Project record
Ramboll CM / Port of Turku; project-specific completion image published 16 June 2026
Port of Turku is rebuilding its passenger harbour through separately procured marine, building, passenger-access and field packages. Terramare completed and handed over the new S1 pier in June 2026 after heavy piling, concrete, underwater erosion-protection and linkspan work. Oteran is renewing about 11 hectares of operational field area, and Skanska holds both the joint passenger-terminal contract and a separate turnkey passenger-gangway and three-bridge package. S1 handover is a civil completion milestone, not operational opening: the first Tallink Silja call is scheduled for March 2027. Quay S2 remains a later refurbishment package targeted for 2028.
Finland / Europe
Ferry-terminal piers, passenger bridges and port-yard renewal
Pier S1 was handed over on 15 June 2026 but will not enter service until March 2027; the joint terminal, passenger bridges and 11-hectare field works remain under construction, while Quay S2 is targeted for 2028 / Confirmed
5 August 2026
Coverage
Ferry-terminal piers, passenger bridges and port-yard renewal is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe first construction contract reached owner handover after piling, concrete, underwater erosion protection, diving and linkspan installation. Operational use remains scheduled for March 2027.
SourceThe later package includes quay refurbishment, a passenger gangway, three boarding bridges, a main deck ramp and side ramp. The Port named no contractor as of 5 August 2026.
SourceThe owner reported underground utilities, stormwater work and lighting-mast foundations in the field area while terminal finishing and building-services installation advanced.
SourceThe owner identified Oteran as project-management contractor for the approximately 11-hectare ISPS field renewal and set a three-stage programme through 2027.
SourceThe turnkey scope covers the gangway between terminal and pier plus three boarding bridges, including design, construction, building services and hydraulics.
SourceThe three-storey terminal exceeds 10,000 m2 and was scheduled for completion around the end of 2026 or early 2027.
SourceTED recorded Terramare Oy as contractor and EUR 20.55 million as award value for the S1 pier construction package.
SourceEvidence gap