Ports & Dredging

Geraldton awarded its breakwater before the wider marine works

Published 20 July 2026 Updated 16 August 2026 Publisher IMWO Region Asia Pacific Confidence Confirmed
Geraldton inner-harbour plan showing Berth 1 and Berth 6 dredging, the new tug harbour and dredged-material reuse locations

Mid West Ports Authority / SLR Consulting; dredging and material-reuse plan in the environmental impact assessment

Mid West Ports has awarded MGN Civil the surge-protection breakwater at Geraldton. The award sits ahead of the separately described dredging, reclamation, berth and tug-harbour works in the approved Port Maximisation Project.

Published scope and current milestone

The owner and Western Australian Government releases both confirm MGN Civil's breakwater award and a start later in 2026, but neither gives a contract value, notice to proceed or mobilisation evidence. Ministerial Statement 1272 and EPA Report 1792 set the approved 258,000 m3 dredging limit and conditions. The environmental assessment supplies the berth, tug-harbour, piling, sequence and material-reuse detail. None of those approval documents names contractors for the wider marine works. Landside Lease 11 activity is not treated as marine mobilisation.

Dredging quantity and delivery implications

The breakwater is intended to reduce the long-period surge that disrupts port operations, create sheltered tug mooring and partly contain the plume from later dredging. Its geometry and construction sequence affect dredger access, reclamation capacity, Berth 1 replacement, Berth 6 extension and the future Berths 8 and 9 layout.

Evidence conclusion

Survey, placement and acceptance evidence

Only the breakwater award is public. The AUD 350 million figure belongs to the whole Port Maximisation programme, not to MGN Civil's contract. Ministerial Statement 1272 allows up to 258,000 m3 of dredging and the wider berth and tug-harbour development, but approval is not an award or a start notice. No notice to proceed or mobilisation is public for the breakwater, and no owner award names contractors for the dredging or berth packages.

Outstanding evidence

  • Breakwater contract value and notice to proceed
  • Armour-rock source, quality testing and marine transport
  • MGN Civil plant and temporary-works mobilisation
  • Berth 1 and Berth 6 procurement notices
  • Capital-dredging contractor and seasonal programme
  • Material-reuse and reclamation capacity
  • Marine-fauna and plume-monitoring results
  • As-built surveys and measured surge reduction

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Sources used 7

Source collections