Port of Antwerp-Bruges is building a 362-metre liquid CO2 export quay at Kanaaldok B2, but the marine civil schedule now runs ahead of several export-chain decisions. Quay works are planned through March 2027, while Fluxys c-grid's 2026 network plan makes the terminal connection conditional on technical and economic justification and signed contracts, and references a mid-2029 operational horizon in its current terminal-planning language.
Belgium / Europe
Port infrastructure
Quay-wall construction and marine works in progress / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The 21 May specification defines a current vapor-network baseline and supersedes the October 2023 version, but it is explicitly non-binding. Terminal, loading-arm, carrier, liquid-product and storage compatibility remain unconfirmed.
Read controlling sourceThe 2026 network plan makes the terminal link conditional on technical and economic justification and signed contracts, and references mid-2029 in its current terminal-operational planning language. It is not a terminal final investment decision or commissioning confirmation.
Read controlling sourceThe 20-year appointment established Fluxys c-grid Antwerp's regulated network role while the first port-area pipeline was already under construction. It did not confirm terminal investment, customer contracts, marine loading, export service, or stored volume.
Read controlling sourceThe owner and contractor place the 362-metre quay package in execution from September 2025, with piling, concrete, demolition, and dredging sequenced through early 2027. Start of works is not berth handover or export readiness.
Read controlling sourceThe owner separated capture, the open-access pipeline backbone, phased liquefaction terminal, and a quay for two simultaneous seagoing vessels. That interface map clarifies dependencies; award, completion, commissioning and carrier availability remain open.
Read controlling sourceThe EUR 144.6 million grant agreement supported shared transport, liquefaction and export infrastructure under a June 2027 action frame. Grant execution is not the EUR 22 million quay award, terminal final investment decision, construction completion, or operation.
Read controlling sourceAir Liquide, Fluxys and the port announced CEF support for an open-access pipeline, liquefaction, buffer-storage and marine-loading system. The announcement described a step toward final investment decision, not the decision itself or physical delivery.
Read controlling sourceDelivery watch
Verify completion of quay-wall concrete works through October 2026 and old-quay demolition and dredging through January 2027, then track berth handover, binding CO2 interface requirements, terminal final investment decision, Phase 1b pipeline connection, marine-loading acceptance, first carrier call, exported volume, and confirmed storage injection.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerPort of Antwerp-Bruges identifies Kanaaldok B2 as an in-progress quay project running from 15 September 2025 to 1 March 2027, with a water barrier, piling, quay-wall concrete, old-quay demolition, and dredging. Herbosch-Kiere identifies the 362-metre quay, Hens-Herbosch-Kiere joint venture, EUR 22 million total tender value, and early-2027 completion. The owner's April 2025 explanation separates capture, a port pipeline backbone, a phased 2.5-to-10-Mtpa liquefaction terminal, and a quay intended to load two seagoing vessels at once. CINEA and Air Liquide establish the EUR 144.6 million EU-backed common infrastructure and June 2027 grant-action frame; those records do not prove final investment decision or operation. Fluxys confirms that the first port-area CO2 pipeline was under construction when c-grid Antwerp received a 20-year local-network appointment in March 2026. Its 2026 Network Development Plan makes the terminal connection a separate Phase 1b package subject to technical and economic justification and signed contracts, and contains compressed wording linking terminal planning to a mid-2029 operational horizon; That sentence is not a firm commissioning commitment. The 21 May 2026 CO2 quality specification supersedes the October 2023 vapor specification but is explicitly non-binding and does not constitute liquid-terminal, ship-loading, carrier, or storage acceptance.
Phase: construction. Evidence reviewed: 15 July 2026.