Project record

Maassluis M2 quay-wall replacement and waterfront renewal

Participation
Not assessed
Project facts checked

TED notice 542353-2026 records a EUR 7,887,000 contract with De Vries Werkendam B.V. concluded on 4 August 2026; the owner plans physical works from 5 October 2026 to 21 July 2028 and publishes no current mobilisation evidence

Project sources

Gemeente Maassluis has awarded De Vries Werkendam B.V. a EUR 7,887,000 contract to replace approximately 210 m of quay wall on the east side of the Haven and reconfigure approximately 3,000 m2 of public space. TED records contract conclusion on 4 August 2026. The municipality's project page, last modified the same day, says physical work is planned for 5 October 2026 to 21 July 2028. That owner programme differs from the TED procurement periods and no cited source yet proves site possession, first waterside operation or installed work.

Official Maassluis Haven M2 quay wall construction phases showing the retaining wall and raking piles in the staged replacement sequence

Gemeente Maassluis / Ingenieursbureau Maters en De Koning; exact official construction-phase drawing, not current progress or as-built evidence

Location

Netherlands / Europe

Segment

Quay-wall replacement and waterfront public-realm renewal

Phase

Award / Confirmed

Last checked

8 August 2026

Coverage

Related sectors

Quay-wall replacement and waterfront public-realm renewal is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Gemeente Maassluis
Delivery parties
De Vries Werkendam B.V. - confirmed main contractor under TED notice 542353-2026, Sheet-pile, piling, demolition, temporary-works, public-realm, survey and utility lower tiers - no organization disclosed
Contract route
Gemeente Maassluis used an EU open works procedure under TED procedure 3618cf23-2ac0-42bb-bbe1-90567d6ff804. Tender notice 107393-2026 was published on 16 February 2026. Award notice 542353-2026, published on 5 August, identifies De Vries Werkendam B.V. as the single winner, records contract conclusion on 4 August and states that no subcontracting is reported.
Execution window
The original tender notice planned 7 July 2026 to 24 December 2027, and the award notice carries 3 August 2026 to 24 December 2027. The municipal page instead plans physical delivery from 5 October 2026 to 21 July 2028. These scheduling fields do not establish site possession, mobilisation, first physical work, completion or acceptance; an accepted contract programme must reconcile them.
Works package
The works replace approximately 210 m of the M2 quay wall on the east side of the Haven and renew approximately 3,000 m2 of adjoining public space. The owner says the 1935 structure has a poor foundation and is rotating toward the water. Its official phase drawing shows staged demolition, temporary support, new retaining-wall installation, raking piles, a structural floor, anchors, quay wall and furniture; the public-space plan shows the linear waterfront arrangement. These drawings define intended scope, not completed quantities.
Marine interfaces
Delivery must maintain stability along an ageing inner-harbour edge while existing elements are removed and a new retaining and piled structure is formed. Critical interfaces include the temporary October 2024 stabilisation, retained foundations, demolition sequence, water-side access, sheet-pile and raking-pile installation, anchors, structural slab, utilities, adjacent properties, traffic and public-space reinstatement. Marine plant, issued-for-construction quantities, utility diversions and navigation controls remain undisclosed.
Commercial evidence boundary
TED records EUR 7,887,000 as the contract result and identifies De Vries Werkendam as a medium-sized enterprise. No cited record establishes a final account, payment status, variations, contingency allocation, lower-tier values or savings. The value should not be combined with unverified programme or municipal budget figures.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Main works award

M2 quay-wall replacement and Haven public-space renewal

Named party
De Vries Werkendam B.V.
Evidence status
Confirmed
Source position
TED notice 542353-2026 records a EUR 7,887,000 result and contract conclusion on 4 August 2026. Source
Physical scope

Approximately 210 m of quay wall and 3,000 m2 of public space

Named party
Gemeente Maassluis and De Vries Werkendam B.V.
Evidence status
Confirmed
Source position
The municipal project page and official drawings define the wall length, public-space area and staged structural concept. Source
Current owner programme

Physical works from 5 October 2026 to 21 July 2028

Named party
Gemeente Maassluis and De Vries Werkendam B.V.
Evidence status
Confirmed
Source position
The owner page last modified on 4 August publishes this planned field window, which differs from both TED period fields. Source
Tender and award calendars

Procedure-period fields

Named party
Gemeente Maassluis and De Vries Werkendam B.V.
Evidence status
Confirmed
Source position
Tender notice 107393-2026 and award notice 542353-2026 publish different start fields and the same 24 December 2027 end field; neither proves physical progress. Source
Lower-tier delivery chain

Piling, steel, demolition, temporary works, utilities, survey and public realm

Named party
No lower-tier organization named
Evidence status
Undisclosed
Source position
TED reports no subcontracting, and no package-specific subcontractor or supplier is disclosed.
Mobilisation and acceptance

Site start, installed work and handover

Named party
Gemeente Maassluis and De Vries Werkendam B.V.
Evidence status
Not evidenced
Source position
The contract is awarded, but no cited source establishes site possession, first operation, measured progress, completion testing or owner acceptance.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

TED publishes the M2 award

The notice fixes De Vries Werkendam and the EUR 7.887 million result while leaving physical mobilisation and lower tiers unproven.

Source

Contract concludes and owner updates the delivery window

The legal award is fixed, while the owner sets a later October 2026 to July 2028 field programme that must be reconciled with TED.

Source

Municipal council approves the plan and budget

The owner authorises replacement of the failing 1935 wall and associated public-space renewal before the later contract award.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Award effectiveness, notice to proceed and site possession
  • Accepted programme reconciling TED and owner dates
  • First physical quay-wall operation after the planned October start
  • Temporary support and responsibility for the 2024 stabilisation interface
  • Retaining-wall, raking-pile, anchor and structural-floor quantities
  • Utilities, traffic, property access and public-space sequencing
  • De Vries delivery team, subcontractors, suppliers and marine plant
  • Progress measurements, variations, final value and owner acceptance

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
8 August 2026
Cited sources
6

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 6