Project record
IWAI signed the five-site Lot A contract with West Coast Marine Yacht Services on 18 March 2026; the procurement plan lists the package under implementation, but fabrication, installation and site acceptance remain publicly unconfirmed
Contract record 1882585 identifies West Coast Marine Yacht Services Private Limited as the supplier for Lot A of IWAI package IN-IWAI-490109-GO-RFB at USD 2,158,478.24. The official tender allocates five National Waterway-1 locations to this lot: Ghoramara, Nischintapur, Nainan and Katakhali in South 24 Parganas, plus Basudevpur in Howrah. Each site is specified with a 24 m by 5 m concrete pontoon assembled from four units and a 9 m by 2 m HDPE floating walkway. Public evidence confirms the signed prime contract, not current fabrication, load-out, installation or acceptance.
India / Asia Pacific
Inland-waterway floating jetties, gangways and passenger facilities
Award / Confirmed
7 August 2026
Coverage
Inland-waterway floating jetties, gangways and passenger facilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogWest Coast Marine Yacht Services became the confirmed supplier and installation contractor at USD 2,158,478.24; lower tiers and physical progress remain undisclosed.
SourceThe tender fixed the five locations in each lot, the modular pontoon and HDPE-walkway scope, the six-month handover requirement and 24-month upkeep obligation.
SourceEvidence gap