infrastructure / Current phase: construction

Cuxhaven offshore-wind terminal at berths 5 to 7

Meuse River began active reclamation work

DEME's project update shows the hopper dredger rainbowing inside the new quay line, moving at least part of the site from waterfront piling into terminal land formation.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Port Hedland Zone 5 Bypass Channel

Pilbara Ports lodged federal sea-dumping application SD2026-4091

The application sought a two-year permit for loading and dumping up to 800,000 cubic metres from the capital works. The current federal register records the application but does not list it among granted or refused permits.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Port Hedland Zone 5 Bypass Channel

The final environmental review documented the execution envelope

The review carried the channel, dredging, disposal, monitoring and marine-fauna controls into the referral record. It defined a maximum environmental envelope, not the awarded bill quantity or completed as-built works.

Read controlling source

Asia Pacific / India / Deep-water ports, dredging and reclamation / Current phase: tender

Vadhvan Greenfield Deep-draft Port

NHAI awarded the port's external highway connection

The road award advances landside connectivity and carries the government's attributed 2030 first-phase operating target. It is not an award, mobilisation or completion record for the breakwater, offshore HAM package, terminals, rail, harbour systems or commercial port service.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: construction

Sabine-Neches Waterway Channel Improvement Project

SNND and USACE established a federal funding route for sponsor delivery

The memorandum allowed SNND to execute the Callan package while remaining eligible to receive federal funds for at least 60 percent of the contract cost. It changed the delivery and funding path but did not itself prove an appropriation, payment, or physical dredging start.

Read controlling source

Europe / United Kingdom / Dredging / Current phase: approval

Southampton Channel Deepening capital dredge

ABP submitted the capital-dredge application

The application defined the SCT 5 and channel depths, approximately 5.5 million m3 volume, maximum 1.3 m local cut and proposed December 2026 to July 2027 work programme. These are proposed works until licensed and contracted.

Read controlling source

Europe / Belgium / Port infrastructure / Current phase: construction

Antwerp Kanaaldok B2 liquid CO2 export quay

Fluxys separated the terminal connection into network Phase 1b

The 2026 network plan makes the terminal link conditional on technical and economic justification and signed contracts, and references mid-2029 in its current terminal-operational planning language. It is not a terminal final investment decision or commissioning confirmation.

Read controlling source

Africa / Senegal / Coastal infrastructure / Current phase: construction

Gorée Island east and west coastal protection works

WACA recorded an 82% overall field baseline

WACA reported the 390-metre eastern work front nearly complete and the 900-metre western work front at 82%, with a 30 June 2026 delivery expectation. The later financing paper supersedes that schedule expectation without proving handover.

Read controlling source

Global islands / Tonga / Port infrastructure / Current phase: award

Nafanua Port resilience improvement

The Ministry sought a dedicated construction-supervision team

The request covered a resident engineer, site inspector and environmental and social specialist for the Nafanua works. It supports delivery preparation but does not prove that the works contractor mobilised.

Read controlling source

Europe / United Kingdom / Port infrastructure / Current phase: prequalification

Ardersier Port Phase 2 dredging procurement

Ardersier opened prequalification for the Phase 2 dredging package

The notice set a GBP 20 million estimate, exact channel geometry, a four-stage negotiated route, a planned shortlist of four and a Q2 2028 dredging window. It did not publish a shortlist, tender issue, bidder, award or mobilisation.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

Ramayapatnam Port capital deepening works

The Tettu serving-station yard reached an advanced stage

The Railways ministry said RPDCL was developing the approximately 5.5-kilometre Ramayapatnam-to-Tettu connection under the Gati-Shakti Multi-Modal Cargo Terminal Policy and that work on the serving-station yard was at an advanced stage. It did not provide a completion date or establish completed rail access and cargo-evacuation readiness.

Read controlling source

Africa / Burundi / Marine infrastructure / Current phase: construction

Bujumbura Port Lake Tanganyika corridor rehabilitation

UNDP presented a climate-resilience engineering study for the port

The study followed the 2024 Lake Tanganyika flooding and proposes phased reinforcement, drainage, and resilient expansion measures. It creates a planning and investment track; it does not establish completion or new physical progress of the active Phase I marine works.

Read controlling source

Europe / United Kingdom / Port infrastructure / Current phase: construction

Maraen Port of Nigg Eastern Inner Dock Quay

Final investment moved the consented quay into funded delivery

Maraen announced the £30 million-plus final investment after securing planning consent and the marine licence, with a £10 million Highlands and Islands Enterprise grant. The decision funded the project boundary but did not establish physical marine works, completion timing, or accepted operating capacity.

Read controlling source

Middle East / Jordan / Marine utilities / Current phase: financing

Aqaba-Amman National Water Carrier marine works

AIIB approved USD 250 million of nonsovereign financing

AIIB approved its financing and set construction-phase environmental and social monitoring expectations. Lender approval contributes to the finance stack but does not establish that all financing conditions are met or that financial close, drawdown, NTP or marine works have occurred.

Read controlling source

Middle East / Iraq / Port infrastructure / Current phase: construction

Grand Faw phase-one marine and port-access system

The owner was still testing operating and partnership models

GCPI reviewed berthing, cargo handling, operating economics, and international partnerships. This confirms that physical assets had moved into operating preparation while final commercial responsibility and the operating model remained open.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

AIIB approved the USD 300 million Project Crane facility

Approval set the nonsovereign senior unsecured corporate loan and result framework for BIPI, MICP/MCT and MICT. The three terminal programmes remained separate, with site-level awards and completion still to be evidenced.

Read controlling source

Europe / Netherlands / Port infrastructure / Current phase: construction

Port of Rotterdam Yangtzekanaal widening and quay programme

Phase A built the enabling cofferdam and reused 80,000 cubic metres of sand

The 2025 annual report identifies a 1,500 by 40 metre temporary watertight structure for Phase B and early material reuse, while recording that the next investment decision and permit still followed at that reporting point. The current programme page later supersedes that planning state with Phase B award and start.

Read controlling source

Europe / Belgium / Port infrastructure / Current phase: construction

Antwerp Kanaaldok B2 liquid CO2 export quay

Flanders appointed the local CO2 network operator

The 20-year appointment established Fluxys c-grid Antwerp's regulated network role while the first port-area pipeline was already under construction. It did not confirm terminal investment, customer contracts, marine loading, export service, or stored volume.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

Radomiro Tomic reservoir entered final construction

The contractor recorded the high-altitude reservoir, manifolds and surrounding pipework nearing physical completion at 3,080 m. Reservoir readiness advances the inland receiving interface, while water arrival, accepted storage, distribution and sustained operation remain unverified.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

MPA renewed the Phase 2 marine work area through September 2026

Port Marine Notice 43 extended the regulated works period from 26 March to 25 September 2026 and revised the work-area chart and craft list. The notice is activity and navigation-control evidence, not a construction-completion or acceptance certificate.

Read controlling source

Africa / West Africa / Coastal infrastructure / Current phase: construction

WACA ResIP 1 coastal protection works programme

The World Bank launched WACA+ as a separate programme

The first WACA+ financing covers new work in Benin and Mauritania. It opens a follow-on pipeline but does not extend every ResIP 1 contract or change the status of the six-country work fronts already under delivery.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: construction

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

Beverley mobilised for offshore intake and outfall installation

The Western Australian Government recorded arrival of the 78 m-leg jack-up barge with a 400 t crane for 24-hour installation of ocean intake and outfall structures. Vessel arrival and offshore activity establish mobilisation, not installed or accepted marine assets.

Read controlling source

Asia Pacific / India / Dredging / Current phase: tender

Kamarajar Port AECTPL Phase I Stage II capital dredging

The published bid window closed

The CPPP schedule reached its submission deadline with a 17 March bid-opening date. This closes the advertised bid window but does not establish technical admission, financial opening, award or a work order.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

ICTSI launched SLCT and described active construction

The launch release says Phase 1 construction started in September 2025, describes a 400-metre quay, and targets September 2027 completion. Those statements conflict with ICTSI's January 2026 425-metre and May-to-September 2027 programme, so neither version should be silently normalized.

Read controlling source

Americas / Brazil / Dredging / Current phase: mobilisation

Paranaguá access channel dredging concession

The 25-year concession contract was signed

DEME confirms the signed contract and PPCC operating vehicle. Signature moved the project into mobilisation and transition, but it did not deliver the future 15.5-metre target or establish physical works acceptance.

Read controlling source

Africa / Nigeria / Deep-water ports and container terminals / Current phase: award

Nigeria Snake Island Container Terminal concession and EPC

MSC signed the sub-concession and finalized the EPC

The container-terminal package now has a 45-year commercial structure, named EPC parties and defined design geometry. The announcement does not establish a work start or operating date.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: planning

Toukley desalination intake and existing-outfall connection

The Commonwealth referral described the offshore intake and existing-outfall connection

EPBC 2026/10457 documented the 2.4 km microtunnel, intake about 1 km offshore, caisson concept and 180 m brine connection. The portal currently records Assessment Approach Determined, not final approval.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: design

Westport Kwinana container port and marine infrastructure

Government introduced legislation for a dedicated Westport Authority

The Bill defines a proposed delivery body and later transfer of completed port and maritime assets. Introduction is a governance change, not passage into law, funding approval, final investment decision, environmental approval, or construction authorization.

Read controlling source

Africa / Democratic Republic of the Congo / Dredging / Current phase: delivery

CVM Congo River Easydredge 2700XL fleet renewal

CVM and Royal IHC signed the customised 2700XL building contract

The contract commits an approximately 3,300 m³ TSHD, Vietnam build and first-year support for Congo River maintenance and land-reclamation duties. Construction start, final specifications, delivery, acceptance, deployment and navigation improvement all require later records.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: tender

Newark Bay FY26 federal navigation maintenance dredging

The district published its annual Newark Bay maintenance notice

The notice described about 830,000 CY across several channels and annual cycles, environmental-bucket dredging and upland placement. It sets the broader programme context but not the FY26 IFB base quantity.

Read controlling source

Americas / United States / Port infrastructure / Current phase: tender

Richmond Inner Harbor FY26 maintenance dredging

The FY2026 planning schedule set an initial baseline

The district planning deck carried a 350,000-cubic-yard estimate, lower cost band and July award target. Those planning figures are retained for change tracking, not treated as current contract terms.

Read controlling source

Europe / United Kingdom / Dredging / Current phase: award

UK Navy Future Dredging Contract

The Ministry of Defence published its Boskalis award decision

The UK6 notice named Boskalis Westminster, recorded a £9.2 million value excluding VAT, two assessed tenders, an earliest signature date of 27 March 2026, and an estimated initial term to March 2028. The decision selected the supplier; signature, notice to proceed, mobilisation, dredging and accepted naval-port access remained open.

Read controlling source

Europe / Netherlands / Dredging / Current phase: delivery

Boskalis SEAWAY 31,000 m³ TSHD

Boskalis still reported SEAWAY under construction

The owner identified SEAWAY as one of its largest 2025 investments and said year-end capital commitments related predominantly to its completion and other named fleet investments. This is a current construction and capital-completion signal, not delivery or service entry.

Read controlling source

Africa / Liberia / Coastal infrastructure / Current phase: approval

West Point Coastal Defence Revetment

Liberia issued the West Point environmental permit

The permit authorises the revetment within defined coordinates after ESIA approval. No works contractor, contract value, notice to proceed, or mobilisation record has yet been published.

Read controlling source

Middle East / Saudi Arabia / Marine utilities / Current phase: construction

Ras Mohaisen Independent Water Project and Marine Intake/Outfall

ACWA classified the full design capacity as under construction

The developer's year-end report records 300,000 cubic metres per day under construction, SAR 2.569 billion total investment cost and Q4 2029 expected PCOD. A portfolio construction classification does not prove offshore mobilisation, installed intake or outfall assets, first water, accepted capacity or commercial operation.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: planning

Toukley desalination intake and existing-outfall connection

Council fixed the current pump-station and intake-route concept

The preferred concept moved the pump station to the plant site and retained only a construction and maintenance shaft near Jenny Dixon Beach. It defines the EIS basis but does not authorise construction.

Read controlling source

Asia Pacific / Singapore / Marine utilities / Current phase: construction

Singapore DTSS2 Tuas WRP nearshore outfall

PUB current programme retains phased commissioning from 2027

The owner schedule keeps whole-system operation as a future gate despite the earlier outfall civil milestone. A commissioning target does not establish first discharge or accepted performance.

Read controlling source

Americas / Argentina / Port infrastructure / Current phase: mobilisation

Argentina Vía Navegable Troncal dredging and signaling concession

Three consortia submitted first-envelope bids

The official award record identifies offers from Jan De Nul-Servimagnus, DEME and DTA Engenharia. Bid receipt established competition, while qualification, technical merit, economics, award and signature remained open.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: completed

Isle of Palms Breach Inlet beneficial-use dredging

Both placement packages reached field completion

The City recorded completion by Ahtna and Cottrell on the same date and identified 265,000 cubic yards placed by Cottrell between 6th and 9th Avenue.

Read controlling source

Africa / Madagascar / Marine infrastructure / Current phase: approval

Madagascar Majunga, Tulear and Pangalanes transport resilience programme

Appraisal documents separated port rehabilitation from canal dredging

The appraisal PID and ESRS defined existing-quay work at Majunga and Tulear without port dredging and assigned spot dredging, turbidity, freshwater habitat and dredged-material management to Pangalanes. Site-specific instruments remained required before related bidding and works.

Read controlling source

Global islands / Fiji / Marine utilities / Current phase: prequalification

Fiji Kinoya wastewater treatment and Laucala Bay outfall programme

Procurement plan defines a US$104.85 million DBO with five years of operations

The plan fixes CW02 as an international, prequalified, prior-review design-build-operate competition with a 70:30 merit-point evaluation. It defines a major treatment and operating package but does not add a new offshore outfall or marine pipeline.

Read controlling source

Middle East / Jordan / Marine utilities / Current phase: financing

Aqaba-Amman National Water Carrier marine works

EBRD approved a senior loan of up to USD 475 million

EBRD board approval set out the proposed senior financing and Category A environmental framework. The project remained at Approved rather than Signed or Implementing status, short of financial close or construction release.

Read controlling source

Africa / Morocco / Deep-water ports and energy terminals / Current phase: commissioning

Nador West Med Deep-water Port

EBRD grant added operating-readiness support

The grant adds institutional and operational capacity work to the launch sequence, while leaving civil acceptance, navigation services, terminal systems, trained operations, and commercial service as independent gates.

Read controlling source

Middle East / Saudi Arabia / Marine utilities / Current phase: commissioning

Rabigh 4 IWP intake, outfall and storage system

The EPC consortium completed the performance test

SEPCOIII reported full design-capacity testing and measured power consumption. The notice does not establish SWPC commercial acceptance, final marine handover or sustained operating performance.

Read controlling source

Europe / United Kingdom / Marine utilities / Current phase: construction

Sizewell C temporary desalination intake, outfall and CDO

Boring and lining started across three sub-seabed utility routes

Notice 11 set commencement for the CDO, temporary desalination intake and desalination outfall and named the initial vessel spread. The notice remains active on the harbour register.

Read controlling source

Africa / Egypt / Deep-water ports and container terminals / Current phase: commissioning

Damietta Alliance Container Terminal (Tahya Misr 1)

Damietta CT2 entered commercial operation

The first Hapag-Lloyd call moved the terminal into live service with 12 ship-to-shore cranes, 40 yard cranes and two operational rail lanes. Full operations and final capacity remain later measures.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

Ramayapatnam Port capital deepening works

The port remained officially under construction

The Ministry of Ports, Shipping and Waterways listed Ramayapatnam among four Andhra Pradesh ports under construction. This is a portfolio-status confirmation, not a package percentage, completion date or operating approval.

Read controlling source

Africa / Senegal / Marine utilities / Current phase: construction

Dakar Mamelles desalination intake and brine discharge

The plant remained under construction in its commissioning year

TPF's supervision visit confirmed active construction and an expectation of commissioning later in 2026, superseding the original 2025 completion plan without proving operating release.

Read controlling source

Africa / Burundi / Marine infrastructure / Current phase: construction

Bujumbura Port Lake Tanganyika corridor rehabilitation

AfDB published adjacent fisher and enterprise-support works procurement

The notice confirms continued activity within the wider corridor programme. Its scope is not a progress certificate for the protective dike, dredging, quays, marine dock, roads, or port equipment.

Read controlling source

Africa / São Tomé and Príncipe / Marine infrastructure / Current phase: financing

São Tomé and Príncipe BEFIRM fisheries infrastructure rehabilitation

AfDB financing agreements were signed

MapAfrica records UA 15 million from the Transition Support Facility and UA 1.5 million from the African Development Fund. Signature moves the programme beyond board approval but does not establish effectiveness, disbursement, procurement, or works execution.

Read controlling source

Asia Pacific / Vietnam / Deep-water ports and container terminals / Current phase: approval

Can Gio International Transshipment Port

Saigon Port approved its consortium and capital position

Shareholders authorised Saigon Port to join VIMC and MSC/TiL in the investor application and to take 15% of the project company's charter capital after approval.

Read controlling source

Global islands / Tuvalu / Port infrastructure / Current phase: completed

Tuvalu Nui and Niutao climate-resilient boat harbours

Nui and Niutao harbour development completed

The joint government and financing-partner announcement confirms both named harbour assets were delivered and Niutao opened, moving the record from construction to completed named works while leaving operating performance and wider-programme close-out separate.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Port Hedland Zone 5 Bypass Channel

The salvage plan linked bypass activation to incident command

The port's response plan tied slow-speed passing and bypass activation to Harbour Master approval, salvage stabilisation and business-continuity sequencing. The procedure is planning evidence, not proof that the unbuilt route is available.

Read controlling source

Africa / Morocco / Deep-water ports and energy terminals / Current phase: commissioning

Nador West Med Deep-water Port

Royal Office reported basic port infrastructure complete

The statement advances the marine base to reported civil completion and sets a fourth-quarter 2026 launch target; hydrographic acceptance, equipped terminals, harbour systems, trial calls, and commercial operation remain separate evidence outcomes.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Cleveland Harbor 2026 maintenance dredging

USACE opened short-term placement scoping

The preliminary-assessment addendum evaluates limited open-water placement, CDF 12, the Port's SPMF, and littoral nourishment for future Cleveland material management. It is an alternatives and public-comment record, not a selected or authorised route for the 2026 DMYLES contract.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: completed

Isle of Palms Breach Inlet beneficial-use dredging

Ahtna entered its final borrow area as Cottrell approached

The City reported fewer than 200,000 cubic yards remaining. Ahtna shifted south of 6th Avenue so the separate Cottrell package could work nearby, while continuing 24-hour operations.

Read controlling source

Europe / Denmark / Germany / Immersed tunnels and marine crossings / Current phase: construction

Fehmarnbelt Fixed Link Immersed Tunnel

Owner withdrew the former 2029 opening baseline

The preparation update establishes that the immersion-vessel delay made a 2029 opening unrealistic and that a new overall schedule would follow early immersion experience; it does not publish replacement dates or a revised final cost.

Read controlling source

Africa / Morocco / Deep-water ports and energy terminals / Current phase: commissioning

Nador West Med Deep-water Port

TIL entry into East-terminal capital completed

The ownership event confirms the East terminal concession structure and operator alignment, but it is not evidence that superstructures, equipment, terminal systems, or vessel-service readiness are complete.

Read controlling source

Africa / Senegal / Deep-water ports and container terminals / Current phase: construction

Port of Ndayane Deep-water Port and Container Terminal

Senegal set 2028 as a full-operation target

The Council of Ministers placed Ndayane among projects intended to become fully operational by 2028. This is a government delivery target, not evidence of completed dredging, accepted quay and terminal systems, commissioned harbour services, or commercial opening.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: design

Westport Kwinana container port and marine infrastructure

Westport appointed its marine and port technical advisor

The Worley Arcadis Joint Venture award advances reference design, approvals, construction planning, cost development, and advice for the channel, breakwater, quay, dredging, and terminal operations. It is a professional-services award, not a capital-dredging or marine-construction contract.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

ICTSI published the first detailed SLCT Phase 1 programme

The release defines a 425-metre quay, 11-hectare yard, four remote super post-Panamax cranes, and 800,000-TEU initial capacity, with construction described as May to September 2027. It is a programme disclosure, not contractor or acceptance evidence.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: construction

Port Mansfield Channel 2026 maintenance dredging

The active navigation notice began

The Coast Guard identified General Bradley and General Marshall, the Daybeacon 18 start area, pipeline crossings and receiving routes to Bird Island and Padre Island Beach.

Read controlling source

Asia Pacific / Bangladesh / Port infrastructure / Current phase: design

Bangladesh Bay Terminal marine infrastructure

Latest implementation report kept physical works at pre-start

The World Bank recorded effective financing and studies nearing completion, while marine works remained pre-start and the terminal PPP RFP awaited feasibility and transaction-structure approval.

Read controlling source

Americas / Mexico / Marine utilities / Current phase: tender

Rosarito 2,200 l/s desalination procurement

Environmental resolution was reported delivered

The reported approval advanced the project beyond environmental review while retaining conditions around the existing CFE intake and discharge route.

Read controlling source

Europe / United Kingdom / Dredging / Current phase: approval

Southampton Channel Deepening capital dredge

ABP launched the two-stage contractor competition

The UK4 notice opened the Conditions of Participation stage for capital dredging at Southampton and in the Nab Deep Water Channel. It did not disclose a usable contract estimate or select a contractor.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: construction

Port of Montreal Contrecœur Container Terminal

Fisheries and Oceans Canada authorized the wharf and underwater works

The authorization clears a central regulatory gate under the Fisheries Act and Species at Risk Act while binding construction to specified measures and conditions. Physical commencement and compliance acceptance remained separate, unreported steps.

Read controlling source

Middle East / Iraq / Port infrastructure / Current phase: construction

Grand Faw phase-one marine and port-access system

Trial shipping calls began while full commercial operation remained a target

The port authority said the navigation channel and main berths had been prepared and first vessels received on trial lines, while infrastructure and land-sea connections were still being developed. Trial calls are not evidence of sustained commercial throughput.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: commissioning

Hassyan IWP seawater intake and outfall programme

First phase reported about 90 percent complete

The progress report narrowed the delivery window and put construction at an advanced stage. A percentage-complete statement left first water, accepted output, intake-outfall performance and commercial operation unverified.

Read controlling source

Middle East / Oman / Marine utilities / Current phase: construction

Ghubrah III IWP desalination marine system

Nama PWP retained a Q1 2027 commercial-operation target

The latest owner annual report lists Ghubrah III under construction at 300,000 m3/day with scheduled commercial operation in Q1 2027, superseding the earlier 2026 programme dates without proving a new accepted completion date.

Read controlling source

Global islands / Comoros / Port infrastructure / Current phase: construction

Boingoma Port expansion and climate-resilient marine works

AfDB recorded Boingoma works in progress

The December implementation report moves the record beyond award and mobilisation. It also shows the wider programme still in start-up, so the report cannot be read as a completed port or as proof of any accepted quantity.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

ICTSI's annual report confirmed that MCT berth expansion began in 2025

The annual report moves MCT beyond a concession-linked investment plan into physical expansion and records more than 300,000 TEUs plus a 13 percent berth-productivity improvement. It does not identify the contractor, dredging progress, or completed wharf length.

Read controlling source

Asia Pacific / Singapore / Marine utilities / Current phase: construction

Singapore DTSS2 Tuas WRP nearshore outfall

Wider DTSS2 reached about 80% and Tuas WRP 57%

All five tunnel contracts had received statutory completion certificates, while plant MEICA work and critical influent-shaft interfaces remained active. The outfall could not be read independently from that unfinished system.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

Owner measured Phase 2 reclamation at 79.5%

MPA's 2025 annual report advanced the aggregate reclamation measure and said the first six completed berths were targeted for handover to PSA in March 2026. It did not confirm handover, marine-civil acceptance, terminal readiness or operation.

Read controlling source

Asia Pacific / India / Dredging / Current phase: tender

Mumbai Port 2026-29 maintenance dredging programme

The 2026-27 budget retained an annual maintenance-dredging line

Mumbai Port's budget records INR 86.02 crore actual expenditure for 2024-25, INR 70 crore revised estimate for 2025-26, and INR 65 crore budget estimate for 2026-27. These are annual accounting figures and are not the E.47/2026 contract value or dredged quantity.

Read controlling source

Middle East / Bahrain / Marine utilities / Current phase: tender

Hawar SWRO offshore intake and outfall tender

Two bids opened for the offshore intake and outfall

Tender Board published accepted opened values from Al Hassanain and Noble Development while retaining technical and financial evaluation before award.

Read controlling source

Middle East / Saudi Arabia / Marine utilities / Current phase: construction

Ras Mohaisen Independent Water Project and Marine Intake/Outfall

Sharakat announced financial close

Financial close establishes funded delivery and the 45/35/20 sponsor structure. Sharakat's release gives initial 100,000-cubic-metre-per-day production in 2028 and full 300,000-cubic-metre-per-day production in 2030; those are phased schedule statements rather than first-water, performance or acceptance records.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

The 48-inch conveyance line crossed beneath the Loa River

Techint completed a 940 m horizontal directional drilling more than 30 m below the riverbed, closing a named continuity risk in the inland pipeline. The crossing is a construction milestone, not proof of full-route hydraulic acceptance or marine-system readiness.

Read controlling source

Middle East / Bahrain / Marine utilities / Current phase: tender

Hawar SWRO offshore intake and outfall tender

Four bids opened for storage tanks and forwarding pumps

The downstream storage and distribution station remained a third EPC competition with its own 18-month duration and acceptance path.

Read controlling source

Europe / United Kingdom / Dredging / Current phase: approval

Southampton Channel Deepening capital dredge

ABP announced the planned procurement

The UK3 notice first set out the principal-contractor route, expected contract period and live-port, pipeline and UXO constraints before the tender opened.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: design

Westport Kwinana container port and marine infrastructure

Westport opened its Professional Services Panel EOI

The EOI created a prequalification route across 14 disciplines including dredging, breakwater design, marine structures, geotechnical, metocean, and marine environmental science. It does not prove panel appointment, task order, construction tender, or physical delivery.

Read controlling source

Middle East / Iraq / Port infrastructure / Current phase: construction

Grand Faw phase-one marine and port-access system

All immersed-tunnel elements were seated beneath Khor Al-Zubair

GCPI marked completion of element placement and allowed a site walk-through, but its notice said service entry would follow in later project stages. Mechanical, electrical, safety, closure, testing, and operating acceptance therefore remain separate from structural placement.

Read controlling source

Middle East / Jordan / Marine utilities / Current phase: financing

Aqaba-Amman National Water Carrier marine works

The lender disclosure fixed the current marine design and controls

The disclosed ESIA package defines the shoreline lagoon, possible cofferdam, nearshore trench, temporary jetty, approximately 3,000 mm outfall, eight-riser diffuser, seabed protection and marine monitoring sequence. Disclosure establishes the assessed design basis, not final design acceptance, permits discharge, construction start or installed marine geometry.

Read controlling source

Africa / São Tomé and Príncipe / Marine infrastructure / Current phase: financing

São Tomé and Príncipe BEFIRM fisheries infrastructure rehabilitation

AfDB published the three-port output and five-year programme boundary

The announcement identifies Neves, Porto Alegre, and Chimalô for rehabilitation, disaster-management support at Port Santo António Praia, 400 fiberglass boats, six cold stores, four refrigerated trucks, and implementation across 2026-2030. These are programme outputs, not awarded quantities or accepted assets.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Taweelah C IPP coastal utility interface

Developer staffing record named cooling-water-system review

A Taweelah C mechanical and piping role requires cooling-water-system knowledge and oversight of EPC piping design, construction testing and handover. The same page describes the plant as inland and uses a 2.4 GW figure that differs from the later 2.6 GW award, so it is role-level interface evidence rather than a controlling design or marine-scope record.

Read controlling source

Americas / Argentina / Port infrastructure / Current phase: mobilisation

Argentina Vía Navegable Troncal dredging and signaling concession

ANPYN issued the national and international concession tender

The final call put modernization, expansion, operation, signalling, dredging, redredging and maintenance into a toll-backed, contractor-risk procurement. Tender scope did not establish an award, final delivery sequence or field execution.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: completed

Isle of Palms Breach Inlet beneficial-use dredging

Cottrell's material routes were separated by shoal

The City said Dewees Inlet material and Breach Inlet shoal 1B material would go to an open-water site before shoal 1A material was placed on the Isle of Palms beach.

Read controlling source

Africa / West Africa / Coastal infrastructure / Current phase: construction

WACA ResIP 1 coastal protection works programme

The regional steering committee put ResIP 1 in its final phase

The update separated ResIP 1 close-out from ResIP 2 expansion into The Gambia, Ghana, and Guinea-Bissau. Each country still needs its own civil-works, safeguards, and acceptance record.

Read controlling source

Americas / Argentina / Port infrastructure / Current phase: mobilisation

Argentina Vía Navegable Troncal dredging and signaling concession

The prior-observations stage closed before final tendering

ANPYN completed the short technical and public comment process on the draft conditions and moved toward final documents. Closing consultation was a procurement-design milestone, not an environmental approval or contractor appointment.

Read controlling source

Europe / Italy / Ports and coastal protection / Current phase: construction

Genoa New Breakwater

Fifteenth caisson and 50,000 gravel-column threshold reached

The update records 15 installed caissons, more than 50,000 gravel columns, reported 79 percent foundation-column progress and 87 percent seabed gravel placement at that date. Foundation monitoring and downstream structural and navigation gates remained open.

Read controlling source

Europe / United Kingdom / Dredging / Current phase: award

UK Navy Future Dredging Contract

The formal tender opened the competitive procedure

The UK4 notice set a competitive flexible procedure, a £16 million estimate, 70% quality and technical weighting, 30% price weighting, and two optional one-year extensions. The estimate described the tender, not an executed contract value, final scope or saving benchmark.

Read controlling source

Global islands / Solomon Islands / Marine utilities / Current phase: tender

Honiara wastewater mains and two deep-sea outfalls

EIB approved a related facility with the marine works excluded

The approval supports Honiara sewer reconfiguration, but the EIB environmental sheet limits its project to new sewer lines and a 60 cubic metre-per-day septage plant and says the new pump stations and sea outfalls are not included.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: construction

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

Navigation closures established the offshore construction footprint

Transport WA issued two 500 m-radius closure notices for intake and outfall works beginning on 10 December 2025, identifying Beverley, Pilbara 400 SEMP, support tugs and work barges. A regulated marine work zone proves planned and authorised activity, not completed piling or structural acceptance.

Read controlling source

Asia Pacific / Bangladesh / Port infrastructure / Current phase: design

Bangladesh Bay Terminal marine infrastructure

IDA financing became effective

The three IDA credits moved from signature to effective status. Effectiveness released the financing framework but did not award or start a marine-works contract.

Read controlling source

Middle East / Iraq / Port infrastructure / Current phase: construction

Grand Faw phase-one marine and port-access system

The owner reported the navigation channel complete and the terminal yard at 96.5%

GCPI reported the 23 km channel at 100%, 19.8 m final depth and 200 m width, the five berths at 100%, and the 2,000 m by 600 m container yard at 96.5%. These are package progress statements; they do not prove hydrographic acceptance, equipment handover, or commercial commissioning.

Read controlling source

Americas / Brazil / Dredging / Current phase: mobilisation

Paranaguá access channel dredging concession

The ministry homologated the auction result

Homologation confirmed CCGD as the selected consortium and closed the auction stage while leaving contract signature, transfer, mobilisation, dredging, and service performance for later evidence.

Read controlling source

Europe / United Kingdom / Port infrastructure / Current phase: prequalification

Ardersier Port Phase 2 dredging procurement

The separate quay-civils package defined the dredging interface

The GBP 23 million civils notice covers the 300-metre new quay and 758-metre existing frontage and expressly leaves dredging to others. The two packages need coordinated programmes but retain separate scope and value.

Read controlling source

Africa / Morocco / Marine utilities / Current phase: construction

Casablanca-Settat desalination marine works and common systems

ONEE's year-end profile kept the 300 million m3/year plant under construction

The owner describes Casablanca as in progress at the end of 2025 and retains the 300 million m3/year, clean-energy programme frame. This confirms owner-side construction status but provides no marine-package quantity, completion measure, acceptance certificate, or first-water evidence.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: design

Westport Kwinana container port and marine infrastructure

Marine science findings changed the proposed port layout

Westport attributed a roughly one-kilometre southward footprint shift, breakwater repositioning, and use of historic dredging zones to the research programme. The update establishes design evolution, not an approved final reference design or accepted environmental outcome.

Read controlling source

Global islands / Fiji / Marine utilities / Current phase: prequalification

Fiji Kinoya wastewater treatment and Laucala Bay outfall programme

Separate Greater Suva water-loss contract awarded to Miya

ADB records a US$25.03 million performance-based non-revenue-water contract to Miya S.A.R.L. This is a programme delivery milestone but is separate from CW02 and does not identify a Kinoya DBO contractor or any marine works award.

Read controlling source

Europe / Portugal / Marine utilities / Current phase: construction

Algarve seawater desalination intake and outfall system

Environmental conformity remained subject to controls

The owner records a favourable execution-design conformity decision conditioned on mitigation, monitoring and compensation. The decision closed a regulatory gate without proving that construction or offshore installation had begun.

Read controlling source

Europe / Netherlands / Port infrastructure / Current phase: construction

Port of Rotterdam Yangtzekanaal widening and quay programme

Harbourmaster notice confirmed south-bank sheet-pile and dredging activity

The notice placed work vessels, stone removal, sheet-pile removal and installation, and dredging in the live channel from 24 November 2025 to 6 March 2026. It is field-execution and navigation-control evidence, not proof of completed quay or accepted channel geometry.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: construction

Skandia Gateway fairway and quay deepening

EIB signed financing for the port's quay package

The signed approximately SEK 850 million financing supports a roughly 700-metre quay project with an estimated SEK 1.7 billion cost. It does not finance or award the complete national fairway, prove construction completion, or establish operating capacity.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: construction

Sabine-Neches Waterway Channel Improvement Project

Owner schedule documented completion of two first-cut reaches

SNND reported that Contract 2B completed about 12.2 million cubic yards in December 2024 and Contract 3 finished about 7 million cubic yards in September 2025. The publication date anchors this record because the underlying completion dates were stated only by month.

Read controlling source

Americas / Barbados / Coastal infrastructure / Current phase: construction

Bridgetown Fisheries Complex breakwater repair

Project team described an advanced but unfinished breakwater

Baird reported the arm and corner rebuilt with salvaged dolos and described the filter and armour layers. Capping, the full crest, jetty replacement, access-road removal and the navigation-light decision remained open despite a first-week-of-December target.

Read controlling source

Americas / Barbados / Coastal infrastructure / Current phase: construction

Bridgetown Fisheries Complex breakwater repair

Fisheries recorded armour stone securely placed at the head

The dated drone image documents armour placement at the breakwater head without providing an inspection, accepted as-built survey or handover certificate.

Read controlling source

Middle East / Syria / Port infrastructure / Current phase: early works

Port of Tartous modernisation and marine access works

DP World took over operations and placed Al Fath in service

Formal handover moved the concession into operation and added a 50-tonne-bollard-pull harbour tug. DP World was still surveying infrastructure and quay readiness and described channel, basin, and berth dredging as an immediate focus, not completed work.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Georgetown Harbor maintenance dredging

South Carolina issued Clean Water Act Section 401 certification

The certification closed a key water-quality approval step for the selected cutterhead-and-upland-placement action. Construction award and restored navigation remained outside the certification.

Read controlling source

Europe / Germany / Port infrastructure / Current phase: construction

Cuxhaven offshore-wind terminal at berths 5 to 7

The waterside pile line closed the 1,250-metre gap

Niedersachsen Ports reported approximately 427 tubular piles and 250 raking piles installed, with further raking-pile connection work continuing before sand filling.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

First offshore seawater-intake tower transferred and installed

The source confirms physical delivery of a named intake structure and advances the marine work front beyond fabrication, without proving connected-system commissioning or accepted hydraulic performance.

Read controlling source

Global islands / Tonga / Port infrastructure / Current phase: completed

Tonga Queen Salote International Wharf climate-resilient upgrade

All marine and civil works declared complete and operational

The Ports Authority chief executive's commissioning statement closes the construction phase for the named works. Post-handover berth availability, operating costs and long-term climate performance remain unreported.

Read controlling source

Americas / Argentina / Port infrastructure / Current phase: mobilisation

Argentina Vía Navegable Troncal dredging and signaling concession

The environmental-management hearing ran for 14 hours

ANPYN recorded 247 participants and received public and specialist input on the management and environmental-evaluation report. The informative hearing supported tender preparation; it was not proof that every future deepening activity had project-specific approval.

Read controlling source

Africa / Morocco / Deep-water ports and energy terminals / Current phase: commissioning

Nador West Med Deep-water Port

West-terminal operating agreement finalised

The agreement fixes a separate West terminal delivery and operating route scheduled from 2027, preventing that programme from being folded into the East terminal's 2026 launch evidence.

Read controlling source

Americas / Brazil / Dredging / Current phase: mobilisation

Paranaguá access channel dredging concession

CCGD won Brazil's first port-access-channel auction

Twenty live bids produced a 12.63% tariff discount and R$276 million grant fee, with R$1.22 billion of first-five-year investment. The auction created a long-term delivery obligation rather than a completed deepening result.

Read controlling source

Africa / Benin / Port infrastructure / Current phase: construction

Port of Cotonou Terminal 5 bulk terminal

PAC continued the owner-representative assignment

The definitive award notice names Inros Lackner for continuity of the owner-representative mission on Terminal 5. It supports continued project oversight but does not establish completion or accepted marine quantities.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: construction

Skandia Gateway fairway and quay deepening

Joint dredging procurement was cancelled after over-budget bids

The two public owners stopped the combined tender because bids exceeded the state-funded budget and announced a split into quay-adjacent and wider-fairway packages. The cancellation invalidated the former procurement route and schedule as an award baseline.

Read controlling source

Europe / Netherlands / Offshore wind foundations / Current phase: award

Zeevonk phase 1 foundation installation

The amended IJmuiden Ver Beta permit became irrevocable

The amended permit supports the two-phase delivery sequence now used by the owner: 1 GW in 2029, followed by a further 1 GW and system-integration capacity in 2032.

Read controlling source

Europe / United Kingdom / Dredging / Current phase: award

UK Navy Future Dredging Contract

The planned procurement notice formalised the future competition

The UK3 notice advanced the requirement from market engagement toward a stated defence dredging procurement. It did not appoint a supplier, define individual Plymouth or Portsmouth campaigns, disclose dredged quantities or sediment routes, or authorise field work.

Read controlling source

Europe / United Kingdom / Dredging / Current phase: award

UK Navy Future Dredging Contract

Preliminary market engagement tested supplier capacity

The UK2 notice opened early engagement around the Navy Future Dredging Contract requirement. Market engagement was evidence of requirement formation only; it was not a tender, award, contract, work package, mobilisation record, or delivered navigation outcome.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: construction

Port of Montreal Contrecœur Container Terminal

Owner confirmed site preparation had started

Fencing, access roads, work platforms, targeted tree cutting, and site facilities established the land-preparation baseline. The owner record does not describe this milestone as sheet-pile driving, dredging, or completed in-water works.

Read controlling source

Europe / Netherlands / Dredging / Current phase: delivery

Boskalis SEAWAY 31,000 m³ TSHD

SEAWAY was christened and launched at Royal IHC

The physical launch closed the hull-launch gate and exposed the named vessel, but Royal IHC explicitly placed final outfitting and extensive testing afterward and retained a future mid-2026 service-entry expectation.

Read controlling source

Global islands / Tonga / Port infrastructure / Current phase: award

Nafanua Port resilience improvement

The revised procurement plan marked the integrated package under implementation

MOI-WK2-13 replaced the earlier split approach in the public plan. The separate passenger-terminal and two-lot breakwater packages are marked cancelled, while the integrated package carries no published contractor or actual contract amount.

Read controlling source

Africa / Democratic Republic of the Congo / Deep-water ports and container terminals / Current phase: construction

Banana Deep-water Port Phase One

Site inspection confirmed active works and coastal-protection interfaces

The government visit confirmed construction activity, naval-base relocation, hydrological review at the Congo River mouth and anti-erosion works. The photographs also show dredged-material placement, but the record does not quantify dredging, formed area, achieved depth, quay completion or owner acceptance.

Read controlling source

Global islands / Fiji / Marine utilities / Current phase: prequalification

Fiji Kinoya wastewater treatment and Laucala Bay outfall programme

Final US$135 million loan agreement signed

The signed agreement fixes the controlling loan amount and a 30 June 2033 closing date. Together with the separate US$10 million grant it supersedes the older approval-news split, but financing signature is not a construction or operating milestone.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: approval

Port Douglas Boat Harbour 2026 maintenance dredging

Killaloe was cleared ahead of the next dredging campaign

TMR reported that clean sand from earlier Port Douglas dredging was removed from Killaloe for beach replenishment. That work restored receiving capacity but does not prove that 2026 material will follow the same beneficial-use route.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Geraldton Port Maximisation marine works

EPA Report 1792 recommended conditional approval

The report established the assessed marine footprint, benthic impacts, material-reuse route and environmental conditions that informed the later Ministerial Statement.

Read controlling source

Americas / Barbados / Coastal infrastructure / Current phase: construction

Bridgetown Fisheries Complex breakwater repair

World Bank documented underwater placement and rock traceability

The feature records imported Norwegian armour rock, diver-guided alignment and geo-referenced placement. It supports the construction method and quality-control chain without establishing completion.

Read controlling source

Europe / Belgium / Port infrastructure / Current phase: construction

Antwerp Kanaaldok B2 liquid CO2 export quay

Kanaaldok B2 quay construction entered its works window

The owner and contractor place the 362-metre quay package in execution from September 2025, with piling, concrete, demolition, and dredging sequenced through early 2027. Start of works is not berth handover or export readiness.

Read controlling source

Global islands / Fiji / Marine utilities / Current phase: prequalification

Fiji Kinoya wastewater treatment and Laucala Bay outfall programme

ADB approved the Healthy Oceans and Water Security programme

Approval established the sovereign programme and its intended water-security and Laucala Bay outcomes. It did not define CW02 award, detailed design, construction start, effluent compliance, or measured ecosystem recovery.

Read controlling source

Americas / Mexico / Marine utilities / Current phase: tender

Rosarito 2,200 l/s desalination procurement

Federal-state coordination agreement was published

The agreement fixed the current first module at 2,200 l/s and listed the plant, intake, brine discharge, conveyance, storage, connections and electrical works as project components.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Port Hedland Zone 5 Bypass Channel

Pilbara Ports issued the offshore geotechnical investigation notice

Ocean Driller II and support craft were scheduled for approximately three weeks of boreholes and seismic work from 13 September under VTS controls. Investigation reduced design uncertainty but did not constitute capital dredging.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Taweelah C IPP coastal utility interface

EWEC received three development proposals

The bid record moved the project from RFP to competitive evaluation and named the three bidding groups. It was not a preferred-bidder decision, award, PPA, EPC contract, or evidence of cooling-water and marine-package definition.

Read controlling source

Asia Pacific / India / Dredging / Current phase: completed

Kamarajar Port Capital Dredging Phase VI

Kamarajar's annual report recorded work in progress

The owner identified Van Oord as contractor, INR 4.407 billion excluding GST as the contract value and June 2026 as the expected completion point.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: award

Port of Luleå Malmporten fairway and deepwater port works

The owners launched an optimized two-stage retender

A redesigned fairway scope returned to market through prequalification and invited bids. The later owner release describes the previous procurement as cancelled in September 2025, while the authority's detailed status record says the common tender had been stopped in February; The two descriptions remain separate rather than being collapsed into one event.

Read controlling source

Global islands / Nauru / Port infrastructure / Current phase: construction

Nauru Aiwo Port climate-resilient redevelopment

Micronesian Ocean berthed at Aiwo

The call demonstrates that the new wharf is handling a Nauru-owned container vessel. It does not close the remaining dredging, yard, road or building scope.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

Coastal energization enabled desalination-plant testing

Techint reported the coastal electrical sector energized and testing and start-up of the desalination plant able to begin, while pumping-station mechanical and electrical work remained active. Energization opens commissioning; it is not accepted output or BOOT service commencement.

Read controlling source

Asia Pacific / India / Deep-water ports, dredging and reclamation / Current phase: tender

Vadhvan Greenfield Deep-draft Port

Owner opened the offshore dredging and reclamation HAM tender

The procurement covers offshore land creation by dredging, reclamation and protection-bund work. The current owner listing carries a 17 July 2026 close, but opening and deadline evidence do not establish technical or financial evaluation, AOC, contract execution, mobilisation or accepted output.

Read controlling source

Africa / Senegal / Deep-water ports and container terminals / Current phase: construction

Port of Ndayane Deep-water Port and Container Terminal

CCCC reported the container-terminal package in main construction

The contractor parent identified Ndayane as entering its main construction phase, advancing the terminal-civil record without publishing a package percentage, completed marine geometry, quay acceptance, or operating-readiness evidence.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Oswego Harbor 2026 breakwater repair phases

The 600-foot Outer West phase moved into construction

USACE recorded the start of the USD 9.1 million Great Lakes Dock and Materials package after completing the separate 2,700-foot West Arrowhead repair. The current programme should not merge those two work limits.

Read controlling source

Global islands / Tonga / Port infrastructure / Current phase: award

Nafanua Port resilience improvement

The Ministry issued the integrated works request for bids

The notice put the breakwater, small-boat berth and passenger-terminal work into one open international, two-envelope Small Works package, replacing the previous split procurement path.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Dunkirk Harbor west breakwater rehabilitation

USACE recorded active stone-handling operations

Buffalo District video shows marine plant and a long-reach material handler working on the Dunkirk breakwater. It confirms construction activity in August 2025 but does not establish production quantities, accepted length or the later second-phase start.

Read controlling source

Middle East / Jordan / Marine utilities / Current phase: financing

Aqaba-Amman National Water Carrier marine works

EIB recorded the latest signature in a EUR 427 million support package

The EIB project record lists five EIB and EU financing or grant signatures through 24 July 2025, totalling EUR 427 million. These commitments support the wider funding plan but do not on their own prove project financial close, NTP or marine construction.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: construction

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

Both TBMs were assembled for the separate intake and outfall drives

Water Corporation announced that two more-than-four-metre-diameter TBMs would begin an 18-month programme beneath the seabed for a 2.5 km intake and 4 km outfall. Assembly and launch readiness do not prove tunnel advance, breakthrough, lining acceptance or offshore connection.

Read controlling source

Middle East / Syria / Port infrastructure / Current phase: early works

Port of Tartous modernisation and marine access works

Thirty-year BOT concession was signed

The signed concession replaced the preliminary memorandum with a 30-year development-and-operation structure and an USD 800 million programme. It did not identify marine package awards, contractors, quantities, target depths, or completion dates.

Read controlling source

Africa / Senegal / Coastal infrastructure / Current phase: construction

Gorée Island east and west coastal protection works

Implementation mission named the delivery team and measured 15% execution

The World Bank mission identified NGE Contracting, NORDA STELO-IDEV, approximately 1.275 kilometres of rock-armour protection, Pier 8 supply constraints, and active environmental and archaeological controls. Physical progress was estimated at 15%.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: design

Westport Kwinana container port and marine infrastructure

Owner documented active marine geotechnical investigations

Two jack-up barges were collecting geotechnical cores and in-situ seabed data over a 12-month campaign, with cone-penetration testing planned for late July to early August. Investigation activity does not establish a complete ground model, design acceptance, dredging quantity, or construction mobilisation.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

AIIB completed Project Crane concept review

The concept-review date establishes the lender's formal appraisal sequence. Earlier MICT, MCT, or BIPI assets and activities cannot be labelled AIIB-financed merely because they later appear inside the corporate facility's result framework.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Cleveland Harbor 2026 maintenance dredging

The Port approved an SPMF capacity bridge through 2029

The Port board awarded a USD 4 million extension project to Mark Haynes Construction to keep the current repository usable until CHEERS is ready. The award establishes a capacity intervention, not completed construction or unlimited placement capacity.

Read controlling source

Americas / Barbados / Coastal infrastructure / Current phase: construction

Bridgetown Fisheries Complex breakwater repair

Fisheries showed reconstruction under way one year after Beryl

The official anniversary update identifies a new breakwater under construction and dates its progress imagery to 24 June 2025.

Read controlling source

Global islands / Solomon Islands / Marine utilities / Current phase: tender

Honiara wastewater mains and two deep-sea outfalls

The eastern landward sewer section reached 3.2 km

ADB's current implementation record reports 3.2 km constructed by 30 June 2025. That progress belongs to the landward network and does not establish marine outfall construction.

Read controlling source

Global islands / Nauru / Port infrastructure / Current phase: construction

Nauru Aiwo Port climate-resilient redevelopment

Monitoring report measures remaining dredging and yard work

The report released in July 2026 records dredging at 78%, the northern-yard interim apron at 97%, all buildings handed over and only the fire-pump system outstanding in the southern yard at the reporting cutoff.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: tender

New Haven Harbor improvement dredging

Industry Day exposed the delivery and placement constraints

USACE set out the channel geometry, seasonal windows, material classes, placement routes, rock and survey requirements while retaining quantity change risk after maintenance dredging.

Read controlling source

Asia Pacific / Indonesia / Port infrastructure / Current phase: construction

Patimban Port Phase 1-2 expansion

JICA monitoring kept both expansion packages in active marine construction

The April-June quarter records ongoing reclamation, dredging, quay and pavement work in Packages 5 and 6. It supplies measured work-item progress but no final marine acceptance or full terminal handover.

Read controlling source

Asia Pacific / Singapore / Marine utilities / Current phase: construction

Singapore DTSS2 Tuas WRP nearshore outfall

Plant testing began within a still-incomplete programme

PUB reported DTSS2 at 77% and Tuas WRP at 54%, with MEICA installation continuing and hydraulic testing under way at selected biosolids facilities. Local tests were not whole-system discharge acceptance.

Read controlling source

Europe / Spain / Port infrastructure / Current phase: construction

Valencia North Terminal quay and automated terminal works

Signed annual accounts confirmed a Q4 2024 physical start

The Port Authority's reformulated 2024 accounts confirm that the awarded works began executing in the final quarter of 2024 and describe the pace as adequate. Physical construction had started, while quay, dredging, reclamation, demolition, civil handover, terminal systems and operations remained incomplete.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

New Mangalore Port 60T battery-electric tug charter

Tender established the vessel and service baseline

The tender specified a new Indian-built 60-tonne GTTP Phase I battery-electric tug, a 24-month delivery requirement, port and vessel charging interfaces, monitoring integration and a 15-year operating term.

Read controlling source

Middle East / Iraq / Port infrastructure / Current phase: construction

Grand Faw phase-one marine and port-access system

Terminal-A filling reached 93% with ground improvement still active

The owner reported more than 11 million m3 of fill, PVD installation and surcharge work behind the five berths. The first area behind berths one and two had preliminary acceptance, showing that quay completion still depended on phased terminal formation and soil consolidation.

Read controlling source

Africa / Nigeria / Deep-water ports and container terminals / Current phase: award

Nigeria Snake Island Container Terminal concession and EPC

NPA reported the development agreement finalized

NPA placed the wider port development on an 85-hectare site and used a USD 1 billion development figure. No EPC value, construction programme or physical progress record was included.

Read controlling source

Africa / Tunisia / Port infrastructure / Current phase: award

Tunisia three-port access and dredged-material programme

OMMP published the second single-lot open dredging tender

The procurement portal recorded one budget-funded maritime-works lot and a 29 July 2025 bid deadline and opening. Its later Complet status closes the tender record, not the physical dredging works.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Baltimore Harbor 2026 maintenance dredging and Cox Creek routing

MPA set out the STAR capacity-recovery plan

Port Commission minutes record a five-year plan to reclaim 1.2 million cubic yards of Cox Creek capacity. The planned recovery remains separate from dredged material received in 2026 and from verified reuse output.

Read controlling source

Global islands / Fiji / Marine utilities / Current phase: prequalification

Fiji Kinoya wastewater treatment and Laucala Bay outfall programme

Environmental assessment defines plant-side upgrade and reuse of the existing outfall

The assessment establishes 36 MLD Stage 1 treatment, disinfection, and discharge through the existing approximately 2.4 km Laucala Bay outfall. It also cautions that wider bay pollution has multiple sources, limiting any claim that plant completion alone proves ecosystem recovery.

Read controlling source

Asia Pacific / Indonesia / Port infrastructure / Current phase: construction

Patimban Port Phase 1-2 expansion

Package 5 completed production of its contracted PC deck slabs

The monitoring report records 1,482 Package 5 PC deck slabs, or 100% of the bill-of-quantities item. Quay assembly, rubble, reclamation, dredging, pavement and terminal handover remained separate work fronts.

Read controlling source

Europe / Ireland / Port infrastructure / Current phase: construction

Dublin Port MP2 Berths 52 and 53 marine construction

The owner defined the live marine package

Dublin Port reported the 290-metre open jetty, nine dolphins, Berth 52 East extension, linkspan and landside systems, while fixing seasonal limits for river piling and dredging.

Read controlling source

Africa / São Tomé and Príncipe / Marine infrastructure / Current phase: financing

São Tomé and Príncipe BEFIRM fisheries infrastructure rehabilitation

Three site safeguard packages exposed the physical marine interfaces

AfDB disclosures cover Chimalô, Neves, and Porto Alegre. They establish concept-level quay, dredging, operating-depth, logistics, cold-chain, utility, resettlement, and environmental controls while remaining pre-contract design and safeguard records.

Read controlling source

Middle East / Jordan / Port infrastructure / Current phase: tender

Aqaba Cement Terminal and Mut'ah berth rehabilitation concession

Initial BOT expression-of-interest deadline

ADC opened market sounding for a silica terminal using the existing Cement Terminal facilities and Mut'ah floating berth. The EOI initiated procurement but did not award a concession, publish asset condition, or establish an executable rehabilitation package.

Read controlling source

Africa / West Africa / Coastal infrastructure / Current phase: construction

WACA ResIP 1 coastal protection works programme

The World Bank revised the Côte d'Ivoire and Senegal timelines

The restructuring paper recorded delays and moved both country programmes to June 2026. It did not create one regional construction schedule: Grand-Lahou, Gorée, and the other work fronts remain separate packages.

Read controlling source

Middle East / Syria / Port infrastructure / Current phase: early works

Port of Tartous modernisation and marine access works

Authority and DP World signed the initial memorandum

The memorandum established an USD 800 million investment intent for development, management, and operation of a multi-purpose terminal. It was an early commercial milestone rather than proof of concession execution, operator handover, or physical works.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Georgetown Harbor maintenance dredging

USACE opened draft SEA and FONSI public review

The review established the environmental decision route for renewed operations and maintenance after the long dredging gap. It preceded the final February 2026 assessment, water-quality certification, and contract award.

Read controlling source

Europe / Netherlands / Port infrastructure / Current phase: construction

Port of Rotterdam Yangtzekanaal widening and quay programme

Ground response forced a vibration-free quay-wall method

Unexpected vibration and settlement risk beside the Rhenus warehouse stopped conventional piling. The team adopted a 30-metre trench with cement-bentonite so foundation pipes and sheet piles could sink into place; the wall was installed by publication, while final section completion remained a later gate.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

St. Joseph Harbor 2026 dredging and sediment-placement research

The 2025 campaign set the baseline for two-season monitoring

USACE paired a smaller, roughly 22,000-cubic-yard outer-harbor campaign with ERDC monitoring planned across 2025 and 2026. That earlier along-shore placement is the comparison case for the new perpendicular geometry; it is not evidence of the 2026 contractor's output.

Read controlling source

Africa / Morocco / Marine utilities / Current phase: construction

Casablanca-Settat desalination marine works and common systems

The Al Baidaa consortium signed project financing

ACCIONA identified the 50/45/5 consortium split, 80/20 debt-equity structure, MAD 6.5 billion investment, renewable-power supply and 27-year construction and O&M role. Financing removes a commercial gate; it does not prove marine mobilisation, physical progress or accepted output.

Read controlling source

Africa / Senegal / Coastal infrastructure / Current phase: construction

Gorée Island east and west coastal protection works

Execution studies and the work-start milestone were recorded as achieved

The July mission memo records the execution-study and work-start action as achieved on 8 May. The same memo separately states that Lot 2 began in February for 15 months and physical works began in March, so the date is a formal milestone rather than a single universal mobilization date.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Cleveland Harbor 2026 maintenance dredging

A separate prior-year DMYLES campaign was scheduled to start

USACE announced a USD 9 million 2025 contract for approximately 180,000 cubic yards from the lower Cuyahoga and CDF placement. USACE later reported 255,651 cubic yards removed in 2025; neither the earlier scope nor that result proves 2026 execution.

Read controlling source

Europe / Belgium / Port infrastructure / Current phase: construction

Antwerp Kanaaldok B2 liquid CO2 export quay

The port defined four separate export-chain packages

The owner separated capture, the open-access pipeline backbone, phased liquefaction terminal, and a quay for two simultaneous seagoing vessels. That interface map clarifies dependencies; award, completion, commissioning and carrier availability remain open.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: completed

Isle of Palms Breach Inlet beneficial-use dredging

USACE confirmed the March 2024 maintenance-contract award

The AIWW fact sheet recorded the award date and said beneficial-use placement was still active on Isle of Palms and Sullivan's Island in April 2025.

Read controlling source

Africa / Democratic Republic of the Congo / Deep-water ports and container terminals / Current phase: construction

Banana Deep-water Port Phase One

DP World gave government a conditional 2026 first-vessel objective

The high-level meeting recorded an attributed delivery and first-call objective if execution remained in order. It is schedule evidence, not proof of marine completion, navigation release, terminal commissioning or a booked commercial service.

Read controlling source

Global islands / Norfolk Island / Dredging and waterways / Current phase: tender

Norfolk Island Kingston Pier channel and repair works

Environmental approval granted with conditions

The controlled action received approval under the EPBC Act, establishing environmental conditions and water-quality monitoring obligations without advancing the procurement or works status.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

Ramayapatnam Port capital deepening works

Government reported 52.95% whole-port progress

A Lok Sabha answer recorded the INR 4,929.39 crore port under implementation at 52.95% and described 34.04 MMTPA Phase I capacity. The percentage predates the DEME award by more than a year and cannot be used as dredging-package progress.

Read controlling source

Africa / Morocco / Deep-water ports and energy terminals / Current phase: commissioning

Nador West Med Deep-water Port

Towage and assistance licence awarded

The award establishes the future towage counterparty and service contract, while tug delivery, licensed mobilisation, crew readiness, harbour procedures, and live vessel assistance remain to be evidenced.

Read controlling source

Asia Pacific / Japan / Offshore energy / Current phase: construction

Oga-Katagami-Akita offshore wind marine installation programme

Sawakigumi base-port development contract signed

The contract names the base-port works counterparty and moves the port interface into contracted preparation. Completed construction, accepted facilities and installation-base availability remain unreported.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Oswego Harbor 2026 breakwater repair phases

USACE awarded the first Outer West package

The USD 9.1 million contract set a 600-foot rubble-mound overlay scope with completion scheduled for winter 2026. That package has a different contractor and acceptance path from the 2026 award.

Read controlling source

Africa / Democratic Republic of the Congo / Deep-water ports and container terminals / Current phase: construction

Banana Deep-water Port Phase One

Mota-Engil disclosed the phase-one construction contract

The regulated notice recorded an approximately EUR 230 million contract and an estimated 24-month term for phase one. It does not define every marine subcontract, total development cost, accepted geometry, completion date or opening date.

Read controlling source

Europe / United Kingdom / Port infrastructure / Current phase: construction

Maraen Port of Nigg Eastern Inner Dock Quay

HIE approved up to £10 million of public support

Highlands and Islands Enterprise linked its support to the heavy-duty quay and Sumitomo cable-factory export route. The funding commitment established public backing and the intended industrial use; it was not a construction award, evidence of grant drawdown, or proof of cable-export operations.

Read controlling source

Americas / Barbados / Coastal infrastructure / Current phase: construction

Bridgetown Fisheries Complex breakwater repair

The fisheries-marina and breakwater contract was signed

The World Bank implementation report records contract signing and work start. It does not give the contract price, detailed acceptance tests or final completion date.

Read controlling source

Middle East / Saudi Arabia / Marine utilities / Current phase: construction

Ras Mohaisen Independent Water Project and Marine Intake/Outfall

L&T announced the Ras Mohaisen EPC order

The award covers design, procurement, construction, testing and commissioning of the SWRO plant and associated intake, outfall, pumping, storage, electrical and solar systems. Award evidence defines responsibility and scope but does not establish marine mobilisation, as-built pipeline length, hydraulic acceptance or operating output.

Read controlling source

Europe / United Kingdom / Port infrastructure / Current phase: construction

Maraen Port of Nigg Eastern Inner Dock Quay

The marine-licence proposal exposed the quay-wall concept

The owner described converting the existing eastern inner-dock rock revetment into a vertical retaining-wall quay. The proposal defined the marine-civil concept, while approval, final investment, contractor appointment, field execution, and acceptance remained separate later gates.

Read controlling source

Global islands / Marshall Islands / Coastal infrastructure / Current phase: construction

Ebeye Coastal Protection Works

The first armourstone shipment reached the Marshall Islands

The World Bank report moved the job from site preparation into marine material delivery. The rock still had to be transferred to barges, landed on Ebeye, placed to the design profile, surveyed, and accepted.

Read controlling source

Africa / Burundi / Marine infrastructure / Current phase: construction

Bujumbura Port Lake Tanganyika corridor rehabilitation

Joint inspection recorded the 545-metre protective dike at 45%

AfDB, the EU, and Burundi set the latest reviewed quantitative baseline and an end-2026 target for the infrastructure works. The release also identified follow-on quay and marine-dock works and 11.7 kilometres of access roads.

Read controlling source

Middle East / UAE / Deep-water ports and energy terminals / Current phase: construction

Ruwais LNG marine access and export terminal

The Petroleum Ports Authority issued the RLNG dredging operations notice

The notice moved the marine record beyond award by identifying phased 24-hour execution, the access-channel work area, two offshore disposal sites and environmental controls.

Read controlling source

Middle East / Oman / Marine utilities / Current phase: construction

Ghubrah III IWP desalination marine system

Savener completed the intake-building IFC design

The detailed design defines three screened intake channels and their control equipment. IFC completion authorises a construction basis; it is not evidence that the building, screens, pumps or marine tie-ins were installed.

Read controlling source

Africa / Senegal / Deep-water ports and container terminals / Current phase: construction

Port of Ndayane Deep-water Port and Container Terminal

Jan De Nul confirmed access-channel dredging had started

The contractor defined five kilometres of channel, about 10 million cubic metres, an 89-hectare reclaimed platform, hard-rock excavation by Willem Van Rubroeck, and a two-and-a-half-year works period. That package evidence does not establish whole-port completion.

Read controlling source

Global islands / Marshall Islands / Coastal infrastructure / Current phase: construction

Ebeye Coastal Protection Works

Hall and Haskoning moved into site mobilisation

The team began the unloading facility, access works, and other preparations needed for the 1.81-kilometre seawall. It was the start of delivery, with armour placement and acceptance still ahead.

Read controlling source

Africa / Benin / Port infrastructure / Current phase: construction

Port of Cotonou Terminal 5 bulk terminal

AfDB and PAC signed the modernisation financing

The EUR 80 million facility supports Terminal 5 and the separate Zongo access project. The later finance signature does not reset the construction start, define the CHEC contract value or prove marine completion.

Read controlling source

Middle East / Saudi Arabia / Marine utilities / Current phase: construction

Ras Mohaisen Independent Water Project and Marine Intake/Outfall

Sharakat signed the 25-year project agreements

The agreements moved the IWP from procurement into contracted development and established the sponsor consortium, offtake structure, designed capacity and storage scope. Signing did not establish EPC completion, offshore works, water production or transfer language beyond the reviewed agreement summary.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: design

Westport Kwinana container port and marine infrastructure

EPA approved Westport's Environmental Scoping Document

Approval fixed the required scope for the later Environmental Review Document and Public Environmental Review. It is not approval for the port to proceed, completion of the Environmental Review Document, or closure of State and Commonwealth assessment.

Read controlling source

Asia Pacific / Indonesia / Port infrastructure / Current phase: construction

Patimban Port Phase 1-2 expansion

Toyota Tsusho joined the container-terminal operating company

The investment in Patimban Global Gateway Terminal established another operating counterparty while the container terminal itself remained under construction. Operator formation is not civil completion or service release.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: award

Port of Luleå Malmporten fairway and deepwater port works

The common dredging tender exceeded budget and was stopped

The Swedish Maritime Administration says the submitted bids exceeded budget and that the deepwater-quay procurement was also stopped. The subsequent design optimization was intended to reduce cost without changing capacity, safety or function.

Read controlling source

Asia Pacific / Vietnam / Deep-water ports and container terminals / Current phase: approval

Can Gio International Transshipment Port

The Prime Minister approved the investment policy

Decision 148/QD-TTg moved Can Gio into the formal investment process and set the basis for investor selection. It did not award the later design or construction packages.

Read controlling source

Middle East / Jordan / Marine utilities / Current phase: financing

Aqaba-Amman National Water Carrier marine works

The Meridiam-SUEZ consortium signed the 30-year concession

The concession created the project company and assigned long-term financing, construction and operating responsibility. SUEZ explicitly made construction conditional on financial close, leaving mobilisation and physical progress ahead.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

Owner raised the Phase 2 reclamation record to about 75%

MPA reported Phase 2 reclamation about 75% complete. Its accompanying statement that 11 Tuas Port berths were operational describes the wider port and cannot be reassigned to Phase 2; civil acceptance, handover, terminal systems, and Phase 2 commissioning remained separate.

Read controlling source

Asia Pacific / Indonesia / Port infrastructure / Current phase: construction

Patimban Port Phase 1-2 expansion

JICA signed the third Patimban development loan

The JPY 83.408 billion agreement finances remaining Phase 1-2 terminal and dredging scope and sets 2028 as the planned point when facilities enter operation. The loan did not certify current construction or award later packages.

Read controlling source

Asia Pacific / India / Deep-water ports, dredging and reclamation / Current phase: tender

Vadhvan Greenfield Deep-draft Port

VPPL approved the nearshore reclamation EPC award

The INR 16.48 billion award to ITD Cementation, now Cemindia Projects, covers about 200 hectares of nearshore reclamation and shore protection. It does not award the proposed offshore breakwater or HAM package and does not prove mobilisation, formed area, settlement performance or owner acceptance.

Read controlling source

Middle East / Qatar / Port infrastructure / Current phase: construction

Hamad Port food security terminal and warehouses

A ministerial visit reviewed final technology and operating-system work

The Ministry of Transport described final operations to equip the terminal with storage, packaging, transport and handling technology. This shows system integration remained active after the first equipment vessel and does not establish final acceptance or commercial operation.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

MCT secured a concession extension and announced a 300-metre berth expansion

The 25-year extension keeps MCT under MICTSI management to 2058 and accompanies a stated investment of more than USD 100 million, including a 300-metre berth extension and new equipment. The announcement records sponsor intent; construction start remains unconfirmed.

Read controlling source

Africa / Senegal / Deep-water ports and container terminals / Current phase: construction

Port of Ndayane Deep-water Port and Container Terminal

Arrival of Willem Van Rubroeck started maritime construction

DP World marked physical commencement of the marine package with the cutter suction dredger's arrival. The milestone begins dredging and reclamation delivery; it does not prove accepted channel depth, completed reclamation, quay handover, or terminal operation.

Read controlling source

Asia Pacific / India / Dredging / Current phase: completed

Kamarajar Port Capital Dredging Phase VI

Government marked the start of the capital-dredging work

The foundation-event release described an INR 5.45 billion capital-dredging investment. That public investment description is not a final account and should not replace the separate tender or award values.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: construction

Skandia Gateway fairway and quay deepening

Owners opened the former joint dredging procurement

The tender described about 9 million cubic metres, 12 beacons, an August 2026 planned start, and February 2028 target completion. Those figures document the former tender frame; the later cancellation and redesign mean they are not the current contracted quantity or schedule.

Read controlling source

Middle East / Iraq / Port infrastructure / Current phase: construction

Grand Faw phase-one marine and port-access system

Iraq received the five completed phase-one berths

The Prime Minister's office recorded handover of the five Daewoo-built berths and the first commercial vessel call. At the same event, the berths were described as the backbone of phase one rather than completion of the entire port system.

Read controlling source

Asia Pacific / India / Dredging / Current phase: completed

Kamarajar Port Capital Dredging Phase VI

Van Oord received the Phase VI award

Kamarajar's annual report records this as the award date for the capital-dredging contract and identifies Van Oord as the delivery contractor.

Read controlling source

Europe / Portugal / Marine utilities / Current phase: construction

Algarve seawater desalination intake and outfall system

The mixed design-build-operate contract was signed

Águas do Algarve fixed the delivery consortium, €107.923 million total and marine system baseline. The contract includes three years of operation after provisional acceptance rather than immediate operating responsibility.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

DENR approved 9,900 square metres of BIPI backfilling

The BIPI ESIA records approval for an auxiliary backfilling component supporting port expansion and coastal protection. Placed volume, completed stabilization, quay acceptance and Phase 2 approval remain outside that backfilling authorization.

Read controlling source

Global islands / Kiribati / Marine utilities / Current phase: completed

South Tarawa sanitation and three-ocean-outfall rehabilitation

Independent validation rated the completed project less than successful

The validation preserves the record of completed infrastructure but shows that physical delivery, service outcomes, water quality and institutional sustainability require separate evidence.

Read controlling source

Americas / Mexico / Marine utilities / Current phase: tender

Rosarito 2,200 l/s desalination procurement

SEMARNAT recorded the environmental filing

The filing described a 4,400 l/s full-site envelope using existing CFE cooling-water intake boxes and the power station's discharge canal for brine return.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

Coastal plant and marine construction work documented

The project update identifies the auxiliary pier, coastal sump, underwater blasting, submarine-pipe trench, intake and brine-return work, establishing a physical marine package rather than a generic desalination interface.

Read controlling source

Africa / Burundi / Marine infrastructure / Current phase: construction

Bujumbura Port Lake Tanganyika corridor rehabilitation

Burundi handed over the separate JICA port-improvement package

The completed package covered container-terminal, ship-repair, drainage-diversion, and basin improvements. Its handover must remain separate from the active AfDB/EU Phase I dike, dredging, quay, dock, road, and equipment scope.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: award

Port of Luleå Malmporten fairway and deepwater port works

The preparatory dredging package finished on plan

The authority records completion of the 2024 preparatory works in October. That package was physical progress, but it did not complete the remaining fairway, harbour-basin, quay or deepwater-port works.

Read controlling source

Europe / Spain / Port infrastructure / Current phase: construction

Valencia North Terminal quay and automated terminal works

TIL received a separate 50-year terminal concession

The concession assigns TIL construction and operation of the future terminal and records EUR 1.098237 billion of proposed private investment outside Port Authority works. The private-investment figure is separate from the EUR 489.18 million marine-civil contract and provides no evidence of installed automation or operating readiness.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: construction

Sabine-Neches Waterway Channel Improvement Project

USACE awarded offshore Contract 6 to Great Lakes Dredge & Dock

The USD 219.108 million firm-fixed-price award established the federal offshore delivery contract after two bids, with a government estimated completion date of 24 March 2027. Later inland Contracts 7, 8 and 9 were neither awarded nor completed by this action.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

Codelco opened independent commissioning-counterpart procurement

The owner sought technical oversight for developer-led commissioning and start-up, separating BOOT delivery responsibility from Codelco's assurance role and later distribution-system operation. No appointment or commissioning acceptance followed from the procurement record alone.

Read controlling source

Europe / Netherlands / Port infrastructure / Current phase: construction

Port of Rotterdam Yangtzekanaal widening and quay programme

Phase B construction-team stage was awarded

The first stage of the two-phase contract moved the inland-shipping quay into contractor-supported design optimisation through the end of 2025. It did not by itself establish the implementation award, price, construction start or accepted berth system.

Read controlling source

Europe / Ireland / Port infrastructure / Current phase: construction

Dublin Port MP2 Berths 52 and 53 marine construction

First marine piles entered the Berth 53 workfront

Dublin Port recorded physical piling and more than 70 Wills Bros staff on the works. This moves the package beyond award without establishing completed foundations or a usable berth.

Read controlling source

Asia Pacific / India / Deep-water ports, dredging and reclamation / Current phase: tender

Vadhvan Greenfield Deep-draft Port

Prime Minister laid the Vadhvan Port foundation stone

The ceremony records political launch of the approved programme. It carries no evidence of contractor mobilisation, dredging, reclamation, breakwater construction, terminal works, accepted capacity or port opening.

Read controlling source

Middle East / UAE / Deep-water ports and energy terminals / Current phase: construction

Ruwais LNG marine access and export terminal

NMDC Group received the marine dredging contract

The award defined an approximately 15 million cubic metre, 5-kilometre channel package worth more than USD 200 million, including navigation aids.

Read controlling source

Americas / Panama / Dredging / Current phase: planning

Panama Canal new TSHD acquisition planning

ACP restated navigation-channel and floating-equipment maintenance as a core operating system

The anniversary record places navigation-channel, floating-equipment, lock, and dam maintenance inside a preventive-maintenance programme backed by more than B/.2 billion over the preceding five years. It establishes operating context, not a TSHD budget or procurement approval.

Read controlling source

Africa / Democratic Republic of the Congo / Deep-water ports and container terminals / Current phase: construction

Banana Deep-water Port Phase One

BII committed minority investment alongside DP World

The up-to-USD 35 million commitment advanced the investment structure and published a 17.5-metre design-depth statement. Marine works were not awarded, DP World's 18-metre statement remained unreconciled, and no construction, acceptance or operating performance was established.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: construction

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

Alliance reporting places the project into its construction phase

The alliance sustainability report dates construction from August 2024 and separates it from detailed design, tunnelling, marine construction, commissioning and operation. This is a programme phase boundary, not evidence that offshore works or tunnel excavation had started in August.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

MICT commissioned three cranes while Berth 8 Phase 2 advanced

Three new Panamax quay cranes became operational and ICTSI described the 300-metre Berth 8 wharf and yard expansion. These commissioned cranes predate AIIB approval and are operating-history context, not evidence of the future electric crane procurement under Project Crane.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

Ramayapatnam Port capital deepening works

North-breakwater, navigation-aid and VTMS funding remained proposals

Parliament listed INR 409.05 crore for the north breakwater, INR 12.59 crore for fire-fighting and navigational aids, and INR 34.35 crore for VTMS among Andhra Pradesh proposals. The ministry requested restructuring and alternative funding exploration; the list is not award or completion evidence.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: award

Taweelah C IPP coastal utility interface

EWEC issued the Taweelah C request for proposals

The RFP opened procurement for development, financing, construction, operation, maintenance and ownership of the carbon-capture-ready CCGT plant. The public notice located the project inside the coastal power and desalination complex but did not publish a project-specific cooling-water or marine works package.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: construction

Port Mansfield Channel 2026 maintenance dredging

GLO executed the Phase II design work order

The work order established survey, sediment testing, beach-template design and USACE/NPS coordination tasks for beneficial-use placement planning and later construction-package coordination.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: award

Port of Luleå Malmporten fairway and deepwater port works

Preparatory dredging entered field execution

Optimus and Kahamari 2 started in the harbour area, followed by Magnor in the Sandgrönn fairway and planned support from Simson. The fleet disclosure is evidence of active preparatory production, not completion of the later main contract.

Read controlling source

Europe / Spain / Port infrastructure / Current phase: construction

Valencia North Terminal quay and automated terminal works

Port Authority awarded the main works contract

The Board selected the ACCIONA-Jan De Nul-Grupo Bertolin joint venture. The Port Authority's annual accounts later state EUR 489.18 million excluding VAT; the award fixes contractor and value, while mobilisation, production, accepted depth and handover remain open.

Read controlling source

Asia Pacific / Bangladesh / Port infrastructure / Current phase: design

Bangladesh Bay Terminal marine infrastructure

World Bank approved the Bay Terminal financing

Approval established the US$650 million project envelope and common marine-infrastructure objective, including the breakwater and channel works. It was not a construction award.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Dunkirk Harbor west breakwater rehabilitation

USACE awarded the original repair contract

The USD 7.56 million Great Lakes Dock & Materials award covered approximately 1,450 feet of lake-side stone overlay and an east-head wrap over two construction seasons. Its limits and value are not directly reconciled to the 2026 phase figures.

Read controlling source

Americas / United States / Dredging and waterways / Current phase: construction

Sabine-Neches Waterway Channel Improvement Project

USACE opened the Contract 6 contractor briefing

The pre-bid conference notice moved the offshore eight-foot deepening and ocean-disposal package into an active federal procurement process. It was a solicitation milestone, not a contract award or construction start.

Read controlling source

Asia Pacific / India / Deep-water ports, dredging and reclamation / Current phase: tender

Vadhvan Greenfield Deep-draft Port

Union Cabinet approved the Vadhvan Port programme

The approval established the INR 762.2 billion programme, SPV structure and design frame including overall reclamation, breakwater, terminals and planned capacity. Programme approval is not a package award, construction start, as-built result or operating record.

Read controlling source

Global islands / Tuvalu / Port infrastructure / Current phase: completed

Tuvalu Nui and Niutao climate-resilient boat harbours

Nui climate-resilient boat harbour opened

The ADB handover record establishes the first named asset entering community use; it does not establish later channel availability, navigation-aid uptime, maintenance performance, or completion of the Niutao package.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: award

Port of Luleå Malmporten fairway and deepwater port works

The first preparatory dredging contract was signed

The approximately SEK 655 million base package, with a further option, covered roughly 1.5 million m³ in the harbour and part of Sandgrönnleden before winter. Its quantity and value must remain separate from the later remaining-works contract.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

Project reached 43% with offshore pipe welding and marine temporary works active

The contractor reported the auxiliary pier and coastal sump under construction and offshore pipeline sections being welded at Mejillones for launch toward Caleta Viuda. Percentage progress and fabrication do not prove installed or accepted intake and return systems.

Read controlling source

Africa / Morocco / Marine utilities / Current phase: construction

Casablanca-Settat desalination marine works and common systems

ONEE launched physical implementation at Sidi Rahal

The owner marked the start of project realization and set the two-phase capacity and programme. Construction launch moves the project into execution while leaving marine method, tunnel progress, permanent intake and discharge installation, integrated testing and operation as later evidence gates.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Cleveland Harbor 2026 maintenance dredging

The Port documented a split sediment route

The Port reported approximately 50,000 cubic yards hydraulically placed into the SPMF for processing and beneficial use and approximately 150,000 cubic yards routed to a silt basin. A separate 20,000-cubic-yard Cleveland-Cliffs dock campaign is excluded from the federal-channel total.

Read controlling source

Africa / Ghana / Port infrastructure / Current phase: financing

Takoradi Project Shiprite floating dock and repair yard

A USD 94 million senior facility agreement was signed

Afreximbank said the agreement secured the full commitment of the capital providers. The later PIDG funding-gap statement shows that this 2024 commitment milestone did not by itself establish financial close or physical construction.

Read controlling source

Europe / Italy / Ports and coastal protection / Current phase: construction

Genoa New Breakwater

First caisson positioned at 25 metres depth

The owner record moves the project from caisson fabrication into offshore placement and documents the first completed tow, sinking, and positioning cycle, without proving repeat production, connected superstructure, or usable port access.

Read controlling source

Americas / United States / Port infrastructure / Current phase: construction

Rocky River Harbor 2026 maintenance dredging

The federal work plan funded sediment and environmental preparation

USACE listed Rocky River for environmental coordination and sediment sampling and analysis. That preparation supports later dredging decisions but did not itself establish the 2026 contract, selected routes or completed field work.

Read controlling source

Global islands / Marshall Islands / Coastal infrastructure / Current phase: construction

Ebeye Coastal Protection Works

The Ebeye seawall construction contract was signed

The World Bank report records the contract date under PREP II. The public record still does not give the executed works value, final bill of quantities, or the contract's risk split.

Read controlling source

Europe / United Kingdom / Port infrastructure / Current phase: prequalification

Ardersier Port Phase 2 dredging procurement

Phase 1 port redevelopment entered construction

Bank reporting confirmed Haventus ownership, a GBP 100 million joint credit facility and construction of the earlier 650-metre quay. That context does not establish progress on the later Phase 2 dredging competition.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: construction

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

Water Corporation selected the ACCIONA-Jacobs alliance for delivery and operation

Jacobs identified design, build, operation and maintenance scope with Water Corporation and ACCIONA, including separate 2.5 km intake and 4.1 km outfall tunnels. The appointment establishes delivery responsibility but not construction mobilisation or accepted marine output.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: commissioning

Hassyan IWP seawater intake and outfall programme

Hassyan IWP reached financial close

The owner announcement set the financed 30-year IWP delivery structure and committed development route. It contained no marine construction progress, commissioning result or accepted desalination capacity.

Read controlling source

Europe / Denmark / Germany / Immersed tunnels and marine crossings / Current phase: construction

Fehmarnbelt Fixed Link Immersed Tunnel

Eighteen-kilometre tunnel trench excavation completed

The owner record closes the main dredging phase at about 15 million cubic metres and identifies FBC's Boskalis-Van Oord delivery role, while bedding, immersion, backfill, protection, portals, systems, and opening remain separate packages and gates.

Read controlling source

Europe / Portugal / Marine utilities / Current phase: construction

Algarve seawater desalination intake and outfall system

APA issued a conditional environmental decision

The study-stage decision required a later execution-design conformity review and additional marine safeguards. It did not authorize the project to be reported as under construction at that time.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: completed

Taweelah RO desalination intake and outfall system

ACWA places commercial operations in Q1 2024

The current project profile classifies the full 200 MIGD plant as commercially operating. That closes the project-level delivery phase but does not publish the final intake and outfall alignment or marine acceptance results.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

Owner reported 70% reclamation and a 2027 completion expectation

MPA advanced the aggregate Phase 2 reclamation measure from the prior 60% record to about 70% and stated that reclamation was expected to finish in 2027. The forecast did not establish final caisson installation, accepted marine works, or terminal readiness.

Read controlling source

Middle East / Oman / Marine utilities / Current phase: construction

Ghubrah III IWP desalination marine system

Nama PWP signed the Ghubrah III project agreement

The agreement fixed Capital Desalination Company as the project vehicle and the 300,000 m3/day capacity. Contract signature preceded construction and does not establish notice to proceed, marine mobilisation or completion.

Read controlling source

Asia Pacific / India / Dredging / Current phase: completed

Kamarajar Port Capital Dredging Phase VI

Global tender was published with a 540-day period

The Government eProcurement record carried an INR 3.8 billion tender value, a 540-day period and an initial 17 April 2024 bid-opening date. These were tender-stage terms, not the later award or actual completion record.

Read controlling source

Global islands / Kiribati / Marine utilities / Current phase: completed

South Tarawa sanitation and three-ocean-outfall rehabilitation

ADB completion report closed the delivery history

The report records the contractor, redesign and retender history, package completion, commissioning, physical completion and mixed outcome evidence. It is the controlling retrospective delivery source.

Read controlling source

Asia Pacific / India / Dredging / Current phase: tender

Mumbai Port 2026-29 maintenance dredging programme

The preceding E.47/2023 package went to Van Oord

The October 2024 register records a INR 216.40 crore item-rate contract with Van Oord India, scheduled from 19 January 2024 to 30 April 2026 and then described as work in progress. It is historical incumbent context, not evidence of an E.47/2026 bid or award.

Read controlling source

Africa / Burundi / Marine infrastructure / Current phase: construction

Bujumbura Port Lake Tanganyika corridor rehabilitation

Government review exposed design and marine-mobilisation delays

Le Renouveau identified Khoury Contracting Company and reported delay associated with plan validation and imported equipment. The record established delivery risk rather than an accepted completion percentage.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Cleveland Harbor 2026 maintenance dredging

USACE published the DMMP and EIS review plan

The review plan defines the technical and peer-review path for long-term dredged-material management. It is planning evidence and does not establish a final DMMP, approved CHEERS capacity, or a selected annual placement route.

Read controlling source

Asia Pacific / India / Dredging / Current phase: tender

Mumbai Port 2026-29 maintenance dredging programme

Mumbai Port approved its dredging and dumping permission SOP

The SOP sets one-month permission, vessel-certificate, VTS, AIS, logbook, 15-day reporting, designated-ground, and unauthorized-dumping controls. It is a general compliance baseline and does not prove permission for the new contract.

Read controlling source

Africa / Democratic Republic of the Congo / Dredging / Current phase: delivery

CVM Congo River Easydredge 2700XL fleet renewal

CVM reported a 30-day FATSHI campaign and 26-foot offered draft

CVM states that the separate existing TSHD opened a new pass and stabilised the offered draft at 26 feet for Banana, Boma and Matadi connectivity. This is owner-reported campaign history, not a current survey, independent acceptance or performance evidence for the new 2700XL.

Read controlling source

Europe / Spain / Port infrastructure / Current phase: construction

Valencia North Terminal quay and automated terminal works

Board initiated the main-works procurement

The Port Authority approved an open procedure and EUR 545.78 million excluding VAT of expenditure. This procurement ceiling is distinct from the later EUR 489.18 million award and from TIL's private concession investment.

Read controlling source

Africa / Egypt / Deep-water ports and container terminals / Current phase: commissioning

Damietta Alliance Container Terminal (Tahya Misr 1)

The international lender group signed a USD 455 million package

The package financed the concession company's terminal superstructure. It did not finance the port authority's separate quay-wall, excavation and dredging scope.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Buffalo Harbor 2026 dredging and Slip 3 wetland placement

The Outer Harbor wetland entered its staged construction sequence

USACE and Erie Canal Harbor Development Corporation described a 6.7-acre Slip 3 wetland requiring approximately 285,000 cubic yards over an estimated three dredging cycles, followed by planting and habitat features. That programme baseline does not establish current fill or ecological performance.

Read controlling source

Africa / São Tomé and Príncipe / Marine infrastructure / Current phase: financing

São Tomé and Príncipe BEFIRM fisheries infrastructure rehabilitation

Project identification confirmed three physical-work sites

The appraisal report records an identification mission from 24 November to 11 December 2023 that confirmed the need for separate environmental and social studies at Chimalô, Neves-Rosema, and Porto Alegre. This is the earliest reviewed site-definition gate, not a construction start.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: construction

Skandia Gateway fairway and quay deepening

NCC entered the quay construction phase

The just-over-SEK-1-billion partnering order moved the quay from detailed design into construction, covering front sheet piling, foundation piles, a crane girder and utility systems. The notice leaves completion and the separate fairway award unresolved.

Read controlling source

Asia Pacific / India / Marine utilities / Current phase: planning

Gopalpur Industrial Park 100 MLD desalination PPP

IDCO separately sought a Rushikulya River intake route

The river-intake notification is evidence of a separate or alternative industrial-water route for Gopalpur Industrial Park. It must not be merged into the seawater PPP or treated as its intake design.

Read controlling source

Africa / Morocco / Marine utilities / Current phase: construction

Casablanca-Settat desalination marine works and common systems

ONEE concluded the long-term public-private partnership

ONEE records the PPP conclusion in November 2023 for design, finance, construction and more than 27 years of operation. The agreement establishes responsibility and delivery structure, not notice to proceed, construction start or marine-system definition and acceptance.

Read controlling source

Europe / Netherlands / Dredging / Current phase: delivery

Boskalis SEAWAY 31,000 m³ TSHD

Boskalis converted the design phase into a construction contract

The owner confirmed Royal IHC, a 31,000 m³ hopper, the dredging and discharge arrangement, propulsion and fuel-preparation concept, build location, and intended mid-2026 service entry. The announcement did not disclose contract value or acceptance terms.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: design

Roberts Bank Terminal 2 landmass and wharf

British Columbia issued its environmental assessment certificate

The provincial certificate added 16 legally enforceable conditions after the federal approval. It did not authorize the site to be reported as under construction.

Read controlling source

Asia Pacific / India / Dredging / Current phase: completed

Kamarajar Port Capital Dredging Phase VI

Draft feasibility report set the upstream planning basis

Kamarajar's 2022-23 annual report recorded approval of a draft feasibility report with about 13.23 million cubic metres and an estimated INR 5.492 billion cost. These are planning estimates, not final measured quantity or expenditure.

Read controlling source

Europe / Netherlands / Port infrastructure / Current phase: construction

Port of Rotterdam Yangtzekanaal widening and quay programme

Phase A construction started in the operating access channel

The authority's 2023 year-end record confirms field execution began on the 500-metre quay and 12 tug berths. Shore power, berth operation and the later Phase B and C outcomes remained unresolved.

Read controlling source

Asia Pacific / Singapore / Marine utilities / Current phase: construction

Singapore DTSS2 Tuas WRP nearshore outfall

Nearshore outfall and Contract 1A permanent works substantially completed

The milestone closed the principal outfall civil package while wider plant, conveyance, commissioning and environmental-performance gates remained open.

Read controlling source

Asia Pacific / Australia / Marine utilities / Current phase: construction

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

Environmental approval established the controlled marine development envelope

EPA records Ministerial Statement 1207 approval for the plant and its marine components. Approval allows implementation under conditions; it is not an alliance award, notice to proceed, construction start or operating approval.

Read controlling source

Africa / Burundi / Marine infrastructure / Current phase: construction

Bujumbura Port Lake Tanganyika corridor rehabilitation

The main Phase I works contract entered its initial 24-month period

The contract start defines the original execution baseline for the active AfDB/EU package. Subsequent inspection evidence displaced that original window and moved the working infrastructure target to end-2026.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: completed

Taweelah RO desalination intake and outfall system

Group 2 received its commercial-operation certificate

ACWA's first-half 2023 results state that EWEC issued the Group 2 certificate and that the plant was supplying 183 MIGD. The remaining step to the current 200 MIGD operating position followed later.

Read controlling source

Europe / Belgium / Port infrastructure / Current phase: construction

Antwerp Kanaaldok B2 liquid CO2 export quay

CINEA handed over the EU grant agreement

The EUR 144.6 million grant agreement supported shared transport, liquefaction and export infrastructure under a June 2027 action frame. Grant execution is not the EUR 22 million quay award, terminal final investment decision, construction completion, or operation.

Read controlling source

Europe / Netherlands / Port infrastructure / Current phase: construction

Port of Rotterdam Yangtzekanaal widening and quay programme

Phase A contracts were signed with Hakkers, Van Oord and De Klerk

The owner award fixed the 500-metre quay, 12-berth scope and contractor consortium, and anticipated work after summer. Contract signature did not prove mobilisation, installed wall, commissioning or the award of later phases.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

Aguas Horizonte issued the EPC order to proceed

The contractor announcement confirms the project moved from BOOT award into EPC execution for the desalination, intake, pumping and conveyance system. The notice did not document mobilisation across every workfront or any completed marine asset.

Read controlling source

Europe / Netherlands / Dredging / Current phase: delivery

Boskalis SEAWAY 31,000 m³ TSHD

Royal IHC and Boskalis signed the construction letter of intent

The letter of intent followed joint design and engineering and established the intended 31,000 m³ custom-build route at Krimpen aan den IJssel. It preceded the later construction contract and was not itself delivery evidence.

Read controlling source

Africa / Nigeria / Deep-water ports and container terminals / Current phase: award

Nigeria Snake Island Container Terminal concession and EPC

Federal Executive Council approved the wider port PPP

The approval established a 45-year, USD 974.19 million multipurpose-port framework for Nigerdock and SIIFZ. ICRC said projects would still proceed to commercial close before commencement.

Read controlling source

Africa / Democratic Republic of the Congo / Deep-water ports and container terminals / Current phase: construction

Banana Deep-water Port Phase One

Government reported initial rock-armour works at the site

The official record identifies early coastal-protection activity. Later phase-one contracting, revetment completion, dredging and reclamation quantities, shoreline acceptance and port completion remain outside that early activity record.

Read controlling source

Europe / Italy / Ports and coastal protection / Current phase: construction

Genoa New Breakwater

First stone marked the formal start of works

The Port Authority and consortium launch record marks the transition from award and executive design into construction. Its original scope and schedule statements remain dated baseline context rather than current completion evidence.

Read controlling source

Americas / Canada / Port infrastructure / Current phase: design

Roberts Bank Terminal 2 landmass and wharf

Federal approval imposed 370 legally binding conditions

The decision statement approved the three-berth terminal, widened causeway and expanded tug basin subject to a substantial compliance programme.

Read controlling source

Asia Pacific / Indonesia / Port infrastructure / Current phase: construction

Patimban Port Phase 1-2 expansion

Package 5 car-terminal construction started

The start opened the separate car-terminal expansion work front under the TOA-led joint operation. It did not change the completed Phase 1-1 boundary or prove the Package 5 marine platform complete.

Read controlling source

Europe / Netherlands / Port infrastructure / Current phase: construction

Port of Rotterdam Yangtzekanaal widening and quay programme

The owner published the three-phase access programme

The programme separated tug berths, inland-shipping berths and later navigation-channel dredging, with different vessel-access objectives. At that point there were no contracts, construction records or achieved-access evidence.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

Owner first published a 60% Phase 2 completion measure

MPA reported reclamation about 60% complete and kept Phase 1 completion and operations separate from Phase 2. This is an aggregate civil-progress baseline, not a berth, dredging, wharf or operating acceptance event.

Read controlling source

Global islands / Solomon Islands / Marine utilities / Current phase: tender

Honiara wastewater mains and two deep-sea outfalls

Environmental design fixed a two-outfall baseline

The assessment defined a 350 m NRH line and 500 m Ranadi line, six pump stations and about 15 km of sewers, while leaving the final offshore installation method to procurement.

Read controlling source

Middle East / Saudi Arabia / Marine utilities / Current phase: commissioning

Rabigh 4 IWP intake, outfall and storage system

SWPC named the preferred bidder

The preferred-bidder notice confirmed the 600,000 m3/day plant and 1,200,000 m3 storage scope. It was a procurement milestone, not a construction or operating result.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: construction

Ocean City and Peck Beach 2026 Periodic Nourishment

City records closed the preceding nourishment cycle

Ocean City reports the 21 November 2022 to 15 February 2023 campaign complete with 1.5 million cubic yards of beachfill and a 47,600-cubic-yard stockpile. Those are prior-cycle results and cannot be carried into 2026 production or acceptance.

Read controlling source

Asia Pacific / Indonesia / Port infrastructure / Current phase: construction

Patimban Port Phase 1-2 expansion

Package 6 container-terminal construction started

The Penta-Ocean-led consortium moved into execution on the 419 m berth, deepening, reclamation and ground-improvement package. Completion and terminal operation remained later gates.

Read controlling source

Asia Pacific / Philippines / Port infrastructure / Current phase: construction

Philippines Project Crane: MICT, MCT and South Luzon terminal works

MICT Berth 8 development began in Q4 2022

ICTSI's signed 2025 annual filing places the civil programme start in the final quarter of 2022 and separates yard Phase 1 from berth-and-yard Phase 2. This long-running construction history must remain distinct from the 2026 corporate financing approval.

Read controlling source

Asia Pacific / Indonesia / Port infrastructure / Current phase: construction

Patimban Port Phase 1-2 expansion

TOA announced the Package 5 car-terminal award

The contractor fixed the five-company joint operation, a roughly USD 209 million value and the berth, quay, reclamation, dredging and terminal scope. Contract award did not establish physical progress or acceptance.

Read controlling source

Europe / Belgium / Port infrastructure / Current phase: construction

Antwerp Kanaaldok B2 liquid CO2 export quay

The EU funding selection moved the hub toward investment

Air Liquide, Fluxys and the port announced CEF support for an open-access pipeline, liquefaction, buffer-storage and marine-loading system. The announcement described a step toward final investment decision, not the decision itself or physical delivery.

Read controlling source

Asia Pacific / Indonesia / Port infrastructure / Current phase: construction

Patimban Port Phase 1-2 expansion

Penta-Ocean announced the Package 6 container-terminal award

The contractor identified a six-company consortium and a roughly JPY 48.4 billion package covering the berth, dredging, reclamation, ground improvement and terminal civil works.

Read controlling source

Middle East / Qatar / Port infrastructure / Current phase: construction

Hamad Port food security terminal and warehouses

The first vessel delivered two mobile harbour cranes at more than 93% progress

The vessel call proved the berth could receive a heavy-lift equipment delivery and brought two Liebherr LHM 280 cranes to site. The owner called it a countdown to operation, so it must not be represented as first food cargo, terminal opening or accepted whole-system service.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

Ramayapatnam Port capital deepening works

Andhra Pradesh recorded initiation of the greenfield port

The SPSR Nellore district event register records initiation of the greenfield Ramayapatnam Port. It establishes the start boundary for the wider programme, not the later DEME package or completion of any marine element.

Read controlling source

Americas / Chile / Marine utilities / Current phase: commissioning

Codelco Northern District desalinated water supply marine works

Codelco authorized the BOOT contract with the Marubeni-Transelec consortium

The owner record establishes the commercial route, consortium, more than USD 1 billion investment frame, marine works and integrated coast-to-mine scope. Contract authorization and award do not prove signature, notice to proceed, construction, commissioning or operation.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: completed

Taweelah RO desalination intake and outfall system

First desalination phase entered operation

ACWA's rights-issue chronology places first-phase water production in June 2022. This was an operating milestone for part of the scheme, not full-capacity completion of the 200 MIGD facility.

Read controlling source

Europe / Spain / Port infrastructure / Current phase: construction

Valencia North Terminal quay and automated terminal works

Port Authority published the pre-tender construction project

The then non-final design carried an estimated EUR 448 million including VAT and 58-month period, plus technical prescriptions for caissons, consolidation, dredged-material characterization, and operability. Those planning figures were superseded by the later procurement and award evidence.

Read controlling source

Americas / United States / Port infrastructure / Current phase: award

Buffalo Harbor 2026 dredging and Slip 3 wetland placement

A prior Buffalo campaign set a historical Ryba baseline

USACE awarded Ryba a separate USD 991,500 contract for approximately 80,000 cubic yards routed to the harbor CDF. That earlier contract shows recurring two-year maintenance but is not evidence of 2026 production.

Read controlling source

Europe / Sweden / Port infrastructure / Current phase: award

Port of Luleå Malmporten fairway and deepwater port works

The market dialogue published the original whole-program baseline

The early owner brief described about 22 million m³, around 1 million m³ of rock, parallel port construction and normal operations, and an April 2024-December 2026 concept. These were procurement-planning assumptions and are not the current 14-million-m³ remaining-works contract.

Read controlling source

Asia Pacific / India / Port infrastructure / Current phase: award

Ramayapatnam Port capital deepening works

Phase I received environmental and CRZ clearance

The Ministry of Environment, Forest and Climate Change granted environmental and coastal-regulation-zone clearance for Phase I subject to project-specific and standard conditions. Clearance enabled the programme but did not award works, approve every later design change or prove construction acceptance.

Read controlling source

Africa / Democratic Republic of the Congo / Deep-water ports and container terminals / Current phase: construction

Banana Deep-water Port Phase One

DP World and the DRC laid the first stone

The ceremony marked political and contractual launch after the collaboration agreement. It did not prove contractor mobilisation, physical marine production, package acceptance, terminal commissioning or operation.

Read controlling source

Middle East / UAE / Port infrastructure / Current phase: award

Khalifa Port EGA berth enhancement programme

AD Ports documented the long-term marine-service baseline through December 2052

The listing prospectus identifies a port-facilities agreement under which AD Ports provides EGA marine and repair services through 8 December 2052. This establishes the operating commercial relationship behind the berth, not a construction contract for the 2026 upgrade.

Read controlling source

Africa / Senegal / Deep-water ports and container terminals / Current phase: construction

Port of Ndayane Deep-water Port and Container Terminal

DP World and Senegal laid the first stone

The ceremony marked the stated start of construction and restated the 840-metre first-phase quay, five-kilometre channel, 1.2 million TEU initial capacity, and later 410-metre quay. A first-stone event is not physical proof that those assets were built or accepted.

Read controlling source

Africa / Democratic Republic of the Congo / Deep-water ports and container terminals / Current phase: construction

Banana Deep-water Port Phase One

DP World and the DRC signed the final development agreement

The agreement set the phased port-development structure, initial 600-metre quay, 30-hectare yard, 450,000-TEU design capacity and 18-metre draft statement. Agreement and design evidence are not construction, as-built geometry or operating capacity.

Read controlling source

Asia Pacific / Australia / Port infrastructure / Current phase: award

Port Hedland Zone 5 Bypass Channel

The proposal fixed the first public channel and material envelope

Pilbara Ports defined a -11.5 m Chart Datum route, one-metre over-dredge allowance, up to 800,000 cubic metres and SG7C placement as a risk-mitigation concept. At that stage approvals, procurement and construction remained unresolved.

Read controlling source

Asia Pacific / Singapore / Marine utilities / Current phase: construction

Singapore DTSS2 Tuas WRP nearshore outfall

PUB documented the outfall pipe under installation

The owner fixed the physical scope at a 1.8 km treated-effluent pipe with diameters from 1.2 m to 3 m, providing project-specific evidence rather than a generic coastal-utility inference.

Read controlling source

Africa / Ghana / Port infrastructure / Current phase: financing

Takoradi Project Shiprite floating dock and repair yard

The ESIA set the dredging-management and monitoring framework

The environmental study requires a site-specific dredging management plan and assigns construction monitoring to the EPC contractor under PMD and engineering oversight. It supplies the control framework but not evidence that the works started.

Read controlling source

Global islands / Norfolk Island / Dredging and waterways / Current phase: tender

Norfolk Island Kingston Pier channel and repair works

Option 3A design and pier condition entered detailed development

The Department recorded archaeological test trenches, sheet-pile degradation and additional plume investigations as inputs to final design and approvals.

Read controlling source

Africa / Liberia / Coastal infrastructure / Current phase: approval

West Point Coastal Defence Revetment

The approved GCF proposal defined the financed programme boundary

The proposal set the wider climate-resilience budget and the concept for a West Point revetment. That programme budget is not a construction contract, and the design still had to pass through permits, final drawings, procurement, and field delivery.

Read controlling source

Africa / Senegal / Deep-water ports and container terminals / Current phase: construction

Port of Ndayane Deep-water Port and Container Terminal

DP World and Senegal signed the development agreement

The agreement established the joint-venture development and operating route and the two-phase port frame. It created the commercial and scope baseline but did not constitute a construction start, marine award, or operating approval.

Read controlling source

Middle East / Qatar / Port infrastructure / Current phase: construction

Hamad Port food security terminal and warehouses

The project was 85% complete against a Q2 2021 operating target

The official update recorded uneven progress across rice, sugar and edible-oil facilities and said the project was targeted to become operational in the second quarter of 2021. Later 2022, 2024 and 2026 records show that target cannot be used as an achieved operating date.

Read controlling source

Africa / Democratic Republic of the Congo / Dredging / Current phase: delivery

CVM Congo River Easydredge 2700XL fleet renewal

The DRC government handed MANZANILLO 2 to CVM

The government record establishes an earlier fleet-renewal and financing step intended to restore stable navigation drafts on the maritime reach. It is historical capacity context and is not combined with the 2026 Royal IHC contract or treated as current channel performance.

Read controlling source

Middle East / Iraq / Port infrastructure / Current phase: construction

Grand Faw phase-one marine and port-access system

The western breakwater was recognised as the world's longest breakwater

Daewoo E&C records a 15.952 km rubble-mound breakwater and Guinness recognition on 2 April 2020. The breakwater created the sheltered-water basis for the port but did not by itself establish navigable depth, berth or terminal readiness.

Read controlling source

Global islands / Kiribati / Marine utilities / Current phase: completed

South Tarawa sanitation and three-ocean-outfall rehabilitation

Whole-project physical completion was recorded

Physical completion followed the earlier outfall works and Q2 2019 testing and commissioning. It does not by itself prove continuing discharge compliance, universal connections or funded long-term maintenance.

Read controlling source

Africa / Burundi / Marine infrastructure / Current phase: construction

Bujumbura Port Lake Tanganyika corridor rehabilitation

AfDB approved the five-component Lake Tanganyika corridor programme

The lender baseline combines port and access-road rehabilitation, port facilities, institutional support, trade facilitation, and project management. MapAfrica currently lists the programme as ongoing with planned completion on 31 December 2027.

Read controlling source

Middle East / UAE / Marine utilities / Current phase: completed

Taweelah RO desalination intake and outfall system

Water purchase agreement established the IWP

ACWA's project archive records the 30-year agreement for the 909,200 m3/day scheme. Award and offtake created the delivery structure before marine construction and operating acceptance.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

The first Phase 2 caisson was installed

MPA marked the first of 227 planned caissons entering the wharf and seawall sequence for the 387-hectare phase. A first installation demonstrated the method and work-front start but did not prove repeat cadence, full wall continuity, reclamation, or terminal delivery.

Read controlling source

Middle East / UAE / Port infrastructure / Current phase: award

Khalifa Port EGA berth enhancement programme

Cape Taweelah made the first fully laden Capesize call after approach works

EGA confirmed that Abu Dhabi Ports had completed the approach-channel works, deepening from 16.5 to 18.5 metres draft and widening from 250 to 280 metres. The vessel call proves the earlier Capesize access state in operation; it does not prove Newcastlemax berth geometry or the new structural and equipment scope.

Read controlling source

Asia Pacific / India / Dredging / Current phase: tender

Mumbai Port 2026-29 maintenance dredging programme

An earlier T.47A/2017 work order established the recurring programme pattern

The historical register records a INR 91.87 crore Van Oord contract covering left-over 2017-18 work and the 2018-19 and 2019-20 cycles. This confirms recurring multi-cycle procurement history without carrying old prices, performance, or contractor identity into 2026.

Read controlling source

Asia Pacific / Singapore / Marine utilities / Current phase: construction

Singapore DTSS2 Tuas WRP nearshore outfall

PUB opened the first Tuas WRP works tender

The site-development and nearshore-outfall scope entered formal procurement as part of a wider multi-package water-reclamation programme, establishing a traceable package baseline before award and construction.

Read controlling source

Africa / Senegal / Coastal infrastructure / Current phase: construction

Gorée Island east and west coastal protection works

World Bank approved the Senegal WACA ResIP financing baseline

Approval established the investment-finance programme that later funded the Gorée package. It does not identify the later works contract or establish any construction output by itself.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

Phase 2 reclamation works commenced

MPA's current programme timeline records physical reclamation commencement on 7 March 2018. This moves the record from award to execution while leaving caisson installation, dredging output, land formation, handover, and operation as later gates.

Read controlling source

Asia Pacific / Singapore / Port infrastructure / Current phase: delivery

Tuas Port Phase 2 reclamation and terminal development

Penta-Ocean announced the Phase 2 reclamation and wharf award

The contractor identified the Penta-Ocean-Hyundai-Boskalis joint venture and a package covering reclamation, deep-water wharf, dredging, soil improvement and caisson works. The award fixed scope and counterparties, while mobilisation and accepted output remained ahead.

Read controlling source

Middle East / UAE / Port infrastructure / Current phase: award

Khalifa Port EGA berth enhancement programme

EGA and Abu Dhabi Ports signed the long-term Capesize facilities agreement

The original agreement committed Abu Dhabi Ports to fund and complete approach-channel, basin and berth dredging and widening so fully laden Capesize bauxite carriers could reach EGA directly. It is the commercial and geometry baseline for measuring the later Newcastlemax upgrade.

Read controlling source

Middle East / Qatar / Port infrastructure / Current phase: construction

Hamad Port food security terminal and warehouses

AlJaber Engineering signed the QAR 1.6 billion design-and-build contract

The original contract established the 53-hectare processing and storage system, bulk silos, conveyors and roughly 500-metre wharf interface. It is the commercial baseline for the terminal, not evidence of completed construction or operations.

Read controlling source

Americas / Panama / Dredging / Current phase: planning

Panama Canal new TSHD acquisition planning

Culebra Cut deepening closed with a mixed owner and contractor fleet

ACP reported 3.2 million cubic metres removed using five authority-owned units alongside Jan De Nul and Boskalis dredgers, demonstrating that internal plant and contracted capacity can operate as complementary delivery routes.

Read controlling source

Americas / Panama / Dredging / Current phase: planning

Panama Canal new TSHD acquisition planning

ACP awarded a US$43 million backhoe-dredger contract after international bidding

The award to IHC Engineering Business added a purpose-built 18-metre-depth, minimum 11-cubic-metre-bucket unit to ACP's fleet. It is a historic procurement precedent and does not identify the route or value of the current TSHD concept.

Read controlling source

Americas / Panama / Dredging / Current phase: planning

Panama Canal new TSHD acquisition planning

ACP awarded the US$95.920 million Quibian I cutter-suction-dredger contract

The formal international procurement replaced the 1942-built Mindi with a 12,000-kilowatt cutter-suction dredger intended for expansion and continuing maintenance. It proves a long owner-fleet strategy, not a current TSHD replacement decision.

Read controlling source

Americas / United States / Coastal infrastructure / Current phase: construction

Ocean City and Peck Beach 2026 Periodic Nourishment

The partnership agreement established the federal coastal programme

The USACE fact sheet records the Project Partnership Agreement on 18 September 1991 and initial construction in 1992, with approximately 6.2 million cubic yards of initial fill and an approximately three-year nourishment cycle. That programme baseline defines the asset history, not current-contract performance.

Read controlling source

Current change window

7D 18 changes

Events dated in the latest seven-day window ending 20 July 2026.

30D 62 changes

Events dated in the latest 30-day window.

2026 214 changes

Source-bound events dated during the current year.

ALL 498 changes

The complete public history across 108 projects.

How to read the log

The event date and evidence-review date are not the same.

Each entry uses the date attached to the controlling event or publication. The project phase shown beside it is the current phase, so readers can place an earlier award, permit, completion, or operating event inside today's project position.

Event date
The date attached to the source-bound change, not the date IMWO last checked the project.
Material change
An event that alters a project conclusion rather than repeating an unchanged source statement.
Current phase
The project's present controlled phase, shown as context and not backdated onto the event.
Controlling source
The record used for the event and its evidence boundary.

Project context and full data

Open the tracker for current project status and filters, or download all project fields and material-change histories as CSV.

Open project tracker Download project CSV