The Montreal Port Authority is developing a 1.15 million TEU container terminal at Contrecœur, about 40 kilometres downstream from Montreal. Site preparation began in October 2025, a 300-tonne marine-construction crane was assembled in June 2026, and the official works log recorded a 13-15 July 2026 window for quay-wall sheet-pile delivery and storage. The owner's documentation centre now exposes annual, monitoring, compensation, communication, complaint, and environmental data routes that should be read separately from physical delivery proof. A CAD 1.16 billion Canada Infrastructure Bank loan supports the programme, while the next physical proof point remains execution of the quay, dredging, and vessel-access works.
Canada / Americas
Port infrastructure
Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access / Confirmed
15 August 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe live works log set 13-15 July for delivery, unloading, and on-site storage of quay-wall sheet piles, advancing the supply sequence without confirming that delivery was completed or that sheet-pile driving and in-water construction had started.
SourceThe owner reports that the crane was raised and ready for pile and sheet-pile operations after delivery in 13 convoys and a week of assembly. Pile driving, quay progress and dredging remained unreported.
SourceThe loan materially strengthens the financing path for the owner-led terminal programme, but it is neither a disclosed total project cost nor evidence that the marine package, dredging, or vessel-access works have been completed.
SourceThe authorization clears a central regulatory gate under the Fisheries Act and Species at Risk Act while binding construction to specified measures and conditions. Physical commencement and compliance acceptance remained separate, unreported steps.
SourceFencing, access roads, work platforms, targeted tree cutting, and site facilities established the land-preparation baseline. The owner record does not describe this milestone as sheet-pile driving, dredging, or completed in-water works.
SourceEvidence gap