Sector intelligence

Marine works intelligence

General waterside civil works, marine access, temporary works, quay interfaces, and specialist packages supporting coastal and port programmes.

Projects retain their detailed work segment and may appear in more than one sector when the scope crosses delivery disciplines.

Last checked 247 public projects 272 related publications 168 connected organizations

Coverage focus

Dredging, navigation access and enabling marine packages

Tracker coverage

247 project records connected to this sector.

Publication coverage

272 current analyses and briefs connect through governed project relationships.

Organization coverage

168 public profiles connect through documented project roles.

Project coverage

All current Marine works project records

247 records
Confirmed

Brazos Island Harbor Phase 2 channel deepening

United States / Capital dredging and navigation-channel deepening / USACE lists Phase 2 in construction with new-work dredging continuing toward an FY2026 scheduled completion; final accepted depth, certified quantity and contract completion are unpublished

delivery / Last checked
Confirmed

Port of Felixstowe four ship-to-shore quay cranes

United Kingdom / Container-terminal handling equipment / The Felixstowe Dock and Railway Company selected ZPMC at GBP 43.594 million excluding VAT for four ship-to-shore cranes; the published award and contract records remain pending, with no later signature, delivery or commissioning notice located

award / Last checked
Confirmed

Langstone Coastal Defence Scheme

United Kingdom / Continuous tidal flood and coastal erosion defence with early contractor involvement / Havant Borough Council selected Jackson Civil Engineering for a GBP 14 million excluding-VAT NEC4 coastal-defence contract; the 1 May 2026 award notice still marked the contract pending, while planning officers recommended conditional permission on 25 June and the owner continues to target two April-November construction windows in 2027 and 2028

award / Last checked
Confirmed

Centreville small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Kerr Limited's CAD 18.86 million contract reached its amended 31 December 2025 expiry after 11 amendments; no cited owner record confirms accepted completion, final dredged quantities or reopening

delivery / Last checked
Confirmed

Port 2000 Chatiere protected river access

France / Ports and coastal protection / Terelian and SDI/DEME are constructing the 1,800 metre protection dike; HAROPA reported nearly 800,000 m3 of foundation material placed by 1 June 2026 after a 760,000 m3 weak-silt purge, while channel dredging, dike tie-ins, completion and operating release remain pending

construction / Last checked
Confirmed

Mahout fishing port construction

Oman / Port infrastructure / OMR 36.995 million construction award approved in July 2026; contractor and detailed marine scope remain undisclosed

award / Last checked
Confirmed

Banjul Port fourth expansion and concession delivery

The Gambia / Port infrastructure / Port concession operating and green ferry commissioned; core jetty and container-terminal expansion completion remains unverified

delivery / Last checked
Confirmed

Banana Deep-water Port Phase One

Democratic Republic of the Congo / Deep-water ports and container terminals / Phase-one contract announced with an estimated 24-month term; no current cited record confirms accepted marine works, terminal commissioning, or commercial opening

construction / Last checked
Confirmed

Malaga Port Quay 4 facing rehabilitation

Spain / Submerged masonry quay repair and structural concrete rehabilitation / Malaga Port Authority's rectified tender remains open until 2 September 2026 for a four-week repair of seven damaged areas on Quay 4; the EUR 78,739.06 excluding-VAT budget is a tender baseline and no contractor has been selected

tender / Last checked
Confirmed

Hammond Cove Marina reconstruction

United States / Marinas, pontoons and berthing infrastructure / New York City's 22 January 2026 award notice names Empire Construction and Property Management Group at USD 4,583,648 for X310-117M; the city hazard plan identifies bulkhead, dock and electrical reconstruction, but no cited record establishes contract signing, notice to proceed, mobilisation or completion

award / Last checked
Confirmed

Kalundu Port rehabilitation and modernization works

Democratic Republic of the Congo / Port infrastructure / PFCIGL reported that GETRA-AXOR remobilized from 15 June 2026 and that Kalundu works were progressively resuming; activity then remained at site installation and ground preparation before effective rehabilitation works

construction / Last checked
Confirmed

Port of Montreal Contrecœur Container Terminal

Canada / Port infrastructure / Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access

construction / Last checked
Confirmed

Khalifa Port EGA berth enhancement programme

UAE / Port infrastructure / CHEC EPC delivery and live-berth works reported by two current staff profiles; owner releases confirm the AED 84 million programme but do not name the contractor

construction / Last checked
Confirmed

Libertad Outfall dredging works

Philippines / Dredging / Group completion reported; Libertad closeout remains unpublished.

construction / Last checked
Confirmed

Dakhla Atlantic Port construction

Morocco / Port infrastructure / Construction reported above 60% in June 2026; marine completion, equipment and operating awards remain open

construction / Last checked
Confirmed

Oswego Harbor 2026 breakwater repair phases

United States / Port infrastructure / USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028

award / Last checked
Confirmed

Boskalis SEAWAY 31,000 m³ TSHD

Netherlands / Dredging / Delivered 20 July 2026; deployment unpublished

completed / Last checked
Confirmed

Port of Ndayane Deep-water Port and Container Terminal

Senegal / Deep-water ports and container terminals / DP World reports the major dredging works complete 13 months ahead of schedule; quay and other marine and civil works remain active, while 2028 is a target rather than an accepted opening date

construction / Last checked
Confirmed

Tuas Port Phase 2 reclamation and terminal development

Singapore / Port infrastructure / Phase 2 reclamation stood at 79.5% in December 2025 and its planned six-berth handover remains unverified; the wider Tuas Port passed 25 million TEU in August 2026, but that operating total began with Phase 1

delivery / Last checked
Confirmed

Wesleyville and Brookfield floating-dock reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Granite Management received DFO contract 4500013526 on 23 December 2021 for a two-site floating-dock package; the 2021-22 Public Accounts mark the contract completed, while physical acceptance records remain unpublished

completed / Last checked
Confirmed

South Moose Lake 2025 harbour improvements

Canada / Remote fishing-harbour timber crib wharf and floating offloading dock / Fisheries and Oceans Canada awarded ZheMaak Inc. contract 4500091055 for CAD 220,542 on 8 August 2025; the published seven-month term ended on 27 March 2026, but the reviewed federal record does not publish physical completion, accepted quantities, owner handover or a final account

delivery / Last checked
Confirmed

Port de Grave marginal wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210731/001/PWD on 15 November 2021; CanadaBuys records a CAD 1,763,368 cumulative contract after amendments, and the 2022-23 Public Accounts mark the Port de Grave contract completed

completed / Last checked
Confirmed

Cap-aux-Meules access-channel dredging

Canada / Capital and maintenance dredging for a remote ferry, cargo and fishing port / PSPC awarded contract CW2402077 to Dragage Ocean DS on 1 September 2025; a CNESST filing places the contractor at the Cap-aux-Meules dredging site from a planned 13 October to 12 November 2025, while a 13 May 2026 amendment lifted the published contract total to CAD 6,724,266.72 without disclosing its scope

construction / Last checked
Confirmed

Winterton small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed

completed / Last checked
Confirmed

Snapper Creek State Boat Harbour shoreline protection works

Australia / Port revetment repair and armour-rock placement / Queensland Transport and Main Roads disclosed Contract MSQ25017 with Hunter Contractors Pty Ltd at AUD 1,981,207 on 10 July 2025, and Maritime Safety Queensland announced a 2 September 2025 construction start; no cited official source confirms installed quantities, completion, acceptance or final account

construction / Last checked
Confirmed

Geraldton Port Maximisation marine works

Australia / Port infrastructure / MGN Civil holds the surge-protection breakwater award; wider dredging, berth and tug-harbour packages remain separately unconfirmed

award / Last checked
Confirmed

Veseli nad Moravou marina phase-one expansion

Czechia / Inland marina quay edges, floating fingers, bank protection and utilities / The Czech Waterways Directorate opened 30 new public berths in August 2025 and the Transport Ministry reports the expanded marina operating with capacity for 66 boats in the 2026 season; IDS holds the phase-one works contract, with the highest reviewed official modification snapshot at CZK 86,312,219.98

completed / Last checked
Confirmed

Edmonds North Portwalk Phase II electrification

United States / Marina electrical infrastructure, waterfront site preparation and public realm / The Port of Edmonds Commission unanimously authorized a contract with TRICO Companies LLC on 8 June 2026; the current owner page marks Phase II in progress and estimates work will begin late in 2026

award / Last checked
Confirmed

Skinners Pond wharf 401 copewall rehabilitation

Canada / Fishing harbour wharf, dredging and shore protection / Kildare Construction Ltd. received CAD 1.10 million contract 4500013345 on 23 December 2021 for structure 401; the 15 June 2022 target date is published, but completion and owner acceptance remain unverified

award / Last checked
Confirmed

Saint-Edouard-de-Kent containment-cell reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Christian Larocque Services LTEE received the CAD 347,878.45 construction contract in November 2021; Harbourside Engineering reports the rebuilt dredge-spoil containment cell completed in March 2022

completed / Last checked
Confirmed

Bellingham Shipping Terminal marine infrastructure and dredging

United States / Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities / Port reporting confirms key dock and stormwater upgrades were completed in 2025 and navigation and environmental work advanced; Washington L&I records American Construction's contractor-reported 8 April 2026 work-completed date, but no filed Notice of Completion, owner acceptance, final hydrographic survey, final dredged quantity or final account is evidenced

delivery / Last checked
Confirmed

San Francisco Pier 80 mooring and berthing improvements

United States / Wharf maintenance, fender piles and marine asset renewal / The San Francisco Port Commission adopted Resolution 25-25 on 13 May 2025, authorizing award of Contract 2871 to Manson Construction Co. for USD 5,518,500 plus a USD 551,850 contingency; the cited official record does not confirm the planned notice to proceed, physical progress, substantial completion or acceptance

award / Last checked
Confirmed

Kuwait Mubarak Al-Kabeer Port Phase I completion

Kuwait / Deep-water ports and container terminals / Phase I EPC signed with CCCC; government follow-up continues, while mobilisation and marine construction remain unverified

award / Last checked
Confirmed

Quriyat fishing port sea dock development

Oman / Port infrastructure / 83% complete in August 2025; completion, contractor and acceptance remain unverified

construction / Last checked
Confirmed

Port of Rotterdam Yangtzekanaal widening and quay programme

Netherlands / Port infrastructure / Phase A tug quay delivered; the same consortium has started Phase B, including 1.4 million m3 of sand dredging; Phase C remains a post-2028 package

construction / Last checked
Confirmed

Port of Durban North Bank revetment repairs

South Africa / Port revetment repair and armour-rock placement / South Africa's official procurement release records an active ZAR 5,466,159 award to KATLANTIC for the Port of Durban North Bank revetment repairs; the public record does not provide an award date, executed contract, notice to proceed, physical progress or completion

award / Last checked
Confirmed

Upper Mississippi Lock and Dam 9 miter-gate replacement

United States / Inland navigation lock rehabilitation and hydraulic steel structures / USACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublished

completed / Last checked
Confirmed

Apia Port climate-resilient breakwater and terminal upgrade

Samoa / Port infrastructure / Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate

construction / Last checked
Confirmed

Los Angeles Berths 238-239 Marine Oil Terminal Improvements

United States / MOTEMS wharf replacement, dolphins, fenders and maintenance dredging / The Port of Los Angeles January 2026 CIP report classifies the project in construction and, using actuals through November 2025, records 22% construction completion, a 31 March 2027 forecast finish, USD 39,288,466 projected project cost and USD 6,315,074 spent to date

construction / Last checked
Confirmed

Petaluma River FY2025 maintenance dredging

United States / Port infrastructure / USACE records the FY2025 campaign complete after Dutra's USD 6.272 million dredging award; three reported subawards expose placement fees, DQM and survey support, tug setup and crew boats, while the final accepted quantity and account remain unpublished

completed / Last checked
Confirmed

Toledo Harbor 2026 maintenance dredging

United States / Port infrastructure / USD 5.3 million 2026 task order issued under a USD 11.1 million two-year Ryba contract; the September start remains planned

award / Last checked
Confirmed

CVM Congo River Easydredge 2700XL fleet renewal

Democratic Republic of the Congo / Dredging / Easydredge 2700XL building contract signed; no yard, trial, delivery, acceptance, or Congo River deployment milestone published

delivery / Last checked
Confirmed

Manangareza river-port station rehabilitation

Madagascar / Inland river-port station and passenger-cargo terminal rehabilitation / ECH BTP signed the USD 1,272,815.07 works contract on 28 November 2025; public records also name the design and supervision consultant, but no notice to proceed, mobilisation, measured progress, completion or acceptance has been located

award / Last checked
Confirmed

Dioro riverbank and port-quay rehabilitation

Mali / Inland river-port quay and bank rehabilitation / Two works lots under ML-UGP-PRTD-477915-CW-RFB were signed in December 2025; the April 2026 procurement plan marks the package under implementation, but no lot-specific mobilisation, progress, completion or acceptance record has been published

award / Last checked
Confirmed

Bristol Floating Harbour 2026 maintenance dredging

United Kingdom / Maintenance dredging, floating-harbour navigation and marina access / Bullo Limited holds the GBP 392,500 contract; Bristol notice 36/26 schedules a 10-17 August Baltic Wharf work window beyond the original 26 June contract end

delivery / Last checked
Confirmed

Le Goulet Harbour 2026 maintenance dredging

Canada / Fishing harbour wharf, dredging and shore protection / CanadaBuys solicitation WS5822483507 is open for Le Goulet harbour-basin maintenance dredging and closes 1 September 2026 at 14:00 EDT; no current winner, contract value, quantity, depth, disposal site, plant or delivery contractor is publicly established

tender / Last checked
Confirmed

Lower Yarra River Maintenance Dredging Program

Australia / Urban waterway maintenance dredging, navigation access and in-river material placement / Buying for Victoria records Australasian Marine Associates on a current AUD 1.93985 million contract starting 8 September 2021; Parks Victoria confirms AMA delivered Campaign C in 2024, while the owner programme was reported complete and the next funding cycle remained open

delivery / Last checked
Confirmed

Norfolk Island Cascade Pier emergency remediation works

Norfolk Island / Pier remediation and island freight access / GP Services' AUD 183,041 emergency-remediation period has elapsed without accepted completion evidence; the separate AUD 10 million apron project is in detailed design with Consult Marine, with no construction award or mobilisation published

award / Last checked
Confirmed

Roberts Bank Terminal 2 landmass and wharf

Canada / Port infrastructure / TerraMarine is preferred proponent; contract negotiations, an in-progress Fisheries Act authorization and development work precede any target-price design-build agreement, financial close or mobilisation

design / Last checked
Confirmed

Dunkirk Harbor west breakwater rehabilitation

United States / Port infrastructure / Great Lakes Dock & Materials holds both phases; USACE reports the last 450 feet continuing through November 2026

construction / Last checked
Confirmed

Georgetown Harbor maintenance dredging

United States / Port infrastructure / Southern Dredging's Dredge BRUNSWICK is listed on active 24/7 work in the Bypass and Steel Mill channels through about 31 August 2026

construction / Last checked
Confirmed

Plymouth Mount Batten pontoon replacement

United Kingdom / Marinas, pontoons and berthing infrastructure / Teignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmed

construction / Last checked
Confirmed

Burry Port pontoon floats

United Kingdom / Marinas, pontoons and berthing infrastructure / Solent Marine holds a GBP 72,600 float award.

award / Last checked
Confirmed

Tinian seaport P-940, P-1001 and P-1002 design

United States / Naval and civil seaport wharf, breakwater and harbor-dredging design / MDPAC JV holds a USD 12.616m architect-engineer task order through 31 December 2026 for P-940 wharf improvements, P-1001 breakwater restoration and P-1002 harbor dredging and Finger Pier A removal; 13 named design-chain subaward records total USD 4.055m, while no construction award or mobilisation is evidenced

design / Last checked
Confirmed

NOC Southampton quayside wall and pontoon repairs

United Kingdom / Seawall, quayside and pontoon repair / National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT; the contract period ran from 13 August to 12 September 2025, but no dated completion, acceptance or final-account record has been located

award / Last checked
Confirmed

Ringvaart 2 dredging

Netherlands / Dredging / Award signed; start unverified.

award / Last checked
Confirmed

Fox Island River channel-wall and marginal-wharf reconstruction

Canada / Small-craft-harbour marginal wharf and channel-wall renewal / DFO-SCH's 2026 proposal remains in federal assessment after the public-comment period ended on 22 June 2026; no environmental determination, procurement, award, contractor, mobilisation or construction is evidenced

approval / Last checked
Confirmed

Fox Island River harbour entrance improvement and re-dredging

Canada / Small-craft-harbour entrance dredging and breakwater works / Marine Contractors' CAD 1.499m entrance-improvement contract and R.J.G Construction's separate CAD 1.133m channel re-dredging contract have both reached their published administrative end dates, but no completion certificate, accepted hydrography, final dredged quantity or causal link between the packages is public

delivery / Last checked
Confirmed

P-835 Lima Wharf and Inner Apra Harbor dredging

United States / Naval-wharf and inner-harbor dredging design / MDPAC JV holds the USD 3.335m P-835 design task order, expanded in August 2025 from DD1391 and 15% design into a design-bid-build package and extended in March 2026 to September 2028; no construction award or physical dredging is evidenced

design / Last checked
Confirmed

Cheticamp Jobs Wharf floating-dock reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Superior Contracting's CAD 1.264 million contract ran from 14 October 2022 to 31 March 2023 for an integrated timber-wharf, dredging, breakwater, floating-dock and electrical package; the reviewed federal record does not publish accepted completion, measured quantities or final account

delivery / Last checked
Confirmed

Los Angeles Berths 49-51 Outer Harbor Cruise Terminal Development

United States / Cruise berth rehabilitation, shore power and marine piling / Los Angeles Harbor Commission Resolution 26-10665 approved Shimmick's USD 61,290,400 bid on 6 January 2026, and RAMP records the award on 26 January; the owner's award presentation estimated a March 2026 notice to proceed and January 2029 completion, while the actual NTP, site mobilisation and installed work remain unconfirmed through 8 August 2026

award / Last checked
Confirmed

Hillarys Boat Harbour jetties A, F, G, H and J replacement

Australia / Marinas, pontoons and berthing infrastructure / Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract

completed / Last checked
Confirmed

Fremantle Fishing Boat Harbour Jetty 3 replacement

Australia / Marinas, pontoons and berthing infrastructure / Transport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade Sales

completed / Last checked
Confirmed

King Abdulaziz Naval Base MMSC IOC facilities

Saudi Arabia / Naval base wharf and fleet-support facilities / USAspending records W912ER-23-C-0002 at USD 400,127,768.96 obligated and exercised, with the current performance period ending 8 March 2027 and the latest modification dated 7 May 2026; no public physical-completion or owner-acceptance record is established

construction / Last checked
Confirmed

Sitra Wharf Berths 5 and 6 liquid-cargo enhancement

Bahrain / Liquid-cargo terminal berth enhancement / Bahrain Tender Board's March 2026 monthly report records a BHD 10,987,831 award to NASS Contracting for Sitra Wharf tender T78534; no award date, contract signature, mobilisation or installed work is published

award / Last checked
Confirmed

Swansea Morfa Quay and New Cut Road pontoons

United Kingdom / Marinas, pontoons and berthing infrastructure / Find a Tender notice 073261-2026 records a GBP 411,775.70 excluding-VAT contract with Inland and Coastal Marina Systems UK Ltd signed on 15 July 2026; the active 20 July to 2 October period is not evidence of physical mobilisation

award / Last checked
Confirmed

Maassluis M2 quay-wall replacement and waterfront renewal

Netherlands / Quay-wall replacement and waterfront public-realm renewal / TED notice 542353-2026 records a EUR 7,887,000 contract with De Vries Werkendam B.V. concluded on 4 August 2026; the owner plans physical works from 5 October 2026 to 21 July 2028 and publishes no current mobilisation evidence

award / Last checked
Confirmed

Apollo Bay Harbour seawall construction

Australia / Harbour seawall renewal and coastal asset protection / Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation

award / Last checked
Confirmed

Ouakam fishing-quay rehabilitation

Senegal / Fish landing quay and fisheries value-chain infrastructure / FIDELE SARL's rehabilitation contract was signed 5 February 2025 for an operating export-approved landing facility; no controlled site start, temporary operating setup or physical progress evidence through 8 August 2026

award / Last checked
Confirmed

Fass Boye modern fishing quay

Senegal / Fish landing quay and fisheries value-chain infrastructure / KELIMANE ENTREPRISE's Lot 01 contract was signed 5 February 2025, while a separate replacement relocation-site package remained awaiting execution in the current plan; no controlled main-works start evidence through 8 August 2026

award / Last checked
Confirmed

Cap Skirring modern fishing quay

Senegal / Fish landing quay and fisheries value-chain infrastructure / Official works launch held 24 July 2025 after ETIC's Lot 02 contract was signed 15 January 2025; no controlled later completion or commissioning evidence through 8 August 2026

construction / Last checked
Confirmed

Liwa Fishery Harbour maintenance dredging procurement 2023

Oman / Operating fishing-port maintenance dredging / Oman eTender 441/2023/MAFWR/HQ-36 reached financial evaluation in Q3 2023, then a Recall-1 procedure closed on 19 December 2023; an awardee, value and mobilisation remain undisclosed

tender / Last checked
Confirmed

Liwa (Nabur) Fishery Harbour construction

Oman / Fishing-port breakwaters, dredging, quay and marine infrastructure / Liwa harbour was operating by 2023 after the original Galfar award and 2015-2017 downstream marine works; formal completion, acceptance and final-account records remain unrecovered

completed / Last checked
Confirmed

Bukha Fishery Harbour maintenance, rehabilitation and dredging

Oman / Fishing-port maintenance, rehabilitation and dredging / Masirah Island International identifies active harbour maintenance, rehabilitation and dredging; a 2025 Oman News Agency owner-side report says the port remained under maintenance, with no public completion or acceptance record

construction / Last checked
Confirmed

Dunkirk port cathodic-protection replacement framework

France / Port structures and underwater asset maintenance / Grand Port Maritime de Dunkerque is procuring a six-year single-provider underwater-works framework with a EUR 1.5 million minimum and EUR 5.0 million maximum; bids close at 12:00 on 4 September 2026 and no holder is named

tender / Last checked
Confirmed

Meteghan floating wharf and pile rehabilitation

Canada / Fishing harbour wharf, dredging and shore protection / Dexter holds CAD 4.29 million CW2462474 for floating-dock and pipe-pile replacement, while Connors Diving holds CAD 1.27 million 4500109325 for Wharf 403 pile jackets and concrete repairs; both awards are active but mobilisation and progress are unverified

award / Last checked
Confirmed

Glace Bay small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified

award / Last checked
Confirmed

La Spezia Terminal del Golfo expansion and redevelopment Lot I

Italy / Container and multipurpose terminal quay extension / TED notice 521188-2026 records a 23 July 2026 works contract with a planned RTI led by Dott. Carlo Agnese at EUR 10,868,519.12 for 419 days; notice to proceed, mobilisation, installed quantities and named subcontractors remain unverified

award / Last checked
Confirmed

Larrys River small craft harbour breakwater reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds active CAD 2.75 million contract CW2455209 through 27 November 2026 for rubble-mound breakwater construction at Larrys River; award and scope are confirmed but mobilisation and physical progress are not

delivery / Last checked
Confirmed

Grande-Anse harbour-basin dredging and containment-cell works

Canada / Fishing harbour wharf, dredging and shore protection / Les Entreprises P E C inc holds active CAD 862,270 contract CW2452382 through 31 December 2026 for barge-excavator dredging and containment-cell reconfiguration; earliest site start was 6 July and field progress remains unverified

delivery / Last checked
Confirmed

Sainte-Marie-Sur-Mer structure 401 wharf and breakwater works

Canada / Fishing harbour wharf, dredging and shore protection / L Breau and Sons Ltd holds active CAD 8.75 million contract CW2440554 through 24 August 2027 for structure 401 wharf reconstruction and a new breakwater; mobilisation, measured work and acceptance remain unconfirmed

delivery / Last checked
Confirmed

Colombo West Container Terminal II Western Breakwater Extension Design

Sri Lanka / Deep-water port expansion, breakwaters and reclaimed logistics land / Dohwa-led detailed-design contract awarded in April 2025; SLPA's May 2026 planning document confirms the engineering study but leaves financing, construction procurement and field start open

design / Last checked
Confirmed

Kustlijnzorg South Holland nourishment (31205037)

Netherlands / Beach and foreshore nourishment / Van den Herik signed the EUR 16.302 million contract on 10 March 2026; Rijkswaterstaat schedules Maasvlakte 2 nourishment for September and names Van den Herik with Van der Kamp there, while mobilisation and the parties' commercial relationship remain unverified

award / Last checked
Confirmed

Kustlijnzorg Walcheren beach nourishment (31205036)

Netherlands / Beach and foreshore nourishment / Fa. Gebr. Van der Lee signed the EUR 8.199 million contract on 31 March 2026; the contract is live through 2027, while no public evidence of physical mobilisation, vessel assignment or accepted production was identified by the 7 August 2026 review

award / Last checked
Confirmed

Kustlijnzorg North Holland and Texel nourishment (31205035)

Netherlands / Beach and foreshore nourishment / Boskalis signed the EUR 26.098 million contract on 12 May 2026; Rijkswaterstaat announced Den Helder tidal-channel nourishment from 14 July to mid-October and Julianadorp sinker-pipe removal from 20 July, while measured production and acceptance remain unpublished

construction / Last checked
Confirmed

Ras Hanzir replacement cargo facility

Malta / Cargo-port quay, land reclamation, piling and utilities / Infrastructure Malta is taking replacement works tender IMT008/2025 to 1 October 2026 after terminating predecessor contract IM027/2020; the replacement works package remains unawarded

tender / Last checked
Confirmed

Tumaco port access-channel deepening, Phase I

Colombia / Capital dredging and navigation-channel deepening / SECOP II records contract GN2862-2026 signed with Consorcio Puerto Tumaco II for COP 26.826 billion and eight months, but the public ledger has no start date, invoicing or payment and the separate supervision procurement remains unawarded

award / Last checked
Confirmed

Barranquilla access-channel maintenance dredging

Colombia / Navigation channel maintenance dredging / SECOP II shows contract 0-525-2024 modified to COP 241.685 billion and 31 December 2026 after a 365-day extension; Cormagdalena reported 80.7% execution at 31 March before the later ledger update, while completion and acceptance remain unconfirmed

delivery / Last checked
Confirmed

Petit-Cap structure 403 wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Landco Construction's CAD 3.08 million contract ran from 2 November 2023 to 4 July 2024 for a Berlin-wall marginal wharf, harbour dredging and electrical reinstatement; CanadaBuys does not publish accepted completion or final quantities

delivery / Last checked
Confirmed

Harbour Grace small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Bulldog Contracting received the CAD 7.05 million award on 1 April 2022 for timber-crib wharf, finger-pier, dredging and utility works; the reviewed federal record does not establish the delivery end date, accepted completion or final account

delivery / Last checked
Confirmed

Pugwash small craft harbour floating-dock works

Canada / Fishing harbour wharf, dredging and shore protection / Brian MacGillivary Construction's CAD 516,100 contract ran from 22 November 2023 to 29 March 2024; CanadaBuys confirms the award and amended term but publishes no accepted dredging quantity, dock handover or completion certificate

delivery / Last checked
Confirmed

Townsville MSQ Base wharf fender-pile replacement

Australia / Wharf maintenance, fender piles and marine asset renewal / Queensland TMR awarded MSQ26005 to Pacific Marine Group on 11 May 2026 for AUD 423,687; no public milestone establishes mobilisation, pile quantities, installation method, completion or acceptance

award / Last checked
Confirmed

Dar es Salaam channel deepening and berth concrete repairs

Tanzania / Capital dredging, berth reconstruction and concrete remediation / Channel and berth civil packages were reported complete in 2024 and the port publishes operational depths; CHEC's separate USD 15.70 million 2025 concrete-repair contract has no cited completion or acceptance evidence

construction / Last checked
Confirmed

Brazos Island Harbor FY24 entrance and jetty maintenance dredging

United States / Maintenance dredging and operating-port access / Great Lakes' Padre Island campaign was publicly scheduled from 20 October to 16 November 2024; an April 2025 final-quantity modification reduced the current federal obligation from USD 8.799 million to USD 7.456 million, while accepted quantities and formal closeout remain unpublished

delivery / Last checked
Confirmed

Sabine-Neches Contract 6 offshore channel deepening

United States / Dredging and waterways / Great Lakes holds the USD 219.108 million Contract 6 obligation; its USD 235.423 million potential value, April 2027 owner finish, production, assigned fleet and lower tiers remain to be confirmed

delivery / Last checked
Confirmed

Port Seine-Metropole Ouest phase-one river-port construction

France / Inland-port basin excavation, sheet-pile quays, pile-supported jetties and multimodal access / HAROPA PORT reports phase-one construction in execution: earthworks, a retaining wall and conveyor loading were active in summer 2026, South Quay sheet-pile installation had started, and piling for the west then east jetties was scheduled from the week of 6 July

construction / Last checked
Confirmed

Salcombe-Kingsbridge estuary 2026 maintenance dredging

United Kingdom / Maintenance dredging and operating-port access / South Hams District Council signed Van Oord UK Limited on 11 March 2026 for GBP 101,600 excluding VAT; water injection dredging was the tendered expectation for Batson Creek, Lincombe and Kingsbridge, but no public mobilisation, post-dredge survey or acceptance record has been located

award / Last checked
Confirmed

Bridgetown Port Sugar Berth seawall and revetment repair

Barbados / Port infrastructure / World Bank contract record 1881500 names C. O. Williams Construction Limited at USD 3.338 million, but the public procurement chronology does not reconcile and no dated mobilisation, progress or completion record has been located

award / Last checked
Confirmed

Nafanua Port resilience improvement

Tonga / Port infrastructure / China Jiangsu International holds the signed USD 4.803 million MOI-WK2-13 award; notice to proceed, mobilisation and physical works remain publicly unconfirmed

award / Last checked
Confirmed

Boulogne-sur-Mer-Calais maintenance dredging framework

France / Dredging / Region Hauts-de-France concluded contract 202613951 with SODRANORD on 24 February 2026 for a purchase-order maintenance dredging framework; the EUR 23 million figure is the four-year maximum ceiling, while the first call-off, 2026 quantity and mobilisation remain unconfirmed

award / Last checked
Confirmed

Preah Sihanouk Marine Fisheries Inspectorate boat mooring and jetty

Cambodia / Marine infrastructure / Taing Cheng Oing Construction & Import Export signed package SCMFP FiA/CW-03 on 9 March 2026; ADB reports a financed amount of 472,336.05 without currency or full contract value, and mobilisation or physical start is not independently confirmed

award / Last checked
Confirmed

Callao access-channel and inner-roadstead maintenance dredging

Peru / Maintenance dredging and operating-port access / APN started the access-channel and inner-roadstead campaign on 20 December 2025; a Jan De Nul post-dredging environmental report covers January 2026 monitoring, while owner acceptance, as-built hydrography and final account remain unverified

commissioning / Last checked
Confirmed

Nanumaga and Nanumea climate-resilient small-boat harbors

Tuvalu / Ports and coastal protection / Hall Civil Contracting signed the USD 62.552 million design-build contract on 21 July 2025; the latest cited mission set August 2027 and January 2028 completion targets for Nanumaga and Nanumea, but no cited source confirms physical mobilisation or current progress

award / Last checked
Confirmed

Rumonge Port EPC and related-services package

Burundi / Port infrastructure / World Bank contract data records a USD 26.453 million EPC works contract signed with China Civil Engineering Construction Corporation on 27 July 2026; no cited source confirms notice to proceed, mobilisation or physical construction

award / Last checked
Confirmed

Santoña North Basin fishing-quay structural repair

Spain / Piled fishing-quay concrete rehabilitation and metal fender renewal / Cantabria formalized the EUR 2,486,545.15 excluding-VAT works contract with the Cuevas Gestión de Obras-COMSA UTE on 9 July 2026; the signed contract requires a viable setting-out check before the 24-month execution period starts, while the setting-out act, site mobilisation, monthly production and lower-tier appointments remain unpublished

award / Last checked
Confirmed

Moss Landing Harbor jetty repair and maintenance dredging

United States / Breakwater armour repair, access dredging and nearshore placement / Ahtna Infrastructure & Technologies held the USD 16,037,425 current-obligation contract for Moss Landing Harbor dredging and jetty repair; the US Coast Guard published 2025 field-work windows and USACE published August-September post-dredge surveys, but the 23 January 2026 contract end does not establish final quantity, jetty acceptance, completion or final account

construction / Last checked
Confirmed

Warrawong Parklands Kully Bay seawall reconstruction

Australia / Foreshore seawall and rip-rap protection / Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence

construction / Last checked
Confirmed

Castletownbere small craft harbour piling and utilities

Ireland / Fishery harbour piling, civil works and marine utilities / TED published the EUR 1.2498795 million Sorensen award on 5 August 2026 and records contract conclusion on 22 June; no project-specific mobilisation, commencement or subcontractor notice has been published

award / Last checked
Confirmed

Harwich Haven maintenance dredging 2026-2031

United Kingdom / Maintenance dredging, beneficial use and dredging technology / GBP 100m award notice names Suffolk Dredging LLP for a five-year base term; a contract-details notice, reconciled extension limit and attribution of 2026 field activity remain unconfirmed

award / Last checked
Confirmed

Port de Plaisance du Grand Large marine works

France / Marinas, pontoons and berthing infrastructure / SPAD concluded three separate Grand Large marina works contracts on 30 June 2026 with Eiffage Travaux Maritimes et Fluviaux, Atlantic Marine and Ramery Travaux Publics; each lot carries a 24-month planned period, but no dated notice to proceed or field mobilisation has been located

award / Last checked
Confirmed

Port de l'Ayguade du Levant Ro-Ro quay

France / Ro-Ro berth and island freight access / Métropole Toulon Provence Méditerranée concluded contract 98RL25 with Océlian and TP Spada at EUR 2,104,311.99 on 20 August 2025 after an earlier procedure ended without an award; no dated mobilisation or completion record has been located

award / Last checked
Confirmed

Cap-des-Caissie small craft harbour upgrade

Canada / Fishing harbour wharf, dredging and shore protection / Mskikue'j Enterprises holds the CAD 5.09 million wharf and shore-protection contract through March 2027; the separate 2025 dredging and containment-cell contract reached its stated expiry without a public completion or measured-quantity record

award / Last checked
Confirmed

New Woodman Point Ammo Jetty

Australia / Marine infrastructure / Advanteering Civil Engineers has completed detailed design and started early off-site construction under DOT413022; on-site work is planned from spring 2026 but no dated mobilisation evidence has been published

construction / Last checked
Confirmed

Woodman Point western boat ramp and Fremantle Jetty 1 renewals

Australia / Marinas, pontoons and berthing infrastructure / Jetty and Marine Constructions holds one design-and-construct contract covering the Woodman Point western boat ramp and Fremantle Fishing Boat Harbour Jetty 1; Woodman Point field works began under a 27 July 2026 closure, while a dated Fremantle mobilisation record has not been published

construction / Last checked
Confirmed

Dunkirk Braek submerged sand-discharge pipeline replacement

France / Coastal protection and dredged-sand reuse / Baggerbedrijf de Boer holds the EUR 1.720365 million replacement contract concluded on 13 January 2025; the planned 31 May 2025 in-service deadline has passed, while physical completion, acceptance and downstream packages remain unverified

award / Last checked
Confirmed

Me-Mel Goat Island Western Broadside Wharf repair

Australia / Port infrastructure / Western Broadside Wharf, adjacent seawall and access-pontoon repairs are underway under two NSW contracts through August and September 2026; the published notices name Polaris Marine Constructions and Clement Marine Constructions but do not disclose their exact package split

construction / Last checked
Confirmed

Pearl Harbor Wharf V5 mooring-buoy installation

United States / Port infrastructure / Oceanetics holds the USD 1.378 million Navy task order through 11 September 2026; two reported subawards identify charter support and Ocean Guard buoy supply, while field installation and acceptance remain unverified

award / Last checked
Confirmed

Dhalkut Port management, operation and development framework

Oman / Small-port commercial activation, maintenance, dredging and berth readiness / A three-year development, management and operation framework was signed with Abu Sultan Enterprises in December 2025; the planned handover for maintenance and simple operations, physical marine works, capital programme and current operating state are not publicly confirmed

planning / Last checked
Confirmed

Dana Point Harbor breakwater repair and access dredging

United States / Breakwater armour repair, access dredging and nearshore placement / Curtin Maritime holds the USD 4.89 million USACE award for breakwater repair and approximately 45,000 yd3 of access dredging; owner and award sources reviewed do not confirm mobilisation or construction progress

award / Last checked
Confirmed

Yorkeys Knob boating facility

Australia / Recreational harbour, breakwaters, dredging and boat-launch infrastructure / The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works

completed / Last checked
Confirmed

St. Lawrence fishing harbour wharf reconstruction

Canada / Fishing harbour timber-wharf reconstruction / R.J.G. Construction holds the CAD 3.02 million wharf-reconstruction contract; the stated contract period ended in April 2026, but completion and acceptance are not publicly confirmed

construction / Last checked
Confirmed

Elizabeth Harbour marine redevelopment

Jersey / Ferry-terminal marine works, dredging and demolition / Final design and planning-condition discharge are evidenced; construction was scheduled for autumn 2026, while Stage Two authorization, dredger or piling mobilisation and physical works start remain unpublished

design / Last checked
Confirmed

Folkestone to Hythe beach management works 2025-2030

United Kingdom / Shingle recycling, beach regrading and coastal flood defence / Chunnel holds the signed beach-management contract; the council reported a 100,000-tonne spring 2026 campaign under way and an April purchase order names Chunnel, while measured completion and profile acceptance remain unpublished

delivery / Last checked
Confirmed

Port of Workington maintenance dredging framework 2026-2030

United Kingdom / Maintenance dredging and operating-port access / Four-year framework awarded to Boskalis Westminster, Dutch Dredging and Van den Herik; the first mini-competition, call-off, assigned vessel, dredged quantity and acceptance remain unconfirmed

award / Last checked
Confirmed

London Gateway C2526 maintenance dredging

United Kingdom / Maintenance dredging and operating-port access / Jan De Nul is the selected supplier under a GBP 57 million award decision; the latest notice estimates a 6 January 2026 to 30 December 2027 contract period, while signature, mobilisation and physical production remain unconfirmed

award / Last checked
Confirmed

Bangladesh WD17 Fish Landing Stations and Markets

Bangladesh / Port infrastructure / World Bank completion reporting confirms three fish landing stations and two fish markets completed by project close on 28 November 2025; five other sites in the original 10-site package could not start because of land-tenure disputes

completed / Last checked
Confirmed

Kidongo Fish Landing Site

Kenya / Port infrastructure / Pristim Supply received the USD 1.355m contract on 11 June 2024; KEMFSED recorded the October 2024 construction launch and published a dated active-workfront photograph, but no completion evidence

construction / Last checked
Confirmed

Kilifi Central Fish Landing Site

Kenya / Port infrastructure / Procost Ideas holds the USD 2.128m contract signed on 11 June 2024; an official November 2024 mission inspected the workfront and reported landing-site works advancing, without a site-specific percentage or completion record

construction / Last checked
Confirmed

Mokowe Fish Landing Site

Kenya / Port infrastructure / Gesken Enterprises holds the USD 1.852m contract signed on 11 June 2024; public sources define a jetty and land-reclamation workfront but do not confirm site-specific mobilisation, completion or acceptance

award / Last checked
Confirmed

Kipini Fish Landing Site

Kenya / Port infrastructure / Toddy Civil Engineering received the USD 1.174m works contract on 11 June 2024 and KEMFSED recorded the October 2024 groundbreaking; no later completion or acceptance evidence has been published

construction / Last checked
Confirmed

Duqm Port Commercial Terminal and Operational Zone IP2

Oman / Port infrastructure / Serka-MSF completed the commercial-terminal fit-out in December 2020; the port is operational, while AIIB's 2025 review says throughput and revenue remain below original forecasts

completed / Last checked
Confirmed

Arctic Bay Small Craft Harbour

Canada / Port infrastructure / Pilitak Enterprises holds the CAD 77.04m construction contract through 7 May 2030; DFO plans construction activity in 2026-27, while current public sources provide no marine mobilisation evidence

construction / Last checked
Confirmed

Sidmouth and East Beach coastal defence scheme

United Kingdom / Two-stage coastal flood and erosion defence, beach recharge and offshore rock works / East Devon selected Boskalis Westminster on 30 June 2026 for a GBP 18.911242 million two-stage NEC4 Option C contract; the 6 July notice still marked the award and contract pending, with standstill to 16 July and future signature scheduled for 17 July, and no later contract-details notice, Stage 1 start or construction commitment is yet published

award / Last checked
Confirmed

Albert Pier and St Helier Marina berthing upgrades

Jersey / Marinas, pontoons and berthing infrastructure / Albert Pier's final berthing stage was complete by 6 April 2022 and St Helier Marina's refurbishment by May 2022; Ports of Jersey subsequently confirmed the marina works were on schedule and the combined capacity benefits were in use

completed / Last checked
Confirmed

Port of Santos 16 m channel deepening

Brazil / Port infrastructure / Jan De Nul contract signed on 12 June 2026; official mobilisation, production and acceptance evidence remain ahead

award / Last checked
Confirmed

Hunan Inland Waterway Green Port programme: Daorenji, Songyanghu III and Songmu II

China / Inland-waterway green-port programme, open-piled bulk and general-cargo berths / Daorenji's main marine structure was reported complete in July 2026 with equipment installation and commissioning next; Songyanghu III moved from 1,556 precast deck panels into field installation in January 2026; no current Phase II construction evidence has been found for Songmu. AIIB still lists the proposed sovereign financing as Proposed

construction / Last checked
Confirmed

Frioul East breakwater rehabilitation and rock spur

France / Historic rubble-mound breakwater rehabilitation and island-port protection / Contract Z250608F00 was concluded on 2 February 2026 with an Océlian-led five-company group for EUR 19.589919 million; the owner reports that the overall rehabilitation programme continues in 2026, while main-contract mobilisation, placed rock, accepted sections and downstream subcontract awards remain unpublished

award / Last checked
Confirmed

Normandy ports maintenance dredging framework 2026-2029

France / Maintenance dredging and operating-port access / Eight call-off lots were concluded on 12 November 2025 for a four-year maximum framework beginning in 2026; the award chain is confirmed, while the first 2026 call-off, vessel mobilisation, measured quantity and port acceptance remain unpublished

award / Last checked
Confirmed

Ploce New Bulk Cargo Terminal

Croatia / Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems / Civil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacity

completed / Last checked
Confirmed

Gdynia Outer Port protective breakwaters

Poland / Caisson breakwaters and port access infrastructure / The May 2026 building permit has moved the design-build contract into principal in-water works; the first reinforced-concrete caisson was launched and towed toward its placement position in July 2026, with the remaining 48 caissons and breakwater systems still to be delivered

construction / Last checked
Confirmed

Jorf Lasfar Multipurpose Terminal Quay Extension

Morocco / Multipurpose berth extension, block quay, mooring dolphin, access bridge and terminal equipment modernisation / Marsa Maroc says the berth-front extension was launched and remained part of its active 2025 investment programme. Execution-design evidence identifies two quay extensions and a mooring dolphin; no owner acceptance or completed operating release has been published

construction / Last checked
Confirmed

Casablanca Multipurpose Terminal Quay Deepening

Morocco / Brownfield quay strengthening, retaining structure, micropiles, scour protection and capital dredging / Works started on 1 October 2024. Marsa Maroc reported a first 230-metre section commissioned at -12 m, while the published delivery programme continues toward 530 metres of deepened quay plus transition zones by 2028; the civil-works award is confirmed but the contractor remains publicly unnamed

construction / Last checked
Confirmed

Poti Sea Port Berth 14 Rehabilitation

Georgia / Container berth rehabilitation, dredging, quay-top renewal and terminal equipment / EBRD lists Phase 1 as Completed, and a TRACECA technical record says Berth 14 was rehabilitated in 2009 for 1,000-TEU feeder vessels; the exact acceptance date, as-built dredging quantity and depth, delivery contractor and final account remain publicly unresolved

completed / Last checked
Confirmed

Saba Black Rocks Harbor and Fort Bay improvement works

Caribbean Netherlands / Hurricane-resilient harbor, breakwater, dredging, quay and marina works / Public Entity Saba reported steady construction progress on 10 May 2026, including breakwater works and Xbloc arrivals, with additional units being produced in Sint Eustatius. Dredging and excavation were active in March 2026, but marine completion, harbor handover, Fort Bay close-out and operational opening remain unconfirmed.

construction / Last checked
Confirmed

Mo i Rana entrance and Langneset deep-water quay

Norway / Deep-water quay, fairway dredging, contaminated-sediment containment and navigation works / Kystverket reported the Langneset quay in its finishing phase on 29 June 2026, with concrete works nearing completion and technical installations scheduled through summer and autumn; completion and an official opening are planned for autumn 2026, but handover, acceptance and operation remain unconfirmed

construction / Last checked
Confirmed

Galati Multimodal Platform Stage I quay works

Romania / Inland-port quay, dredging, basin infill and intermodal berth works / TED published a further contract modification on 27 May 2026, extending the recorded execution duration by 4 months and 23 days and reducing the stated contract value by RON 1,270.26; the latest owner progress figure located is 62.04% at 30 June 2025, and no completion or acceptance record has been published

construction / Last checked
Confirmed

Marsaxlokk fishing-port fairway dredging

Malta / Fishing-port fairway dredging and beneficial reuse / Transport Malta described the Marsaxlokk works as ongoing on 26 June 2026; the original navigation notice ran to 31 July, but no public final hydrographic survey, accepted quantity, completion certificate or final account was located by 2 August

construction / Last checked
Confirmed

Saint-Malo Terminal du Naye Lot 2 marine works

France / Ferry-terminal marine works, dredging and demolition / Région Bretagne reported one of the two old lock-guide structures under demolition on 1 April 2026 after the 270-tonne Ro-Ro ramp was removed in December 2025; the new reinforced-concrete guide caissons and maintenance dredging remain inside the two-year Lot 2 mission, with no owner acceptance published

construction / Last checked
Confirmed

Höfn Grynnslin 2025 maintenance dredging

Iceland / Maintenance dredging and operating-port access / Jan De Nul confirms that trailing suction hopper dredger Tristão da Cunha deepened the Höfn access channel between January and February 2025; the measured quantity and post-dredge acceptance remain unpublished, and a separate Boskalis contract now covers 2026-2028

completed / Last checked
Confirmed

Killybegs Smooth Point breasting dolphins and shore power

Ireland / Fishery harbour berthing, marine piling and shore power / Sorensen reported all 24 dolphin piles installed in August 2025; the government project page published the following month still described the works as ongoing with substantial completion due in Q3 2025, and DAFM has not published a later handover record

construction / Last checked
Confirmed

Cabo Verde Porto Ingles and Palmeira Ports Modernisation Programme

Cabo Verde / Port infrastructure / Porto Ingles marine works were inaugurated on 7 September 2022 and later received a final price-revision authorization; Palmeira's landside package was awarded to GRINER / Armando Cunha Cabo Verde in July 2024, with no public completion or acceptance record identified by 2 August 2026

construction / Last checked
Confirmed

Dublin Port Marine Works Framework and Berth 29

Ireland / Port infrastructure / Single-party framework active with Murphy International; Berth 29 was handed over in 2024, Murphy reports 21 call-offs delivered during 2025, and owner confirmation of the contractor-stated July 2026 completion target for Berths 30/31 and McCairns Yard has not been identified

construction / Last checked
Confirmed

Aktau Port Berths 3 and 12 Modernisation

Kazakhstan / Port infrastructure / Berths 3 and 12 design-build tender closed at first stage on 17 April 2026; construction-supervision tender remains open to 28 August 2026, with no works award or dredging start publicly confirmed

tender / Last checked
Confirmed

Husøy Fishing Port Deepening

Norway / Dredging / Kystverket's latest dated update records blasting complete and about 26,000 solid cubic metres of clean material dredged by 21 April 2026; the owner page says work remains in progress toward December 2026 completion

construction / Last checked
Confirmed

Inis Oírr Pier Improvement Project

Ireland / Port infrastructure / The construction contract started on 24 September 2025 and Marine Notice 23/2026 records Ward & Burke commencing the two-year marine works; no later completed work package has been published

construction / Last checked
Confirmed

Port Atlantique La Rochelle Chef de Baie 4 terminal

France / Port infrastructure / Quay construction and the four-hectare yard remain the latest official delivery state; handover to operator AMLP was targeted for the second half of 2026 but has not been published

construction / Last checked
Confirmed

Fehmarnbelt Fixed Link Immersed Tunnel

Denmark / Germany / Immersed tunnels and marine crossings / Third tunnel element immersed and connected on 1 August 2026; protection, serial immersion, systems integration, and a two-stage road-then-rail opening remain active

construction / Last checked
Confirmed

Busan New Port West Container Terminal Phase 2-6

South Korea / Deep-water ports and automated container terminals / BPA completed the 23-caisson substructure in August 2024 and is advancing superstructure and automated-equipment packages toward an October 2027 completion and second-half 2027 opening target

construction / Last checked
Confirmed

Thessaloniki Port Pier 6 expansion

Greece / Container terminal expansion, quay construction and dredging / ThPA signed the EUR 195.6 million METKA-TEKAL construction contract in November 2025 and installed the first of 21 quay caissons in July 2026; the second caisson was under construction at publication

construction / Last checked
Confirmed

Port of Aberdeen 2026-2028 maintenance dredging

United Kingdom / Maintenance dredging and operating-port access / Port of Aberdeen awarded Boskalis Westminster a three-year contract for annual North and South Harbour campaigns in 2026-2028; the 2026 campaign was scheduled from March with Freeway and MTS Valour, but no accepted campaign-completion record has been published

award / Last checked
Confirmed

Oslo Kneppeskjaer East quay replacement and expansion

Norway / Multipurpose quays, dredging and carbon-logistics infrastructure / Repstad Anlegg began works in August 2025; demolition, dredging and subsea blasting preceded a 99-pile quay-foundation programme scheduled from March to July 2026

construction / Last checked
Confirmed

London Gateway Berth 5 quay and automated yard

United Kingdom / Deep-water ports and automated container terminals / Port of London Authority reported the 430-metre Berth 5 quay extension complete by 1 August 2026 while further retaining-wall piling continued toward the Berth 6 interface; the separately contracted ten-module automated yard remains on a contractor-reported programme to March 2027

construction / Last checked
Confirmed

Port of Tanjung Pelepas Berth Zero

Malaysia / Deep-water ports and container terminals / Malaysia Marine Department notices documented Package 1 and Package 2 work vessels on site from January 2026; PTP is delivering a 360-metre berth, dredging, reclamation, yard works and four quay cranes toward commissioning by 2028

construction / Last checked
Confirmed

Noatum Ports Pointe-Noire Terminal

Republic of the Congo / Deep-water ports and container terminals / AD Ports Group awarded two marine and topside contracts to the MAR Contracting-MBTP joint venture and a crane contract to ZPMC on 18 May 2026; the 420-metre terminal is expected to be built over approximately two years

award / Last checked
Confirmed

Congo Terminal East Mole expansion

Republic of the Congo / Deep-water ports, dredging and multipurpose terminals / Congo Terminal reported 400 metres of the planned 750-metre quay complete by 6 July 2026 after all 558 steel piles were driven; dredging and electric-terminal integration remain active toward the 2027 delivery target

construction / Last checked
Confirmed

Tema Port Terminal 3 Phase 2 expansion

Ghana / Deep-water ports and container terminals / Eiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021

completed / Last checked
Confirmed

Colombo West International Terminal

Sri Lanka / Deep-water ports and automated container terminals / Phase 1 has operated since April 2025 and handled one million TEU in its first year; the 1,400-metre quay was complete by March 2026 while Phase 2 crane deployment and full-terminal construction continue

construction / Last checked
Confirmed

Puerto Antioquia multipurpose deep-water terminal

Colombia / Deep-water ports, dredging and multipurpose terminals / Commercial operations began on 5 February 2026 after four controlled vessel trials; the operator's current port-status ledger shows repeat container, breakbulk and refrigerated calls through July 2026

completed / Last checked
Confirmed

San Antonio Puerto Exterior common marine works

Chile / Deep-water ports, dredging and reclamation / Environmental approval was granted on 26 May 2026; six bidders or consortia are prequalified for the common marine-works tender, but no construction award has been announced

tender / Last checked
Confirmed

Baltic Hub T3 deep-water container terminal

Poland / Deep-water ports and container terminals / Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation

completed / Last checked
Confirmed

Mombasa SEZ DK1 port and jacket quay

Kenya / Port infrastructure / TOA's Package 1 is in construction; KPA reports confirm quay and trestle foundation dredging, while channel, basin, jacket installation and accepted quantities remain open

construction / Last checked
Confirmed

Sagar-Eastern Channel capital dredging

India / Port infrastructure / SMPK completed a non-binding global market EOI for phased capital dredging; a formal RFQ, works award and dredging contractor are not verified

tender / Last checked
Confirmed

Kandla Cargo Berths No. 1-6 upgrade

India / Port infrastructure / DPA is assessing berth-wide repair, strengthening or replacement for an intended EPC package; no expanded-consultant award, EPC tender or works contractor is verified

design / Last checked
Confirmed

Kandla Multipurpose Cargo Berth No. 17

India / Port infrastructure / DPR work started in March 2025; no construction RFP, PPP award, concessionaire or works contractor is verified

design / Last checked
Confirmed

Chennai Port Berth 19A North Quay reconstruction

India / Port infrastructure / Technical audit and detailed engineering are commissioned through 31 December 2027; no construction tender, award or works contractor is verified

design / Last checked
Confirmed

Daba fishing port development

Oman / Port infrastructure / 75% complete in June 2024 with some facilities operating; full completion and formal opening remain unverified

commissioning / Last checked
Confirmed

Masirah multipurpose fishing port

Oman / Port infrastructure / OMR 28.612 million design-and-build award confirmed; current construction progress and marine subcontract chain remain partly undisclosed

construction / Last checked
Confirmed

New Haven Harbor improvement dredging

United States / Dredging and waterways / Bid abstract posted 20 July 2026; four bids opened and Great Lakes submitted the lowest total at USD 69.469 million; no award or notice to proceed posted

evaluation / Last checked
Confirmed

NOAA Newport MOC-P maintenance dredging

United States / Dredging / Six timely bids are publicly tabulated; no award, permit issuance, notice to proceed or mobilisation has been announced

evaluation / Last checked
Confirmed

Vermilion Harbor East Pier repair

United States / Port infrastructure / USACE officially completed the East Pier repair on 24 July 2026 after rebuilding 900 feet of the 1,333-foot structure

completed / Last checked
Confirmed

Norfolk Island Kingston Pier channel and repair works

Norfolk Island / Dredging and waterways / Rock revetment contractor appointed; the separate channel-dredging and pier-repair package was released to tender on 14 May 2026

tender / Last checked
Confirmed

New Zealand regional-port dredging barge

New Zealand / Dredging / NZD 8 million of government co-funding confirmed; designer, shipyard, build contract and first port assignment not disclosed

planning / Last checked
Confirmed

Redwood City Channel FY26 maintenance dredging

United States / Dredging and waterways / HME Construction under contract; 24/7 clamshell dredging and dump-scow operations notified for July 2026

construction / Last checked
Confirmed

Zeevonk phase 1 foundation installation

Netherlands / Offshore wind foundations / DEME holds the transport and installation contract for 69 monopile foundations; offshore mobilisation has not been announced

award / Last checked
Confirmed

Port of Cotonou Terminal 5 bulk terminal

Benin / Port infrastructure / The port authority reports 69% physical progress and 72% overall progress, while its published 2021-2024 delivery period is no longer current

construction / Last checked
Confirmed

Damietta Alliance Container Terminal (Tahya Misr 1)

Egypt / Deep-water ports and container terminals / Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity

commissioning / Last checked
Confirmed

Can Gio International Transshipment Port

Vietnam / Deep-water ports and container terminals / Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced

approval / Last checked
Confirmed

Itajaí-Mirim flood-channel widening and dredging

Brazil / Dredging and waterways / World Bank project is Active and Board Approved; the April 2026 procurement plan omits the Itajaí-Mirim main works package

approval / Last checked
Confirmed

Port Mansfield Channel 2026 maintenance dredging

United States / Dredging and waterways / Callan Marine dredging has reached the Gulf Intracoastal Waterway junction; the Navigation District says the next work front is the harbor and turning basin

construction / Last checked
Confirmed

Richmond Inner Harbor FY26 maintenance dredging

United States / Port infrastructure / Updated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recorded

tender / Last checked
Confirmed

Bangladesh Bay Terminal marine infrastructure

Bangladesh / Port infrastructure / IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started

design / Last checked
Confirmed

Port Douglas Boat Harbour 2026 maintenance dredging

Australia / Port infrastructure / Owner-defined cutter-suction campaign scheduled from July to October 2026; contractor and mobilisation remain unconfirmed

approval / Last checked
Confirmed

Nauru Aiwo Port climate-resilient redevelopment

Nauru / Port infrastructure / ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items

construction / Last checked
Confirmed

Patimban Port Phase 1-2 expansion

Indonesia / Port infrastructure / Phase 1-1 is completed and partly operating; Package 5 car-terminal and Package 6 container-terminal works remained active through June 2025; Package 7 construction lacks a current owner or contractor mobilisation date

construction / Last checked
Confirmed

Southampton Channel Deepening capital dredge

United Kingdom / Dredging / Marine licence MLA/2026/00178 remains submitted and open for consultation; the principal-contractor participation stage closed on 6 February 2026 and no award notice is published in the reviewed procurement family

approval / Last checked
Confirmed

Kamarajar Port Capital Dredging Phase VI

India / Dredging / The Government of India reports Phase VI complete and Kamarajar operating at 18.0 metres draft; the post-dredge survey sheet and a first fully laden Capesize call are not published

completed / Last checked
Confirmed

Nigeria Snake Island Container Terminal concession and EPC

Nigeria / Deep-water ports and container terminals / MSC signed a 45-year sub-concession and finalized the ITB/DEME EPC on 11 March 2026; the reviewed project sources do not record mobilisation

award / Last checked
Confirmed

Dublin Port MP2 Berths 52 and 53 marine construction

Ireland / Port infrastructure / Marine construction is active; the 2026 harbour notice keeps the buoyed work zone in place through January 2027, while berth acceptance and service release remain open

construction / Last checked
Confirmed

Ardersier Port Phase 2 dredging procurement

United Kingdom / Port infrastructure / PQQ closed on 1 May 2026; no shortlist, ITT or award notice is present in the reviewed public chain

prequalification / Last checked
Confirmed

Rocky River Harbor 2026 maintenance dredging

United States / Port infrastructure / Mechanical dredging began in late May 2026 and is scheduled to continue through August

construction / Last checked
Confirmed

DEME next-generation 22,000 m³ TSHD

Belgium / Dredging / 22,000 m³ TSHD ordered; China hull build, Singapore completion, trials, and 2029 delivery remain pending

delivery / Last checked
Confirmed

UK Navy Future Dredging Contract

United Kingdom / Dredging / Award decision published to Boskalis Westminster; contract signature and start not evidenced

award / Last checked
Confirmed

Port of Progreso expansion dredging and north-platform procurement

Mexico / Dredging / Initial state dredging phase completed and a separate private berth stage is active; the federal 40 ha north-platform construction-dredging tender was declared void on 8 July 2026, with no rebid confirmed

tender / Last checked
Confirmed

Paranaguá access channel dredging concession

Brazil / Dredging / Concession signed; 1 August operating transition remains scheduled, with the 13.3-metre baseline still controlling

mobilisation / Last checked
Confirmed

Ramayapatnam Port capital deepening works

India / Port infrastructure / Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed

award / Last checked
Confirmed

Westport Kwinana container port and marine infrastructure

Australia / Port infrastructure / Marine reference design, investigations, environmental-review preparation, and construction planning active; Westport Bill remains before Parliament

design / Last checked
Confirmed

Port Hedland Zone 5 Bypass Channel

Australia / Port infrastructure / A$50 million dredging contract awarded; the federal sea-dumping application remains unresolved ahead of planned September mobilisation

award / Last checked
Confirmed

Vadhvan Greenfield Deep-draft Port

India / Deep-water ports, dredging and reclamation / The approximately 200-hectare nearshore reclamation and shore-protection EPC package is awarded; as of 15 July 2026, the owner tender page lists the offshore dredging, reclamation and protection-bund HAM package closing on 17 July and the Daman marine-sand investigation closing on 15 July, while no award or AOC is published for either package or for the 10.14-kilometre offshore breakwater

tender / Last checked
Confirmed

Genoa New Breakwater

Italy / Ports and coastal protection / 24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active

construction / Last checked
Confirmed

Sabine-Neches Waterway Channel Improvement Project

United States / Dredging and waterways / Callan Marine 44-foot package awarded; Great Lakes offshore Contract 6 in delivery; final 48-foot inland cut remains separate

construction / Last checked
Confirmed

Skandia Gateway fairway and quay deepening

Sweden / Port infrastructure / Quay construction active; port-side dredging awarded; optimized national fairway package in procurement for 2027-2028 delivery

construction / Last checked

Current research

Latest publications connected to this sector

6 shown / 272 current
Engineering visualization of Brazos Island Harbor pipeline dredging, with a cutter suction dredge, survey launch and floating pipeline operating in the marked channel
Brief / Confirmed

Brazos Phase 2 links 7 million yd3 to a three-dredge delivery chain

Brazos Island Harbor Phase 2 is unusually legible at the award-to-field boundary. The owner defines approximately 7 million cubic yards across a 13-mile, 10-foot channel deepening. The federal ledger names Callan Marine and reports USD 109.240 million in current obligations, while an amended navigation notice traces the field sequence from General Marshall and General Bradley to General MacArthur with pipeline routed to confined Placement Area 5B.

Updated
A survey team checking the dredged Libertad Outfall cross-section, sediment records and hydraulic clearance in urban Pasay
Brief / Confirmed

Libertad dredging is reported complete without published package closeout

Rayman Builders signed the USD 1.071 million Libertad Outfall dredging contract on 6 October 2023. The Philippines Commission on Audit identifies the same package as DPWH contract 22Z00033, records a PHP 60.833 million contract cost and lists PHP 60.665 million in construction in progress at 31 December 2024. A November-December 2025 World Bank mission reports that all eight DPWH dredging contracts were completed. That supports completed contract status for the group that includes Libertad, but it does not publish this package's measured volume, sediment destination, as-built geometry, hydraulic clearance or DPWH acceptance.

Updated
Official Port of Durban North Bank revetment cross-section showing armour, 50-100 kg rock and filter layers
Brief / Confirmed

Durban's ZAR 5.47m revetment award leaves delivery unverified

National Treasury's active award record names KATLANTIC at ZAR 5,466,159, while TNPA's RFP fixes the workfront at a damaged entrance-channel section requiring approximately 1,000 m3 of 50-100 kg rock. Neither source confirms contract signature, notice to proceed, installed quantities or completion.

Updated
Old and new miter gates at the Lock and Dam 9 replacement workfront during the July 2026 installation
Brief / Confirmed

Lock and Dam 9 separates G&G fabrication from USACE installation

USACE's 11 August completion account resolves the most important delivery-chain question at Lock and Dam 9. G&G Steel fabricated the four replacement miter-gate leaves in Alabama over about two years, but it did not perform the reported field installation. St. Paul and Rock Island District maintenance and repair crews completed that work over four July closure days with Rock Island's 500-ton heavy-lift crane The Quad Cities.

Updated
Samoa Ports Authority milestone table for Apia Port showing CHEC's Section 1, Section 2 and the December 2026 milestone for the Section 3 breakwater
Brief / Confirmed

Apia's 100-metre breakwater moves to the July 2027 critical path

Samoa Ports Authority's July-December 2024 monitoring report placed CHEC's Section 3 breakwater and whole-project completion in December 2026. The later implementation baseline moves the 100-metre breakwater works to mid-July 2027, followed by a one-year defects period. Sections 1 and 2 had June 2026 close-out and handover expectations, but no later signed acceptance certificate was published.

Updated
Port of Los Angeles contractor and subcontractor table for Berths 238-239 showing Manson and 12 named lower-tier firms
Brief / Confirmed

Manson's Berths 238-239 award resolves 12 subcontract packages

Los Angeles RAMP displays the USD 27,414,900 opportunity amount on 13 award-participant rows, but the Port of Los Angeles contractor attachment resolves the structure: Manson is the prime and 12 named subcontractors carry bid-stage packages totaling USD 3,331,945, or 12.15% of the bid. Johnson-Peltier's USD 1,530,000 electrical package is the largest lower-tier line. The Port's January 2026 capital report separately records the owner project at 22% construction completion through November 2025.

Updated

Delivery network

Organizations connected to this collection

6 shown / 168 profiled
Aerial view of Callan Marine cutter suction dredge General Bradley working beside a floating pipeline and coastal placement area
Dredging and marine construction contractor

Callan Marine

Capital and maintenance dredging contractor / Navigation-channel and berth dredging contractor / Beneficial-use and dredged-material placement contractor

Last checked
Cruise vessel M.V. Empress alongside Chennai Port with the harbour water and working quay visible
Indian major-port authority and east-coast public port owner

Chennai Port Authority

Statutory major-port authority / Chennai port owner and public infrastructure client / Navigation channel, berthing and marine traffic administrator

Last checked
Working Kandla cargo-berth line at Deendayal Port with bulk vessels, ship cranes and quay cranes
Indian major-port authority and Kandla public port owner

Deendayal Port Authority

Statutory major-port authority / Kandla port owner and public infrastructure client / Port planning, regulation and operations administrator

Last checked
Port of Apollo Bay harbour with its commercial fishing fleet, marina berths, wharf and breakwater
Victorian statutory coastal and local-port authority

Great Ocean Road Coast and Parks Authority

Statutory coast-and-parks manager / Port manager for Apollo Bay, Port Campbell and Lorne / Apollo Bay waterway manager and harbour-master function holder

Last checked
Traditional fishing boats moored in Marsaxlokk Harbour, one of Infrastructure Malta's maritime project locations
Maltese public infrastructure delivery agency and maritime works client

Infrastructure Malta

Statutory public infrastructure agency / Maritime infrastructure development and maintenance body / Harbour, quay, breakwater and ferry-landing works client

Last checked

Continue the sector evidence review

Search the public index for this delivery discipline, compare mapped projects, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.

Search Marine works Open project tracker Open sector guide Review methodology