Sector intelligence

Port infrastructure intelligence

Quays, berths, terminals, navigation access, port redevelopment, logistics waterfronts, and capacity expansion packages.

Projects retain their detailed work segment and may appear in more than one sector when the scope crosses delivery disciplines.

Latest item update 249 public projects 282 related publications 160 connected organizations
On this page

Coverage focus

Quays, terminals and navigation-access programmes

Tracker coverage

249 project records connected to this sector.

Publication coverage

282 current analyses and briefs connect through governed project relationships.

Organization coverage

160 public profiles connect through documented project roles.

Project coverage

All current Port infrastructure project records

249 records
Confirmed

Nigeria Lekki Deep Sea Port Phase I marine works

Nigeria / Port channel dredging, breakwaters and coastal sand management / Phase I construction completion recorded in October 2022; presidential commissioning 23 January 2023; owner states full operation since 1 April 2023.

completed / Last checked
Confirmed

Lagos Omi Eko jetties, stations and maintenance facilities

Nigeria / Passenger jetties and shore charging civil infrastructure / EIB financing signed 11 December 2025; appraisal defines planned jetty, charging and maintenance scope with environmental and land-delivery conditions

planning / Last checked
Confirmed

Makassar New Port phases 1A, 1B and 1C

Indonesia / Container quay and terminal phased development / Phases 1B/1C physically complete in Q4 2023 and operating from February 2024; Phase 1D described separately as demand-led development

completed / Last checked
Confirmed

Lach Huyen berth 4 and ancillary barge/service wharves

Vietnam / Container berth and ancillary barge/tug wharves / Berth 4 and ancillary wharves opened in April 2025; an August 2025 owner account reports conditional approval in principle for larger partially laden ships; HTIT records an October 2026 service launch

delivery / Last checked
Confirmed

FY27 Galveston-area Scope Dredge to Budget

United States / Navigation channel maintenance dredging / 3 November presolicitation plans unrestricted firm-fixed-price maintenance dredging

planning / Last checked
Confirmed

Marsa LNG Sohar jetty and marine access

Oman / Deep-water ports and energy terminals / Access-channel dredging completed; LNG jetty, shore protection and drainage under construction

construction / Last checked
Confirmed

Itajai 2026 channel maintenance dredging

Brazil / Navigation channel maintenance dredging / Daily Njord water injection reported; Utrecht return planned for November

construction / Last checked
Confirmed

Aqaba New Oil Terminal marine EPC package

Jordan / Liquid-cargo terminal berth enhancement / December bids advertised; document requests closed 28 October and access needs ADC confirmation

tender / Last checked
Confirmed

Kishorn Phase 1B East Quay development

United Kingdom / Port infrastructure / Restricted selection and marine pre-application consultation for the proposed East Quay

prequalification / Last checked
Confirmed

Montrose Port Berths 9-11 redevelopment

United Kingdom / Port infrastructure / Initial selection closed 16 October; invitations expected 20 November 2026

prequalification / Last checked
Confirmed

King Abdulaziz Naval Base MMSC IOC facilities

Saudi Arabia / Naval base wharf and fleet-support facilities / USAspending records USD 400,172,871.91 obligated and exercised across 28 transactions through 7 July 2026; current performance end 8 March 2027

construction / Last checked
Confirmed

Vadhvan Greenfield Deep-draft Port

India / Deep-water ports, dredging and reclamation / Afcons disclosed receipt of VPPL's Letter of Award on 9 June 2026 for the 10.14 km offshore breakwater, valued at INR 53.01 billion excluding GST. The nearshore EPC award is separate; the offshore HAM procurement outcome and current field progress require their own records.

award / Last checked
Confirmed

Malaga Port Quay 4 facing rehabilitation

Spain / Submerged masonry quay repair and structural concrete rehabilitation / Malaga Port Authority declared Quay 4 procedure 26exma-033 unsuccessful on 7 September 2026 after receiving no bids; the 15 September notice retains the seven-zone repair design and EUR 78,739.06 excluding-VAT tender budget, with no works award under this procedure

tender / Last checked
Confirmed

Le Goulet Harbour 2026 maintenance dredging

Canada / Fishing harbour wharf, dredging and shore protection / CanadaBuys' 13 October data records the CAD 948,750 tax-inclusive Le Goulet contract CW2466490 awarded to Les Entreprises P E C inc on 10 September 2026; mobilisation, plant, dredged quantities and acceptance remain unreported

award / Last checked
Confirmed

Dunkirk port mechanical preventive-maintenance framework

France / Port structures and mechanical installations maintenance / BOAMP extended submissions to 28 September 2026; that date has passed and the latest buyer-profile result remains unverified

tender / Last checked
Confirmed

Dunkirk port cathodic-protection replacement framework

France / Port structures and underwater asset maintenance / The published 4 September 2026 bid deadline has passed; the latest buyer-profile result and framework holder remain unverified

tender / Last checked
Confirmed

Aktau Port Berths 3 and 12 Modernisation

Kazakhstan / Port infrastructure / ECEPP marks the berth first-stage and supervision invitations closed; the supervision page lists 10 September 2026 as its final deadline; later-stage and other-package participation remain unverified

tender / Last checked
Confirmed

Ardersier Port Phase 2 dredging procurement

United Kingdom / Port infrastructure / PQQ closed on 1 May 2026; subsequent invitation to tender and supplier appointment remain unconfirmed in the reviewed notice

prequalification / Last checked
Confirmed

Bristol Floating Harbour 2026 maintenance dredging

United Kingdom / Maintenance dredging, floating-harbour navigation and marina access / Bullo holds the signed GBP 392,500 excluding-VAT contract; July and August navigation windows are historical, with the post-term instruction and accepted output unconfirmed

award / Last checked
Confirmed

Port of Felixstowe four ship-to-shore quay cranes

United Kingdom / Container-terminal handling equipment / Find a Tender records an active award to ZPMC for four STS cranes at GBP 43.594 million excluding VAT; actual contract signature, manufacture, shipment, commissioning and acceptance remain unconfirmed

award / Last checked
Confirmed

Burry Port pontoon floats

United Kingdom / Marinas, pontoons and berthing infrastructure / Solent Marine holds a GBP 72,600 float award.

award / Last checked
Confirmed

NOC Southampton quayside wall and pontoon repairs

United Kingdom / Seawall, quayside and pontoon repair / National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT; the contract period ran from 13 August to 12 September 2025, but no dated completion, acceptance or final-account record has been located

award / Last checked
Confirmed

Swansea Morfa Quay and New Cut Road pontoons

United Kingdom / Marinas, pontoons and berthing infrastructure / Swansea signed the GBP 411,775.70 excluding-VAT two-pontoon contract on 15 July; the August amendment revised its start to 5 August, retaining a 2 October end, with site completion and acceptance unconfirmed

award / Last checked
Confirmed

Burry Port Harbour emergency sand dredging

United Kingdom / Maintenance dredging, approach-channel access and beach placement / Carmarthenshire County Council signed a GBP 425,000 excluding VAT emergency dredging contract with Kaymac Marine & Civil Engineering on 29 June 2026 for a 13 July to 31 October delivery window; the council has published no mobilisation, dredger, production, survey, completion or acceptance update

award / Last checked
Confirmed

Harwich Haven five-year maintenance dredging

United Kingdom / Maintenance dredging, beneficial use and dredging technology / HHA confirmed Suffolk Dredging LLP's five-year maintenance award in July; the March procurement family was withdrawn for a scope-description correction, with current value and exact commencement unconfirmed

award / Last checked
Confirmed

Duwamish Waterway FY2026 maintenance dredging

United States / Navigation channel maintenance dredging / USACE awarded the USD 2.852 million contract to American Construction on 24 September 2026; dredging is scheduled no sooner than 1 December and mobilisation remains unreported

award / Last checked
Confirmed

Sandusky Harbor 2026 maintenance dredging and nearshore placement

United States / Navigation channel maintenance dredging / USACE scheduled Morrish-Wallace's 109,000-cubic-yard campaign to start on 6 October 2026 and finish by 1 November; actual mobilisation remains unverified

construction / Last checked
Confirmed

Sines quay and north-west breakwater design interface

Portugal / Ports and coastal protection / Design and environmental assessment; APS makes new-quay construction conditional on industrial demand and rules out a near-term works tender

design / Last checked
Confirmed

Anaklia marine infrastructure and terminal-delivery interface

Georgia / Capital dredging and navigation-channel deepening / Initial breakwater-channel dredging reported; main basin campaign and private terminal milestones follow separate delivery stages

construction / Last checked
Confirmed

Paradip 18.5m capital dredging and terminal-readiness interface

India / Capital dredging and navigation-channel deepening / Owner reports channel completion and inaugurated 18.5m capability; earlier berth-specific admissible drafts require their own operating amendment

completed / Last checked
Confirmed

Jurien Bay Boat Harbour entrance reconfiguration

Australia / Ports and coastal protection / April maintenance dredging complete; 170m northern breakwater extension in detailed design, with construction tender to follow

design / Last checked
Confirmed

Brazos Island Harbor Phase 2 channel deepening

United States / Capital dredging and navigation-channel deepening / USACE lists Phase 2 in construction with new-work dredging continuing toward an FY2026 scheduled completion; final accepted depth, certified quantity and contract completion are unpublished

delivery / Last checked
Confirmed

Igoumenitsa Port three-berth OPS shore-power systems

Greece / Commercial-port shore power and electrical utility integration / HEDNO signed the EUR 6.82 million turnkey contract with Paralos on 11 February 2026 for two 3 MVA OPS positions and one 0.5 MVA position. TED names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors; mobilisation, installation, energisation, vessel connection and acceptance remain unconfirmed

award / Last checked
Confirmed

Molo Sali Phase B sheet-pile restoration and quay completion

Italy / Sheet-pile rehabilitation and port-yard conversion / TED notice 514687-2026 records a EUR 8,295,571.84 contract concluded on 23 July 2026 with the Rossi Renzo Costruzioni-led four-member RTI; notice to proceed, mobilisation, named subcontractors and installed work remain unverified

award / Last checked
Confirmed

Centreville small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Kerr Limited's CAD 18.86 million contract reached its amended 31 December 2025 expiry after 11 amendments; no cited owner record confirms accepted completion, final dredged quantities or reopening

delivery / Last checked
Confirmed

Port 2000 Chatiere protected river access

France / Ports and coastal protection / Terelian and SDI/DEME are constructing the 1,800 metre protection dike; HAROPA reported nearly 800,000 m3 of foundation material placed by 1 June 2026 after a 760,000 m3 weak-silt purge, while channel dredging, dike tie-ins, completion and operating release remain pending

construction / Last checked
Confirmed

Mahout fishing port construction

Oman / Port infrastructure / OMR 36.995 million construction award approved in July 2026; contractor and detailed marine scope remain undisclosed

award / Last checked
Confirmed

Banjul Port fourth expansion and concession delivery

The Gambia / Port infrastructure / Port concession operating and green ferry commissioned; core jetty and container-terminal expansion completion remains unverified

delivery / Last checked
Confirmed

Banana Deep-water Port Phase One

Democratic Republic of the Congo / Deep-water ports and container terminals / Phase-one contract announced with an estimated 24-month term; no current cited record confirms accepted marine works, terminal commissioning, or commercial opening

construction / Last checked
Confirmed

Hammond Cove Marina reconstruction

United States / Marinas, pontoons and berthing infrastructure / New York City's 22 January 2026 award notice names Empire Construction and Property Management Group at USD 4,583,648 for X310-117M; the city hazard plan identifies bulkhead, dock and electrical reconstruction, but no cited record establishes contract signing, notice to proceed, mobilisation or completion

award / Last checked
Confirmed

Dundee Beach boat-ramp maintenance

Australia / Public boat-launch infrastructure, maintenance dredging and fixed access / Northern Territory Tenders Online records T25-1462 as a 12-month awarded period contract to Polaris Marine Constructions at AUD 676,047.56 on an estimated-unit-rate basis

award / Last checked
Confirmed

Kalundu Port rehabilitation and modernization works

Democratic Republic of the Congo / Port infrastructure / PFCIGL reported that GETRA-AXOR remobilized from 15 June 2026 and that Kalundu works were progressively resuming; activity then remained at site installation and ground preparation before effective rehabilitation works

construction / Last checked
Confirmed

Nador West Med Deep-water Port

Morocco / Deep-water ports and energy terminals / Basic port infrastructure reported complete; access-control, port-management, systems, staffing, and service preparations remain active ahead of the East terminal's Q4 2026 commissioning target, while the West terminal follows from 2027

commissioning / Last checked
Confirmed

Port of Montreal Contrecœur Container Terminal

Canada / Port infrastructure / Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access

construction / Last checked
Confirmed

Khalifa Port EGA berth enhancement programme

UAE / Port infrastructure / CHEC EPC delivery and live-berth works reported by two current staff profiles; owner releases confirm the AED 84 million programme but do not name the contractor

construction / Last checked
Confirmed

Parks Victoria Bays Maintenance Dredging Program

Australia / Maintenance dredging, approach-channel access and beach placement / Buying for Victoria records Birdon Pty Ltd on a current AUD 31.9 million contract starting 1 November 2021; Birdon describes a 2021-2030 term and names dredge Ballina with support craft Willie Tell and Bella, while site-level quantities and owner acceptance remain campaign-specific

delivery / Last checked
Confirmed

Dakhla Atlantic Port construction

Morocco / Port infrastructure / Construction reported above 60% in June 2026; marine completion, equipment and operating awards remain open

construction / Last checked
Confirmed

Oswego Harbor 2026 breakwater repair phases

United States / Port infrastructure / USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028

award / Last checked
Confirmed

Port of Ndayane Deep-water Port and Container Terminal

Senegal / Deep-water ports and container terminals / DP World reports the major dredging works complete 13 months ahead of schedule; quay and other marine and civil works remain active, while 2028 is a target rather than an accepted opening date

construction / Last checked
Confirmed

Tuas Port Phase 2 reclamation and terminal development

Singapore / Port infrastructure / Phase 2 reclamation stood at 79.5% in December 2025 and its planned six-berth handover remains unverified; the wider Tuas Port passed 25 million TEU in August 2026, but that operating total began with Phase 1

delivery / Last checked
Confirmed

Wesleyville and Brookfield floating-dock reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Granite Management received DFO contract 4500013526 on 23 December 2021 for a two-site floating-dock package; the 2021-22 Public Accounts mark the contract completed, while physical acceptance records remain unpublished

completed / Last checked
Confirmed

South Moose Lake 2025 harbour improvements

Canada / Remote fishing-harbour timber crib wharf and floating offloading dock / Fisheries and Oceans Canada awarded ZheMaak Inc. contract 4500091055 for CAD 220,542 on 8 August 2025; the published seven-month term ended on 27 March 2026, but the reviewed federal record does not publish physical completion, accepted quantities, owner handover or a final account

delivery / Last checked
Confirmed

Port de Grave marginal wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210731/001/PWD on 15 November 2021; CanadaBuys records a CAD 1,763,368 cumulative contract after amendments, and the 2022-23 Public Accounts mark the Port de Grave contract completed

completed / Last checked
Confirmed

Cap-aux-Meules access-channel dredging

Canada / Capital and maintenance dredging for a remote ferry, cargo and fishing port / PSPC awarded contract CW2402077 to Dragage Ocean DS on 1 September 2025; a CNESST filing places the contractor at the Cap-aux-Meules dredging site from a planned 13 October to 12 November 2025, while a 13 May 2026 amendment lifted the published contract total to CAD 6,724,266.72 without disclosing its scope

construction / Last checked
Confirmed

Winterton small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed

completed / Last checked
Confirmed

Snapper Creek State Boat Harbour shoreline protection works

Australia / Port revetment repair and armour-rock placement / Queensland Transport and Main Roads disclosed Contract MSQ25017 with Hunter Contractors Pty Ltd at AUD 1,981,207 on 10 July 2025, and Maritime Safety Queensland announced a 2 September 2025 construction start; no cited official source confirms installed quantities, completion, acceptance or final account

construction / Last checked
Confirmed

ACME Duqm green-ammonia CBM export terminal

Oman / Deep-water ports and energy terminals / Phase 1 plant construction and CBM equipment delivery are active. Masirah Marine is the reported installation lead; its contract, vessel allocation and ASD-tug support remain undisclosed

construction / Last checked
Confirmed

Geraldton Port Maximisation marine works

Australia / Port infrastructure / MGN Civil holds the surge-protection breakwater award; wider dredging, berth and tug-harbour packages remain separately unconfirmed

award / Last checked
Confirmed

Veseli nad Moravou marina phase-one expansion

Czechia / Inland marina quay edges, floating fingers, bank protection and utilities / The Czech Waterways Directorate opened 30 new public berths in August 2025 and the Transport Ministry reports the expanded marina operating with capacity for 66 boats in the 2026 season; IDS holds the phase-one works contract, with the highest reviewed official modification snapshot at CZK 86,312,219.98

completed / Last checked
Confirmed

Edmonds North Portwalk Phase II electrification

United States / Marina electrical infrastructure, waterfront site preparation and public realm / The Port of Edmonds Commission unanimously authorized a contract with TRICO Companies LLC on 8 June 2026; the current owner page marks Phase II in progress and estimates work will begin late in 2026

award / Last checked
Confirmed

Skinners Pond wharf 401 copewall rehabilitation

Canada / Fishing harbour wharf, dredging and shore protection / Kildare Construction Ltd. received CAD 1.10 million contract 4500013345 on 23 December 2021 for structure 401; the 15 June 2022 target date is published, but completion and owner acceptance remain unverified

award / Last checked
Confirmed

Saint-Edouard-de-Kent containment-cell reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Christian Larocque Services LTEE received the CAD 347,878.45 construction contract in November 2021; Harbourside Engineering reports the rebuilt dredge-spoil containment cell completed in March 2022

completed / Last checked
Confirmed

Bellingham Shipping Terminal marine infrastructure and dredging

United States / Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities / Port reporting confirms key dock and stormwater upgrades were completed in 2025 and navigation and environmental work advanced; Washington L&I records American Construction's contractor-reported 8 April 2026 work-completed date, but no filed Notice of Completion, owner acceptance, final hydrographic survey, final dredged quantity or final account is evidenced

delivery / Last checked
Confirmed

San Francisco Pier 80 mooring and berthing improvements

United States / Wharf maintenance, fender piles and marine asset renewal / The San Francisco Port Commission adopted Resolution 25-25 on 13 May 2025, authorizing award of Contract 2871 to Manson Construction Co. for USD 5,518,500 plus a USD 551,850 contingency; the cited official record does not confirm the planned notice to proceed, physical progress, substantial completion or acceptance

award / Last checked
Confirmed

Kuwait Mubarak Al-Kabeer Port Phase I completion

Kuwait / Deep-water ports and container terminals / Phase I EPC signed with CCCC; government follow-up continues, while mobilisation and marine construction remain unverified

award / Last checked
Confirmed

Quriyat fishing port sea dock development

Oman / Port infrastructure / 83% complete in August 2025; completion, contractor and acceptance remain unverified

construction / Last checked
Confirmed

Port of Rotterdam Yangtzekanaal widening and quay programme

Netherlands / Port infrastructure / Phase A tug quay delivered; the same consortium has started Phase B, including 1.4 million m3 of sand dredging; Phase C remains a post-2028 package

construction / Last checked
Confirmed

Port of Durban North Bank revetment repairs

South Africa / Port revetment repair and armour-rock placement / South Africa's official procurement release records an active ZAR 5,466,159 award to KATLANTIC for the Port of Durban North Bank revetment repairs; the public record does not provide an award date, executed contract, notice to proceed, physical progress or completion

award / Last checked
Confirmed

Apia Port climate-resilient breakwater and terminal upgrade

Samoa / Port infrastructure / Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate

construction / Last checked
Confirmed

Los Angeles Berths 238-239 Marine Oil Terminal Improvements

United States / MOTEMS wharf replacement, dolphins, fenders and maintenance dredging / The Port of Los Angeles January 2026 CIP report classifies the project in construction and, using actuals through November 2025, records 22% construction completion, a 31 March 2027 forecast finish, USD 39,288,466 projected project cost and USD 6,315,074 spent to date

construction / Last checked
Confirmed

Bapco wharf and pipeline repair term services

Bahrain / Liquid-cargo terminal maintenance / Bahrain Tender Board's May 2026 report records a BHD 340,000 extension under tender T17600(65), following the May 2021 BHD 2,489,690 five-year award to Bahrain Maintenance and Diving Services; the extension duration and work orders remain undisclosed

award / Last checked
Confirmed

Petaluma River FY2025 maintenance dredging

United States / Port infrastructure / USACE records the FY2025 campaign complete after Dutra's USD 6.272 million dredging award; three reported subawards expose placement fees, DQM and survey support, tug setup and crew boats, while the final accepted quantity and account remain unpublished

completed / Last checked
Confirmed

Toledo Harbor 2026 maintenance dredging

United States / Port infrastructure / USD 5.3 million 2026 task order issued under a USD 11.1 million two-year Ryba contract; the September start remains planned

award / Last checked
Confirmed

Manangareza river-port station rehabilitation

Madagascar / Inland river-port station and passenger-cargo terminal rehabilitation / ECH BTP signed the USD 1,272,815.07 works contract on 28 November 2025; public records also name the design and supervision consultant, but no notice to proceed, mobilisation, measured progress, completion or acceptance has been located

award / Last checked
Confirmed

Dioro riverbank and port-quay rehabilitation

Mali / Inland river-port quay and bank rehabilitation / Two works lots under ML-UGP-PRTD-477915-CW-RFB were signed in December 2025; the April 2026 procurement plan marks the package under implementation, but no lot-specific mobilisation, progress, completion or acceptance record has been published

award / Last checked
Confirmed

Elizabeth Quay ferry platform and gangway additions

Australia / Urban ferry terminal, floating platform and passenger gangway / Maritime Constructions holds the AUD 1,756,143 fixed-price design-and-construct award; Tenders WA does not publish a start date, expiry date, mobilisation or completion milestone

award / Last checked
Confirmed

Lower Yarra River Maintenance Dredging Program

Australia / Urban waterway maintenance dredging, navigation access and in-river material placement / Buying for Victoria records Australasian Marine Associates on a current AUD 1.93985 million contract starting 8 September 2021; Parks Victoria confirms AMA delivered Campaign C in 2024, while the owner programme was reported complete and the next funding cycle remained open

delivery / Last checked
Confirmed

Norfolk Island Cascade Pier emergency remediation works

Norfolk Island / Pier remediation and island freight access / GP Services' AUD 183,041 emergency-remediation period has elapsed without accepted completion evidence; the separate AUD 10 million apron project is in detailed design with Consult Marine, with no construction award or mobilisation published

award / Last checked
Confirmed

Roberts Bank Terminal 2 landmass and wharf

Canada / Port infrastructure / TerraMarine is preferred proponent; contract negotiations, an in-progress Fisheries Act authorization and development work precede any target-price design-build agreement, financial close or mobilisation

design / Last checked
Confirmed

Dunkirk Harbor west breakwater rehabilitation

United States / Port infrastructure / Great Lakes Dock & Materials holds both phases; USACE reports the last 450 feet continuing through November 2026

construction / Last checked
Confirmed

Georgetown Harbor maintenance dredging

United States / Port infrastructure / Southern Dredging's Dredge BRUNSWICK is listed on active 24/7 work in the Bypass and Steel Mill channels through about 31 August 2026

construction / Last checked
Confirmed

Plymouth Mount Batten pontoon replacement

United Kingdom / Marinas, pontoons and berthing infrastructure / Teignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmed

construction / Last checked
Confirmed

NW-1 Bihar-West Bengal: six steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Cleghorn Mfg. Co. signed the six-location bundled supply and installation contract on 24 April 2025; public evidence does not confirm final sites, fabrication, installation, commissioning or acceptance

award / Last checked
Confirmed

NW-1 West Bengal: seven 30 m steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Nalanda Engineering Enterprise signed the seven-location bundled supply and installation contract on 3 April 2025; public evidence does not confirm fabrication, installation, commissioning or acceptance

award / Last checked
Confirmed

Tinian seaport P-940, P-1001 and P-1002 design

United States / Naval and civil seaport wharf, breakwater and harbor-dredging design / MDPAC JV holds a USD 12.616m architect-engineer task order through 31 December 2026 for P-940 wharf improvements, P-1001 breakwater restoration and P-1002 harbor dredging and Finger Pier A removal; 13 named design-chain subaward records total USD 4.055m, while no construction award or mobilisation is evidenced

design / Last checked
Confirmed

Fox Island River channel-wall and marginal-wharf reconstruction

Canada / Small-craft-harbour marginal wharf and channel-wall renewal / DFO-SCH's 2026 proposal remains in federal assessment after the public-comment period ended on 22 June 2026; no environmental determination, procurement, award, contractor, mobilisation or construction is evidenced

approval / Last checked
Confirmed

Fox Island River harbour entrance improvement and re-dredging

Canada / Small-craft-harbour entrance dredging and breakwater works / Marine Contractors' CAD 1.499m entrance-improvement contract and R.J.G Construction's separate CAD 1.133m channel re-dredging contract have both reached their published administrative end dates, but no completion certificate, accepted hydrography, final dredged quantity or causal link between the packages is public

delivery / Last checked
Confirmed

P-835 Lima Wharf and Inner Apra Harbor dredging

United States / Naval-wharf and inner-harbor dredging design / MDPAC JV holds the USD 3.335m P-835 design task order, expanded in August 2025 from DD1391 and 15% design into a design-bid-build package and extended in March 2026 to September 2028; no construction award or physical dredging is evidenced

design / Last checked
Confirmed

Tarifa fishing-wharf electrical utility upgrade

Spain / Fishing-wharf electrical distribution and utility connection / APBA awarded the EUR 273,030 works to VES Renewable; contract formalization and setting-out remain unpublished

award / Last checked
Confirmed

La Pozona harbour upgrade

Spain / Dredging, pontoons, piles and utilities / Cantabria awarded the EUR 2.647m works to a three-member UTE; contract and mobilisation remain unpublished

award / Last checked
Confirmed

Cheticamp Jobs Wharf floating-dock reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Superior Contracting's CAD 1.264 million contract ran from 14 October 2022 to 31 March 2023 for an integrated timber-wharf, dredging, breakwater, floating-dock and electrical package; the reviewed federal record does not publish accepted completion, measured quantities or final account

delivery / Last checked
Confirmed

Menzel Abderrahmane fishing-port extension and coastal esplanade

Tunisia / Fishing-port expansion, dredging, breakwater, quay and coastal esplanade / ETEP signed the TND 20,018,762.19 works contract on 28 April 2025, but Tunisia's parliament still described the port and esplanade project as delayed during a February 2026 site visit; physical start, achieved quantities and supervision award remain unverified

award / Last checked
Confirmed

Port-Vendres Quai Dezoums shore-power electrification

France / Commercial-port shore power and electrical utility integration / BOAMP notice 25-50611 records a EUR 5,436,212 contract issued on 3 April 2025 to the SPIE CityNetworks-led consortium with Nidec ASI and T.A.E.H., plus subcontractor Guintoli. A 24 March 2026 Department presentation classifies the work as in progress; energisation, vessel connection, commissioning, acceptance and completion remain unconfirmed

construction / Last checked
Confirmed

Los Angeles Berths 49-51 Outer Harbor Cruise Terminal Development

United States / Cruise berth rehabilitation, shore power and marine piling / Los Angeles Harbor Commission Resolution 26-10665 approved Shimmick's USD 61,290,400 bid on 6 January 2026, and RAMP records the award on 26 January; the owner's award presentation estimated a March 2026 notice to proceed and January 2029 completion, while the actual NTP, site mobilisation and installed work remain unconfirmed through 8 August 2026

award / Last checked
Confirmed

Hillarys Boat Harbour jetties A, F, G, H and J replacement

Australia / Marinas, pontoons and berthing infrastructure / Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract

completed / Last checked
Confirmed

Fremantle Fishing Boat Harbour Jetty 3 replacement

Australia / Marinas, pontoons and berthing infrastructure / Transport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade Sales

completed / Last checked
Confirmed

Sitra Wharf Berths 5 and 6 liquid-cargo enhancement

Bahrain / Liquid-cargo terminal berth enhancement / Bahrain Tender Board's March 2026 monthly report records a BHD 10,987,831 award to NASS Contracting for Sitra Wharf tender T78534; no award date, contract signature, mobilisation or installed work is published

award / Last checked
Confirmed

Maassluis M2 quay-wall replacement and waterfront renewal

Netherlands / Quay-wall replacement and waterfront public-realm renewal / TED notice 542353-2026 records a EUR 7,887,000 contract with De Vries Werkendam B.V. concluded on 4 August 2026; the owner plans physical works from 5 October 2026 to 21 July 2028 and publishes no current mobilisation evidence

award / Last checked
Confirmed

Apollo Bay Harbour seawall construction

Australia / Harbour seawall renewal and coastal asset protection / Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation

award / Last checked
Confirmed

Ouakam fishing-quay rehabilitation

Senegal / Fish landing quay and fisheries value-chain infrastructure / FIDELE SARL's rehabilitation contract was signed 5 February 2025 for an operating export-approved landing facility; no controlled site start, temporary operating setup or physical progress evidence through 8 August 2026

award / Last checked
Confirmed

Fass Boye modern fishing quay

Senegal / Fish landing quay and fisheries value-chain infrastructure / KELIMANE ENTREPRISE's Lot 01 contract was signed 5 February 2025, while a separate replacement relocation-site package remained awaiting execution in the current plan; no controlled main-works start evidence through 8 August 2026

award / Last checked
Confirmed

Cap Skirring modern fishing quay

Senegal / Fish landing quay and fisheries value-chain infrastructure / Official works launch held 24 July 2025 after ETIC's Lot 02 contract was signed 15 January 2025; no controlled later completion or commissioning evidence through 8 August 2026

construction / Last checked
Confirmed

Liwa Fishery Harbour development, management and operation PPP

Oman / Fishing-port concession, commercial waterfront and operating PPP / Liwa remained in Oman's 2024 PPP and fisheries-investment pipeline after 2021 and 2023 market approaches; a selected developer and financial close remain undisclosed through 8 August 2026

tender / Last checked
Confirmed

Liwa Fishery Harbour maintenance dredging procurement 2023

Oman / Operating fishing-port maintenance dredging / Oman eTender 441/2023/MAFWR/HQ-36 reached financial evaluation in Q3 2023, then a Recall-1 procedure closed on 19 December 2023; an awardee, value and mobilisation remain undisclosed

tender / Last checked
Confirmed

Liwa (Nabur) Fishery Harbour construction

Oman / Fishing-port breakwaters, dredging, quay and marine infrastructure / Liwa harbour was operating by 2023 after the original Galfar award and 2015-2017 downstream marine works; formal completion, acceptance and final-account records remain unrecovered

completed / Last checked
Confirmed

Bukha Fishery Harbour maintenance, rehabilitation and dredging

Oman / Fishing-port maintenance, rehabilitation and dredging / Masirah Island International identifies active harbour maintenance, rehabilitation and dredging; a 2025 Oman News Agency owner-side report says the port remained under maintenance, with no public completion or acceptance record

construction / Last checked
Confirmed

Meteghan floating wharf and pile rehabilitation

Canada / Fishing harbour wharf, dredging and shore protection / Dexter holds CAD 4.29 million CW2462474 for floating-dock and pipe-pile replacement, while Connors Diving holds CAD 1.27 million 4500109325 for Wharf 403 pile jackets and concrete repairs; both awards are active but mobilisation and progress are unverified

award / Last checked
Confirmed

Glace Bay small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified

award / Last checked
Confirmed

La Spezia Terminal del Golfo expansion and redevelopment Lot I

Italy / Container and multipurpose terminal quay extension / TED notice 521188-2026 records a 23 July 2026 works contract with a planned RTI led by Dott. Carlo Agnese at EUR 10,868,519.12 for 419 days; notice to proceed, mobilisation, installed quantities and named subcontractors remain unverified

award / Last checked
Confirmed

Larrys River small craft harbour breakwater reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds active CAD 2.75 million contract CW2455209 through 27 November 2026 for rubble-mound breakwater construction at Larrys River; award and scope are confirmed but mobilisation and physical progress are not

delivery / Last checked
Confirmed

Grande-Anse harbour-basin dredging and containment-cell works

Canada / Fishing harbour wharf, dredging and shore protection / Les Entreprises P E C inc holds active CAD 862,270 contract CW2452382 through 31 December 2026 for barge-excavator dredging and containment-cell reconfiguration; earliest site start was 6 July and field progress remains unverified

delivery / Last checked
Confirmed

Sainte-Marie-Sur-Mer structure 401 wharf and breakwater works

Canada / Fishing harbour wharf, dredging and shore protection / L Breau and Sons Ltd holds active CAD 8.75 million contract CW2440554 through 24 August 2027 for structure 401 wharf reconstruction and a new breakwater; mobilisation, measured work and acceptance remain unconfirmed

delivery / Last checked
Confirmed

Colombo West Container Terminal II Western Breakwater Extension Design

Sri Lanka / Deep-water port expansion, breakwaters and reclaimed logistics land / Dohwa-led detailed-design contract awarded in April 2025; SLPA's May 2026 planning document confirms the engineering study but leaves financing, construction procurement and field start open

design / Last checked
Confirmed

Granville Herel main breakwater and sill-wall repair

France / Breakwater and reinforced-concrete marine-structure rehabilitation / The owner-confirmed nine-month repair started on 25 August 2025; its planned end-May 2026 acceptance window has passed without a published completion certificate, handover or final account

construction / Last checked
Confirmed

Ras Hanzir replacement cargo facility

Malta / Cargo-port quay, land reclamation, piling and utilities / Infrastructure Malta is taking replacement works tender IMT008/2025 to 1 October 2026 after terminating predecessor contract IM027/2020; the replacement works package remains unawarded

tender / Last checked
Confirmed

NW-1 Bihar: ten steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Signed with Merolyn on 11 November 2025; procurement is under implementation, while physical delivery is unverified

award / Last checked
Confirmed

NW-1 West Bengal Lot A: five concrete floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / IWAI signed the five-site Lot A contract with West Coast Marine Yacht Services on 18 March 2026; the procurement plan lists the package under implementation, but fabrication, installation and site acceptance remain publicly unconfirmed

award / Last checked
Confirmed

Yukonhaven Jetty 4 LNG bunker-loading berth

Netherlands / LNG jetty, combi-wall, mooring structures, dredging and shore works / Gate took FID in January 2026, Port of Rotterdam signed the Hakkers Waterbouw-De Klerk combination on 6 February, and April works notices support early construction; start-up is planned around the end of 2028

construction / Last checked
Confirmed

Tumaco port access-channel deepening, Phase I

Colombia / Capital dredging and navigation-channel deepening / SECOP II records contract GN2862-2026 signed with Consorcio Puerto Tumaco II for COP 26.826 billion and eight months, but the public ledger has no start date, invoicing or payment and the separate supervision procurement remains unawarded

award / Last checked
Confirmed

Barranquilla access-channel maintenance dredging

Colombia / Navigation channel maintenance dredging / SECOP II shows contract 0-525-2024 modified to COP 241.685 billion and 31 December 2026 after a 365-day extension; Cormagdalena reported 80.7% execution at 31 March before the later ledger update, while completion and acceptance remain unconfirmed

delivery / Last checked
Confirmed

Petit-Cap structure 403 wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Landco Construction's CAD 3.08 million contract ran from 2 November 2023 to 4 July 2024 for a Berlin-wall marginal wharf, harbour dredging and electrical reinstatement; CanadaBuys does not publish accepted completion or final quantities

delivery / Last checked
Confirmed

Harbour Grace small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Bulldog Contracting received the CAD 7.05 million award on 1 April 2022 for timber-crib wharf, finger-pier, dredging and utility works; the reviewed federal record does not establish the delivery end date, accepted completion or final account

delivery / Last checked
Confirmed

Pugwash small craft harbour floating-dock works

Canada / Fishing harbour wharf, dredging and shore protection / Brian MacGillivary Construction's CAD 516,100 contract ran from 22 November 2023 to 29 March 2024; CanadaBuys confirms the award and amended term but publishes no accepted dredging quantity, dock handover or completion certificate

delivery / Last checked
Confirmed

West Bengal 45-jetty contract ledger

India / Inland-waterway floating jetties, gangways and passenger facilities / World Bank data identifies 21 direct works contracts across the 29-jetty Phase I and 16-jetty Phase II programme; the June 2026 ISR says 44 of 45 locations are complete with Metiabruze under implementation, while its results table says all 45 are complete

construction / Last checked
Confirmed

Townsville MSQ Base wharf fender-pile replacement

Australia / Wharf maintenance, fender piles and marine asset renewal / Queensland TMR awarded MSQ26005 to Pacific Marine Group on 11 May 2026 for AUD 423,687; no public milestone establishes mobilisation, pile quantities, installation method, completion or acceptance

award / Last checked
Confirmed

Dar es Salaam channel deepening and berth concrete repairs

Tanzania / Capital dredging, berth reconstruction and concrete remediation / Channel and berth civil packages were reported complete in 2024 and the port publishes operational depths; CHEC's separate USD 15.70 million 2025 concrete-repair contract has no cited completion or acceptance evidence

construction / Last checked
Confirmed

Port Seine-Metropole Ouest phase-one river-port construction

France / Inland-port basin excavation, sheet-pile quays, pile-supported jetties and multimodal access / HAROPA PORT reports phase-one construction in execution: earthworks, a retaining wall and conveyor loading were active in summer 2026, South Quay sheet-pile installation had started, and piling for the west then east jetties was scheduled from the week of 6 July

construction / Last checked
Confirmed

Poona boat ramp and access-channel upgrade

Australia / Public boat-launch infrastructure, capital dredging and fixed access / Australian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026

construction / Last checked
Confirmed

Newell Beach all-tide boat ramp upgrade

Australia / Public boat-launch infrastructure, capital dredging and fixed access / Queensland TMR completed the upgraded all-tide facility in May 2022 after Australian Marine & Civil delivered the main works under CN-17011; the published contract disclosure rose from AUD 2,560,154 to AUD 2,603,835 after a variation

completed / Last checked
Confirmed

Bridgetown Port Sugar Berth seawall and revetment repair

Barbados / Port infrastructure / World Bank contract record 1881500 names C. O. Williams Construction Limited at USD 3.338 million, but the public procurement chronology does not reconcile and no dated mobilisation, progress or completion record has been located

award / Last checked
Confirmed

Nafanua Port resilience improvement

Tonga / Port infrastructure / China Jiangsu International holds the signed USD 4.803 million MOI-WK2-13 award; notice to proceed, mobilisation and physical works remain publicly unconfirmed

award / Last checked
Confirmed

Nanumaga and Nanumea climate-resilient small-boat harbors

Tuvalu / Ports and coastal protection / Hall Civil Contracting signed the USD 62.552 million design-build contract on 21 July 2025; the latest cited mission set August 2027 and January 2028 completion targets for Nanumaga and Nanumea, but no cited source confirms physical mobilisation or current progress

award / Last checked
Confirmed

Rumonge Port EPC and related-services package

Burundi / Port infrastructure / World Bank contract data records a USD 26.453 million EPC works contract signed with China Civil Engineering Construction Corporation on 27 July 2026; no cited source confirms notice to proceed, mobilisation or physical construction

award / Last checked
Confirmed

Santoña North Basin fishing-quay structural repair

Spain / Piled fishing-quay concrete rehabilitation and metal fender renewal / Cantabria formalized the EUR 2,486,545.15 excluding-VAT works contract with the Cuevas Gestión de Obras-COMSA UTE on 9 July 2026; the signed contract requires a viable setting-out check before the 24-month execution period starts, while the setting-out act, site mobilisation, monthly production and lower-tier appointments remain unpublished

award / Last checked
Confirmed

Mopti boat-quay access dredging and sediment clearance

Mali / Inland river-port access dredging and sediment clearance / The package was officially launched on 13 February 2025 and a project team inspected progress on 6 March 2025; the latest disclosed procurement plan, dated 13 April 2026, still records the contract only as signed, and no official completion, accepted bathymetry or operating release has been published

construction / Last checked
Confirmed

Ferry Terminal Turku marine and landside works

Finland / Ferry-terminal piers, passenger bridges and port-yard renewal / Pier S1 was handed over on 15 June 2026 but will not enter service until March 2027; the joint terminal, passenger bridges and 11-hectare field works remain under construction, while Quay S2 is targeted for 2028

construction / Last checked
Confirmed

Hooghly four-location floating passenger-jetties package

India / Inland-waterway floating jetties, gangways and passenger facilities / Two lots were signed on 16 August 2024 for Tamlipara, Chinsurah, Metiabruze and Pujali; the June 2026 World Bank ISR says Metiabruze remains under implementation but its results table says all 45 project jetties are complete

construction / Last checked
Confirmed

Castletownbere small craft harbour piling and utilities

Ireland / Fishery harbour piling, civil works and marine utilities / TED published the EUR 1.2498795 million Sorensen award on 5 August 2026 and records contract conclusion on 22 June; no project-specific mobilisation, commencement or subcontractor notice has been published

award / Last checked
Confirmed

Port de Plaisance du Grand Large marine works

France / Marinas, pontoons and berthing infrastructure / SPAD concluded three separate Grand Large marina works contracts on 30 June 2026 with Eiffage Travaux Maritimes et Fluviaux, Atlantic Marine and Ramery Travaux Publics; each lot carries a 24-month planned period, but no dated notice to proceed or field mobilisation has been located

award / Last checked
Confirmed

Port de l'Ayguade du Levant Ro-Ro quay

France / Ro-Ro berth and island freight access / Métropole Toulon Provence Méditerranée concluded contract 98RL25 with Océlian and TP Spada at EUR 2,104,311.99 on 20 August 2025 after an earlier procedure ended without an award; no dated mobilisation or completion record has been located

award / Last checked
Confirmed

Cap-des-Caissie small craft harbour upgrade

Canada / Fishing harbour wharf, dredging and shore protection / Mskikue'j Enterprises holds the CAD 5.09 million wharf and shore-protection contract through March 2027; the separate 2025 dredging and containment-cell contract reached its stated expiry without a public completion or measured-quantity record

award / Last checked
Confirmed

Woodman Point western boat ramp and Fremantle Jetty 1 renewals

Australia / Marinas, pontoons and berthing infrastructure / Jetty and Marine Constructions holds one design-and-construct contract covering the Woodman Point western boat ramp and Fremantle Fishing Boat Harbour Jetty 1; Woodman Point field works began under a 27 July 2026 closure, while a dated Fremantle mobilisation record has not been published

construction / Last checked
Confirmed

Me-Mel Goat Island Western Broadside Wharf repair

Australia / Port infrastructure / Western Broadside Wharf, adjacent seawall and access-pontoon repairs are underway under two NSW contracts through August and September 2026; the published notices name Polaris Marine Constructions and Clement Marine Constructions but do not disclose their exact package split

construction / Last checked
Confirmed

Pearl Harbor Wharf V5 mooring-buoy installation

United States / Port infrastructure / Oceanetics holds the USD 1.378 million Navy task order through 11 September 2026; two reported subawards identify charter support and Ocean Guard buoy supply, while field installation and acceptance remain unverified

award / Last checked
Confirmed

Dar es Salaam berths 1-7 and RoRo electrical-power package

Tanzania / Port berth electrical systems and commissioning / DERM Group signed the USD 20.16 million berth electrical-power works contract in October 2024; the planned June 2026 end has passed without public completion or acceptance evidence

construction / Last checked
Confirmed

Dhalkut Port management, operation and development framework

Oman / Small-port commercial activation, maintenance, dredging and berth readiness / A three-year development, management and operation framework was signed with Abu Sultan Enterprises in December 2025; the planned handover for maintenance and simple operations, physical marine works, capital programme and current operating state are not publicly confirmed

planning / Last checked
Confirmed

Yorkeys Knob boating facility

Australia / Recreational harbour, breakwaters, dredging and boat-launch infrastructure / The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works

completed / Last checked
Confirmed

St. Lawrence fishing harbour wharf reconstruction

Canada / Fishing harbour timber-wharf reconstruction / R.J.G. Construction holds the CAD 3.02 million wharf-reconstruction contract; the stated contract period ended in April 2026, but completion and acceptance are not publicly confirmed

construction / Last checked
Confirmed

Elizabeth Harbour marine redevelopment

Jersey / Ferry-terminal marine works, dredging and demolition / Final design and planning-condition discharge are evidenced; construction was scheduled for autumn 2026, while Stage Two authorization, dredger or piling mobilisation and physical works start remain unpublished

design / Last checked
Confirmed

Raysut Fishery Harbour rehabilitation and sedimentation works

Oman / Fishing-port dredging, breakwater, groyne, quay and reclamation / The Ministry reported 100% completion in May 2026 after an 81% owner update in January; final hydrography, formal acceptance, operating release and most downstream marine packages remain undisclosed

completed / Last checked
Confirmed

Bangladesh WD17 Fish Landing Stations and Markets

Bangladesh / Port infrastructure / World Bank completion reporting confirms three fish landing stations and two fish markets completed by project close on 28 November 2025; five other sites in the original 10-site package could not start because of land-tenure disputes

completed / Last checked
Confirmed

Kidongo Fish Landing Site

Kenya / Port infrastructure / Pristim Supply received the USD 1.355m contract on 11 June 2024; KEMFSED recorded the October 2024 construction launch and published a dated active-workfront photograph, but no completion evidence

construction / Last checked
Confirmed

Kilifi Central Fish Landing Site

Kenya / Port infrastructure / Procost Ideas holds the USD 2.128m contract signed on 11 June 2024; an official November 2024 mission inspected the workfront and reported landing-site works advancing, without a site-specific percentage or completion record

construction / Last checked
Confirmed

Mokowe Fish Landing Site

Kenya / Port infrastructure / Gesken Enterprises holds the USD 1.852m contract signed on 11 June 2024; public sources define a jetty and land-reclamation workfront but do not confirm site-specific mobilisation, completion or acceptance

award / Last checked
Confirmed

Kipini Fish Landing Site

Kenya / Port infrastructure / Toddy Civil Engineering received the USD 1.174m works contract on 11 June 2024 and KEMFSED recorded the October 2024 groundbreaking; no later completion or acceptance evidence has been published

construction / Last checked
Confirmed

Duqm Port Commercial Terminal and Operational Zone IP2

Oman / Port infrastructure / Serka-MSF completed the commercial-terminal fit-out in December 2020; the port is operational, while AIIB's 2025 review says throughput and revenue remain below original forecasts

completed / Last checked
Confirmed

Arctic Bay Small Craft Harbour

Canada / Port infrastructure / Pilitak Enterprises holds the CAD 77.04m construction contract through 7 May 2030; DFO plans construction activity in 2026-27, while current public sources provide no marine mobilisation evidence

construction / Last checked
Confirmed

Albert Pier and St Helier Marina berthing upgrades

Jersey / Marinas, pontoons and berthing infrastructure / Albert Pier's final berthing stage was complete by 6 April 2022 and St Helier Marina's refurbishment by May 2022; Ports of Jersey subsequently confirmed the marina works were on schedule and the combined capacity benefits were in use

completed / Last checked
Confirmed

Port of Santos 16 m channel deepening

Brazil / Port infrastructure / Jan De Nul contract signed on 12 June 2026; official mobilisation, production and acceptance evidence remain ahead

award / Last checked
Confirmed

Hunan Inland Waterway Green Port programme: Daorenji, Songyanghu III and Songmu II

China / Inland-waterway green-port programme, open-piled bulk and general-cargo berths / Daorenji's main marine structure was reported complete in July 2026 with equipment installation and commissioning next; Songyanghu III moved from 1,556 precast deck panels into field installation in January 2026; no current Phase II construction evidence has been found for Songmu. AIIB still lists the proposed sovereign financing as Proposed

construction / Last checked
Confirmed

Frioul East breakwater rehabilitation and rock spur

France / Historic rubble-mound breakwater rehabilitation and island-port protection / Contract Z250608F00 was concluded on 2 February 2026 with an Océlian-led five-company group for EUR 19.589919 million; the owner reports that the overall rehabilitation programme continues in 2026, while main-contract mobilisation, placed rock, accepted sections and downstream subcontract awards remain unpublished

award / Last checked
Confirmed

Ploce New Bulk Cargo Terminal

Croatia / Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems / Civil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacity

completed / Last checked
Confirmed

Gdynia Outer Port protective breakwaters

Poland / Caisson breakwaters and port access infrastructure / The May 2026 building permit has moved the design-build contract into principal in-water works; the first reinforced-concrete caisson was launched and towed toward its placement position in July 2026, with the remaining 48 caissons and breakwater systems still to be delivered

construction / Last checked
Confirmed

Jorf Lasfar Multipurpose Terminal Quay Extension

Morocco / Multipurpose berth extension, block quay, mooring dolphin, access bridge and terminal equipment modernisation / Marsa Maroc says the berth-front extension was launched and remained part of its active 2025 investment programme. Execution-design evidence identifies two quay extensions and a mooring dolphin; no owner acceptance or completed operating release has been published

construction / Last checked
Confirmed

Casablanca Multipurpose Terminal Quay Deepening

Morocco / Brownfield quay strengthening, retaining structure, micropiles, scour protection and capital dredging / Works started on 1 October 2024. Marsa Maroc reported a first 230-metre section commissioned at -12 m, while the published delivery programme continues toward 530 metres of deepened quay plus transition zones by 2028; the civil-works award is confirmed but the contractor remains publicly unnamed

construction / Last checked
Confirmed

Poti Sea Port Berth 14 Rehabilitation

Georgia / Container berth rehabilitation, dredging, quay-top renewal and terminal equipment / EBRD lists Phase 1 as Completed, and a TRACECA technical record says Berth 14 was rehabilitated in 2009 for 1,000-TEU feeder vessels; the exact acceptance date, as-built dredging quantity and depth, delivery contractor and final account remain publicly unresolved

completed / Last checked
Confirmed

Saba Black Rocks Harbor and Fort Bay improvement works

Caribbean Netherlands / Hurricane-resilient harbor, breakwater, dredging, quay and marina works / Public Entity Saba reported steady construction progress on 10 May 2026, including breakwater works and Xbloc arrivals, with additional units being produced in Sint Eustatius. Dredging and excavation were active in March 2026, but marine completion, harbor handover, Fort Bay close-out and operational opening remain unconfirmed.

construction / Last checked
Confirmed

Mo i Rana entrance and Langneset deep-water quay

Norway / Deep-water quay, fairway dredging, contaminated-sediment containment and navigation works / Kystverket reported the Langneset quay in its finishing phase on 29 June 2026, with concrete works nearing completion and technical installations scheduled through summer and autumn; completion and an official opening are planned for autumn 2026, but handover, acceptance and operation remain unconfirmed

construction / Last checked
Confirmed

Galati Multimodal Platform Stage I quay works

Romania / Inland-port quay, dredging, basin infill and intermodal berth works / TED published a further contract modification on 27 May 2026, extending the recorded execution duration by 4 months and 23 days and reducing the stated contract value by RON 1,270.26; the latest owner progress figure located is 62.04% at 30 June 2025, and no completion or acceptance record has been published

construction / Last checked
Confirmed

Marsaxlokk fishing-port fairway dredging

Malta / Fishing-port fairway dredging and beneficial reuse / Transport Malta described the Marsaxlokk works as ongoing on 26 June 2026; the original navigation notice ran to 31 July, but no public final hydrographic survey, accepted quantity, completion certificate or final account was located by 2 August

construction / Last checked
Confirmed

Saint-Malo Terminal du Naye Lot 2 marine works

France / Ferry-terminal marine works, dredging and demolition / Région Bretagne reported one of the two old lock-guide structures under demolition on 1 April 2026 after the 270-tonne Ro-Ro ramp was removed in December 2025; the new reinforced-concrete guide caissons and maintenance dredging remain inside the two-year Lot 2 mission, with no owner acceptance published

construction / Last checked
Confirmed

Killybegs Smooth Point breasting dolphins and shore power

Ireland / Fishery harbour berthing, marine piling and shore power / Sorensen reported all 24 dolphin piles installed in August 2025; the government project page published the following month still described the works as ongoing with substantial completion due in Q3 2025, and DAFM has not published a later handover record

construction / Last checked
Confirmed

Cabo Verde Porto Ingles and Palmeira Ports Modernisation Programme

Cabo Verde / Port infrastructure / Porto Ingles marine works were inaugurated on 7 September 2022 and later received a final price-revision authorization; Palmeira's landside package was awarded to GRINER / Armando Cunha Cabo Verde in July 2024, with no public completion or acceptance record identified by 2 August 2026

construction / Last checked
Confirmed

Dublin Port Marine Works Framework and Berth 29

Ireland / Port infrastructure / Single-party framework active with Murphy International; Berth 29 was handed over in 2024, Murphy reports 21 call-offs delivered during 2025, and owner confirmation of the contractor-stated July 2026 completion target for Berths 30/31 and McCairns Yard has not been identified

construction / Last checked
Confirmed

Inis Oírr Pier Improvement Project

Ireland / Port infrastructure / The construction contract started on 24 September 2025 and Marine Notice 23/2026 records Ward & Burke commencing the two-year marine works; no later completed work package has been published

construction / Last checked
Confirmed

Port Atlantique La Rochelle Chef de Baie 4 terminal

France / Port infrastructure / Quay construction and the four-hectare yard remain the latest official delivery state; handover to operator AMLP was targeted for the second half of 2026 but has not been published

construction / Last checked
Confirmed

Busan New Port West Container Terminal Phase 2-6

South Korea / Deep-water ports and automated container terminals / BPA completed the 23-caisson substructure in August 2024 and is advancing superstructure and automated-equipment packages toward an October 2027 completion and second-half 2027 opening target

construction / Last checked
Confirmed

Thessaloniki Port Pier 6 expansion

Greece / Container terminal expansion, quay construction and dredging / ThPA signed the EUR 195.6 million METKA-TEKAL construction contract in November 2025 and installed the first of 21 quay caissons in July 2026; the second caisson was under construction at publication

construction / Last checked
Confirmed

Oslo Kneppeskjaer East quay replacement and expansion

Norway / Multipurpose quays, dredging and carbon-logistics infrastructure / Repstad Anlegg began works in August 2025; demolition, dredging and subsea blasting preceded a 99-pile quay-foundation programme scheduled from March to July 2026

construction / Last checked
Confirmed

London Gateway Berth 5 quay and automated yard

United Kingdom / Deep-water ports and automated container terminals / Port of London Authority reported the 430-metre Berth 5 quay extension complete by 1 August 2026 while further retaining-wall piling continued toward the Berth 6 interface; the separately contracted ten-module automated yard remains on a contractor-reported programme to March 2027

construction / Last checked
Confirmed

Port of Tanjung Pelepas Berth Zero

Malaysia / Deep-water ports and container terminals / Malaysia Marine Department notices documented Package 1 and Package 2 work vessels on site from January 2026; PTP is delivering a 360-metre berth, dredging, reclamation, yard works and four quay cranes toward commissioning by 2028

construction / Last checked
Confirmed

Noatum Ports Pointe-Noire Terminal

Republic of the Congo / Deep-water ports and container terminals / AD Ports Group awarded two marine and topside contracts to the MAR Contracting-MBTP joint venture and a crane contract to ZPMC on 18 May 2026; the 420-metre terminal is expected to be built over approximately two years

award / Last checked
Confirmed

Congo Terminal East Mole expansion

Republic of the Congo / Deep-water ports, dredging and multipurpose terminals / Congo Terminal reported 400 metres of the planned 750-metre quay complete by 6 July 2026 after all 558 steel piles were driven; dredging and electric-terminal integration remain active toward the 2027 delivery target

construction / Last checked
Confirmed

Tema Port Terminal 3 Phase 2 expansion

Ghana / Deep-water ports and container terminals / Eiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021

completed / Last checked
Confirmed

Colombo West International Terminal

Sri Lanka / Deep-water ports and automated container terminals / Phase 1 has operated since April 2025 and handled one million TEU in its first year; the 1,400-metre quay was complete by March 2026 while Phase 2 crane deployment and full-terminal construction continue

construction / Last checked
Confirmed

Puerto Antioquia multipurpose deep-water terminal

Colombia / Deep-water ports, dredging and multipurpose terminals / Commercial operations began on 5 February 2026 after four controlled vessel trials; the operator's current port-status ledger shows repeat container, breakbulk and refrigerated calls through July 2026

completed / Last checked
Confirmed

San Antonio Puerto Exterior common marine works

Chile / Deep-water ports, dredging and reclamation / Environmental approval was granted on 26 May 2026; six bidders or consortia are prequalified for the common marine-works tender, but no construction award has been announced

tender / Last checked
Confirmed

Baltic Hub T3 deep-water container terminal

Poland / Deep-water ports and container terminals / Marine construction was completed in 2025 and T3 entered full operation in October 2025; 2026 aRMG relocation and yard-line commissioning continue as operational optimisation

completed / Last checked
Confirmed

NEOM green-ammonia export jetty

Saudi Arabia / Deep-water ports and energy terminals / Overall complex above 90% complete; energization and commissioning started, with jetty VTS radar commissioned but first ammonia transfer not confirmed

commissioning / Last checked
Confirmed

Mombasa SEZ DK1 port and jacket quay

Kenya / Port infrastructure / TOA's Package 1 is in construction; KPA reports confirm quay and trestle foundation dredging, while channel, basin, jacket installation and accepted quantities remain open

construction / Last checked
Confirmed

Sagar-Eastern Channel capital dredging

India / Port infrastructure / SMPK completed a non-binding global market EOI for phased capital dredging; a formal RFQ, works award and dredging contractor are not verified

tender / Last checked
Confirmed

Kandla Cargo Berths No. 1-6 upgrade

India / Port infrastructure / DPA is assessing berth-wide repair, strengthening or replacement for an intended EPC package; no expanded-consultant award, EPC tender or works contractor is verified

design / Last checked
Confirmed

Kandla Multipurpose Cargo Berth No. 17

India / Port infrastructure / DPR work started in March 2025; no construction RFP, PPP award, concessionaire or works contractor is verified

design / Last checked
Confirmed

Chennai Port Berth 19A North Quay reconstruction

India / Port infrastructure / Technical audit and detailed engineering are commissioned through 31 December 2027; no construction tender, award or works contractor is verified

design / Last checked
Confirmed

Daba fishing port development

Oman / Port infrastructure / 75% complete in June 2024 with some facilities operating; full completion and formal opening remain unverified

commissioning / Last checked
Confirmed

Masirah multipurpose fishing port

Oman / Port infrastructure / OMR 28.612 million design-and-build award confirmed; current construction progress and marine subcontract chain remain partly undisclosed

construction / Last checked
Confirmed

Vermilion Harbor East Pier repair

United States / Port infrastructure / USACE officially completed the East Pier repair on 24 July 2026 after rebuilding 900 feet of the 1,333-foot structure

completed / Last checked
Confirmed

Port of Cotonou Terminal 5 bulk terminal

Benin / Port infrastructure / The port authority reports 69% physical progress and 72% overall progress, while its published 2021-2024 delivery period is no longer current

construction / Last checked
Confirmed

Ruwais LNG marine access and export terminal

UAE / Deep-water ports and energy terminals / Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published

construction / Last checked
Confirmed

Damietta Alliance Container Terminal (Tahya Misr 1)

Egypt / Deep-water ports and container terminals / Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity

commissioning / Last checked
Confirmed

Can Gio International Transshipment Port

Vietnam / Deep-water ports and container terminals / Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced

approval / Last checked
Confirmed

Richmond Inner Harbor FY26 maintenance dredging

United States / Port infrastructure / Updated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recorded

tender / Last checked
Confirmed

Bangladesh Bay Terminal marine infrastructure

Bangladesh / Port infrastructure / IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started

design / Last checked
Confirmed

Port Douglas Boat Harbour 2026 maintenance dredging

Australia / Port infrastructure / Owner-defined cutter-suction campaign scheduled from July to October 2026; contractor and mobilisation remain unconfirmed

approval / Last checked
Confirmed

Nauru Aiwo Port climate-resilient redevelopment

Nauru / Port infrastructure / ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items

construction / Last checked
Confirmed

Patimban Port Phase 1-2 expansion

Indonesia / Port infrastructure / Phase 1-1 is completed and partly operating; Package 5 car-terminal and Package 6 container-terminal works remained active through June 2025; Package 7 construction lacks a current owner or contractor mobilisation date

construction / Last checked
Confirmed

Nigeria Snake Island Container Terminal concession and EPC

Nigeria / Deep-water ports and container terminals / MSC signed a 45-year sub-concession and finalized the ITB/DEME EPC on 11 March 2026; the reviewed project sources do not record mobilisation

award / Last checked
Confirmed

Dublin Port MP2 Berths 52 and 53 marine construction

Ireland / Port infrastructure / Marine construction is active; the 2026 harbour notice keeps the buoyed work zone in place through January 2027, while berth acceptance and service release remain open

construction / Last checked
Confirmed

Rocky River Harbor 2026 maintenance dredging

United States / Port infrastructure / Mechanical dredging began in late May 2026 and is scheduled to continue through August

construction / Last checked
Confirmed

Ramayapatnam Port capital deepening works

India / Port infrastructure / Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed

award / Last checked
Confirmed

Westport Kwinana container port and marine infrastructure

Australia / Port infrastructure / Marine reference design, investigations, environmental-review preparation, and construction planning active; Westport Bill remains before Parliament

design / Last checked
Confirmed

Port Hedland Zone 5 Bypass Channel

Australia / Port infrastructure / A$50 million dredging contract awarded; the federal sea-dumping application remains unresolved ahead of planned September mobilisation

award / Last checked
Confirmed

Genoa New Breakwater

Italy / Ports and coastal protection / 24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active

construction / Last checked
Confirmed

Skandia Gateway fairway and quay deepening

Sweden / Port infrastructure / Quay construction active; port-side dredging awarded; optimized national fairway package in procurement for 2027-2028 delivery

construction / Last checked

Current research

Latest publications connected to this sector

6 shown / 282 current
Lekki Port entrance buildings, container stacks and quayside cranes in a 2026 port-context photograph
Brief / Confirmed

Lekki: Match Maintenance Dredging to the Beach Sand Budget

Lekki's design connects maintenance dredging to the artificial beach east of the port. A 2023 study by authors at CCCC-FHDI and China Harbour describes west-to-east sand transport interrupted by the port structures, with nourishment intended to replenish the downdrift beach. Its modelled sand supply combines western deposits with material recovered from the basin and channel [1]. A dredging campaign feeding that beach needs both a navigation cut and a suitable fill supply.

Updated
Lagos Omi Eko diagram contrasts parking reallocation and additional charging land with the jetty and passenger-access interface
Brief / Confirmed

Lagos Omi Eko: The Charging Footprint Changes the Jetty Workfront

Lagos's Omi Eko electric-ferry programme brings a land problem into the jetty design. The environmental assessment identifies room for charging at Marina, Ikorodu, Badore, Bariga and Festac through parking reallocation. Falomo faces a tighter site with likely additional land requirements; Ebute Ojo, Liverpool, Oworonshoki and Baiyeku also require additional land in that assessment. EIB's June 2025 appraisal describes 25 jetties and stations, 12 charging and electricity-generation locations and two terminals equipped for daily or light maintenance. Each civil workfront needs enough shore space to make its waterfront usable. [2][3]

Updated
Makassar New Port separates Q1 2025 berth and yard occupancy from domestic crane effective-time and berth-time productivity
Brief / Confirmed

Makassar New Port: Test the Berth-Time Loss Before Committing Phase 1D

Makassar New Port entered its expanded operating phase with 1,280 m of quay and a reported 52 ha footprint at its February 2024 inauguration. Pelindo described Phase 1D as a further increment to be developed in response to demand. The subsequent operating records give an owner a practical starting point for that decision: the terminal's first-quarter 2025 berth occupancy was 28.49%, with yard occupancy of 39.61%. Pelindo's publication through August 2026 lists TPK New Makassar at 26.88 boxes per ship-hour gross for domestic containers. These dated measures support a closer examination of how existing berth time is used. [1][3][4]

Updated
Lach Huyen schematic separates the 375 m main berth, perpendicular 150 m barge wharf and parallel 50 m tug base, with dated full-load and partial-load ship cases
Brief / Confirmed

Lach Huyen: Planning a Partial-Load Call Across Three Wharves

HTIT welcomed MSC SPARKLE III and launched MSC's Pearl service on 9 October 2026. Behind that new service sits a conditional ship-size approval: Port of Hai Phong's 14 August 2025 account describes approval in principle for partially laden container ships of up to 165,000 DWT at berths 3 and 4. Its earlier April opening notice described berth 4 accepting 100,000-DWT ships fully laden. A planner needs the vessel's actual arrival condition alongside those dated operating records. [1][3][4]

Updated
Mumbai marina diagram separates 424 Phase I berths and the remaining 180 to a planned 604, alongside port-built marine and concession scope.
Brief / Confirmed

Mumbai Marina Bids Need a Defined Marine-Asset Handover

Mumbai Port is procuring a 45-year marina concession while undertaking Phase I marine works. Bidders need to connect the revenue offer to the condition, capacity and release dates of the assets they will operate.

Updated
Paranagua Moegao task-duration diagram distinguishes two hours of lifting and four more fixing a 55 m,35-tonne structure during the 11 October operation.
Brief / Confirmed

Paranagua Conveyor Lift Connects Two Construction Programmes

A 55 m steel structure connects ALTP to the Moegao rail-receiving system. The installed link now needs to become part of a tested material-handling route, with public and terminal work reaching the same handover condition.

Updated

Delivery network

Organizations connected to this collection

6 shown / 160 profiled
Harwich Haven waters and Port of Felixstowe cranes in the operating context of HHA's Tiamat launch
UK dredging joint-venture LLP

Suffolk Dredging LLP

Maintenance-dredging contract supplier / Tiamat licensee / Harwich dredging joint venture

Last checked
American Construction Company floating crane, tug and marine construction plant working on a Seattle waterfront
Pacific Northwest marine construction and dredging contractor

American Construction Company

Navigational maintenance-dredging contractor / Environmental and contaminated-sediment dredging contractor / Open-water and contained material-placement contractor

Last checked
USACE hopper dredge Essayons operating in the Columbia River near Cathlamet, Washington
Federal water-resources agency and navigation-project owner

U.S. Army Corps of Engineers, Civil Works

Federal navigation project owner / Coastal and inland navigation asset manager / Planning, design, construction and operations-and-maintenance authority

Last checked
IMWO illustrated guide to Boskalis' Dredging and Inland Infra, Offshore Energy, and Towage and Salvage businesses, separating corporate capabilities from individual project assignments
Dredging, marine infrastructure and offshore-energy contractor

Boskalis

Capital and maintenance dredging contractor / Port, waterway and reclamation contractor / Coastal defence, riverbank and hydraulic-infrastructure contractor

Corporate facts reviewed Procurement checked
Official execution drawing comparing Tarifa fishing wharf's existing 20 kV route with the proposed 20 kV route to the new transformation centre
Spanish state-port authority and marine-infrastructure owner

Algeciras Bay Port Authority (APBA)

State-port authority / Port infrastructure owner and landlord / Marine and utility works client

Last checked
Aerial view of Callan Marine cutter suction dredge General Bradley working beside a floating pipeline and coastal placement area
Dredging and marine construction contractor

Callan Marine

Capital and maintenance dredging contractor / Navigation-channel and berth dredging contractor / Beneficial-use and dredged-material placement contractor

Last checked

Continue the sector evidence review

Search the public index for this delivery discipline, compare mapped projects, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.

Search Port infrastructure Open project tracker Open sector guide Review methodology