Projects
Khalifa Port is moving EGA from Capesize access to a Newcastlemax berth system
EGA's dedicated Khalifa Port berth already received fully laden Capesize vessels after approach-channel works entered service in June 2019. AD Ports Group and EGA now confirm an AED 84 million Newcastlemax upgrade for August 2028. Two current China Harbour Engineering Company staff profiles independently identify the matching EPC and active live-berth refurbishment, while the owner releases still do not name the contractor.
Published scope and current milestone
EGA's 2017 and 2019 records establish the original facilities agreement, completed approach-channel works, 16.5-to-18.5-metre deepening, 250-to-280-metre widening and first fully laden Capesize call. AD Ports' prospectus and EGA's current operations page establish the long-term marine-service and conveyor-linked operating baseline. The 29 June 2026 releases define the separate AED 84 million Newcastlemax programme, planned August 2028 completion and approximately 8 million tonnes of annual handling. A current CHEC technical manager identifies the exact AED 84 million EPC from November 2025; a second current CHEC manager describes the matching live-berth scope from October 2025. The profiles support reported contractor and execution attribution but do not disclose the owner award, dredging subcontract, unloader supplier, accepted quantities or Newcastlemax readiness.
Port delivery and operating implications
This is not a greenfield berth announcement. It is a tenant-backed vessel-class and cargo-system upgrade built on a long-term facilities agreement, an operating 18.5-metre approach and a five-kilometre conveyor link to Al Taweelah. The CHEC profiles move the delivery chain beyond an unnamed programme: one identifies the exact AED 84 million EPC and another describes active capping-beam, piling, crane-rail, fender, bollard and utility work. They remain reported evidence, not an owner award notice or proof that dredging and acceptance are complete.
Evidence conclusion
Handover, readiness and service evidence
The 2017 long-term agreement funded the first channel and basin works, and the 2019 Cape Taweelah call proved Capesize access. AD Ports later documented marine and repair services through December 2052. The 2026 agreement defines a second cycle covering dredging, marine civil work, mooring, equipment, utilities and systems integration. Two current CHEC staff profiles support a reported EPC and active-construction attribution from October-November 2025. Close the phase only after owner confirmation, defined dredging and equipment packages, measured physical progress, hydrography, integrated berth testing and a fully laden Newcastlemax operating call.
Outstanding evidence
- Owner confirmation of CHEC's appointment, EPC boundary, contract date, and notice to proceed
- Dredging scope, target depth, quantities, plant, material route, and hydrography
- Berth structure, fender, bollard, utility, and pavement completion
- Crane, conveyor, cargo-system, safety, and integrated acceptance testing
- First Newcastlemax call, repeat vessel handling, and sustained terminal performance
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 9
- AD Ports Group and Emirates Global Aluminium expand long-term partnership AD Ports Group, 29 June 2026
- AED 84 million infrastructure development at Khalifa Port Emirates Global Aluminium, 29 June 2026
- Khalifa Port profile AD Ports Group, Current page reviewed 5 August 2026
- EGA and Abu Dhabi Ports welcome the first fully laden Capesize call at Khalifa Port Emirates Global Aluminium, 24 June 2019
- EGA signs long-term agreement to use Khalifa Port facilities Emirates Global Aluminium, 7 December 2017
- AD Ports Group listing prospectus AD Ports Group, 31 January 2022
- EGA Al Taweelah operations profile Emirates Global Aluminium, Current page reviewed 5 August 2026
- EGA Berth Renovation Project, Khalifa Port, AED 84 million EPC Francis Feng, China Harbour Engineering Company UAE, Current profile reviewed 5 August 2026
- Refurbishment of EGA Berth, Khalifa Port Rudolf Vincent, China Harbour Engineering Company, Current profile reviewed 5 August 2026