Market signal
Port modernisation equipment mobilised
Sector intelligence
Quays, berths, terminals, navigation access, port redevelopment, logistics waterfronts, and capacity expansion packages.
This controlled sector is a parent research lens. Projects retain their detailed work segment and can appear in more than one sector where the documented scope crosses delivery disciplines.
Port modernisation equipment mobilised
56 project records connected to this sector.
64 current analyses and briefs connect through governed project relationships.
40 public profiles connect through documented project roles.
Project coverage
United States / Port infrastructure / USACE lists four current federal-standard placement routes; Alabama Code Section 33-7-13 takes effect on 1 October 2026
delivery / Evidence reviewedAustralia / Port infrastructure / MGN Civil holds the surge-protection breakwater award; wider dredging, berth and tug-harbour packages remain separately unconfirmed
award / Evidence reviewedTonga / Port infrastructure / World Bank's revised procurement plan marks MOI-WK2-13 under implementation; contractor, contract value, notice to proceed and site mobilisation remain publicly unconfirmed
award / Evidence reviewedGermany / Port infrastructure / Sand reclamation is active behind the new quay line; phased terminal delivery runs through 2028
construction / Evidence reviewedBenin / Port infrastructure / The port authority reports 69% physical progress and 72% overall progress, while its published 2021-2024 delivery period is no longer current
construction / Evidence reviewedUAE / Deep-water ports and energy terminals / Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published
construction / Evidence reviewedEgypt / Deep-water ports and container terminals / Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity
commissioning / Evidence reviewedVietnam / Deep-water ports and container terminals / Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced
approval / Evidence reviewedGhana / Port infrastructure / PIDG capital committed; financial close and construction start still to be confirmed
financing / Evidence reviewedSingapore / Port infrastructure / Owner reports Phase 2 reclamation at 79.5% as of December 2025; its March 2026 target for handing six completed berths to PSA remains unverified, while current marine notices confirm active delivery
delivery / Evidence reviewedUnited States / Port infrastructure / Updated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recorded
tender / Evidence reviewedBangladesh / Port infrastructure / IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started
design / Evidence reviewedBrazil / Port infrastructure / Jan De Nul contract signed on 12 June 2026; official mobilisation, production and acceptance evidence remain ahead
award / Evidence reviewedIndia / Port infrastructure / Fifteen-year charter awarded on 30 June 2026; construction, delivery, port acceptance and service commencement remain ahead
award / Evidence reviewedAustralia / Port infrastructure / Owner-defined cutter-suction campaign scheduled from July to October 2026; contractor and mobilisation remain unconfirmed
approval / Evidence reviewedNauru / Port infrastructure / ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items
construction / Evidence reviewedIndonesia / Port infrastructure / Phase 1-1 is completed and partly operating; Package 5 car-terminal and Package 6 container-terminal works remained active through June 2025; Package 7 construction lacks a current owner or contractor mobilisation date
construction / Evidence reviewedNigeria / Deep-water ports and container terminals / MSC signed a 45-year sub-concession and finalized the ITB/DEME EPC on 11 March 2026; the reviewed project sources do not record mobilisation
award / Evidence reviewedTonga / Port infrastructure / AIFFP and Ports Authority Tonga confirmed all marine and civil works complete and operational on 5 November 2025
completed / Evidence reviewedComoros / Port infrastructure / World Bank and AfDB implementation records confirm works are under way; the contractor's current target is 11 August 2027
construction / Evidence reviewedIreland / Port infrastructure / Marine construction is active; the 2026 harbour notice keeps the buoyed work zone in place through January 2027, while berth acceptance and service release remain open
construction / Evidence reviewedCanada / Port infrastructure / TerraMarine is preferred proponent; contract negotiations and development work precede any target-price design-build agreement, financial close or mobilisation
design / Evidence reviewedUnited States / Port infrastructure / USACE scheduled MURDEN to work through May 2026; measured production and completion remain unpublished
construction / Evidence reviewedUnited Kingdom / Port infrastructure / PQQ closed on 1 May 2026; no shortlist, ITT or award notice is present in the reviewed public chain
prequalification / Evidence reviewedUnited States / Port infrastructure / Curtin Maritime's DB Avalon was operating in the Patapsco River on 16 June 2026
construction / Evidence reviewedUnited States / Port infrastructure / Mechanical dredging began in late May 2026 and is scheduled to continue through August
construction / Evidence reviewedUnited States / Port infrastructure / USACE reports the first phase nearing completion and a 450-foot second phase continuing through November 2026
construction / Evidence reviewedUnited States / Port infrastructure / USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028
award / Evidence reviewedUnited States / Port infrastructure / USD 2.3 million Ryba award confirmed; field start scheduled from 18 July 2026
award / Evidence reviewedUnited States / Port infrastructure / Outer harbor dredging and ERDC placement monitoring active
construction / Evidence reviewedJordan / Port infrastructure / DFBOT proposals due 17 August 2026
tender / Evidence reviewedUnited States / Port infrastructure / USD 11.7 million award confirmed; no 2026 field execution is documented
award / Evidence reviewedIndia / Port infrastructure / Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed
award / Evidence reviewedCanada / Port infrastructure / Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access
construction / Evidence reviewedUnited Kingdom / Port infrastructure / Construction contract awarded; site preparations commenced
construction / Evidence reviewedUnited States / Port infrastructure / USD 3.587 million award; July 2026 start expected but mobilisation remains unconfirmed
award / Evidence reviewedUAE / Port infrastructure / AED 84 million Newcastlemax upgrade agreed; design, package awards and delivery remain open
award / Evidence reviewedPhilippines / Port infrastructure / AIIB loan approved; three terminal programmes active on separate schedules
construction / Evidence reviewedSyria / Port infrastructure / Operations active; modernisation equipment mobilising
early works / Evidence reviewedSpain / Port infrastructure / Main quay works under construction after the Q4 2024 start
construction / Evidence reviewedArgentina / Port infrastructure / Concession signed; operating transfer complete and August maintenance mobilisation remains to be evidenced
mobilisation / Evidence reviewedAustralia / Port infrastructure / A$50 million dredging contract awarded; federal sea-dumping application remains an open evidence gate before September mobilisation
award / Evidence reviewedNetherlands / Port infrastructure / Phase A tug quay complete; Phase B inland-shipping quay started; Phase C dredging remains a post-2028 package
construction / Evidence reviewedSweden / Port infrastructure / Dredging contract signed for 2027 start
award / Evidence reviewedIndia / Deep-water ports, dredging and reclamation / The approximately 200-hectare nearshore reclamation and shore-protection EPC package is awarded; as of 15 July 2026, the owner tender page lists the offshore dredging, reclamation and protection-bund HAM package closing on 17 July and the Daman marine-sand investigation closing on 15 July, while no award or AOC is published for either package or for the 10.14-kilometre offshore breakwater
tender / Evidence reviewedDemocratic Republic of the Congo / Deep-water ports and container terminals / Phase-one marine and terminal works are under way; the DRC government was still pressing for acceleration in May 2026, so the previously stated 2026 delivery and first-vessel dates remain targets rather than evidence of accepted operation
construction / Evidence reviewedSenegal / Deep-water ports and container terminals / Marine works and container-terminal construction are active; the access channel, reclamation, quay and terminal packages remain under delivery, while 2028 is a government operating target rather than an accepted opening date
construction / Evidence reviewedBelgium / Port infrastructure / Quay-wall construction and marine works in progress
construction / Evidence reviewedItaly / Ports and coastal protection / 24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active
construction / Evidence reviewedIraq / Port infrastructure / Core marine assets built; terminal, tunnel, and commercial-operating interfaces remain under verification
construction / Evidence reviewedQatar / Port infrastructure / Owner reports 98% construction; full-system handover pending
construction / Evidence reviewedSweden / Port infrastructure / Quay construction active; port-side dredging awarded; optimized national fairway package in procurement for 2027-2028 delivery
construction / Evidence reviewedTunisia / Port infrastructure / Dredging contract signed; enabling and supervision sequence forming
award / Evidence reviewedMorocco / Deep-water ports and energy terminals / Basic port infrastructure reported complete; East terminal, towage, port systems, staffing, and service activation remain on the Q4 2026 launch path, while the West terminal follows from 2027
commissioning / Evidence reviewedAustralia / Port infrastructure / Marine reference design, investigations, environmental-review preparation, and construction planning active; Westport Bill remains before Parliament
design / Evidence reviewedTuvalu / Port infrastructure / Nui and Niutao harbour works completed and opened; operating performance and maintenance now under review
completed / Evidence reviewedCurrent research
Mobile Harbor produces roughly 6 million cubic yards of dredged material in a typical year. USACE recognizes thin-layer placement inside its sediment strategy, while Alabama's law taking effect on 1 October counts public-water placement only when it forms part of shoreline restoration or marsh creation.
Evidence updated
USACE dredging records are split between SAM.gov, the Navigation and Civil Works Decision Support Center, district engineering pages, DQM and local sponsor files. A solicitation, bid abstract, award, plant trace, hydrographic survey and acceptance record answer different questions.
Evidence updated
Mid West Ports has awarded MGN Civil the surge-protection breakwater at Geraldton. The award sits ahead of the separately described dredging, reclamation, berth and tug-harbour works in the approved Port Maximisation Project.
Evidence updated
Tonga's current Nafanua Port package combines entrance-breakwater repair and extension, a new small-boat berth and a new passenger terminal. A revised World Bank procurement plan marks the package under implementation after earlier separate packages were cancelled.
Evidence updated
DEME's Meuse River is rainbowing sand behind the new quay line at Cuxhaven berths 5-7. The operation is forming part of a 38-hectare heavy-load terminal for wind components after a 2025 piling campaign created a continuous waterside line along the site.
Evidence updated
PIDG joined Project Shiprite on 1 June with USD 9.7 million in equity and shareholder lending. The money fills the last reported gap in the USD 137 million Takoradi floating-dock scheme and clears a route to financial close. A close date, civil EPC, dock builder, notice to proceed and first marine work have yet to be announced.
Evidence updatedDelivery network
Damietta Port authority and common-infrastructure custodian / Entrance-channel, breakwater, basin and navigational-access authority / Container Terminal II quay-wall, excavation and dredging client
Evidence reviewed
Ardersier Energy Transition Facility owner and developer / Phase 2 dredging client and contracting authority / Quay-wall, quayside-civils and landside package sponsor
Evidence reviewed
Geraldton Port and Fishing Boat Harbour operator / Port-reserve, berth, channel and marine-asset custodian / Geraldton Port Maximisation Project proponent and works client
Evidence reviewed
New Mangalore harbour owner and statutory port authority / Vessel traffic, navigation-aid and port-control operator / Channel, waterfront and basin-depth monitoring authority
Evidence reviewed
Hamad Port food-security terminal owner-side delivery authority / Public design, procurement and construction-governance body / Dedicated berth, quay-wall and ship-unloading interface client
Evidence reviewed
Government implementing agency for climate-resilient maritime infrastructure / Marine and Ports Division policy and delivery lead / Nafanua Port integrated works procuring authority
Evidence reviewedSearch the public index for this delivery discipline, compare mapped projects, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.
Search Port infrastructure Open project tracker Open sector guide Review methodology