Mid West Ports Authority awarded MGN Civil the surge-protection breakwater contract on 3 June 2026 and says construction will start later in 2026. The breakwater is one marine package inside the State-funded AUD 350 million Geraldton Port Maximisation Project. Ministerial Statement 1272 separately approves a wider envelope covering up to 258,000 m3 of dredging, reclamation, Berth 1 replacement, Berth 6 extension, future Berths 8 and 9 and a new tug harbour.
Project signal
Award in Australia
Keep the award, approval and construction gates separate. MGN Civil is named only for the surge-protection breakwater. The AUD 350 million figure funds the overall programme and is not the breakwater contract value. Ministerial approval defines the permitted marine envelope but does not prove that the dredging, berth or tug-harbour works have been tendered, awarded or mobilised.
Current statusMGN Civil holds the surge-protection breakwater award; wider dredging, berth and tug-harbour packages remain separately unconfirmedSource confidenceConfirmed
Location
Australia / Asia Pacific
Segment
Port infrastructure
Status
MGN Civil holds the surge-protection breakwater award; wider dredging, berth and tug-harbour packages remain separately unconfirmed / Confirmed
Evidence reviewed
20 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
Mid West Ports Authority
Delivery parties
MGN Civil Pty Ltd - surge-protection breakwater
Contract route
Mid West Ports Authority announced a direct project-specific award to MGN Civil for the surge-protection breakwater on 3 June 2026. The owner did not publish the contract value, notice-to-proceed date, rock-supply chain or subcontractors. The Western Australian Government describes PMaxP as a State-funded AUD 350 million programme. No cited source identifies construction awards for the Berth 1 replacement, Berth 6 extension, future Berths 8 and 9, or the capital-dredging packages.
Execution window
The owner says breakwater construction will commence later in 2026. A May 2026 parliamentary statement placed major construction from mid-2026 and expected the breakwater to build effectiveness through the end of 2027, but the owner's award notice gives no completion date. The 2024-25 annual report's 2028 programme target predates Ministerial approval, and no current owner notice gives package-specific completion dates for the wider marine works.
Works package
The approved proposal allows up to 258,000 m3 of dredging: 240,000 m3 of capital dredging and a once-off 18,000 m3 maintenance campaign. The environmental assessment describes a roughly 450-metre northern breakwater and new tug harbour, Berth 1 replacement with a 293-by-22-metre deck, Berth 6 extension to about 287 metres, and a future roughly 500-metre Berths 8 and 9 wharf. It anticipates about 480 piles across the berth and tug-harbour works. Dredged material is intended for on-site reuse and reclamation rather than offshore disposal, subject to suitability.
Marine interfaces
The environmental assessment places the breakwater before the main dredging works so it can reduce long-period surge inside the port and partially contain the dredging plume. That sequence links armour placement and breakwater geometry to tug-harbour operability, dredging access, reclamation capacity and the later berth layouts. The approval also prohibits capital dredging from 1 December to 28 February unless the regulator agrees otherwise and requires marine-fauna observation during piling, dredging and rock breaking.
Commercial read
The breakwater is allocated to MGN Civil. The wider programme remains a set of separate potential packages, not one AUD 350 million contract. Market activity should be tied to owner-issued procurement, named contractors or mobilisation evidence for dredging, Berth 1, Berth 6, future Berths 8 and 9, tug-harbour jetties, survey, monitoring and material handling rather than inferred from the approval envelope.
Next milestone
A notice to proceed or visible mobilisation for the MGN breakwater package, including armour source and marine plant, followed by owner procurement or award notices for dredging, Berth 1, Berth 6 and tug-harbour works.
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Mid West Ports awarded the surge-protection breakwater
MGN Civil became the named contractor for the first disclosed marine construction package. The announcement did not publish contract value, notice to proceed, rock source or mobilisation evidence.
Ministerial Statement 1272 allowed the proposal to proceed
The approval set the 258,000 m3 dredging limit, seasonal restriction and environmental-management conditions for the wider project. It did not award the dredging or berth packages.
The report established the assessed marine footprint, benthic impacts, material-reuse route and environmental conditions that informed the later Ministerial Statement.
A notice to proceed or visible mobilisation for the MGN breakwater package, including armour source and marine plant, followed by owner procurement or award notices for dredging, Berth 1, Berth 6 and tug-harbour works.
Decision watchpoints
Breakwater contract value, notice to proceed and baseline surveys
Armour-rock source, testing, transport and placement sequence
MGN Civil plant, temporary works and marine-access mobilisation
Berth 1 replacement and Berth 6 extension procurement
Dredging contractor, method, quantities and seasonal work window
Dredged-material suitability, placement and reclamation capacity
Marine-fauna observations, plume monitoring and regulator reporting
As-built hydrography, berth acceptance and measured surge performance
Mid West Ports AuthorityOrganization profile / Western Australian port authority and Government Trading Enterprise
Project availability status
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed20 July 2026Sources in this record7
Source record
Mid West Ports Authority controls the current breakwater award and start statement. Ministerial Statement 1272 controls the approved limits and environmental conditions. EPA Report 1792 and the project environmental assessment define the dredging quantities, berth geometry, piling, material-reuse route and proposed sequence. The annual report and parliamentary record provide programme context only. Lease 11 truck-unloader construction started in May 2025, but it is landside work and is not evidence that the approved marine packages or MGN breakwater have mobilised.