Coverage focus
Urban waterfront and mixed-use waterside delivery
Sector intelligence
Urban waterfronts, marinas, logistics edges, tourism waterfronts, resilience upgrades, and mixed-use waterside construction.
Projects retain their detailed work segment and may appear in more than one sector when the scope crosses delivery disciplines.
Urban waterfront and mixed-use waterside delivery
25 project records connected to this sector.
32 current analyses and briefs connect through governed project relationships.
20 public profiles connect through documented project roles.
Project coverage
Australia / Public jetty and towage access / Design and approvals;2027 start planned
planning / Last checkedIndia / Marina infrastructure and concession / Concession bids due 15 December 2026
tender / Last checkedUnited Kingdom / Moveable bridge marine access / Span removal scheduled for 2 November week
construction / Last checkedFiji / Marine utilities / CW02 prequalification applications closed on 30 September 2026; bidding invitations expected in December 2026
prequalification / Last checkedCanada / Port infrastructure / Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access
construction / Last checkedCzechia / Inland marina quay edges, floating fingers, bank protection and utilities / The Czech Waterways Directorate opened 30 new public berths in August 2025 and the Transport Ministry reports the expanded marina operating with capacity for 66 boats in the 2026 season; IDS holds the phase-one works contract, with the highest reviewed official modification snapshot at CZK 86,312,219.98
completed / Last checkedUnited Kingdom / Port infrastructure / Construction contract awarded; site preparations commenced
construction / Last checkedAustralia / Urban ferry terminal, floating platform and passenger gangway / Maritime Constructions holds the AUD 1,756,143 fixed-price design-and-construct award; Tenders WA does not publish a start date, expiry date, mobilisation or completion milestone
award / Last checkedIndia / Inland-waterway floating jetties, gangways and passenger facilities / Cleghorn Mfg. Co. signed the six-location bundled supply and installation contract on 24 April 2025; public evidence does not confirm final sites, fabrication, installation, commissioning or acceptance
award / Last checkedIndia / Inland-waterway floating jetties, gangways and passenger facilities / Nalanda Engineering Enterprise signed the seven-location bundled supply and installation contract on 3 April 2025; public evidence does not confirm fabrication, installation, commissioning or acceptance
award / Last checkedNetherlands / Quay-wall replacement and waterfront public-realm renewal / TED notice 542353-2026 records a EUR 7,887,000 contract with De Vries Werkendam B.V. concluded on 4 August 2026; the owner plans physical works from 5 October 2026 to 21 July 2028 and publishes no current mobilisation evidence
award / Last checkedOman / Fishing-port concession, commercial waterfront and operating PPP / Liwa remained in Oman's 2024 PPP and fisheries-investment pipeline after 2021 and 2023 market approaches; a selected developer and financial close remain undisclosed through 8 August 2026
tender / Last checkedIndia / Inland-waterway floating jetties, gangways and passenger facilities / Signed with Merolyn on 11 November 2025; procurement is under implementation, while physical delivery is unverified
award / Last checkedIndia / Inland-waterway floating jetties, gangways and passenger facilities / IWAI signed the five-site Lot A contract with West Coast Marine Yacht Services on 18 March 2026; the procurement plan lists the package under implementation, but fabrication, installation and site acceptance remain publicly unconfirmed
award / Last checkedBarbados / Coastal infrastructure / C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished
construction / Last checkedIndia / Inland-waterway floating jetties, gangways and passenger facilities / World Bank data identifies 21 direct works contracts across the 29-jetty Phase I and 16-jetty Phase II programme; the June 2026 ISR says 44 of 45 locations are complete with Metiabruze under implementation, while its results table says all 45 are complete
construction / Last checkedFinland / Ferry-terminal piers, passenger bridges and port-yard renewal / Pier S1 was handed over on 15 June 2026 but will not enter service until March 2027; the joint terminal, passenger bridges and 11-hectare field works remain under construction, while Quay S2 is targeted for 2028
construction / Last checkedIndia / Inland-waterway floating jetties, gangways and passenger facilities / Two lots were signed on 16 August 2024 for Tamlipara, Chinsurah, Metiabruze and Pujali; the June 2026 World Bank ISR says Metiabruze remains under implementation but its results table says all 45 project jetties are complete
construction / Last checkedBurundi / Marine infrastructure / Ongoing at programme level; March 2025 remains the latest quantitative Phase I physical-progress baseline
construction / Last checkedAustralia / Port infrastructure / Owner-defined cutter-suction campaign scheduled from July to October 2026; contractor and mobilisation remain unconfirmed
approval / Last checkedLiberia / Coastal infrastructure / The West Point revetment has an approved ESIA and March 2026 environmental permit; construction award, notice to proceed and physical start are not established
approval / Last checkedSenegal / Coastal infrastructure / Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed
construction / Last checkedSpain / Port infrastructure / Main quay works under construction after the Q4 2024 start
construction / Last checkedBelgium / Port infrastructure / Quay-wall construction and marine works in progress
construction / Last checkedTuvalu / Port infrastructure / Nui and Niutao harbour works completed and opened; operating performance and maintenance now under review
completed / Last checkedCurrent research
Mumbai Port is procuring a 45-year marina concession while undertaking Phase I marine works. Bidders need to connect the revenue offer to the condition, capacity and release dates of the assets they will operate.
Updated
Three Pero's Bridge spans are due to move by barge in the week of 2 November. Survey work and the approaching Netham winter closure put separate constraints on harbour access and marine plant movements.
Updated
Bowen's public jetty and proposed commercial towage wharf may share a wider, higher causeway. Public access and commercial servicing would use common infrastructure while the towage facility follows its own funding and approval process.
Updated
Six procurement routes compare adviser selection, dredging, licensing, concessions and treatment-plant prequalification. Southampton includes its 12 August Boskalis selection and a 15 October licence-status review; Kinoya includes the September deadline correction and expected December invitations. Four other cases retain their dated August positions.
Updated
WAF's CW02 prequalification applications closed on 30 September 2026 at 15:00 Fiji time (GMT+12), following a September corrigendum. Bidding invitations are expected in December for up to three shortlisted eligible applicants. The estimated US$104.85 million Kinoya upgrade combines 36 MLD treatment capacity, five years of operations and reuse of the existing 2.4 km Laucala Bay outfall.
Updated
Maritime Constructions holds the AUD 1,756,143 PROPTA25042 design-and-construct award for a new ferry platform and gangway at Elizabeth Quay. Tenders WA confirms five submissions and an integrated scope from engineering and fabrication through installation, testing, commissioning and warranty, while commencement, expiry and field mobilisation remain unpublished.
UpdatedDelivery network
National public water and wastewater utility / Kinoya treatment-plant owner and existing operator / CW02 employer, procuring agency and contract-management counterparty
Last checked
Capital and maintenance dredging contractor / Port, waterway and reclamation contractor / Coastal defence, riverbank and hydraulic-infrastructure contractor
Corporate facts reviewed Procurement checked
Statutory public passenger transport authority / Transperth metropolitan ferry-service client and system manager / Public transport infrastructure designer, builder and maintainer
Last checked
National inland-waterway investment preparation and delivery / Public port, landing-place and mooring infrastructure / Waterway modernization, repair and maintenance
Last checked
National-waterway development and statutory regulation / Fairway maintenance, hydrographic surveying and dredging / Multimodal terminals, community jetties and floating pontoons
Last checked
Integrated infrastructure developer and contractor / Water design and construction contractor / Desalination EPC and commissioning lead
Last checkedSearch the public index for this delivery discipline, compare mapped projects, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.
Search Waterfront infrastructure Open project tracker Open sector guide Review methodology