Kidongo Fish Landing Site

Officials inspecting active foundation and retaining works at Kidongo Fish Landing Site in Mombasa County

KEMFSED Habari newsletter, January 2025; official Kidongo construction inspection photograph

The State Department awarded Pristim Supply Limited the Kidongo Fish Landing Site contract for USD 1,354,881.48. The package includes a social fish banda, hall, BMU office and sanitation, a one-tonne-per-day ice plant, wastewater systems, retaining wall, drainage, access and utilities at Shanzu in Mombasa County. KEMFSED formally launched construction in October 2024 and published an active foundation and retaining-workfront photograph.

Project signal

Construction in Kenya

Current status Pristim Supply received the USD 1.355m contract on 11 June 2024; KEMFSED recorded the October 2024 construction launch and published a dated active-workfront photograph, but no completion evidence Source confidence Confirmed

Location

Kenya / Africa

Segment

Port infrastructure

Status

Pristim Supply received the USD 1.355m contract on 11 June 2024; KEMFSED recorded the October 2024 construction launch and published a dated active-workfront photograph, but no completion evidence / Confirmed

Last checked

3 August 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Kenya State Department for the Blue Economy and Fisheries through KEMFSED, World Bank project P163980
Delivery parties
Pristim Supply Limited - prime works contractor under KE-MOMBEMA-MSA-2024-008-CW
Contract route
Kidongo was tendered as a World Bank-financed Request for Bids subject to post review. The awards dataset records contract 1793484 signed on 11 June 2024 and excludes subcontract awards and cofinancing, leaving the ice, wastewater, retaining and utility supply chain open.
Execution window
The works package allowed 12 calendar months for construction. KEMFSED recorded the formal construction launch in October 2024 and published the site photograph in January 2025. Current percentage, completion, defects close-out and operating handover remain unreported through 3 August 2026.
Works package
Build a social fish banda, social hall, BMU office and ablution facilities, plus a one-tonne-per-day ice plant. Civil and external works include MBBR and biological wastewater treatment, dissolved-air flotation, biodigester, retaining wall, drainage, landscaping, access roads, perimeter wall, water, power, mechanical and electrical systems.
Marine interfaces
Kidongo's interface is a shoreline fish-landing and handling facility rather than a disclosed jetty or dredging package. The retaining wall, access and drainage have to protect a constrained coastal workfront and connect fish landing to sanitary handling and cold-chain functions. No source discloses shoreline quantities, marine plant or lower-tier specialists.
Commercial evidence boundary
A USD 1,354,881.48 supplier commitment defines the prime-award value, not paid expenditure or final account. Public records do not allocate value to the ice plant, retaining wall, wastewater systems or subcontractors.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

KEMFSED formally launched Kidongo construction

The official project newsletter records the October launch and shows active foundation and retaining works, confirming physical activity without proving completion.

Source

Pristim received the Kidongo works contract

World Bank contract 1793484 identifies Pristim Supply, reference KE-MOMBEMA-MSA-2024-008-CW and USD 1,354,881.48 committed supplier value, while leaving specialist systems subcontractors undisclosed.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Current civil and retaining-wall progress
  • Ice-plant supplier and accepted capacity
  • Wastewater-system suppliers and commissioning
  • Prime and lower-tier package boundaries
  • Completion and defects certification
  • BMU handover and operating performance

Reporting status

Construction, confirmed confidence

Last checked 3 August 2026 across 5 cited sources. The dated timeline above carries the project events.