Coverage focus
Dredging, navigation access and enabling marine packages
Sector intelligence
General waterside civil works, marine access, temporary works, quay interfaces, and specialist packages supporting coastal and port programmes.
Projects retain their detailed work segment and may appear in more than one sector when the scope crosses delivery disciplines.
Dredging, navigation access and enabling marine packages
247 project records connected to this sector.
272 current analyses and briefs connect through governed project relationships.
168 public profiles connect through documented project roles.
Project coverage
United States / Capital dredging and navigation-channel deepening / USACE lists Phase 2 in construction with new-work dredging continuing toward an FY2026 scheduled completion; final accepted depth, certified quantity and contract completion are unpublished
delivery / Last checkedUnited Kingdom / Container-terminal handling equipment / The Felixstowe Dock and Railway Company selected ZPMC at GBP 43.594 million excluding VAT for four ship-to-shore cranes; the published award and contract records remain pending, with no later signature, delivery or commissioning notice located
award / Last checkedUnited Kingdom / Continuous tidal flood and coastal erosion defence with early contractor involvement / Havant Borough Council selected Jackson Civil Engineering for a GBP 14 million excluding-VAT NEC4 coastal-defence contract; the 1 May 2026 award notice still marked the contract pending, while planning officers recommended conditional permission on 25 June and the owner continues to target two April-November construction windows in 2027 and 2028
award / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Kerr Limited's CAD 18.86 million contract reached its amended 31 December 2025 expiry after 11 amendments; no cited owner record confirms accepted completion, final dredged quantities or reopening
delivery / Last checkedFrance / Ports and coastal protection / Terelian and SDI/DEME are constructing the 1,800 metre protection dike; HAROPA reported nearly 800,000 m3 of foundation material placed by 1 June 2026 after a 760,000 m3 weak-silt purge, while channel dredging, dike tie-ins, completion and operating release remain pending
construction / Last checkedOman / Port infrastructure / OMR 36.995 million construction award approved in July 2026; contractor and detailed marine scope remain undisclosed
award / Last checkedThe Gambia / Port infrastructure / Port concession operating and green ferry commissioned; core jetty and container-terminal expansion completion remains unverified
delivery / Last checkedIndia / Dredging / Tender E.47/2026 remains open; bids due 24 August 2026 under Corrigendum VI
tender / Last checkedDemocratic Republic of the Congo / Deep-water ports and container terminals / Phase-one contract announced with an estimated 24-month term; no current cited record confirms accepted marine works, terminal commissioning, or commercial opening
construction / Last checkedTunisia / Port infrastructure / Dredging contract signed; enabling and supervision sequence forming
award / Last checkedSpain / Submerged masonry quay repair and structural concrete rehabilitation / Malaga Port Authority's rectified tender remains open until 2 September 2026 for a four-week repair of seven damaged areas on Quay 4; the EUR 78,739.06 excluding-VAT budget is a tender baseline and no contractor has been selected
tender / Last checkedUnited States / Marinas, pontoons and berthing infrastructure / New York City's 22 January 2026 award notice names Empire Construction and Property Management Group at USD 4,583,648 for X310-117M; the city hazard plan identifies bulkhead, dock and electrical reconstruction, but no cited record establishes contract signing, notice to proceed, mobilisation or completion
award / Last checkedDemocratic Republic of the Congo / Port infrastructure / PFCIGL reported that GETRA-AXOR remobilized from 15 June 2026 and that Kalundu works were progressively resuming; activity then remained at site installation and ground preparation before effective rehabilitation works
construction / Last checkedCanada / Port infrastructure / Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access
construction / Last checkedUAE / Port infrastructure / CHEC EPC delivery and live-berth works reported by two current staff profiles; owner releases confirm the AED 84 million programme but do not name the contractor
construction / Last checkedPhilippines / Dredging / Group completion reported; Libertad closeout remains unpublished.
construction / Last checkedMorocco / Port infrastructure / Construction reported above 60% in June 2026; marine completion, equipment and operating awards remain open
construction / Last checkedUnited States / Port infrastructure / USACE lists four current federal-standard placement routes; Alabama Code Section 33-7-13 takes effect on 1 October 2026
delivery / Last checkedUnited States / Port infrastructure / USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028
award / Last checkedNetherlands / Dredging / Delivered 20 July 2026; deployment unpublished
completed / Last checkedSenegal / Deep-water ports and container terminals / DP World reports the major dredging works complete 13 months ahead of schedule; quay and other marine and civil works remain active, while 2028 is a target rather than an accepted opening date
construction / Last checkedSingapore / Port infrastructure / Phase 2 reclamation stood at 79.5% in December 2025 and its planned six-berth handover remains unverified; the wider Tuas Port passed 25 million TEU in August 2026, but that operating total began with Phase 1
delivery / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Granite Management received DFO contract 4500013526 on 23 December 2021 for a two-site floating-dock package; the 2021-22 Public Accounts mark the contract completed, while physical acceptance records remain unpublished
completed / Last checkedCanada / Remote fishing-harbour timber crib wharf and floating offloading dock / Fisheries and Oceans Canada awarded ZheMaak Inc. contract 4500091055 for CAD 220,542 on 8 August 2025; the published seven-month term ended on 27 March 2026, but the reviewed federal record does not publish physical completion, accepted quantities, owner handover or a final account
delivery / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210731/001/PWD on 15 November 2021; CanadaBuys records a CAD 1,763,368 cumulative contract after amendments, and the 2022-23 Public Accounts mark the Port de Grave contract completed
completed / Last checkedCanada / Capital and maintenance dredging for a remote ferry, cargo and fishing port / PSPC awarded contract CW2402077 to Dragage Ocean DS on 1 September 2025; a CNESST filing places the contractor at the Cap-aux-Meules dredging site from a planned 13 October to 12 November 2025, while a 13 May 2026 amendment lifted the published contract total to CAD 6,724,266.72 without disclosing its scope
construction / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed
completed / Last checkedAustralia / Port revetment repair and armour-rock placement / Queensland Transport and Main Roads disclosed Contract MSQ25017 with Hunter Contractors Pty Ltd at AUD 1,981,207 on 10 July 2025, and Maritime Safety Queensland announced a 2 September 2025 construction start; no cited official source confirms installed quantities, completion, acceptance or final account
construction / Last checkedUruguay / Dredging / Hang Jun 4018 is working Darsena II while Draga 9 maintains the port and access channel
construction / Last checkedAustralia / Port infrastructure / MGN Civil holds the surge-protection breakwater award; wider dredging, berth and tug-harbour packages remain separately unconfirmed
award / Last checkedTonga / Port infrastructure / AIFFP and Ports Authority Tonga confirmed all marine and civil works complete and operational on 5 November 2025
completed / Last checkedUnited States / Port infrastructure / USD 2.3 million Ryba contract awarded; July-August 2026 dredging and placement programme announced
award / Last checkedCzechia / Inland marina quay edges, floating fingers, bank protection and utilities / The Czech Waterways Directorate opened 30 new public berths in August 2025 and the Transport Ministry reports the expanded marina operating with capacity for 66 boats in the 2026 season; IDS holds the phase-one works contract, with the highest reviewed official modification snapshot at CZK 86,312,219.98
completed / Last checkedUnited States / Marina electrical infrastructure, waterfront site preparation and public realm / The Port of Edmonds Commission unanimously authorized a contract with TRICO Companies LLC on 8 June 2026; the current owner page marks Phase II in progress and estimates work will begin late in 2026
award / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Kildare Construction Ltd. received CAD 1.10 million contract 4500013345 on 23 December 2021 for structure 401; the 15 June 2022 target date is published, but completion and owner acceptance remain unverified
award / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Christian Larocque Services LTEE received the CAD 347,878.45 construction contract in November 2021; Harbourside Engineering reports the rebuilt dredge-spoil containment cell completed in March 2022
completed / Last checkedUnited States / Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities / Port reporting confirms key dock and stormwater upgrades were completed in 2025 and navigation and environmental work advanced; Washington L&I records American Construction's contractor-reported 8 April 2026 work-completed date, but no filed Notice of Completion, owner acceptance, final hydrographic survey, final dredged quantity or final account is evidenced
delivery / Last checkedUnited States / Wharf maintenance, fender piles and marine asset renewal / The San Francisco Port Commission adopted Resolution 25-25 on 13 May 2025, authorizing award of Contract 2871 to Manson Construction Co. for USD 5,518,500 plus a USD 551,850 contingency; the cited official record does not confirm the planned notice to proceed, physical progress, substantial completion or acceptance
award / Last checkedKuwait / Deep-water ports and container terminals / Phase I EPC signed with CCCC; government follow-up continues, while mobilisation and marine construction remain unverified
award / Last checkedOman / Port infrastructure / 83% complete in August 2025; completion, contractor and acceptance remain unverified
construction / Last checkedJordan / Port infrastructure / DFBOT proposals due 17 August 2026
tender / Last checkedNetherlands / Port infrastructure / Phase A tug quay delivered; the same consortium has started Phase B, including 1.4 million m3 of sand dredging; Phase C remains a post-2028 package
construction / Last checkedUnited Kingdom / Port infrastructure / Construction contract awarded; site preparations commenced
construction / Last checkedSouth Africa / Port revetment repair and armour-rock placement / South Africa's official procurement release records an active ZAR 5,466,159 award to KATLANTIC for the Port of Durban North Bank revetment repairs; the public record does not provide an award date, executed contract, notice to proceed, physical progress or completion
award / Last checkedUnited States / Inland navigation lock rehabilitation and hydraulic steel structures / USACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublished
completed / Last checkedSamoa / Port infrastructure / Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate
construction / Last checkedUnited States / MOTEMS wharf replacement, dolphins, fenders and maintenance dredging / The Port of Los Angeles January 2026 CIP report classifies the project in construction and, using actuals through November 2025, records 22% construction completion, a 31 March 2027 forecast finish, USD 39,288,466 projected project cost and USD 6,315,074 spent to date
construction / Last checkedUnited States / Port infrastructure / USACE records the FY2025 campaign complete after Dutra's USD 6.272 million dredging award; three reported subawards expose placement fees, DQM and survey support, tug setup and crew boats, while the final accepted quantity and account remain unpublished
completed / Last checkedUnited States / Port infrastructure / USD 5.3 million 2026 task order issued under a USD 11.1 million two-year Ryba contract; the September start remains planned
award / Last checkedDemocratic Republic of the Congo / Dredging / Easydredge 2700XL building contract signed; no yard, trial, delivery, acceptance, or Congo River deployment milestone published
delivery / Last checkedArgentina / Port infrastructure / Concession signed and oversight council active; operating transfer is complete while August maintenance mobilisation remains to be evidenced
mobilisation / Last checkedMadagascar / Inland river-port station and passenger-cargo terminal rehabilitation / ECH BTP signed the USD 1,272,815.07 works contract on 28 November 2025; public records also name the design and supervision consultant, but no notice to proceed, mobilisation, measured progress, completion or acceptance has been located
award / Last checkedMali / Inland river-port quay and bank rehabilitation / Two works lots under ML-UGP-PRTD-477915-CW-RFB were signed in December 2025; the April 2026 procurement plan marks the package under implementation, but no lot-specific mobilisation, progress, completion or acceptance record has been published
award / Last checkedUnited Kingdom / Maintenance dredging, floating-harbour navigation and marina access / Bullo Limited holds the GBP 392,500 contract; Bristol notice 36/26 schedules a 10-17 August Baltic Wharf work window beyond the original 26 June contract end
delivery / Last checkedUnited States / Dredging and waterways / Breakwater Marine under USD 12,984,450 contract; USACE programme page records construction ongoing after the May-July marine-operations window
construction / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / CanadaBuys solicitation WS5822483507 is open for Le Goulet harbour-basin maintenance dredging and closes 1 September 2026 at 14:00 EDT; no current winner, contract value, quantity, depth, disposal site, plant or delivery contractor is publicly established
tender / Last checkedAustralia / Urban waterway maintenance dredging, navigation access and in-river material placement / Buying for Victoria records Australasian Marine Associates on a current AUD 1.93985 million contract starting 8 September 2021; Parks Victoria confirms AMA delivered Campaign C in 2024, while the owner programme was reported complete and the next funding cycle remained open
delivery / Last checkedNorfolk Island / Pier remediation and island freight access / GP Services' AUD 183,041 emergency-remediation period has elapsed without accepted completion evidence; the separate AUD 10 million apron project is in detailed design with Consult Marine, with no construction award or mobilisation published
award / Last checkedIndia / Dredging / Corrigendum-9 extends bid submission and opening to 18 August 2026; no bidder, evaluation result or award is disclosed
tender / Last checkedCanada / Port infrastructure / TerraMarine is preferred proponent; contract negotiations, an in-progress Fisheries Act authorization and development work precede any target-price design-build agreement, financial close or mobilisation
design / Last checkedUnited States / Port infrastructure / Great Lakes Dock & Materials holds both phases; USACE reports the last 450 feet continuing through November 2026
construction / Last checkedUnited States / Port infrastructure / Southern Dredging's Dredge BRUNSWICK is listed on active 24/7 work in the Bypass and Steel Mill channels through about 31 August 2026
construction / Last checkedUnited Kingdom / Marinas, pontoons and berthing infrastructure / Teignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmed
construction / Last checkedUnited Kingdom / Marinas, pontoons and berthing infrastructure / Solent Marine holds a GBP 72,600 float award.
award / Last checkedUnited States / Naval and civil seaport wharf, breakwater and harbor-dredging design / MDPAC JV holds a USD 12.616m architect-engineer task order through 31 December 2026 for P-940 wharf improvements, P-1001 breakwater restoration and P-1002 harbor dredging and Finger Pier A removal; 13 named design-chain subaward records total USD 4.055m, while no construction award or mobilisation is evidenced
design / Last checkedUnited Kingdom / Seawall, quayside and pontoon repair / National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT; the contract period ran from 13 August to 12 September 2025, but no dated completion, acceptance or final-account record has been located
award / Last checkedNetherlands / Dredging / Award signed; start unverified.
award / Last checkedCanada / Small-craft-harbour marginal wharf and channel-wall renewal / DFO-SCH's 2026 proposal remains in federal assessment after the public-comment period ended on 22 June 2026; no environmental determination, procurement, award, contractor, mobilisation or construction is evidenced
approval / Last checkedCanada / Small-craft-harbour entrance dredging and breakwater works / Marine Contractors' CAD 1.499m entrance-improvement contract and R.J.G Construction's separate CAD 1.133m channel re-dredging contract have both reached their published administrative end dates, but no completion certificate, accepted hydrography, final dredged quantity or causal link between the packages is public
delivery / Last checkedUnited States / Naval-wharf and inner-harbor dredging design / MDPAC JV holds the USD 3.335m P-835 design task order, expanded in August 2025 from DD1391 and 15% design into a design-bid-build package and extended in March 2026 to September 2028; no construction award or physical dredging is evidenced
design / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Superior Contracting's CAD 1.264 million contract ran from 14 October 2022 to 31 March 2023 for an integrated timber-wharf, dredging, breakwater, floating-dock and electrical package; the reviewed federal record does not publish accepted completion, measured quantities or final account
delivery / Last checkedUnited States / Cruise berth rehabilitation, shore power and marine piling / Los Angeles Harbor Commission Resolution 26-10665 approved Shimmick's USD 61,290,400 bid on 6 January 2026, and RAMP records the award on 26 January; the owner's award presentation estimated a March 2026 notice to proceed and January 2029 completion, while the actual NTP, site mobilisation and installed work remain unconfirmed through 8 August 2026
award / Last checkedAustralia / Marinas, pontoons and berthing infrastructure / Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract
completed / Last checkedAustralia / Marinas, pontoons and berthing infrastructure / Transport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade Sales
completed / Last checkedSaudi Arabia / Naval base wharf and fleet-support facilities / USAspending records W912ER-23-C-0002 at USD 400,127,768.96 obligated and exercised, with the current performance period ending 8 March 2027 and the latest modification dated 7 May 2026; no public physical-completion or owner-acceptance record is established
construction / Last checkedBahrain / Liquid-cargo terminal berth enhancement / Bahrain Tender Board's March 2026 monthly report records a BHD 10,987,831 award to NASS Contracting for Sitra Wharf tender T78534; no award date, contract signature, mobilisation or installed work is published
award / Last checkedUnited Kingdom / Marinas, pontoons and berthing infrastructure / Find a Tender notice 073261-2026 records a GBP 411,775.70 excluding-VAT contract with Inland and Coastal Marina Systems UK Ltd signed on 15 July 2026; the active 20 July to 2 October period is not evidence of physical mobilisation
award / Last checkedNetherlands / Quay-wall replacement and waterfront public-realm renewal / TED notice 542353-2026 records a EUR 7,887,000 contract with De Vries Werkendam B.V. concluded on 4 August 2026; the owner plans physical works from 5 October 2026 to 21 July 2028 and publishes no current mobilisation evidence
award / Last checkedAustralia / Harbour seawall renewal and coastal asset protection / Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation
award / Last checkedSenegal / Fish landing quay and fisheries value-chain infrastructure / FIDELE SARL's rehabilitation contract was signed 5 February 2025 for an operating export-approved landing facility; no controlled site start, temporary operating setup or physical progress evidence through 8 August 2026
award / Last checkedSenegal / Fish landing quay and fisheries value-chain infrastructure / KELIMANE ENTREPRISE's Lot 01 contract was signed 5 February 2025, while a separate replacement relocation-site package remained awaiting execution in the current plan; no controlled main-works start evidence through 8 August 2026
award / Last checkedSenegal / Fish landing quay and fisheries value-chain infrastructure / Official works launch held 24 July 2025 after ETIC's Lot 02 contract was signed 15 January 2025; no controlled later completion or commissioning evidence through 8 August 2026
construction / Last checkedOman / Operating fishing-port maintenance dredging / Oman eTender 441/2023/MAFWR/HQ-36 reached financial evaluation in Q3 2023, then a Recall-1 procedure closed on 19 December 2023; an awardee, value and mobilisation remain undisclosed
tender / Last checkedOman / Fishing-port breakwaters, dredging, quay and marine infrastructure / Liwa harbour was operating by 2023 after the original Galfar award and 2015-2017 downstream marine works; formal completion, acceptance and final-account records remain unrecovered
completed / Last checkedOman / Fishing-port maintenance, rehabilitation and dredging / Masirah Island International identifies active harbour maintenance, rehabilitation and dredging; a 2025 Oman News Agency owner-side report says the port remained under maintenance, with no public completion or acceptance record
construction / Last checkedFrance / Port structures and underwater asset maintenance / Grand Port Maritime de Dunkerque is procuring a six-year single-provider underwater-works framework with a EUR 1.5 million minimum and EUR 5.0 million maximum; bids close at 12:00 on 4 September 2026 and no holder is named
tender / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Dexter holds CAD 4.29 million CW2462474 for floating-dock and pipe-pile replacement, while Connors Diving holds CAD 1.27 million 4500109325 for Wharf 403 pile jackets and concrete repairs; both awards are active but mobilisation and progress are unverified
award / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified
award / Last checkedItaly / Container and multipurpose terminal quay extension / TED notice 521188-2026 records a 23 July 2026 works contract with a planned RTI led by Dott. Carlo Agnese at EUR 10,868,519.12 for 419 days; notice to proceed, mobilisation, installed quantities and named subcontractors remain unverified
award / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds active CAD 2.75 million contract CW2455209 through 27 November 2026 for rubble-mound breakwater construction at Larrys River; award and scope are confirmed but mobilisation and physical progress are not
delivery / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Les Entreprises P E C inc holds active CAD 862,270 contract CW2452382 through 31 December 2026 for barge-excavator dredging and containment-cell reconfiguration; earliest site start was 6 July and field progress remains unverified
delivery / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / L Breau and Sons Ltd holds active CAD 8.75 million contract CW2440554 through 24 August 2027 for structure 401 wharf reconstruction and a new breakwater; mobilisation, measured work and acceptance remain unconfirmed
delivery / Last checkedSri Lanka / Deep-water port expansion, breakwaters and reclaimed logistics land / Dohwa-led detailed-design contract awarded in April 2025; SLPA's May 2026 planning document confirms the engineering study but leaves financing, construction procurement and field start open
design / Last checkedNetherlands / Beach and foreshore nourishment / Van den Herik signed the EUR 16.302 million contract on 10 March 2026; Rijkswaterstaat schedules Maasvlakte 2 nourishment for September and names Van den Herik with Van der Kamp there, while mobilisation and the parties' commercial relationship remain unverified
award / Last checkedNetherlands / Beach and foreshore nourishment / Fa. Gebr. Van der Lee signed the EUR 8.199 million contract on 31 March 2026; the contract is live through 2027, while no public evidence of physical mobilisation, vessel assignment or accepted production was identified by the 7 August 2026 review
award / Last checkedNetherlands / Beach and foreshore nourishment / Boskalis signed the EUR 26.098 million contract on 12 May 2026; Rijkswaterstaat announced Den Helder tidal-channel nourishment from 14 July to mid-October and Julianadorp sinker-pipe removal from 20 July, while measured production and acceptance remain unpublished
construction / Last checkedMalta / Cargo-port quay, land reclamation, piling and utilities / Infrastructure Malta is taking replacement works tender IMT008/2025 to 1 October 2026 after terminating predecessor contract IM027/2020; the replacement works package remains unawarded
tender / Last checkedColombia / Capital dredging and navigation-channel deepening / SECOP II records contract GN2862-2026 signed with Consorcio Puerto Tumaco II for COP 26.826 billion and eight months, but the public ledger has no start date, invoicing or payment and the separate supervision procurement remains unawarded
award / Last checkedColombia / Navigation channel maintenance dredging / SECOP II shows contract 0-525-2024 modified to COP 241.685 billion and 31 December 2026 after a 365-day extension; Cormagdalena reported 80.7% execution at 31 March before the later ledger update, while completion and acceptance remain unconfirmed
delivery / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Landco Construction's CAD 3.08 million contract ran from 2 November 2023 to 4 July 2024 for a Berlin-wall marginal wharf, harbour dredging and electrical reinstatement; CanadaBuys does not publish accepted completion or final quantities
delivery / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Bulldog Contracting received the CAD 7.05 million award on 1 April 2022 for timber-crib wharf, finger-pier, dredging and utility works; the reviewed federal record does not establish the delivery end date, accepted completion or final account
delivery / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Brian MacGillivary Construction's CAD 516,100 contract ran from 22 November 2023 to 29 March 2024; CanadaBuys confirms the award and amended term but publishes no accepted dredging quantity, dock handover or completion certificate
delivery / Last checkedAustralia / Wharf maintenance, fender piles and marine asset renewal / Queensland TMR awarded MSQ26005 to Pacific Marine Group on 11 May 2026 for AUD 423,687; no public milestone establishes mobilisation, pile quantities, installation method, completion or acceptance
award / Last checkedTanzania / Capital dredging, berth reconstruction and concrete remediation / Channel and berth civil packages were reported complete in 2024 and the port publishes operational depths; CHEC's separate USD 15.70 million 2025 concrete-repair contract has no cited completion or acceptance evidence
construction / Last checkedUnited States / Maintenance dredging and operating-port access / Great Lakes' Padre Island campaign was publicly scheduled from 20 October to 16 November 2024; an April 2025 final-quantity modification reduced the current federal obligation from USD 8.799 million to USD 7.456 million, while accepted quantities and formal closeout remain unpublished
delivery / Last checkedUnited States / Dredging and waterways / Great Lakes holds the USD 219.108 million Contract 6 obligation; its USD 235.423 million potential value, April 2027 owner finish, production, assigned fleet and lower tiers remain to be confirmed
delivery / Last checkedFrance / Inland-port basin excavation, sheet-pile quays, pile-supported jetties and multimodal access / HAROPA PORT reports phase-one construction in execution: earthworks, a retaining wall and conveyor loading were active in summer 2026, South Quay sheet-pile installation had started, and piling for the west then east jetties was scheduled from the week of 6 July
construction / Last checkedUnited Kingdom / Maintenance dredging and operating-port access / South Hams District Council signed Van Oord UK Limited on 11 March 2026 for GBP 101,600 excluding VAT; water injection dredging was the tendered expectation for Batson Creek, Lincombe and Kingsbridge, but no public mobilisation, post-dredge survey or acceptance record has been located
award / Last checkedBarbados / Port infrastructure / World Bank contract record 1881500 names C. O. Williams Construction Limited at USD 3.338 million, but the public procurement chronology does not reconcile and no dated mobilisation, progress or completion record has been located
award / Last checkedTonga / Port infrastructure / China Jiangsu International holds the signed USD 4.803 million MOI-WK2-13 award; notice to proceed, mobilisation and physical works remain publicly unconfirmed
award / Last checkedFrance / Dredging / Region Hauts-de-France concluded contract 202613951 with SODRANORD on 24 February 2026 for a purchase-order maintenance dredging framework; the EUR 23 million figure is the four-year maximum ceiling, while the first call-off, 2026 quantity and mobilisation remain unconfirmed
award / Last checkedCambodia / Marine infrastructure / Taing Cheng Oing Construction & Import Export signed package SCMFP FiA/CW-03 on 9 March 2026; ADB reports a financed amount of 472,336.05 without currency or full contract value, and mobilisation or physical start is not independently confirmed
award / Last checkedPeru / Maintenance dredging and operating-port access / APN started the access-channel and inner-roadstead campaign on 20 December 2025; a Jan De Nul post-dredging environmental report covers January 2026 monitoring, while owner acceptance, as-built hydrography and final account remain unverified
commissioning / Last checkedTuvalu / Ports and coastal protection / Hall Civil Contracting signed the USD 62.552 million design-build contract on 21 July 2025; the latest cited mission set August 2027 and January 2028 completion targets for Nanumaga and Nanumea, but no cited source confirms physical mobilisation or current progress
award / Last checkedBurundi / Port infrastructure / World Bank contract data records a USD 26.453 million EPC works contract signed with China Civil Engineering Construction Corporation on 27 July 2026; no cited source confirms notice to proceed, mobilisation or physical construction
award / Last checkedSpain / Piled fishing-quay concrete rehabilitation and metal fender renewal / Cantabria formalized the EUR 2,486,545.15 excluding-VAT works contract with the Cuevas Gestión de Obras-COMSA UTE on 9 July 2026; the signed contract requires a viable setting-out check before the 24-month execution period starts, while the setting-out act, site mobilisation, monthly production and lower-tier appointments remain unpublished
award / Last checkedUnited States / Breakwater armour repair, access dredging and nearshore placement / Ahtna Infrastructure & Technologies held the USD 16,037,425 current-obligation contract for Moss Landing Harbor dredging and jetty repair; the US Coast Guard published 2025 field-work windows and USACE published August-September post-dredge surveys, but the 23 January 2026 contract end does not establish final quantity, jetty acceptance, completion or final account
construction / Last checkedAustralia / Foreshore seawall and rip-rap protection / Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence
construction / Last checkedIreland / Fishery harbour piling, civil works and marine utilities / TED published the EUR 1.2498795 million Sorensen award on 5 August 2026 and records contract conclusion on 22 June; no project-specific mobilisation, commencement or subcontractor notice has been published
award / Last checkedUnited Kingdom / Maintenance dredging, beneficial use and dredging technology / GBP 100m award notice names Suffolk Dredging LLP for a five-year base term; a contract-details notice, reconciled extension limit and attribution of 2026 field activity remain unconfirmed
award / Last checkedFrance / Marinas, pontoons and berthing infrastructure / SPAD concluded three separate Grand Large marina works contracts on 30 June 2026 with Eiffage Travaux Maritimes et Fluviaux, Atlantic Marine and Ramery Travaux Publics; each lot carries a 24-month planned period, but no dated notice to proceed or field mobilisation has been located
award / Last checkedFrance / Ro-Ro berth and island freight access / Métropole Toulon Provence Méditerranée concluded contract 98RL25 with Océlian and TP Spada at EUR 2,104,311.99 on 20 August 2025 after an earlier procedure ended without an award; no dated mobilisation or completion record has been located
award / Last checkedCanada / Fishing harbour wharf, dredging and shore protection / Mskikue'j Enterprises holds the CAD 5.09 million wharf and shore-protection contract through March 2027; the separate 2025 dredging and containment-cell contract reached its stated expiry without a public completion or measured-quantity record
award / Last checkedAustralia / Marine infrastructure / Advanteering Civil Engineers has completed detailed design and started early off-site construction under DOT413022; on-site work is planned from spring 2026 but no dated mobilisation evidence has been published
construction / Last checkedAustralia / Marinas, pontoons and berthing infrastructure / Jetty and Marine Constructions holds one design-and-construct contract covering the Woodman Point western boat ramp and Fremantle Fishing Boat Harbour Jetty 1; Woodman Point field works began under a 27 July 2026 closure, while a dated Fremantle mobilisation record has not been published
construction / Last checkedFrance / Coastal protection and dredged-sand reuse / Baggerbedrijf de Boer holds the EUR 1.720365 million replacement contract concluded on 13 January 2025; the planned 31 May 2025 in-service deadline has passed, while physical completion, acceptance and downstream packages remain unverified
award / Last checkedAustralia / Port infrastructure / Western Broadside Wharf, adjacent seawall and access-pontoon repairs are underway under two NSW contracts through August and September 2026; the published notices name Polaris Marine Constructions and Clement Marine Constructions but do not disclose their exact package split
construction / Last checkedUnited States / Port infrastructure / Oceanetics holds the USD 1.378 million Navy task order through 11 September 2026; two reported subawards identify charter support and Ocean Guard buoy supply, while field installation and acceptance remain unverified
award / Last checkedOman / Small-port commercial activation, maintenance, dredging and berth readiness / A three-year development, management and operation framework was signed with Abu Sultan Enterprises in December 2025; the planned handover for maintenance and simple operations, physical marine works, capital programme and current operating state are not publicly confirmed
planning / Last checkedUnited States / Breakwater armour repair, access dredging and nearshore placement / Curtin Maritime holds the USD 4.89 million USACE award for breakwater repair and approximately 45,000 yd3 of access dredging; owner and award sources reviewed do not confirm mobilisation or construction progress
award / Last checkedAustralia / Recreational harbour, breakwaters, dredging and boat-launch infrastructure / The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works
completed / Last checkedCanada / Fishing harbour timber-wharf reconstruction / R.J.G. Construction holds the CAD 3.02 million wharf-reconstruction contract; the stated contract period ended in April 2026, but completion and acceptance are not publicly confirmed
construction / Last checkedJersey / Ferry-terminal marine works, dredging and demolition / Final design and planning-condition discharge are evidenced; construction was scheduled for autumn 2026, while Stage Two authorization, dredger or piling mobilisation and physical works start remain unpublished
design / Last checkedUnited Kingdom / Shingle recycling, beach regrading and coastal flood defence / Chunnel holds the signed beach-management contract; the council reported a 100,000-tonne spring 2026 campaign under way and an April purchase order names Chunnel, while measured completion and profile acceptance remain unpublished
delivery / Last checkedUnited Kingdom / Maintenance dredging and operating-port access / Four-year framework awarded to Boskalis Westminster, Dutch Dredging and Van den Herik; the first mini-competition, call-off, assigned vessel, dredged quantity and acceptance remain unconfirmed
award / Last checkedUnited Kingdom / Maintenance dredging and operating-port access / Jan De Nul is the selected supplier under a GBP 57 million award decision; the latest notice estimates a 6 January 2026 to 30 December 2027 contract period, while signature, mobilisation and physical production remain unconfirmed
award / Last checkedBangladesh / Port infrastructure / World Bank completion reporting confirms three fish landing stations and two fish markets completed by project close on 28 November 2025; five other sites in the original 10-site package could not start because of land-tenure disputes
completed / Last checkedKenya / Port infrastructure / Pristim Supply received the USD 1.355m contract on 11 June 2024; KEMFSED recorded the October 2024 construction launch and published a dated active-workfront photograph, but no completion evidence
construction / Last checkedKenya / Port infrastructure / Procost Ideas holds the USD 2.128m contract signed on 11 June 2024; an official November 2024 mission inspected the workfront and reported landing-site works advancing, without a site-specific percentage or completion record
construction / Last checkedKenya / Port infrastructure / Gesken Enterprises holds the USD 1.852m contract signed on 11 June 2024; public sources define a jetty and land-reclamation workfront but do not confirm site-specific mobilisation, completion or acceptance
award / Last checkedKenya / Port infrastructure / Toddy Civil Engineering received the USD 1.174m works contract on 11 June 2024 and KEMFSED recorded the October 2024 groundbreaking; no later completion or acceptance evidence has been published
construction / Last checkedOman / Port infrastructure / Serka-MSF completed the commercial-terminal fit-out in December 2020; the port is operational, while AIIB's 2025 review says throughput and revenue remain below original forecasts
completed / Last checkedCanada / Port infrastructure / Pilitak Enterprises holds the CAD 77.04m construction contract through 7 May 2030; DFO plans construction activity in 2026-27, while current public sources provide no marine mobilisation evidence
construction / Last checkedUnited Kingdom / Two-stage coastal flood and erosion defence, beach recharge and offshore rock works / East Devon selected Boskalis Westminster on 30 June 2026 for a GBP 18.911242 million two-stage NEC4 Option C contract; the 6 July notice still marked the award and contract pending, with standstill to 16 July and future signature scheduled for 17 July, and no later contract-details notice, Stage 1 start or construction commitment is yet published
award / Last checkedJersey / Marinas, pontoons and berthing infrastructure / Albert Pier's final berthing stage was complete by 6 April 2022 and St Helier Marina's refurbishment by May 2022; Ports of Jersey subsequently confirmed the marina works were on schedule and the combined capacity benefits were in use
completed / Last checkedBrazil / Port infrastructure / Jan De Nul contract signed on 12 June 2026; official mobilisation, production and acceptance evidence remain ahead
award / Last checkedIndia / Port infrastructure / Fifteen-year charter awarded on 30 June 2026; construction, delivery, port acceptance and service commencement remain ahead
award / Last checkedChina / Inland-waterway green-port programme, open-piled bulk and general-cargo berths / Daorenji's main marine structure was reported complete in July 2026 with equipment installation and commissioning next; Songyanghu III moved from 1,556 precast deck panels into field installation in January 2026; no current Phase II construction evidence has been found for Songmu. AIIB still lists the proposed sovereign financing as Proposed
construction / Last checkedFrance / Historic rubble-mound breakwater rehabilitation and island-port protection / Contract Z250608F00 was concluded on 2 February 2026 with an Océlian-led five-company group for EUR 19.589919 million; the owner reports that the overall rehabilitation programme continues in 2026, while main-contract mobilisation, placed rock, accepted sections and downstream subcontract awards remain unpublished
award / Last checkedFrance / Maintenance dredging and operating-port access / Eight call-off lots were concluded on 12 November 2025 for a four-year maximum framework beginning in 2026; the award chain is confirmed, while the first 2026 call-off, vessel mobilisation, measured quantity and port acceptance remain unpublished
award / Last checkedCroatia / Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems / Civil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacity
completed / Last checkedPoland / Caisson breakwaters and port access infrastructure / The May 2026 building permit has moved the design-build contract into principal in-water works; the first reinforced-concrete caisson was launched and towed toward its placement position in July 2026, with the remaining 48 caissons and breakwater systems still to be delivered
construction / Last checkedMorocco / Multipurpose berth extension, block quay, mooring dolphin, access bridge and terminal equipment modernisation / Marsa Maroc says the berth-front extension was launched and remained part of its active 2025 investment programme. Execution-design evidence identifies two quay extensions and a mooring dolphin; no owner acceptance or completed operating release has been published
construction / Last checkedMorocco / Brownfield quay strengthening, retaining structure, micropiles, scour protection and capital dredging / Works started on 1 October 2024. Marsa Maroc reported a first 230-metre section commissioned at -12 m, while the published delivery programme continues toward 530 metres of deepened quay plus transition zones by 2028; the civil-works award is confirmed but the contractor remains publicly unnamed
construction / Last checkedGeorgia / Container berth rehabilitation, dredging, quay-top renewal and terminal equipment / EBRD lists Phase 1 as Completed, and a TRACECA technical record says Berth 14 was rehabilitated in 2009 for 1,000-TEU feeder vessels; the exact acceptance date, as-built dredging quantity and depth, delivery contractor and final account remain publicly unresolved
completed / Last checkedCaribbean Netherlands / Hurricane-resilient harbor, breakwater, dredging, quay and marina works / Public Entity Saba reported steady construction progress on 10 May 2026, including breakwater works and Xbloc arrivals, with additional units being produced in Sint Eustatius. Dredging and excavation were active in March 2026, but marine completion, harbor handover, Fort Bay close-out and operational opening remain unconfirmed.
construction / Last checkedNorway / Deep-water quay, fairway dredging, contaminated-sediment containment and navigation works / Kystverket reported the Langneset quay in its finishing phase on 29 June 2026, with concrete works nearing completion and technical installations scheduled through summer and autumn; completion and an official opening are planned for autumn 2026, but handover, acceptance and operation remain unconfirmed
construction / Last checkedRomania / Inland-port quay, dredging, basin infill and intermodal berth works / TED published a further contract modification on 27 May 2026, extending the recorded execution duration by 4 months and 23 days and reducing the stated contract value by RON 1,270.26; the latest owner progress figure located is 62.04% at 30 June 2025, and no completion or acceptance record has been published
construction / Last checkedMalta / Fishing-port fairway dredging and beneficial reuse / Transport Malta described the Marsaxlokk works as ongoing on 26 June 2026; the original navigation notice ran to 31 July, but no public final hydrographic survey, accepted quantity, completion certificate or final account was located by 2 August
construction / Last checkedFrance / Ferry-terminal marine works, dredging and demolition / Région Bretagne reported one of the two old lock-guide structures under demolition on 1 April 2026 after the 270-tonne Ro-Ro ramp was removed in December 2025; the new reinforced-concrete guide caissons and maintenance dredging remain inside the two-year Lot 2 mission, with no owner acceptance published
construction / Last checkedIceland / Maintenance dredging and operating-port access / Jan De Nul confirms that trailing suction hopper dredger Tristão da Cunha deepened the Höfn access channel between January and February 2025; the measured quantity and post-dredge acceptance remain unpublished, and a separate Boskalis contract now covers 2026-2028
completed / Last checkedIreland / Fishery harbour berthing, marine piling and shore power / Sorensen reported all 24 dolphin piles installed in August 2025; the government project page published the following month still described the works as ongoing with substantial completion due in Q3 2025, and DAFM has not published a later handover record
construction / Last checkedCabo Verde / Port infrastructure / Porto Ingles marine works were inaugurated on 7 September 2022 and later received a final price-revision authorization; Palmeira's landside package was awarded to GRINER / Armando Cunha Cabo Verde in July 2024, with no public completion or acceptance record identified by 2 August 2026
construction / Last checkedIreland / Port infrastructure / Single-party framework active with Murphy International; Berth 29 was handed over in 2024, Murphy reports 21 call-offs delivered during 2025, and owner confirmation of the contractor-stated July 2026 completion target for Berths 30/31 and McCairns Yard has not been identified
construction / Last checkedKazakhstan / Port infrastructure / Berths 3 and 12 design-build tender closed at first stage on 17 April 2026; construction-supervision tender remains open to 28 August 2026, with no works award or dredging start publicly confirmed
tender / Last checkedNorway / Dredging / Kystverket's latest dated update records blasting complete and about 26,000 solid cubic metres of clean material dredged by 21 April 2026; the owner page says work remains in progress toward December 2026 completion
construction / Last checkedIreland / Port infrastructure / The construction contract started on 24 September 2025 and Marine Notice 23/2026 records Ward & Burke commencing the two-year marine works; no later completed work package has been published
construction / Last checkedFrance / Port infrastructure / Quay construction and the four-hectare yard remain the latest official delivery state; handover to operator AMLP was targeted for the second half of 2026 but has not been published
construction / Last checkedDenmark / Germany / Immersed tunnels and marine crossings / Third tunnel element immersed and connected on 1 August 2026; protection, serial immersion, systems integration, and a two-stage road-then-rail opening remain active
construction / Last checkedSouth Korea / Deep-water ports and automated container terminals / BPA completed the 23-caisson substructure in August 2024 and is advancing superstructure and automated-equipment packages toward an October 2027 completion and second-half 2027 opening target
construction / Last checkedGreece / Container terminal expansion, quay construction and dredging / ThPA signed the EUR 195.6 million METKA-TEKAL construction contract in November 2025 and installed the first of 21 quay caissons in July 2026; the second caisson was under construction at publication
construction / Last checkedUnited Kingdom / Maintenance dredging and operating-port access / Port of Aberdeen awarded Boskalis Westminster a three-year contract for annual North and South Harbour campaigns in 2026-2028; the 2026 campaign was scheduled from March with Freeway and MTS Valour, but no accepted campaign-completion record has been published
award / Last checkedNorway / Multipurpose quays, dredging and carbon-logistics infrastructure / Repstad Anlegg began works in August 2025; demolition, dredging and subsea blasting preceded a 99-pile quay-foundation programme scheduled from March to July 2026
construction / Last checkedUnited Kingdom / Deep-water ports and automated container terminals / Port of London Authority reported the 430-metre Berth 5 quay extension complete by 1 August 2026 while further retaining-wall piling continued toward the Berth 6 interface; the separately contracted ten-module automated yard remains on a contractor-reported programme to March 2027
construction / Last checkedMalaysia / Deep-water ports and container terminals / Malaysia Marine Department notices documented Package 1 and Package 2 work vessels on site from January 2026; PTP is delivering a 360-metre berth, dredging, reclamation, yard works and four quay cranes toward commissioning by 2028
construction / Last checkedRepublic of the Congo / Deep-water ports and container terminals / AD Ports Group awarded two marine and topside contracts to the MAR Contracting-MBTP joint venture and a crane contract to ZPMC on 18 May 2026; the 420-metre terminal is expected to be built over approximately two years
award / Last checkedRepublic of the Congo / Deep-water ports, dredging and multipurpose terminals / Congo Terminal reported 400 metres of the planned 750-metre quay complete by 6 July 2026 after all 558 steel piles were driven; dredging and electric-terminal integration remain active toward the 2027 delivery target
construction / Last checkedGhana / Deep-water ports and container terminals / Eiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021
completed / Last checkedSri Lanka / Deep-water ports and automated container terminals / Phase 1 has operated since April 2025 and handled one million TEU in its first year; the 1,400-metre quay was complete by March 2026 while Phase 2 crane deployment and full-terminal construction continue
construction / Last checkedColombia / Deep-water ports, dredging and multipurpose terminals / Commercial operations began on 5 February 2026 after four controlled vessel trials; the operator's current port-status ledger shows repeat container, breakbulk and refrigerated calls through July 2026
completed / Last checkedChile / Deep-water ports, dredging and reclamation / Environmental approval was granted on 26 May 2026; six bidders or consortia are prequalified for the common marine-works tender, but no construction award has been announced
tender / Last checkedPoland / Deep-water ports and container terminals / Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation
completed / Last checkedKenya / Port infrastructure / TOA's Package 1 is in construction; KPA reports confirm quay and trestle foundation dredging, while channel, basin, jacket installation and accepted quantities remain open
construction / Last checkedIndia / Port infrastructure / SMPK completed a non-binding global market EOI for phased capital dredging; a formal RFQ, works award and dredging contractor are not verified
tender / Last checkedIndia / Port infrastructure / DPA is assessing berth-wide repair, strengthening or replacement for an intended EPC package; no expanded-consultant award, EPC tender or works contractor is verified
design / Last checkedIndia / Port infrastructure / DPR work started in March 2025; no construction RFP, PPP award, concessionaire or works contractor is verified
design / Last checkedIndia / Port infrastructure / Technical audit and detailed engineering are commissioned through 31 December 2027; no construction tender, award or works contractor is verified
design / Last checkedOman / Port infrastructure / 75% complete in June 2024 with some facilities operating; full completion and formal opening remain unverified
commissioning / Last checkedOman / Port infrastructure / OMR 28.612 million design-and-build award confirmed; current construction progress and marine subcontract chain remain partly undisclosed
construction / Last checkedSão Tomé and Príncipe / Marine infrastructure / AfDB financing signed and three site-level safeguard packages disclosed; design-supervision and works awards remain unverified
financing / Last checkedUnited States / Dredging and waterways / Bid abstract posted 20 July 2026; four bids opened and Great Lakes submitted the lowest total at USD 69.469 million; no award or notice to proceed posted
evaluation / Last checkedUnited States / Dredging / Six timely bids are publicly tabulated; no award, permit issuance, notice to proceed or mobilisation has been announced
evaluation / Last checkedUnited States / Port infrastructure / USACE officially completed the East Pier repair on 24 July 2026 after rebuilding 900 feet of the 1,333-foot structure
completed / Last checkedNorfolk Island / Dredging and waterways / Rock revetment contractor appointed; the separate channel-dredging and pier-repair package was released to tender on 14 May 2026
tender / Last checkedNew Zealand / Dredging / NZD 8 million of government co-funding confirmed; designer, shipyard, build contract and first port assignment not disclosed
planning / Last checkedUnited Kingdom / Port infrastructure / Early development and design work is funded; construction timing remains unconfirmed
planning / Last checkedMalaysia / Dredging / Overall progress reached 69% at 30 June 2026, three percentage points ahead of programme
construction / Last checkedUnited States / Dredging and waterways / HME Construction under contract; 24/7 clamshell dredging and dump-scow operations notified for July 2026
construction / Last checkedBurundi / Marine infrastructure / Ongoing at programme level; March 2025 remains the latest quantitative Phase I physical-progress baseline
construction / Last checkedUnited States / Dredging and waterways / IFB W912DS26BA027 open; 237,945 CY in the base dredging CLINs; bids due 31 July 2026; no award or mobilisation recorded
tender / Last checkedGermany / Port infrastructure / Sand reclamation is active behind the new quay line; phased terminal delivery runs through 2028
construction / Last checkedNetherlands / Offshore wind foundations / DEME holds the transport and installation contract for 69 monopile foundations; offshore mobilisation has not been announced
award / Last checkedBenin / Port infrastructure / The port authority reports 69% physical progress and 72% overall progress, while its published 2021-2024 delivery period is no longer current
construction / Last checkedEgypt / Deep-water ports and container terminals / Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity
commissioning / Last checkedVietnam / Deep-water ports and container terminals / Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced
approval / Last checkedGhana / Port infrastructure / PIDG capital committed; financial close and construction start still to be confirmed
financing / Last checkedBrazil / Dredging and waterways / World Bank project is Active and Board Approved; the April 2026 procurement plan omits the Itajaí-Mirim main works package
approval / Last checkedUnited States / Dredging / Three preliminary bids opened for MFP-364.003; evaluation and award remain pending
evaluation / Last checkedUnited States / Dredging and waterways / Callan Marine dredging has reached the Gulf Intracoastal Waterway junction; the Navigation District says the next work front is the harbor and turning basin
construction / Last checkedUnited States / Port infrastructure / Updated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recorded
tender / Last checkedBangladesh / Port infrastructure / IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started
design / Last checkedAustralia / Port infrastructure / Owner-defined cutter-suction campaign scheduled from July to October 2026; contractor and mobilisation remain unconfirmed
approval / Last checkedNauru / Port infrastructure / ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items
construction / Last checkedIndonesia / Port infrastructure / Phase 1-1 is completed and partly operating; Package 5 car-terminal and Package 6 container-terminal works remained active through June 2025; Package 7 construction lacks a current owner or contractor mobilisation date
construction / Last checkedUnited Kingdom / Dredging / Marine licence MLA/2026/00178 remains submitted and open for consultation; the principal-contractor participation stage closed on 6 February 2026 and no award notice is published in the reviewed procurement family
approval / Last checkedIndia / Dredging / The Government of India reports Phase VI complete and Kamarajar operating at 18.0 metres draft; the post-dredge survey sheet and a first fully laden Capesize call are not published
completed / Last checkedNigeria / Deep-water ports and container terminals / MSC signed a 45-year sub-concession and finalized the ITB/DEME EPC on 11 March 2026; the reviewed project sources do not record mobilisation
award / Last checkedComoros / Port infrastructure / World Bank and AfDB implementation records confirm works are under way; the contractor's current target is 11 August 2027
construction / Last checkedIndia / Dredging / The open tender closed on 16 March 2026; no award, work order or mobilisation is identified
tender / Last checkedIreland / Port infrastructure / Marine construction is active; the 2026 harbour notice keeps the buoyed work zone in place through January 2027, while berth acceptance and service release remain open
construction / Last checkedUnited States / Port infrastructure / USACE scheduled MURDEN to work through May 2026; measured production and completion remain unpublished
construction / Last checkedUnited Kingdom / Port infrastructure / PQQ closed on 1 May 2026; no shortlist, ITT or award notice is present in the reviewed public chain
prequalification / Last checkedUnited States / Port infrastructure / Curtin Maritime's DB Avalon was operating in the Patapsco River on 16 June 2026
construction / Last checkedUnited States / Port infrastructure / Mechanical dredging began in late May 2026 and is scheduled to continue through August
construction / Last checkedBelgium / Dredging / 22,000 m³ TSHD ordered; China hull build, Singapore completion, trials, and 2029 delivery remain pending
delivery / Last checkedUnited Kingdom / Dredging / Award decision published to Boskalis Westminster; contract signature and start not evidenced
award / Last checkedUnited States / Port infrastructure / Outer harbor dredging and ERDC placement monitoring active
construction / Last checkedMexico / Dredging / Initial state dredging phase completed and a separate private berth stage is active; the federal 40 ha north-platform construction-dredging tender was declared void on 8 July 2026, with no rebid confirmed
tender / Last checkedBrazil / Dredging / Concession signed; 1 August operating transition remains scheduled, with the 13.3-metre baseline still controlling
mobilisation / Last checkedUnited States / Port infrastructure / USD 11.7 million award confirmed; no 2026 field execution is documented
award / Last checkedIndia / Port infrastructure / Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed
award / Last checkedPanama / Dredging / Market survey closed; potential public procurement anticipated before end-2026
planning / Last checkedPhilippines / Port infrastructure / AIIB loan approved; three terminal programmes active on separate schedules
construction / Last checkedSyria / Port infrastructure / Operations active; modernisation equipment mobilising
early works / Last checkedSpain / Port infrastructure / Main quay works under construction after the Q4 2024 start
construction / Last checkedAustralia / Port infrastructure / Marine reference design, investigations, environmental-review preparation, and construction planning active; Westport Bill remains before Parliament
design / Last checkedMadagascar / Marine infrastructure / IDA financing signed; marine packages are planned, under review, pending, cancelled, or absent from the reviewed plan
approval / Last checkedAustralia / Port infrastructure / A$50 million dredging contract awarded; the federal sea-dumping application remains unresolved ahead of planned September mobilisation
award / Last checkedSweden / Port infrastructure / Dredging contract signed for 2027 start
award / Last checkedIndia / Deep-water ports, dredging and reclamation / The approximately 200-hectare nearshore reclamation and shore-protection EPC package is awarded; as of 15 July 2026, the owner tender page lists the offshore dredging, reclamation and protection-bund HAM package closing on 17 July and the Daman marine-sand investigation closing on 15 July, while no award or AOC is published for either package or for the 10.14-kilometre offshore breakwater
tender / Last checkedBelgium / Port infrastructure / Quay-wall construction and marine works in progress
construction / Last checkedItaly / Ports and coastal protection / 24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active
construction / Last checkedUnited States / Dredging and waterways / Callan Marine 44-foot package awarded; Great Lakes offshore Contract 6 in delivery; final 48-foot inland cut remains separate
construction / Last checkedIraq / Port infrastructure / Core marine assets built; terminal, tunnel, and commercial-operating interfaces remain under verification
construction / Last checkedQatar / Port infrastructure / Owner reports 98% construction; full-system handover pending
construction / Last checkedSweden / Port infrastructure / Quay construction active; port-side dredging awarded; optimized national fairway package in procurement for 2027-2028 delivery
construction / Last checkedTuvalu / Port infrastructure / Nui and Niutao harbour works completed and opened; operating performance and maintenance now under review
completed / Last checkedCurrent research
Brazos Island Harbor Phase 2 is unusually legible at the award-to-field boundary. The owner defines approximately 7 million cubic yards across a 13-mile, 10-foot channel deepening. The federal ledger names Callan Marine and reports USD 109.240 million in current obligations, while an amended navigation notice traces the field sequence from General Marshall and General Bradley to General MacArthur with pipeline routed to confined Placement Area 5B.
Updated
Rayman Builders signed the USD 1.071 million Libertad Outfall dredging contract on 6 October 2023. The Philippines Commission on Audit identifies the same package as DPWH contract 22Z00033, records a PHP 60.833 million contract cost and lists PHP 60.665 million in construction in progress at 31 December 2024. A November-December 2025 World Bank mission reports that all eight DPWH dredging contracts were completed. That supports completed contract status for the group that includes Libertad, but it does not publish this package's measured volume, sediment destination, as-built geometry, hydraulic clearance or DPWH acceptance.
Updated
National Treasury's active award record names KATLANTIC at ZAR 5,466,159, while TNPA's RFP fixes the workfront at a damaged entrance-channel section requiring approximately 1,000 m3 of 50-100 kg rock. Neither source confirms contract signature, notice to proceed, installed quantities or completion.
Updated
USACE's 11 August completion account resolves the most important delivery-chain question at Lock and Dam 9. G&G Steel fabricated the four replacement miter-gate leaves in Alabama over about two years, but it did not perform the reported field installation. St. Paul and Rock Island District maintenance and repair crews completed that work over four July closure days with Rock Island's 500-ton heavy-lift crane The Quad Cities.
Updated
Samoa Ports Authority's July-December 2024 monitoring report placed CHEC's Section 3 breakwater and whole-project completion in December 2026. The later implementation baseline moves the 100-metre breakwater works to mid-July 2027, followed by a one-year defects period. Sections 1 and 2 had June 2026 close-out and handover expectations, but no later signed acceptance certificate was published.
Updated
Los Angeles RAMP displays the USD 27,414,900 opportunity amount on 13 award-participant rows, but the Port of Los Angeles contractor attachment resolves the structure: Manson is the prime and 12 named subcontractors carry bid-stage packages totaling USD 3,331,945, or 12.15% of the bid. Johnson-Peltier's USD 1,530,000 electrical package is the largest lower-tier line. The Port's January 2026 capital report separately records the owner project at 22% construction completion through November 2025.
UpdatedDelivery network
Capital and maintenance dredging contractor / Navigation-channel and berth dredging contractor / Beneficial-use and dredged-material placement contractor
Last checked
Statutory major-port authority / Chennai port owner and public infrastructure client / Navigation channel, berthing and marine traffic administrator
Last checked
Statutory major-port authority / Kandla port owner and public infrastructure client / Port planning, regulation and operations administrator
Last checked
Autonomous-port system planner and administrator / Fishing and recreational port infrastructure owner / Port capital-works and maintenance client
Last checked
Statutory coast-and-parks manager / Port manager for Apollo Bay, Port Campbell and Lorne / Apollo Bay waterway manager and harbour-master function holder
Last checked
Statutory public infrastructure agency / Maritime infrastructure development and maintenance body / Harbour, quay, breakwater and ferry-landing works client
Last checkedSearch the public index for this delivery discipline, compare mapped projects, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.
Search Marine works Open project tracker Open sector guide Review methodology