Project record

Antwerp Kanaaldok B2 liquid CO2 export quay

Kanaaldok B2 quay construction preparation beside the working dock, with excavation, temporary lining, earthworks, and marine-industry infrastructure visible across the water

Herbosch-Kiere

Port of Antwerp-Bruges is building a 362-metre liquid CO2 export quay at Kanaaldok B2, but the marine civil schedule now runs ahead of several export-chain decisions. Quay works are planned through March 2027, while Fluxys c-grid's 2026 network plan makes the terminal connection conditional on technical and economic justification and signed contracts, and references a mid-2029 operational horizon in its current terminal-planning language.

Project signal

Construction in Belgium

Current status Quay-wall construction and marine works in progress Source confidence Confirmed

Location

Belgium / Europe

Segment

Port infrastructure

Status

Quay-wall construction and marine works in progress / Confirmed

Last checked

15 July 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Port of Antwerp-Bruges
Delivery parties
Hens NV, Herbosch-Kiere NV
Contract route
EUR 22 million quay-wall works contract delivered by the Hens-Herbosch-Kiere joint venture; the wider Antwerp@C CO2 Export Hub has separate EU-backed terminal, pipeline, and operating arrangements
Execution window
Quay works run from September 2025 to early March 2027. The owner schedule places piling in January-April 2026, concrete quay-wall construction in January-October 2026, and old-quay demolition and dredging in April 2026-January 2027.
Works package
Construct a 362-metre quay wall at berths 770-772 for seagoing liquid CO2 carriers, including a water-retaining barrier, piling, concrete quay works, demolition of existing pavement and quay infrastructure, dredging, and integration with the adjacent export-terminal plot.
Marine interfaces
The package joins active-dock piling, earth and water retention, concrete quay construction, old-quay demolition, dredging, berth geometry, mooring, marine loading, vessel access, terminal storage and liquefaction, the port-area CO2 pipeline, and onward shipping to permanent North Sea storage.
Commercial evidence boundary
The EUR 22 million marine construction package is awarded and in progress, but its March 2027 works endpoint is not the export-service start. The latest network plan keeps the terminal connection dependent on technical and economic justification and signed contracts; the May 2026 vapor-quality specification is explicitly non-binding. Berth acceptance, liquid-CO2 loading systems, terminal investment and commissioning, pipeline connectivity, carrier availability, receiving-storage access, and contracted customer volumes remain separate commercial and delivery gates.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

The port published an updated CO2 quality interface

The 21 May specification defines a current vapor-network baseline and supersedes the October 2023 version, but it is explicitly non-binding. Terminal, loading-arm, carrier, liquid-product and storage compatibility remain unconfirmed.

Source

Fluxys separated the terminal connection into network Phase 1b

The 2026 network plan makes the terminal link conditional on technical and economic justification and signed contracts, and references mid-2029 in its current terminal-operational planning language. It is not a terminal final investment decision or commissioning confirmation.

Source

Flanders appointed the local CO2 network operator

The 20-year appointment established Fluxys c-grid Antwerp's regulated network role while the first port-area pipeline was already under construction. It did not confirm terminal investment, customer contracts, marine loading, export service, or stored volume.

Source

Kanaaldok B2 quay construction entered its works window

The owner and contractor place the 362-metre quay package in execution from September 2025, with piling, concrete, demolition, and dredging sequenced through early 2027. Start of works is not berth handover or export readiness.

Source

The port defined four separate export-chain packages

The owner separated capture, the open-access pipeline backbone, phased liquefaction terminal, and a quay for two simultaneous seagoing vessels. That interface map clarifies dependencies; award, completion, commissioning and carrier availability remain open.

Source

CINEA handed over the EU grant agreement

The EUR 144.6 million grant agreement supported shared transport, liquefaction and export infrastructure under a June 2027 action frame. Grant execution is not the EUR 22 million quay award, terminal final investment decision, construction completion, or operation.

Source

The EU funding selection moved the hub toward investment

Air Liquide, Fluxys and the port announced CEF support for an open-access pipeline, liquefaction, buffer-storage and marine-loading system. The announcement described a step toward final investment decision, not the decision itself or physical delivery.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Quay-wall concrete and pile acceptance
  • Old-quay demolition and dredging progress
  • Berth depth, mooring, and marine-loading acceptance
  • CO2 pipeline and liquefaction-terminal commissioning
  • First carrier call and evidenced export volume
  • Alignment with receiving transport and North Sea storage capacity

Reporting status

Construction, confirmed confidence

Last checked 15 July 2026 across 10 cited sources. The dated timeline above carries the project events.

Last checked 15 July 2026 Cited sources 10

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 10