Knowledge / Coastal resilience

Coastal resilience and waterfront protection.

Coastal protection is a performance system: offshore forcing, nearshore morphology, structural response, drainage, landward consequences and recovery all matter. A completed structure is only one part of that system.

Updated 77 tracked projects 89 publications

Protection is a system, not a structure

Beaches, dunes, revetments, seawalls and breakwaters change wave, water-level and sediment response in different ways. Their value is measured against a defined hazard and service objective, not by visual completion alone.

Image: Judgefloro via Wikimedia Commons, CC0

Define the hazard envelope

Pair waves with tide, surge, mean sea-level allowance, currents, storm duration and antecedent beach condition. A single return-period water level does not describe the load case.

Choose the intervention family

Hold, advance, nourish, accommodate and managed realignment solve different problems. The preferred option must address the dominant failure mechanism without exporting unacceptable erosion or flood risk.

State the service criterion

Acceptable overtopping, crest access, navigation operability, asset damage, habitat function and recovery time are separate limits. Each needs a threshold, receptor and inspection or monitoring route.

01 Forcing and terrain

Establish offshore waves and water levels, transform them across bathymetry, and account for currents, sediment pathways, shoreline orientation and storm sequencing.

02 Hydraulic response

Test run-up, overtopping, reflection, transmission, drawdown and local velocities at the structure, along the crest and across landward drainage routes.

03 Resistance and stability

Check foundation, toe, filters, underlayers, armour, crest, transitions, drainage and geotechnical stability as one load path rather than isolated quantities.

04 Consequence and recovery

Map receptors, residual inundation, access loss and cascading utility effects, then define inspection triggers, repair resources and the time needed to restore service.

Five coastal systems require different acceptance records

The acceptance record changes with the intervention. Volume, length or contract completion cannot substitute for the geometry and performance measure that the asset was designed to deliver.

Beach nourishment

Ocean City: contract quantity to accepted beach profile

The current contract sets more than 1.6 million cubic yards and USACE records the dredge mobilised. The ledger now needs daily placement, cumulative quantity, borrow-area control, surveyed berm width and elevation, access restoration and USACE acceptance.

Rock revetment

Ebeye: quarry release to island handover

Quarry grading, ocean carriage, deep-water transfer and landing are all part of delivery. The final construction record still turns on surveyed chainage and cross-sections, toe and filter inspection, tie-ins, drainage, defects closure and funded maintenance responsibility.

Dikes and breakwaters

Gorée: protect the scope behind each percentage

The published 82%, 85% and 75% figures use different dates or scope boundaries. Segment completion for the eastern and western works must be read alongside the school wall, mosque slope, UNESCO validation, promenade, landscaping and the proposed finance extension.

Preconstruction

West Point: permit secured, works evidence still ahead

Finance, an approved ESIA and the March 2026 environmental permit establish a serious project. The next commercial record is the works solicitation or award, followed by notice to proceed, quarry approvals, mobilisation and a baseline shoreline survey.

Research placement

St. Joseph: field activity before performance findings

The 83,000-cubic-yard campaign and perpendicular nearshore placement establish the 2026 field test. Bathymetry, turbidity, sediment movement and shoreline response will decide what the method achieved and whether it supports wider use.

Failure often begins at an interface

Armour size receives attention because it is visible. Many consequential defects start elsewhere: at the toe, through an incompatible filter, at a transition, behind a wall or where drainage has no safe outlet.

Toe and foundation

Scour, trench tolerance, weak founding material and differential settlement can remove support before the armour slope appears distressed. Foundation level and toe embedment need survey control and exposure records.

Filter continuity

Granular filters and geotextiles must retain the base while passing flow. Segregation, puncture, open laps and missing transition zones allow internal erosion that surface inspection may not reveal.

Returns and tie-ins

A robust central section can still be bypassed at a buried end, outlet, access ramp, quay interface or change in crest level. Drawings and as-built surveys must close every transition.

Crest and drainage

Overtopping damage depends on discharge, flow depth, velocity, duration and the landward surface. Crest details, rear-slope protection and drainage paths belong in the hydraulic design.

Quantities need engineering boundaries

A correct number can still misstate delivery when its location, date, material state or acceptance basis is omitted.

t Tonnes

Ebeye's roughly 65,000-tonne intended armour use and approximately 80,000-tonne supplier record describe different parts of the chain. Reconcile both with certified installed quantities.

yd3 Cubic yards

Ocean City's current 1.6-million-cubic-yard contract is separate from the completed 2022-23 cycle. Keep contract, produced, placed and accepted volumes in separate columns.

km Linear extent

Ebeye's 1.81 kilometres of new seawall sits inside a 2.1-kilometre programme indicator that includes 300 metres of existing protection. State what is new before comparing lengths.

% Progress

Every percentage needs an as-of date, denominator and excluded scope. Gorée shows how protection works, landscaping and overall programme progress can produce valid but different figures.

Construction control is part of performance

Design assumptions only survive construction when source material, placement sequence, geometry and hidden layers remain traceable.

01Source qualification

For armourstone, verify grading, density, durability, shape and quarry production consistency. For nourishment, verify grading compatibility, fines, contaminants and borrow-area limits.

02Temporary states

Open filters, incomplete toes, exposed excavations, temporary accesses and partly closed beach sections can govern risk during storms. Hold points should match the forecast and workable-weather plan.

03Placement records

Link delivery tickets and vessel logs to chainage, level, layer and survey. Material received on site is not the same as material placed within tolerance.

04As-built baseline

Capture profiles, crest and toe levels, transitions, drainage outlets, beach volumes and photographs before handover so later movement can be separated from original nonconformance.

Resilience is observed over an event series

A calm-weather completion survey proves geometry, not resilience. Useful performance records pair the loading history with the condition and service response that followed.

Event loading

Record water levels, wave conditions, duration, direction and whether several storms arrived before recovery. Without exposure data, condition changes cannot be interpreted consistently.

Residual condition

Repeat fixed profiles and inspections at toes, transitions, crests and drainage points. Distinguish tolerable reshaping from progressive loss of section or function.

Adaptive response

Beaches, dunes, wetlands and hybrid systems are expected to move. Their monitoring plan should define performance metrics, intervention thresholds and replenishment or repair actions before an event.

Cross-project coastal comparison

The July coastal protection monitor compares six named projects on a consistent basis: intervention type, delivery stage, quantity boundary and unresolved acceptance evidence. Each conclusion links back to its project record.

Open coastal protection monitor Read the Gorée brief Read the Ebeye brief

Coastal Engineering Manual

USACE guidance covers coastal processes, planning and design, with resistance to damage, functional performance and wider project consequences treated as risk questions.

Open USACE manual

Wave overtopping

EurOtop separates embankments, rubble-mound slopes and vertical structures, and makes uncertainty and receptor-specific allowable discharge part of the assessment.

Open Environment Agency reference

Natural and hybrid features

The USACE international guidance treats natural and nature-based features as engineered systems that require objectives, design, monitoring and adaptive management.

Open NNBF guidance

Reports and data

Project records and references

These reports, datasets and source links preserve project dates, quantities, methods and the distinction between award, construction, acceptance and observed performance.

Reports / PDF publication / 763.7 kB

Coastal Protection: Funding the Work That Completes the Defence (PDF)

Version 2.0 / Data through

Full English six-case review of coastal material allocation, scope changes, repair measurement and completion finance, with original figures and primary-source references.

Read reportView PDF Bookmarked PDF PDF reading copy PDF presentation revised
Data exports / CSV export / 2.4 MB

Project tracker CSV

Marine and hydraulic project data with participation status, deadlines, works packages and sources; the complete 34-column schema is published on Data Services.

Data exports / CSV export / 3.2 kB

Coastal completion case register: October2026

Fourteen dated observations with quantity, allocation, award or approval basis and primary source, covering the six cases in the coastal delivery review.

Source references / Web resource

Source register

Primary owner, authority, lender, contractor and technical references cited by IMWO records, with last checked dates and direct source routes.

Open page

Current evidence

Coastal resilience collection

Coastal resilience coverage connects hazard envelope, hydraulic response, geotechnical and structural resistance, construction control, landward consequence and post-event recovery.

Publications
89
Projects
77
Confirmed
77
Regions
6
Change histories
63
Updated
5 November 2026

Engineering frame

Technical scope

Hazard and design
Connect waves, water levels, currents, morphology and storm sequencing to the adopted intervention and service limits.
Material and logistics
Qualify armourstone, fill and sediment sources, then connect transport and placement records to layer, chainage, level and survey acceptance.
Community interface
Define overtopping and inundation receptors, public access, livelihoods, heritage, utilities and environmental functions as explicit performance consequences.
Durability and upkeep
Pair as-built condition with event loading, residual geometry, service response, intervention thresholds and funded recovery actions.
89 publications / 77 projects
Record type

Current analysis and reports

Article / Published analysis

Ocean City's Next Sand Bill

Ocean City completed its summer nourishment before New Jersey requested storm-repair assistance. The Fire Island repair record explains how surveys, funding eligibility and available dredging plant shape the next sand purchase.

21 October 2026 / 10 sources
Article / Published analysis

Ebeye's Seawall: Buying a Continuous Protection Line

Ebeye's completed seawall links critical-asset protection to material allocation, defence continuity and the cost sensitivity of an island project. World Bank records show how these choices affected its procurement and construction sequence.

21 October 2026 / 7 sources
Brief / Confirmed

Fort George underpinning: recorded tender deadline passed

Historic Environment Scotland's 8 October notice covered concrete underpinning at Fort George North Glacis, near Ardersier: temporary propping, beach-side excavation, secured formwork, mass-concrete fill and beach reinstatement. The recorded PCS Postbox submission deadline of 17:00 GMT on 4 November 2026 has passed; the advertised duration is 28 working days.

4 November 2026 / 3 sources
Brief / Confirmed

Mermaid Beach repair scope centres on six displaced walkway units

Folkestone and Hythe's Mermaid Beach tender covers recovery, repair and reinstatement of six 32-tonne precast walkway units. The council reports the rock structure intact. Submissions closed on 25 September 2026 at 13:00 UTC+01:00, with an award and actual repair progress still unconfirmed.

14 October 2026 / 4 sources
Brief / Confirmed

Sines makes new quay construction conditional on industrial demand

Sines' port authority has put a commercial condition on its proposed general-cargo quay: construction will depend on demand from new industrial projects. APS says the existing multipurpose terminal can handle current volumes and that a construction competition is not planned in the near term.

2 September 2026 / 3 sources
Article / Published analysis

Absecon's outfall repairs reconnect drainage with the engineered beach

A USD 19.695 million Absecon Island award puts stormwater outlets and beach access into the coastal works programme. The engineering interface runs from street-end collection to the seaward discharge, where pipe support, sediment and tide conditions matter alongside the dune profile.

1 September 2026 / 5 sources
Brief / Confirmed

Avalon stages beachfill equipment ahead of hydraulic placement

Avalon's 28 August update reports equipment staging and completed pre-project surveys under review ahead of hydraulic beachfill. Sand pumping remains anticipated around 5 September. The transition matters because a prepared workfront, the dredging start and the completed coastal-protection profile are separate milestones.

30 August 2026 / 4 sources
Article / Published analysis

Portugal's beach recovery: the benchmark behind the percentage

Portugal's post-storm beach assessment compares both historical condition and recovery of a particular winter's losses. Those benchmarks answer different engineering questions. Survey extent, elapsed time and the contractual measurement basis determine how the findings can inform nourishment design, monitoring and payment.

23 August 2026 / 5 sources
Brief / Confirmed

Sines' quay and breakwater plans run on separate consultation clocks

Sines' proposed general-cargo quay combines two berth fronts and a 19-hectare platform with a separately assessed 400m extension to the eastern breakwater. Their engineering interfaces overlap, but their environmental consultations close on different days: 9 September for the quay and 17 September for the breakwater.

24 August 2026 / 5 sources
Brief / Confirmed

Centreville contract expired without published acceptance records

Centreville's integrated wharf, dredging and breakwater contract moved from an 84-week requirement ending 31 August 2024 to a 31 December 2025 expiry. CanadaBuys reports CAD 18,864,176.72 after 11 amendments, while Public Accounts publishes different fiscal snapshots. None of the cited records supplies the physical and commercial close-out evidence needed to call the harbour work complete.

16 August 2026 / 4 sources
Brief / Confirmed

Cap-des-Caissie's two awards do not form one completion claim

Cap-des-Caissie now has two named marine primes across different workfronts: Les Entreprises St Louis on the CAD 710,930 dredging and containment-cell contract and Mskikue'j Enterprises on the CAD 5,094,275.75 wharf and shore-protection contract. The first term has expired and the second is awarded, but neither official record establishes physical completion.

5 August 2026 / 5 sources
Brief / Confirmed

Three 2026 Atlantic Canada awards split wharf, dredging and breakwater markets

Three active 2026 CanadaBuys awards place CAD 12,360,523.57 of Atlantic harbour work under named primes: L Breau and Sons at Sainte-Marie-Sur-Mer, Les Entreprises P E C at Grande-Anse and Zutphen Contractors at Larrys River. The packages are not interchangeable. One joins a Berlin-wall wharf to a title-level new breakwater, one specifies barge-excavator and scow dredging with a containment cell, and one reconstructs a rubble-mound breakwater inside a core fishing harbour.

7 August 2026 / 5 sources
Brief / Confirmed

L Breau holds the 79-week structure 401 contract

L Breau and Sons Ltd holds CAD 8,745,856.95 contract CW2440554 for Sainte-Marie-Sur-Mer structure 401 through 24 August 2027. CanadaBuys describes a 79-week replacement of the timber-crib wharf with a Berlin-wall structure, while the procurement title also includes a new breakwater whose dimensions and quantities remain unpublished.

7 August 2026 / 3 sources
Brief / Confirmed

Zutphen holds Larrys River's 25-week breakwater contract

Zutphen Contractors holds CAD 2,752,396.62 contract CW2455209 for rubble-mound breakwater construction at Larrys River Small Craft Harbour through 27 November 2026. The 25-week requirement includes delineating the construction zone from the operating facility, but published records give no breakwater dimensions, rock quantities, quarry source or first-placement date.

7 August 2026 / 3 sources
Brief / Confirmed

Goat Island's two marine contracts leave package split undisclosed

NSW has disclosed two related contracts for the Western Broadside Wharf, adjacent seawall and access pontoon at Me-Mel (Goat Island). Polaris Marine Constructions holds CAN-116963 at AUD 683,971.41 including GST and Clement Marine Constructions holds CAN-116428 at AUD 1,282,988.82 including GST. NPWS confirms that repair is underway, but neither notice explains how the physical scope is divided between the two contractors.

5 August 2026 / 4 sources
Brief / Confirmed

Folkestone-Hythe links Chunnel's contract to a spring beach order

Chunnel's signed GBP 2.3 million excluding-VAT beach-management contract has a corrected three-year initial term and a two-year extension option. The council's March 2026 announcement scheduled a 100,000-tonne spring cycle, and its April disclosure names Chunnel against a GBP 120,000 purchase order. Completed tonnage, accepted beach profiles and current autumn work remain unconfirmed.

14 October 2026 / 5 sources
Article / Published analysis

Island marine delivery depends on logistics, interfaces and operations

Thirteen public island records, current to 14 August 2026, show why contract status alone is a poor proxy for usability: remote supply, live-port constraints, package interfaces, accepted works and operating evidence close on different records.

16 August 2026 / 20 sources
Article / Published analysis

Africa marine works sit at different release points

The 17 public Africa project records currently divide into four at approval or financing, two awarded, nine in physical delivery and two in commissioning. Contractors, suppliers and operators need a different primary record at each position.

26 July 2026 / 12 sources
Brief / Confirmed

WACA's six country programmes are approaching close-out at different speeds

WACA ResIP 1 is nearing its final phase across six West African countries. Its lagoon, shoreline, quay, dike, drainage and community packages run under different contracts and timetables, while Senegal is seeking a later closing date. A single regional completion figure would mask the sites still controlling delivery.

16 July 2026 / 6 sources
Brief / Confirmed

Isle of Palms moved dredged sand straight to the intertidal beach

USACE linked two different maintenance jobs to one Isle of Palms receiving area. Ahtna rehandled stored AIWW material, while Cottrell dredged active shoals and used both open-water and beach-placement routes. About 700,000 cubic yards were placed below high tide between 2nd and 10th Avenue.

18 July 2026 / 7 sources
Brief / Confirmed

Rocky River is sending 50,000 cubic yards of sediment nearshore

Rocky River Harbor's 2026 maintenance package divides approximately 59,000 cubic yards between two destinations: about 50,000 cubic yards to a nearshore area east of the harbor and 9,000 cubic yards to a designated open-lake area.

18 July 2026 / 4 sources
Article / Published analysis

Beach nourishment closes through quantity, profile, demobilization and response

Ocean City has a mobilized 1.6-million-cubic-yard contract, Carolina and Kure beaches have nearly 2 million cubic yards placed, and St. Joseph is monitoring nearshore movement. Each sits at a different point between planned quantity and an accepted coastal outcome.

23 July 2026 / 9 sources
Article / Published analysis

Mobile Bay dredging now faces two definitions of beneficial use

Mobile Harbor produces roughly 6 million cubic yards of dredged material in a typical year. USACE recognizes thin-layer placement inside its sediment strategy, while Alabama's law taking effect on 1 October counts public-water placement only when it forms part of shoreline restoration or marsh creation.

13 August 2026 / 9 sources
Article / Published analysis

For coastal revetments, the quarry is part of the job

Ebeye, Goree and West Point all depend on armourstone, but their routes from quarry approval to accepted shoreline protection sit at very different stages.

17 July 2026 / 7 sources
Brief / Confirmed

Genoa breakwater reaches 24 caissons and one kilometre

Genoa's New Breakwater passed one kilometre and 24 installed caissons in June 2026. Those milestones cannot be extrapolated into completion: seabed treatment, rock foundation, caisson continuity, filling, armour and superstructure, dredging, old-breakwater interfaces, hydrography and formal navigation opening remain unfinished or unverified.

21 July 2026 / 5 sources
Brief / Confirmed

Gorée reports 85% completion, with finance and handover still unresolved

WACA measured Gorée at 82% overall on 31 March 2026. A later World Bank paper uses a narrower and newer boundary: 85% for protection works and 75% including landscaping, while seeking EUR 3.5 million (US$4.0 million equivalent) and a 30 June 2027 close. Owner acceptance has not been reported.

16 July 2026 / 6 sources
Brief / Confirmed

Ebeye reached 1,421 m before an unexpected rock shortfall emerged

By 28 November 2025, 1,421 metres of Ebeye's 1,800 metres of new seawall had been built, nearly 80% of the scope. The January 2026 World Bank report recorded an unexpected rock shortfall and a remedy under development. That account describes the material constraint within a USD 52,635,577.03 construction contract and a quarry-to-shore supply chain from Ras Al Khaimah. The President's Office subsequently confirmed handover of the completed seawall and footpath on 17 September 2026.

21 October 2026 / 10 sources
Report / Version 2.0

Coastal Protection: Funding the Work That Completes the Defence

Six coastal projects show how scarce material, revised scope and funding dates change the cost of completing a functioning defence. This review traces Ebeye's protection line, Gorée's displaced landscaping budget, Ocean City's repair account, Genoa's caisson queue, Vadhvan's breakwater award and West Point's permitted footprint.

22 October 2026 / 13 sources
Brief / Confirmed

Madagascar's US$102.24m marine component spans ports, canal works and fisheries facilities

Final World Bank documents allocate US$102.24 million to Madagascar's port and waterway component: US$30 million for Majunga, US$32 million for Tulear and US$29.94 million for 200 kilometres of the Pangalanes Canal. The first procurement plan records a US$28 million Majunga works package pending implementation and a US$6.36 million canal maintenance and dredging-fleet package under review; active main Tulear and canal-dredging works packages are absent from that revision.

15 July 2026 / 10 sources
Brief / Confirmed

BEFIRM defines three São Tomé landing-site scopes before works award

BEFIRM is no longer only a grant headline. AfDB records signed financing and site-level safeguards for Neves, Porto Alegre and Chimalô. Porto Alegre includes a replacement quay and about 1,940 m³ of foundation dredging, Neves has a 4.0-metre operating-depth basis, and Chimalô carries cold-chain and logistics works. Design-supervision and works awards are not disclosed.

1 August 2026 / 9 sources
Brief / Confirmed

Kinoya's US$104.85m DBO keeps the existing Laucala Bay outfall

WAF's CW02 prequalification applications closed on 30 September 2026 at 15:00 Fiji time (GMT+12), following a September corrigendum. Bidding invitations are expected in December for up to three shortlisted eligible applicants. The estimated US$104.85 million Kinoya upgrade combines 36 MLD treatment capacity, five years of operations and reuse of the existing 2.4 km Laucala Bay outfall.

14 October 2026 / 8 sources
Brief / Confirmed

USACE starts 83,000 yd³ St. Joseph dredging with monitored nearshore placement

USACE Detroit District's July 2026 St. Joseph Harbor operation moves beyond a routine Great Lakes maintenance item: Viking Marine Construction will hydraulically dredge roughly 83,000 cubic yards from the federal channel while ERDC monitors a perpendicular shoreline placement to understand sediment movement under Lake Michigan wave action.

21 July 2026 / 5 sources
Brief / Confirmed

Niagara fish passage closes construction, not monitoring

USACE has completed the USD 13.4 million, 778-foot Emerald Shiner Fish Passage along Freedom Park's Niagara River seawall. Field measurements reportedly kept velocity below the shiner swimming threshold, while observed fish use remains an early result rather than a seasonal performance record.

23 July 2026 / 3 sources
Brief / Confirmed

Buffalo Harbor splits its 2026 dredging between disposal and a future wetland

Buffalo Harbor's 2026 maintenance package will mechanically remove approximately 190,000 cubic yards from deep-draft federal channels. The planned routing sends about 110,000 cubic yards to CDF #4 and about 80,000 cubic yards to Shipping Slip 3, whose containment breakwater was completed in 2024. Slip 3 placement is the second phase of a 285,000-cubic-yard programme expected to continue through 2028; habitat formation follows after the required fill level is reached.

16 August 2026 / 5 sources
Brief / Confirmed

USACE awards the second of three Oswego breakwater repair phases

USACE has split more than 1,330 feet of Oswego Harbor breakwater repairs into three phases. A USD 9.1 million Outer West package is already under way. The new USD 14.9 million Dean Marine award covers 425 feet of East Arrowhead and another 307 feet of Outer West, with a third funded phase planned to start in 2027.

16 August 2026 / 5 sources
Article / Published analysis

Dredged-material routing is becoming a front-end works signal

Disposal, beneficial-use, reclamation and placement routes now shape schedule confidence, permitting friction, production method, community exposure and whether a dredging package is ready for delivery. Georgetown's current field notice and Alabama's 70% rule show that material routing is a front-end commercial, legal and environmental decision, not a close-out detail.

10 August 2026 / 11 sources
Brief / Confirmed

Great Lakes Dock holds Dunkirk's last 450-foot repair phase

Official federal award data identifies Great Lakes Dock & Materials for Dunkirk Harbor's remaining 450-foot breakwater phase at USD 1.936 million. The contract record resolves the contractor and supports USACE's USD 1.9 million narrative, while leaving the same release's USD 4.5 million bullet unsupported.

10 August 2026 / 6 sources
Brief / Confirmed

Vermilion closes construction with an open scope reconciliation

USACE officially completed Vermilion Harbor's East Pier repair on 24 July after rebuilding 900 feet with about 4,700 tons of crushed rock and new stone. The earlier USD 6.5 million award baseline covered 600 feet; the additional reported length and final value remain unexplained.

25 July 2026 / 3 sources
Brief / Confirmed

Ocean City planned 15,000 cubic yards for the Assateague bypass

USACE's May 2026 plan paired two Ocean City Inlet shoaling areas with one material route: approximately 15,000 cubic yards were assigned to MURDEN for authorized placement south of the inlet, offshore Assateague Island.

18 July 2026 / 4 sources
Brief / Confirmed

Boingoma's 256-metre quay is taking shape

The Arab Contractors is executing Boingoma Port's EUR 60 million design-build contract on Moheli. The current programme runs to 11 August 2027 and combines a 256-metre quay wall, breakwater, dredging and rock excavation, a fixed pontoon and a 12,800 m2 yard.

18 July 2026 / 5 sources
Brief / Confirmed

Aiwo wharf enters service while wider port works continue

Cargo vessels are using Aiwo's new wharf and fuel line. ADB's latest monitoring report puts dredging at 78% and the northern-yard interim apron at 97% by June 2025, with all buildings handed over; the current project page still carries a broader unfinished-work list.

3 August 2026 / 7 sources
Brief / Confirmed

Can Gio selects VIMC, Saigon Port and TiL for a 7.5 km berth programme

Ho Chi Minh City has approved Vietnam Maritime Corporation, Saigon Port and Terminal Investment Limited Holding as the investor for Can Gio International Transshipment Port. The plan covers about 571 hectares and 7.5 kilometres of main berths, with two to four berths in the initial stage and capacity for container ships up to 250,000 DWT.

20 July 2026 / 6 sources
Brief / Confirmed

Cotonou Terminal 5 owner page reports 69% physical progress

Port Autonome de Cotonou's live Terminal 5 page reports 69% physical progress and 72% overall progress. The same page still gives a 2021-2024 delivery period, so the percentages show unfinished construction but do not supply a current finish date. CHEC's marine scope includes a 350-metre breakwater extension and an 891-metre revetment protected by ACCROPODE II units.

21 July 2026 / 6 sources
Brief / Confirmed

Bridgetown fisheries harbour repair awaits final acceptance

At Bridgetown Fisheries, World Bank contract 1841608 names the Barbadian contractor COW at USD 8,482,143.17 for the breakwater repairs. Its description says the contract was signed on 4 March 2025, an implementation report says 14 March and works started, while STEP shows 21 June. Major armour works were in place by November and the complex was used in May 2026, but an accepted as-built survey, owner handover and final account have not been published.

7 August 2026 / 9 sources
Brief / Confirmed

Nafanua Port has a USD 4.8m works contractor but no mobilisation record

China Jiangsu International is the signed contractor for Tonga's integrated Nafanua Port package at USD 4,803,074.31. The award covers entrance-breakwater repair and extension, a new small-boat berth and a new passenger terminal, while mobilisation and physical works remain unverified.

6 August 2026 / 7 sources
Brief / Confirmed

Geraldton awarded its breakwater before the wider marine works

Mid West Ports has awarded MGN Civil the surge-protection breakwater at Geraldton. The award sits ahead of the separately described dredging, reclamation, berth and tug-harbour works in the approved Port Maximisation Project.

16 August 2026 / 7 sources
Brief / Confirmed

New Zealand backs a regional-port dredging barge with NZD 8 million

New Zealand has committed NZD 8 million to a crane dredger hopper barge for smaller regional ports. Johnson Bros will cover the rest of the NZD 12.9 million cost, and the government expects the vessel to enter service in late 2027.

23 July 2026 / 7 sources
Brief / Confirmed

Alabama's 70% dredged-material rule has three conditions

From 1 October, dredgers moving more than 1 million cubic yards a year in Alabama's coastal area must put at least 70% of the material to a beneficial use. The requirement applies only to the extent that federal funding has been allocated and permitted in-state sites have capacity for suitable material.

10 August 2026 / 4 sources
Brief / Confirmed

Ocean City's 1.6 million-cubic-yard contract closes on surveyed beach geometry

USACE awarded Great Lakes Dredge & Dock a USD 19.5 million Ocean City beachfill contract for more than 1.6 million cubic yards, records construction starting on 7 July 2026, and records dredge Illinois mobilised at the 10 July field-status boundary. Those milestones define commitment and readiness. Current-cycle production, placed quantity, surveyed berm geometry, completion and acceptance remain separately unverified.

16 July 2026 / 6 sources
Brief / Confirmed

West Point's permit clears the way for revetment procurement

Liberia's environmental permit authorizes a coastal defence revetment inside defined West Point coordinates after ESIA approval. The wider programme has a USD 25.638905 million financing plan, completed met-ocean data collection and a July 2027 implementation window. The coastal works contractor, executed contract value, notice to proceed and mobilisation are not disclosed.

16 July 2026 / 5 sources
Brief / Confirmed

Mus seawall enters post-bid evaluation with EPC award still unpublished

Andaman Lakshadweep Harbour Works closed its two-cover EPC recall for 450 metres of seawall and shore protection at Mus on 6 May 2026. The portal still lists evaluation without an AOC. Ministry records retain an INR 471.3 million sanctioned scheme, an INR 421.3 million 2026-27 provision and proposed NTCPWC design revalidation, while IIT Madras is listed separately for PMC services.

16 August 2026 / 9 sources
Brief / Confirmed

Saba turned a turbidity plume into a construction control

Black Rocks Harbor is reusing excavated seabed material in the breakwater core and temporary basin bunds. When fine particles created a visible turbidity plume in March 2026, the contractor stopped the activity and changed the excavation method so fines would be filtered on land.

2 August 2026 / 6 sources
Article / Published analysis

Gdynia's first caisson moves the Outer Port breakwaters onto the water

Gdynia's PLN 438.70 million design-build breakwater contract has received its principal construction permit and launched the first of 49 reinforced-concrete caissons. The consortium is public, but the specialist subcontract chain is not.

2 August 2026 / 5 sources
Brief / Confirmed

Gdynia's first caisson exposes the next contractor-chain questions

Gdynia's protective-breakwater contract has crossed its main permit gate and launched the first of 49 reinforced-concrete caissons. Budimex leads the PLN 438.70 million net design-build consortium with 50%, while Roverpol and Rover Maritime each hold 25%. The next intelligence gap is below that legal consortium: detailed design, survey, seabed preparation, dredging, caisson production, towage, material supply, navigation systems and testing remain unattributed in published project records.

2 August 2026 / 5 sources
Brief / Confirmed

Frioul awards East breakwater works to five-company group

Métropole Aix-Marseille-Provence concluded a EUR 19.589919 million contract for the Frioul East breakwater and internal rock spur with an Océlian-led five-company group. The award resolves the client, legal winners and contract value after five bids. Mobilisation, internal workshare, quarry and marine-logistics suppliers, placed quantities and accepted progress remain unpublished.

2 August 2026 / 5 sources
Brief / Confirmed

Granville's end-May breakwater acceptance remains undocumented

Granville's Herel breakwater repair has an unusually clear award and start record: EUR 5,897,585 in BOAMP, a Marc-NGE-ETPO delivery group named by the owner, a 25 August 2025 site start and a nine-month programme. The planned end-May 2026 acceptance date has passed, however, and the current official record still lacks an actual completion or acceptance notice, measured repair quantities, defects status and final account.

7 August 2026 / 4 sources
Brief / Confirmed

Braek's replacement pipeline is contracted but not publicly handed over

Grand Port Maritime de Dunkerque concluded a EUR 1,720,365 excluding-VAT contract with Baggerbedrijf de Boer B.V. to remove and replace the submerged sand-discharge line in front of the Braek dike. The tender required service by 31 May 2025, while public project records publish no physical completion or acceptance milestone. A 2018 predecessor award shows the same contractor installed a 1.5 km line intended to support annual nourishment of 0.5 million to 2 million m3.

5 August 2026 / 6 sources
Brief / Confirmed

Harwich confirms Suffolk Dredging's five-year maintenance contract

Harwich Haven Authority confirmed a five-year maintenance award to Suffolk Dredging LLP and a Tiamat licence in July. The March procurement family had been withdrawn for a scope-description correction; its GBP 100 million estimate remains historical.

14 October 2026 / 11 sources
Brief / Confirmed

Warrawong's live seawall contract still needs a completion record

Warrawong Parklands has moved from a failed timber seawall and open tender into a live AUD 3.814 million construction contract with Civil Constructions. NSW Planning reports work underway and targets completion by year end. The public record still does not provide the installed rip-rap quantity, habitat-feature acceptance, final value, practical completion or reopening evidence needed to close the project.

5 August 2026 / 4 sources
Brief / Confirmed

Moss Landing has post-dredge surveys, not a full closeout

Moss Landing Harbor now has a traceable award, physical work windows, named dredging fleet and published post-dredge surveys. Ahtna's current official obligation is USD 16.037 million and the contract period ended on 23 January 2026. The public chain still stops before final dredged quantity, accepted jetty repairs, practical completion and certified final value.

5 August 2026 / 7 sources
Brief / Confirmed

Libertad dredging is reported complete without published package closeout

Rayman Builders signed the USD 1.071 million Libertad Outfall dredging contract on 6 October 2023. The Philippines Commission on Audit identifies the same package as DPWH contract 22Z00033, records a PHP 60.833 million contract cost and lists PHP 60.665 million in construction in progress at 31 December 2024. A November-December 2025 World Bank mission reports that all eight DPWH dredging contracts were completed. That supports completed contract status for the group that includes Libertad, but it does not publish this package's measured volume, sediment destination, as-built geometry, hydraulic clearance or DPWH acceptance.

16 August 2026 / 5 sources
Brief / Confirmed

Sugar Berth has a contractor but not a clean delivery chronology

World Bank contract record 1881500 names C. O. Williams Construction Limited at USD 3,338,256.29 for Sugar Berth seawall, pavement and revetment repairs. Yet a procurement plan revised in December 2025 still called the works Pending Implementation and planned a January 2026 signature, while the API reports a September 2025 signature and April 2026 no-objection. Field mobilisation and completion remain unconfirmed by a dated official record.

6 August 2026 / 4 sources
Brief / Confirmed

Menzel Abderrahmane's ETEP award still lacks a verified works start

TED confirms that ETEP signed the combined fishing-port and coastal-esplanade contract for TND 20,018,762.19 on 28 April 2025, with a stated 28-month duration. The EIA exposes a substantial marine package, including a 493 m breakwater and 5,400 m3 of planned dredging. Yet the public delivery chain stops short of technical works: July 2025 reporting described site-facility locations and pending administration, and parliament still described the project as delayed in February 2026.

9 August 2026 / 5 sources
Brief / Confirmed

Newell Beach physical completion lacks a published final account

TMR confirms that Newell Beach's ramp, fixed walkway, fishing platform, rock wall and dredged all-tide access were complete in May 2022. The commercial record is less closed: CN-17011 rose from AUD 2,560,154 to AUD 2,603,835 after a disclosed variation; RECS held a separate AUD 44,000 inspection contract; and completion reporting used an AUD 3.5 million whole-facility figure. None is a public final account.

6 August 2026 / 6 sources
Brief / Confirmed

Poona's January target passed before access dredging began

TMR expected Poona's full boat-ramp package to finish by January 2026. MSQ then scheduled approach dredging and foreshore nourishment for 9-27 February and closed the ramp from 16 February while upgrade works continued. The contract disclosure rose from AUD 2,041,001 to AUD 2,448,002, but the variation scope and final account remain unpublished.

6 August 2026 / 8 sources
Brief / Confirmed

Burry Port's dredging and advice contracts name different suppliers

Carmarthenshire County Council signed Kaymac Marine & Civil Engineering on 29 June 2026 for outer-harbour and approach-channel sand dredging with placement on East Beach. The GBP 425,000 excluding-VAT works have a 13 July to 31 October period. Anthony D. Bates Partnership's GBP 48,848 excluding-VAT advice contract runs from 4 December 2025 to 25 November 2026 and considers mechanical and water-injection dredging over a 5-10-year maintenance horizon. Physical works and accepted advisory deliverables remain unconfirmed.

14 October 2026 / 7 sources
Brief / Confirmed

Langstone appoints Jackson and refines its April 2027 programme

Havant announced Jackson Civil Engineering's appointment on 26 June 2026 for Langstone's one-kilometre coastal-defence scheme. The UK6 selected value is GBP 14 million excluding VAT, GBP 16.8 million including VAT; the council describes a separate GBP 23.6 million overall programme. Coastal Partners' August update retains an April 2027 main start and an intended shorter programme under refinement. Signed terms, final consent documents, approved programme and defence acceptance remain outstanding.

14 October 2026 / 8 sources
Brief / Confirmed

Atlantic Canada adds CAD 14.45m across three wharf systems

Three confirmed base contracts place CAD 14,454,531.96 of Nova Scotia fishing-harbour work under named primes. Zutphen Contractors holds Glace Bay's D1-D11 demolition and steel H-pile marginal-wharf package. Dexter Construction holds Meteghan's floating-dock and pipe-pile replacement. Connors Diving holds Meteghan's separate Wharf 403 concrete-repair and FRP pile-jacket package. The exact sum defines current award scale, while the three contracts retain different methods, terms, work fronts and acceptance records.

8 August 2026 / 6 sources
Brief / Confirmed

Glace Bay puts D1-D11 under a CAD 8.90m prime contract

A CAD 8,896,913.40 federal award places demolition and reconstruction of Glace Bay wharf structures D1 through D11 with Zutphen Contractors under CW2454987. The replacement changes the structural system from mainly timber cribs to a steel H-pile-supported marginal wharf. The federal contract page fixes the prime, amount and 2 June 2026 to 31 March 2027 period; DFO's earlier navigation filing fixes the Renwick Brook worksite. Neither source establishes site possession, first demolition or first pile.

8 August 2026 / 3 sources
Brief / Confirmed

Meteghan splits floating access from pile rehabilitation

Two separate contracts now govern Meteghan Small Craft Harbour. Dexter Construction holds CAD 4,292,100.00 CW2462474 through 30 November 2026 to replace three floating-dock systems and associated pipe piles, except the middle set replaced in 2018. Connors Diving holds CAD 1,265,518.56 contract 4500109325 through 31 March 2027 for Wharf 403 concrete removal, repairs and FRP pile jackets. Shared geography does not create a prime-subcontract relationship or a common acceptance record.

8 August 2026 / 4 sources
Brief / Confirmed

Apollo Bay's AUD896,000 seawall mobilisation remains unverified

Buying for Victoria identifies Maintenance Concepts Pty Ltd and a fixed AUD 896,000 contract for Apollo Bay Harbour's seawall, with a 20 July to 21 September 2026 period. The official owner design places a new gravity-block wall seaward of the existing structure. The record still lacks an award date, site-possession evidence, first physical operation, installed quantities, named lower tiers and acceptance.

8 August 2026 / 4 sources
Brief / Confirmed

Fox Island River has three package clocks, not one

Fox Island River's current public chain contains a 2023 entrance-improvement award, a separate 2024 channel re-dredging award and a 2026 marginal-wharf proposal still in assessment. Each package has a different supplier or open supplier gate, scope and evidence clock.

9 August 2026 / 6 sources
Brief / Confirmed

Fox Island River wharf remains a pre-award workfront

Fox Island River's 2026 channel-wall proposal is still an assessment-stage project. Its disclosed work covers marginal-wharf demolition and replacement, steel sheet piling, reinforced concrete, shoreline reinstatement, parking, a jib crane, lighting and an electrical shed, while procurement and delivery parties remain open.

9 August 2026 / 4 sources
Brief / Confirmed

NOC's 2025 wall-and-pontoon contract names Seawork

National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT. The contract covered quayside wall and pontoon repairs at NOC Southampton and ran from 13 August to 12 September 2025. Mobilisation, repair quantities, handback, acceptance and final payment remain unconfirmed in public sources.

14 October 2026 / 4 sources
Brief / Confirmed

Apia's 100-metre breakwater moves to the July 2027 critical path

Samoa Ports Authority's July-December 2024 monitoring report placed CHEC's Section 3 breakwater and whole-project completion in December 2026. The later implementation baseline moves the 100-metre breakwater works to mid-July 2027, followed by a one-year defects period. Sections 1 and 2 had June 2026 close-out and handover expectations, but no later signed acceptance certificate was published.

16 August 2026 / 5 sources
Brief / Confirmed

Durban's ZAR 5.47m revetment award leaves delivery unverified

National Treasury's active award record names KATLANTIC at ZAR 5,466,159, while TNPA's RFP fixes the workfront at a damaged entrance-channel section requiring approximately 1,000 m3 of 50-100 kg rock. Neither source confirms contract signature, notice to proceed, installed quantities or completion.

16 August 2026 / 3 sources
Brief / Confirmed

Snapper Creek shoreline award covers two harbour workfronts

Queensland's contract disclosure fixes MSQ25017 at AUD 1,981,207 with Hunter Contractors Pty Ltd, while Maritime Safety Queensland's 29 August 2025 notice supplies the planned start, two work areas and access constraints. The official project map resolves the location of both workfronts. Installed quantities, completion, acceptance and final account remain unconfirmed.

13 August 2026 / 3 sources
Brief / Confirmed

Sandusky splits 109,000 cubic yards between nearshore and open-lake placement

USACE scheduled Morrish-Wallace Construction's USD 628,000 Sandusky Harbor maintenance campaign to start on 6 October. Approximately 109,000 cubic yards are planned from the Moseley and Straight channels, with 100,000 cubic yards routed to nearshore nourishment and 9,000 cubic yards to a designated open-lake site. The announced start and 1 November completion target remain distinct from verified field progress.

6 October 2026 / 4 sources
Brief / Confirmed

Torcross Rock Armour Depends on an Offshore Transfer Chain

Torcross plans sea delivery for 58,000 tonnes of armour stone and road delivery for 30,000 tonnes of filter material. Its offshore transfer and tide-dependent beach landing govern the installation sequence.

3 November 2026 / 4 sources
Brief / Confirmed

Lymington Ties Flap Renewal to a Changing-Tide Handover Test

Lymington's replacement tidal flaps were installed in September. The redacted works contract requires a low-to-high-tide function inspection for completion, while the owner's October account identifies a separate regulating-float repair still to follow.

3 November 2026 / 4 sources
Brief / Confirmed

Humber Defence Design Links the Land Footprint to Consent Timing

Barton to New Holland's October update links inland embankment footprints, landowner discussions and habitat-sensitive design. Barrow Haven adaptation may follow separately as the team works toward a summer 2027 business case.

3 November 2026 / 4 sources
Brief / Confirmed

Nga Bay: Hand Over Each Riverbank With Its Drainage Connections

Nga Bay's riverbank and drainage works were proceeding on different programmes in Can Tho's June 2026 progress account. Package 1 covered embankments and Pham Hung green infrastructure, with completion then expected by 31 December 2026. Package 2 covered storm drainage, sewer collection and wastewater treatment, with completion expected in November 2027. Across the scheme, about 3.1 km of new banks along Xeo Vong, Cai Con and Soc Trang connect to a planned stormwater system with 22 outlets and to works at Xang Thoi Lake. That combination makes the drainage connection a specific handover question for each completed bank reach. [1][2]

4 November 2026 / 4 sources
Brief / Confirmed

Duke Marine Lab: Quantifying a Living Shoreline's Elevation Deficit

Duke Marine Lab's living shoreline has retained its granite sill while the water around it has risen. NOAA's site report records consistent sill elevations between the post-construction survey and a 2025 resurvey. Its 2004-24 monitoring summary puts lower-marsh elevation gain at 2.0 mm/year and mid-marsh gain at 0.3 mm/year, against a local mean sea-level rise of 4.5 mm/year [1]. Those measurements describe different maintenance demands within one functioning coastal asset.

5 November 2026 / 3 sources
Brief / Confirmed

Lekki: Match Maintenance Dredging to the Beach Sand Budget

Lekki's design connects maintenance dredging to the artificial beach east of the port. A 2023 study by authors at CCCC-FHDI and China Harbour describes west-to-east sand transport interrupted by the port structures, with nourishment intended to replenish the downdrift beach. Its modelled sand supply combines western deposits with material recovered from the basin and channel [1]. A dredging campaign feeding that beach needs both a navigation cut and a suitable fill supply.

5 November 2026 / 4 sources
Brief / Confirmed

Bridgwater's Gate Redesign Meets the Concrete Programme

Bridgwater's revised tidal-barrier design puts the gate-drive equipment at the base of three towers while work advances on the permanent foundations. The Environment Agency announced the changes on 15 January 2026: towers approximately 15 m high, a 10 m reduction, with simpler shapes and lighter operational walkways. Somerset Council's October construction account reports reinforcement beneath the central pier and permanent concrete taking shape. The next interface is between the revised machinery arrangement and the concrete being cast. [1][2]

5 November 2026 / 5 sources
Brief / Confirmed

Poplar Island: Grading for the Marsh That Develops After Placement

At Poplar Island, the grading level helps determine how a constructed marsh develops after planting. A 2024 field study compared two areas of Cell 5AB with initial platform elevations of 0.22 m and 0.32 m NAVD88. Three surface elevation tables monitored each area. Mean elevation gains were 13.2 and 7.8 mm/year respectively over the study record through 2021. The lower area gained height faster; the higher area began with 0.10 m more elevation above the same datum. [1]

5 November 2026 / 3 sources

Related project records

United Kingdom / Source confidence: Confirmed

Mermaid Beach breakwater walkway-unit recovery and repair

Participation: Awarded / Checked / Notice and deadline

Submission deadline:

Coastal infrastructure / UK6 notice 097475-2026 names Chunnel Plant Hire and Contractors Limited for the six-unit repair at GBP 169,187.49 excluding VAT; signature is scheduled for 19 October 2026, with reinstatement and acceptance unconfirmed

Last checked 19 October 2026 / 5 sources
Netherlands / Source confidence: Confirmed

IJsselmeerdijk foreshore and conventional dike reinforcement

Participation: Not assessed

Coastal infrastructure / Owner reports realization has begun with the lake-side foreshore; conventional dike work planned from early 2027, quantities and acceptance unconfirmed

Last checked 4 September 2026 / 4 sources
United Kingdom / Source confidence: Confirmed

Fort George North Glacis sea-wall underpinning

Participation: Submissions closed / Checked / Notice and deadline

Submission deadline:

Coastal infrastructure / Recorded tender deadline passed on 4 November 2026 at 17:00 GMT; advertised duration 28 working days

Last checked 15 October 2026 / 4 sources
United States / Source confidence: Confirmed

Absecon Island outfall repair and Ventnor vehicle-ramp works

Participation: Not assessed

Marine utilities / Agate named for outfall repair or extension and vehicle-ramp works; notice to proceed and mobilisation not confirmed

Last checked 1 September 2026 / 5 sources
United States / Source confidence: Confirmed

Avalon and Stone Harbor hydraulic beach nourishment, 2026 campaign

Participation: Not assessed

Beach and foreshore nourishment / Avalon equipment staged and survey review reported; hydraulic placement start and accepted profiles remain outstanding

Last checked 30 August 2026 / 4 sources
Portugal / Source confidence: Confirmed

Sines quay and north-west breakwater design interface

Participation: Not assessed

Ports and coastal protection / Design and environmental assessment; APS makes new-quay construction conditional on industrial demand and rules out a near-term works tender

Last checked 2 September 2026 / 6 sources
Netherlands / Source confidence: Confirmed

Kustlijnzorg North Holland and Texel nourishment (31205035)

Participation: Not assessed

Beach and foreshore nourishment / Boskalis signed the EUR 26.098 million contract on 12 May 2026; Rijkswaterstaat announced Den Helder tidal-channel nourishment from 14 July to mid-October and Julianadorp sinker-pipe removal from 20 July, while measured production and acceptance remain unpublished

Last checked 7 August 2026 / 5 sources
Netherlands / Source confidence: Confirmed

Kustlijnzorg Walcheren beach nourishment (31205036)

Participation: Not assessed

Beach and foreshore nourishment / Fa. Gebr. Van der Lee signed the EUR 8.199 million contract on 31 March 2026; the contract is live through 2027, while no public evidence of physical mobilisation, vessel assignment or accepted production was identified by the 7 August 2026 review

Last checked 7 August 2026 / 5 sources
Netherlands / Source confidence: Confirmed

Kustlijnzorg South Holland nourishment (31205037)

Participation: Not assessed

Beach and foreshore nourishment / Van den Herik signed the EUR 16.302 million contract on 10 March 2026; Rijkswaterstaat schedules Maasvlakte 2 nourishment for September and names Van den Herik with Van der Kamp there, while mobilisation and the parties' commercial relationship remain unverified

Last checked 7 August 2026 / 4 sources
Canada / Source confidence: Confirmed

Centreville small craft harbour wharf reconstruction

Participation: Not assessed

Fishing harbour wharf, dredging and shore protection / Kerr Limited's CAD 18.86 million contract reached its amended 31 December 2025 expiry after 11 amendments; no cited owner record confirms accepted completion, final dredged quantities or reopening

Last checked 16 August 2026 / 6 sources
Canada / Source confidence: Confirmed

Cap-des-Caissie small craft harbour upgrade

Participation: Not assessed

Fishing harbour wharf, dredging and shore protection / Mskikue'j Enterprises holds the CAD 5.09 million wharf and shore-protection contract through March 2027; the separate 2025 dredging and containment-cell contract reached its stated expiry without a public completion or measured-quantity record

Last checked 5 August 2026 / 8 sources
Canada / Source confidence: Confirmed

Sainte-Marie-Sur-Mer structure 401 wharf and breakwater works

Participation: Not assessed

Fishing harbour wharf, dredging and shore protection / L Breau and Sons Ltd holds active CAD 8.75 million contract CW2440554 through 24 August 2027 for structure 401 wharf reconstruction and a new breakwater; mobilisation, measured work and acceptance remain unconfirmed

Last checked 7 August 2026 / 4 sources
Canada / Source confidence: Confirmed

Larrys River small craft harbour breakwater reconstruction

Participation: Not assessed

Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds active CAD 2.75 million contract CW2455209 through 27 November 2026 for rubble-mound breakwater construction at Larrys River; award and scope are confirmed but mobilisation and physical progress are not

Last checked 7 August 2026 / 4 sources
Australia / Source confidence: Confirmed

Me-Mel Goat Island Western Broadside Wharf repair

Participation: Not assessed

Port infrastructure / Western Broadside Wharf, adjacent seawall and access-pontoon repairs are underway under two NSW contracts through August and September 2026; the published notices name Polaris Marine Constructions and Clement Marine Constructions but do not disclose their exact package split

Last checked 5 August 2026 / 5 sources
United Kingdom / Source confidence: Confirmed

Folkestone to Hythe beach management works 2025-2030

Participation: Awarded / Checked / Notice and deadline

Shingle recycling, beach regrading and coastal flood defence / Chunnel holds the signed beach-management contract; the March campaign and April order are historical programme evidence, with autumn activity and accepted output unconfirmed

Last checked 14 October 2026 / 8 sources
United States / Source confidence: Confirmed

Isle of Palms Breach Inlet beneficial-use dredging

Participation: Not assessed

Coastal infrastructure / Two dredging packages completed on 27 February 2026; clay cleanup followed in April and staging was cleared in May

Last checked 18 July 2026 / 7 sources
United States / Source confidence: Confirmed

Mobile Harbor operations and maintenance sediment routing

Participation: Not assessed

Port infrastructure / USACE lists four current federal-standard placement routes; Alabama Code Section 33-7-13 takes effect on 1 October 2026

Last checked 14 August 2026 / 9 sources
Italy / Source confidence: Confirmed

Genoa New Breakwater

Participation: Not assessed

Ports and coastal protection / 24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active

Last checked 15 July 2026 / 10 sources
Benin / Côte d'Ivoire / Mauritania / São Tomé and Príncipe / Senegal / Togo / Source confidence: Confirmed

WACA ResIP 1 coastal protection works programme

Participation: Not assessed

Coastal infrastructure / ResIP 1 in finalisation; country work fronts and closing dates remain separate

Last checked 17 July 2026 / 5 sources
Senegal / Source confidence: Confirmed

Gorée Island east and west coastal protection works

Participation: Not assessed

Coastal infrastructure / Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed

Last checked 16 July 2026 / 6 sources
Marshall Islands / Source confidence: Confirmed

Ebeye Coastal Protection Works

Participation: Not assessed

Coastal infrastructure / Completed seawall and footpath handed over on 17 September 2026; final account and post-storm performance unverified

Last checked 21 October 2026 / 12 sources
United States / Source confidence: Confirmed

Ocean City and Peck Beach 2026 Periodic Nourishment

Participation: Not assessed

Coastal infrastructure / USACE records September 7 completion; the city reports 1.6 million cubic yards placed; New Jersey requested storm-repair assistance on October 16

Last checked 21 October 2026 / 8 sources
Liberia / Source confidence: Confirmed

West Point Coastal Defence Revetment

Participation: Not assessed

Coastal infrastructure / The West Point revetment has an approved ESIA and March 2026 environmental permit; construction award, notice to proceed and physical start are not established

Last checked 17 July 2026 / 5 sources
Fiji / Source confidence: Confirmed

Fiji Kinoya wastewater treatment and Laucala Bay outfall programme

Participation: Submissions closed / Checked / Notice and deadline

Submission deadline: Next notice (expected):

Marine utilities / CW02 prequalification applications closed on 30 September 2026; bidding invitations expected in December 2026

Last checked 14 October 2026 / 8 sources
United States / Source confidence: Confirmed

Niagara River Emerald Shiner Fish Passage

Participation: Not assessed

Coastal infrastructure / USACE reports the 700-foot full phase completed in May 2026 and the combined 778-foot fish passage opened with a ribbon-cutting on 23 July 2026

Last checked 23 July 2026 / 5 sources
United States / Source confidence: Confirmed

Buffalo Harbor 2026 dredging and Slip 3 wetland placement

Participation: Not assessed

Port infrastructure / USD 2.3 million Ryba contract awarded; July-August 2026 dredging and placement programme announced

Last checked 13 August 2026 / 6 sources
United States / Source confidence: Confirmed

Oswego Harbor 2026 breakwater repair phases

Participation: Not assessed

Port infrastructure / USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028

Last checked 14 August 2026 / 5 sources
United States / Source confidence: Confirmed

Dunkirk Harbor west breakwater rehabilitation

Participation: Not assessed

Port infrastructure / Great Lakes Dock & Materials holds both phases; USACE reports the last 450 feet continuing through November 2026

Last checked 10 August 2026 / 6 sources
United States / Source confidence: Confirmed

Vermilion Harbor East Pier repair

Participation: Not assessed

Port infrastructure / USACE officially completed the East Pier repair on 24 July 2026 after rebuilding 900 feet of the 1,333-foot structure

Last checked 25 July 2026 / 4 sources
United States / Source confidence: Confirmed

Rocky River Harbor 2026 maintenance dredging

Participation: Not assessed

Port infrastructure / Mechanical dredging began in late May 2026 and is scheduled to continue through August

Last checked 18 July 2026 / 4 sources
Comoros / Source confidence: Confirmed

Boingoma Port expansion and climate-resilient marine works

Participation: Not assessed

Port infrastructure / World Bank and AfDB implementation records confirm works are under way; the contractor's current target is 11 August 2027

Last checked 18 July 2026 / 7 sources
Nauru / Source confidence: Confirmed

Nauru Aiwo Port climate-resilient redevelopment

Participation: Not assessed

Port infrastructure / ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items

Last checked 19 July 2026 / 9 sources
Vietnam / Source confidence: Confirmed

Can Gio International Transshipment Port

Participation: Not assessed

Deep-water ports and container terminals / Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced

Last checked 20 July 2026 / 6 sources
Benin / Source confidence: Confirmed

Port of Cotonou Terminal 5 bulk terminal

Participation: Not assessed

Port infrastructure / The port authority reports 69% physical progress and 72% overall progress, while its published 2021-2024 delivery period is no longer current

Last checked 20 July 2026 / 6 sources
Barbados / Source confidence: Confirmed

Bridgetown Fisheries Complex breakwater repair

Participation: Not assessed

Coastal infrastructure / C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished

Last checked 7 August 2026 / 11 sources
Tonga / Source confidence: Confirmed

Nafanua Port resilience improvement

Participation: Not assessed

Port infrastructure / China Jiangsu International holds the signed USD 4.803 million MOI-WK2-13 award; notice to proceed, mobilisation and physical works remain publicly unconfirmed

Last checked 6 August 2026 / 7 sources
Australia / Source confidence: Confirmed

Geraldton Port Maximisation marine works

Participation: Not assessed

Port infrastructure / MGN Civil holds the surge-protection breakwater award; wider dredging, berth and tug-harbour packages remain separately unconfirmed

Last checked 13 August 2026 / 8 sources
India / Source confidence: Confirmed

Mus seawall at Car Nicobar

Participation: Not assessed

Coastal infrastructure / Recall tender is in post-bid evaluation; no public AOC or named EPC contractor

Last checked 16 August 2026 / 9 sources
New Zealand / Source confidence: Confirmed

New Zealand regional-port dredging barge

Participation: Not assessed

Dredging / NZD 8 million of government co-funding confirmed; designer, shipyard, build contract and first port assignment not disclosed

Last checked 23 July 2026 / 7 sources
Caribbean Netherlands / Source confidence: Confirmed

Saba Black Rocks Harbor and Fort Bay improvement works

Participation: Not assessed

Hurricane-resilient harbor, breakwater, dredging, quay and marina works / Public Entity Saba reported steady construction progress on 10 May 2026, including breakwater works and Xbloc arrivals, with additional units being produced in Sint Eustatius. Dredging and excavation were active in March 2026, but marine completion, harbor handover, Fort Bay close-out and operational opening remain unconfirmed.

Last checked 2 August 2026 / 11 sources
Poland / Source confidence: Confirmed

Gdynia Outer Port protective breakwaters

Participation: Not assessed

Caisson breakwaters and port access infrastructure / The May 2026 building permit has moved the design-build contract into principal in-water works; the first reinforced-concrete caisson was launched and towed toward its placement position in July 2026, with the remaining 48 caissons and breakwater systems still to be delivered

Last checked 2 August 2026 / 5 sources
France / Source confidence: Confirmed

Frioul East breakwater rehabilitation and rock spur

Participation: Not assessed

Historic rubble-mound breakwater rehabilitation and island-port protection / Contract Z250608F00 was concluded on 2 February 2026 with an Océlian-led five-company group for EUR 19.589919 million; the owner reports that the overall rehabilitation programme continues in 2026, while main-contract mobilisation, placed rock, accepted sections and downstream subcontract awards remain unpublished

Last checked 2 August 2026 / 7 sources
France / Source confidence: Confirmed

Granville Herel main breakwater and sill-wall repair

Participation: Not assessed

Breakwater and reinforced-concrete marine-structure rehabilitation / The owner-confirmed nine-month repair started on 25 August 2025; its planned end-May 2026 acceptance window has passed without a published completion certificate, handover or final account

Last checked 7 August 2026 / 5 sources
France / Source confidence: Confirmed

Dunkirk Braek submerged sand-discharge pipeline replacement

Participation: Not assessed

Coastal protection and dredged-sand reuse / Baggerbedrijf de Boer holds the EUR 1.720365 million replacement contract concluded on 13 January 2025; the planned 31 May 2025 in-service deadline has passed, while physical completion, acceptance and downstream packages remain unverified

Last checked 5 August 2026 / 8 sources
United Kingdom / Source confidence: Confirmed

Harwich Haven five-year maintenance dredging

Participation: Awarded / Checked / Notice and deadline

Maintenance dredging, beneficial use and dredging technology / HHA confirmed Suffolk Dredging LLP's five-year maintenance award in July; the March procurement family was withdrawn for a scope-description correction, with current value and exact commencement unconfirmed

Last checked 14 October 2026 / 15 sources
Australia / Source confidence: Confirmed

Warrawong Parklands Kully Bay seawall reconstruction

Participation: Not assessed

Foreshore seawall and rip-rap protection / Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence

Last checked 5 August 2026 / 5 sources
United States / Source confidence: Confirmed

Moss Landing Harbor jetty repair and maintenance dredging

Participation: Not assessed

Breakwater armour repair, access dredging and nearshore placement / Ahtna Infrastructure & Technologies held the USD 16,037,425 current-obligation contract for Moss Landing Harbor dredging and jetty repair; the US Coast Guard published 2025 field-work windows and USACE published August-September post-dredge surveys, but the 23 January 2026 contract end does not establish final quantity, jetty acceptance, completion or final account

Last checked 5 August 2026 / 7 sources
Philippines / Source confidence: Confirmed

Libertad Outfall dredging works

Participation: Not assessed

Dredging / Group completion reported; Libertad closeout remains unpublished.

Last checked 14 August 2026 / 7 sources
Barbados / Source confidence: Confirmed

Bridgetown Port Sugar Berth seawall and revetment repair

Participation: Not assessed

Port infrastructure / World Bank contract record 1881500 names C. O. Williams Construction Limited at USD 3.338 million, but the public procurement chronology does not reconcile and no dated mobilisation, progress or completion record has been located

Last checked 6 August 2026 / 4 sources
Tunisia / Source confidence: Confirmed

Menzel Abderrahmane fishing-port extension and coastal esplanade

Participation: Not assessed

Fishing-port expansion, dredging, breakwater, quay and coastal esplanade / ETEP signed the TND 20,018,762.19 works contract on 28 April 2025, but Tunisia's parliament still described the port and esplanade project as delayed during a February 2026 site visit; physical start, achieved quantities and supervision award remain unverified

Last checked 9 August 2026 / 8 sources
Australia / Source confidence: Confirmed

Newell Beach all-tide boat ramp upgrade

Participation: Not assessed

Public boat-launch infrastructure, capital dredging and fixed access / Queensland TMR completed the upgraded all-tide facility in May 2022 after Australian Marine & Civil delivered the main works under CN-17011; the published contract disclosure rose from AUD 2,560,154 to AUD 2,603,835 after a variation

Last checked 6 August 2026 / 10 sources
Australia / Source confidence: Confirmed

Poona boat ramp and access-channel upgrade

Participation: Not assessed

Public boat-launch infrastructure, capital dredging and fixed access / Australian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026

Last checked 6 August 2026 / 10 sources
United Kingdom / Source confidence: Confirmed

Burry Port Harbour emergency sand dredging

Participation: Awarded / Checked / Notice and deadline

Maintenance dredging, approach-channel access and beach placement / Carmarthenshire County Council signed a GBP 425,000 excluding VAT emergency dredging contract with Kaymac Marine & Civil Engineering on 29 June 2026 for a 13 July to 31 October delivery window; the council has published no mobilisation, dredger, production, survey, completion or acceptance update

Last checked 14 October 2026 / 9 sources
United Kingdom / Source confidence: Confirmed

Langstone Coastal Defence Scheme

Participation: Awarded / Checked / Notice and deadline

Continuous tidal flood and coastal erosion defence with early contractor involvement / Jackson is appointed; April 2027 main construction is planned, with the programme under refinement and signed terms and consent documents outstanding

Last checked 14 October 2026 / 9 sources
Canada / Source confidence: Confirmed

Glace Bay small craft harbour wharf reconstruction

Participation: Not assessed

Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified

Last checked 8 August 2026 / 4 sources
Canada / Source confidence: Confirmed

Meteghan floating wharf and pile rehabilitation

Participation: Not assessed

Fishing harbour wharf, dredging and shore protection / Dexter holds CAD 4.29 million CW2462474 for floating-dock and pipe-pile replacement, while Connors Diving holds CAD 1.27 million 4500109325 for Wharf 403 pile jackets and concrete repairs; both awards are active but mobilisation and progress are unverified

Last checked 8 August 2026 / 5 sources
Australia / Source confidence: Confirmed

Apollo Bay Harbour seawall construction

Participation: Not assessed

Harbour seawall renewal and coastal asset protection / Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation

Last checked 8 August 2026 / 4 sources
Canada / Source confidence: Confirmed

Fox Island River harbour entrance improvement and re-dredging

Participation: Not assessed

Small-craft-harbour entrance dredging and breakwater works / Marine Contractors' CAD 1.499m entrance-improvement contract and R.J.G Construction's separate CAD 1.133m channel re-dredging contract have both reached their published administrative end dates, but no completion certificate, accepted hydrography, final dredged quantity or causal link between the packages is public

Last checked 9 August 2026 / 7 sources
Canada / Source confidence: Confirmed

Fox Island River channel-wall and marginal-wharf reconstruction

Participation: Not assessed

Small-craft-harbour marginal wharf and channel-wall renewal / DFO-SCH's 2026 proposal remains in federal assessment after the public-comment period ended on 22 June 2026; no environmental determination, procurement, award, contractor, mobilisation or construction is evidenced

Last checked 9 August 2026 / 4 sources
United Kingdom / Source confidence: Confirmed

NOC Southampton quayside wall and pontoon repairs

Participation: Awarded / Checked / Notice and deadline

Seawall, quayside and pontoon repair / National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT; the contract period ran from 13 August to 12 September 2025, but no dated completion, acceptance or final-account record has been located

Last checked 14 October 2026 / 5 sources
Samoa / Source confidence: Confirmed

Apia Port climate-resilient breakwater and terminal upgrade

Participation: Not assessed

Port infrastructure / Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate

Last checked 11 August 2026 / 8 sources
South Africa / Source confidence: Confirmed

Port of Durban North Bank revetment repairs

Participation: Not assessed

Port revetment repair and armour-rock placement / South Africa's official procurement release records an active ZAR 5,466,159 award to KATLANTIC for the Port of Durban North Bank revetment repairs; the public record does not provide an award date, executed contract, notice to proceed, physical progress or completion

Last checked 11 August 2026 / 4 sources
Australia / Source confidence: Confirmed

Snapper Creek State Boat Harbour shoreline protection works

Participation: Not assessed

Port revetment repair and armour-rock placement / Queensland Transport and Main Roads disclosed Contract MSQ25017 with Hunter Contractors Pty Ltd at AUD 1,981,207 on 10 July 2025, and Maritime Safety Queensland announced a 2 September 2025 construction start; no cited official source confirms installed quantities, completion, acceptance or final account

Last checked 13 August 2026 / 4 sources
United States / Source confidence: Confirmed

Sandusky Harbor 2026 maintenance dredging and nearshore placement

Participation: Not assessed

Navigation channel maintenance dredging / USACE scheduled Morrish-Wallace's 109,000-cubic-yard campaign to start on 6 October 2026 and finish by 1 November; actual mobilisation remains unverified

Last checked 6 October 2026 / 4 sources
United Kingdom / Source confidence: Confirmed

Torcross rock-armour sea-defence renewal

Participation: Requires review / Checked / Notice and deadline

Rock-armour coastal defence / Construction reported begun 14 October 2026; rock-delivery and installation programme extends into 2027

Last checked 3 November 2026 / 4 sources
United Kingdom / Source confidence: Confirmed

Lymington Toll Bridge tidal-flap and sill renewal

Participation: Awarded / Checked / Notice and deadline

Tidal outfall and flood-gate renewal / September flap installation reported 7 October; separate regulating-float repair planned by yearend

Last checked 3 November 2026 / 4 sources
United Kingdom / Source confidence: Confirmed

Barton to New Holland tidal flood-defence scheme

Participation: Planned procurement / Checked / Notice and deadline

Tidal embankment and outfall adaptation / Detailed design, land discussions and environmental assessment; Full Business Case targeted for summer 2027

Last checked 3 November 2026 / 4 sources
Vietnam / Source confidence: Confirmed

Nga Bay riverbank embankments and lake flow control

Participation: Not assessed

Riverbank embankment and urban flood outfall works / June 2026 government account reports embankment work and drainage-package mobilisation; subsequent reach acceptance and programme updates remain to be checked

Last checked 4 November 2026 / 4 sources
United States / Source confidence: Confirmed

United States Duke Marine Lab marsh-sill living shoreline

Participation: Not assessed

Living shoreline sill and intertidal marsh / Restoration completed in 2002; NOAA reports stable sill geometry through a 2025 resurvey and long-term marsh monitoring.

Last checked 4 November 2026 / 4 sources
Nigeria / Source confidence: Confirmed

Nigeria Lekki Deep Sea Port Phase I marine works

Participation: Not assessed

Port channel dredging, breakwaters and coastal sand management / Phase I construction completion recorded in October 2022; presidential commissioning 23 January 2023; owner states full operation since 1 April 2023.

Last checked 4 November 2026 / 9 sources
United Kingdom / Source confidence: Confirmed

Bridgwater Tidal Barrier and downstream flood defences

Participation: Not assessed

Tidal surge barrier and downstream flood defences / Permanent reinforced-concrete foundations advancing; revised superstructure scheduled from early 2027

Last checked 5 November 2026 / 5 sources
United States / Source confidence: Confirmed

Poplar Island dredged-material ecosystem restoration

Participation: Not assessed

Dredged-material placement and intertidal marsh creation / Phased dredged-material placement and habitat development; published monitoring covers established marsh cells

Last checked 5 November 2026 / 4 sources

Scope and corrections

This general technical reference is not project-specific design advice. Project status is dated and linked to its public sources; corrections can be submitted with the relevant design, survey, inspection, monitoring or field record.