Location
UAE / Middle East
Project record
EGA's Khalifa Port bulk system moved from a 2017 long-term facilities agreement through completed channel deepening and widening to the first fully laden Capesize call in June 2019. AD Ports Group and EGA now confirm an AED 84 million Newcastlemax upgrade for August 2028. Two current China Harbour Engineering Company staff profiles independently identify the matching EPC and active live-berth refurbishment, advancing the record from programme agreement to reported construction while leaving the official award, dredging package and equipment suppliers undisclosed.
UAE / Middle East
Port infrastructure
CHEC EPC delivery and live-berth works reported by two current staff profiles; owner releases confirm the AED 84 million programme but do not name the contractor / Confirmed
15 August 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe joint investment defines dredging, capping-beam, fender, bollard, crane-foundation, utility and additional-unloader interfaces for planned August 2028 completion and about 8 million tonnes of annual handling. It is a programme agreement, not a design acceptance, construction award, mobilisation notice or completed capacity increase.
SourceA CHEC technical manager identifies the exact AED 84 million EGA Berth Renovation Project as an EPC active from November 2025. A second CHEC manager describes matching live-berth structural, piling, rail, fender, bollard, utility and lifting work from October 2025; this supports Reported CHEC attribution, but not the owner award, full EPC boundary, dredging subcontract or accepted progress.
SourceThe listing prospectus identifies a port-facilities agreement under which AD Ports provides EGA marine and repair services through 8 December 2052. This establishes the operating commercial relationship behind the berth, not a construction contract for the 2026 upgrade.
SourceEGA confirmed that Abu Dhabi Ports had completed the approach-channel works, deepening from 16.5 to 18.5 metres draft and widening from 250 to 280 metres. The vessel call proves the earlier Capesize access state in operation; it does not prove Newcastlemax berth geometry or the new structural and equipment scope.
SourceThe original agreement committed Abu Dhabi Ports to fund and complete approach-channel, basin and berth dredging and widening so fully laden Capesize bauxite carriers could reach EGA directly. It is the commercial and geometry baseline for measuring the later Newcastlemax upgrade.
SourceEvidence gap