Water Authority of Fiji has opened CW02 for an estimated US$104.85 million operate-design-build-operate upgrade of Kinoya wastewater treatment plant, including five years of operations and maintenance. ADB's environmental assessment fixes the current marine boundary: the 36 MLD Stage 1 plant will disinfect treated effluent before reusing the existing 2.4 km Laucala Bay ocean outfall, with no new offshore pipeline identified in the reviewed package.

Project signal

Prequalification in Fiji

Treat CW02 as a plant-process, commissioning, operations, and discharge-compliance opportunity with a confirmed existing marine receptor. Do not market it as a new outfall or offshore pipeline package unless later design, permit, or tender documents add such scope. Separate treatment performance at the plant boundary from ecosystem response across the wider Laucala Bay catchment.

Current status CW02 international prequalification open; Water Authority of Fiji lists a 28 August 2026 closing date Source confidence Confirmed

Location

Fiji / Global islands

Segment

Marine utilities

Status

CW02 international prequalification open; Water Authority of Fiji lists a 28 August 2026 closing date / Confirmed

Evidence reviewed

15 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Water Authority of Fiji
Delivery parties
CW02 design-build-operate contractor not appointed; international prequalification remains open, Miya S.A.R.L. (separate Greater Suva non-revenue-water performance contract)
Contract route
ADB-financed international open competitive bidding with prequalification for CW02, a design-build-operate contract including five years of operations and maintenance; the February 2026 plan applies prior review, a 70:30 merit-point evaluation, and an estimated US$104.85 million package value
Execution window
Water Authority of Fiji lists CW02 prequalification closing at 3:00 PM Fiji time on 28 August 2026. The February 2026 procurement plan scheduled the international process from Q2 2026; the final loan agreement closes on 30 June 2033. Current public records do not provide award, detailed-design, construction, commissioning, or operating-start dates.
Works package
Operate-design-build-operate upgrade of Kinoya wastewater treatment plant to a 36 MLD / 180,000 population-equivalent Stage 1, including inlet pumping, screening and grit removal, primary and secondary treatment, tertiary treatment, sludge and co-digestion systems, disinfection, commissioning, and five years of operations and maintenance
Marine interfaces
Disinfected treated effluent returns to Laucala Bay through the existing approximately 2.4 km HDPE ocean outfall. The reviewed ESIA and procurement plan do not identify a new offshore pipeline, diffuser, dredging, or marine-construction package.
Commercial read
CW02 creates a defined US$104.85 million international DBO opportunity concentrated in treatment-process design, civil and mechanical works, controls, commissioning, effluent compliance, sludge systems, operator capability, and five-year performance. The existing outfall remains an operating and monitoring interface, not an evidenced new marine works award.
Next milestone
Confirm the CW02 prequalification result and issue of bidding documents, then identify the selected DBO contractor, contract value, programme, final hydraulic tie-in, existing-outfall condition requirements, discharge-consent obligations, and commissioning acceptance tests.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

WAF current tender list confirms CW02 open with a 28 August closing date

The live utility list advances Kinoya from approval into active international prequalification for an operate-design-build-operate package. An open process does not prove shortlist, award, notice to proceed, construction, or accepted performance.

Read controlling source

Procurement plan defines a US$104.85 million DBO with five years of operations

The plan fixes CW02 as an international, prequalified, prior-review design-build-operate competition with a 70:30 merit-point evaluation. It defines a major treatment and operating package but does not add a new offshore outfall or marine pipeline.

Read controlling source

Separate Greater Suva water-loss contract awarded to Miya

ADB records a US$25.03 million performance-based non-revenue-water contract to Miya S.A.R.L. This is a programme delivery milestone but is separate from CW02 and does not identify a Kinoya DBO contractor or any marine works award.

Read controlling source

ADB financing became effective

Effectiveness moved the programme beyond signature into an active financing period. Procurement completion, field mobilisation, plant construction and environmental performance require later evidence.

Read controlling source

Final US$135 million loan agreement signed

The signed agreement fixes the controlling loan amount and a 30 June 2033 closing date. Together with the separate US$10 million grant it supersedes the older approval-news split, but financing signature is not a construction or operating milestone.

Read controlling source

ADB approved the Healthy Oceans and Water Security programme

Approval established the sovereign programme and its intended water-security and Laucala Bay outcomes. It did not define CW02 award, detailed design, construction start, effluent compliance, or measured ecosystem recovery.

Read controlling source

Environmental assessment defines plant-side upgrade and reuse of the existing outfall

The assessment establishes 36 MLD Stage 1 treatment, disinfection, and discharge through the existing approximately 2.4 km Laucala Bay outfall. It also cautions that wider bay pollution has multiple sources, limiting any claim that plant completion alone proves ecosystem recovery.

Read controlling source

Delivery watch

Evidence needed next

Confirm the CW02 prequalification result and issue of bidding documents, then identify the selected DBO contractor, contract value, programme, final hydraulic tie-in, existing-outfall condition requirements, discharge-consent obligations, and commissioning acceptance tests.

Decision watchpoints

  • CW02 prequalification outcome, shortlist, bidding documents, award, and notice to proceed
  • 36 MLD Stage 1 process design, hydraulic tie-in, disinfection, sludge and co-digestion scope
  • Condition and operating envelope of the existing 2.4 km Laucala Bay ocean outfall
  • Commissioning evidence against BOD, suspended-solids, faecal-coliform, ammonia, nitrogen, and phosphorus limits
  • Bay-wide monitoring that distinguishes Kinoya discharge effects from other point and non-point pollution sources

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 15 July 2026 Sources in this record 7

Source record

The final signed financing and procurement records supersede the approval-news financing split: the September 2025 loan agreement records a US$135 million ADB loan, the programme also carries a US$10 million grant, and the February 2026 plan records US$145 million of ADB financing within US$171 million total project financing. The ESIA defines Kinoya Stage 1 at 36 MLD / 180,000 population equivalent and says disinfected effluent will use the existing approximately 2.4 km Laucala Bay outfall. Its outcome target is for 80% of outfall monitoring results to meet national standards for BOD, TSS, faecal coliform, ammonia, total nitrogen, and total phosphorus. The same assessment cautions that Kinoya may be only a minor nutrient source relative to other bay inputs, so plant compliance remains separate from bay-wide recovery.

Phase: prequalification. Evidence reviewed: 15 July 2026.