Global coastal protection monitor
Global coastal protection monitor
Six coastal protection projects across five regions show why delivery cannot be reduced to a single progress percentage. Beach nourishment, island revetments, heritage dikes and walls, deep-water breakwaters, reclamation interfaces and approval-stage defences each depend on different material chains and acceptance evidence.
Public web report / version 1.1 / published 14 July 2026 / data cutoff 16 July 2026.
U.S. Army Corps of Engineers, Charleston District / Dylan Burnell
Evidence scope
Six public IMWO project records in the United States, Liberia, Senegal, Marshall Islands, Italy and India, spanning approval, tender and construction phases across beach nourishment, rubble-mound revetments, dikes and walls, deep-water caisson breakwaters, reclamation and shore protection.
Portfolio composition
Calculated from 6 public project records in this edition. Counts describe the current portfolio, not market size, expenditure, or completion progress.
Global coastal protection monitor
Coastal and port owners, marine contractors, dredging and quarry suppliers, designers, lenders, environmental teams, public authorities and institutions comparing current shoreline-protection delivery evidence.
Open web and PDF report. No registration or access request is required.
Download report PDFDownload the fixed project evidence set used for this edition, including phase, confidence, update date, and primary source fields.
Download report CSVPublication record
International Marine Work Organization (2026). Global Coastal Protection Delivery Monitor: July 2026 (Version 1.1, IMWO-REP-2026-07-COASTAL; data cutoff 16 July 2026). https://imwo.org/reports/report-global-coastal-protection-delivery-monitor
Calculated snapshot
Every count uses the same six-record denominator at the stated cutoff. The figures describe evidence maturity, region and phase within the included set; they are not market shares, forecasts, capacity measures or estimates of protection performance.
All six records satisfy the named-project, physical-interface, structured-source and anti-double-counting rules.
6 of 6 included recordsOcean City, Ebeye, Gorée and Genoa have current construction evidence, while West Point is at approval and Vadhvan at tender.
4 of 6 included recordsWest Point has an environmental permit without public award or mobilisation evidence; Vadhvan has separate awarded and unawarded package states.
2 of 6 included recordsThe set covers Africa, the Americas, Asia Pacific, Europe and Global islands, with two distinct African project records.
5 region labels across 6 included recordsThe six coastal projects differ in material route, workability window and acceptance method, so shoreline length alone is not a meaningful delivery comparison.
Ocean City's current contract quantity begins at an offshore borrow site, while its separate 2022-23 placed quantity and stockpile are historical results. Ebeye's armourstone begins at a Ras Al Khaimah quarry and crosses an ocean before barge transfer. In both projects, material produced, shipped, landed or pumped remains different from surveyed, compliant and owner-accepted protection geometry.
West Point has project finance, met-ocean work, an approved ESIA and a March 2026 environmental permit, but the reviewed public record does not identify a works contractor or notice to proceed. Procurement and mobilisation are now the material events; another statement that the project exists would not change its status.
Genoa and Vadhvan both contain major breakwater and seabed interfaces, yet their evidence states differ sharply. Genoa has installed caissons and active foundation work; Vadhvan has an awarded nearshore package while the offshore breakwater and dredging-reclamation packages remain separate procurement questions.
Gorée's extension request ties delay and cost pressure to sea conditions, supply constraints, inflation and heritage-specific design adjustments. Ebeye adds long-haul rock logistics and transfer conditions, while Ocean City works inside a compressed seasonal beach and environmental window. Published end dates therefore need method-specific evidence.
A nourishment contract closes through placed volume and surveyed berm geometry; revetments require toe, filter and armour acceptance; caisson breakwaters require foundation, continuity and navigation interfaces; reclamation requires settlement, perimeter protection and hydrographic proof. One generic percentage-complete field cannot safely compare the set.
Six Confirmed public project records form the denominator for this edition. Each project page carries the current scope, delivery parties, commercial boundary, next milestone, visual context and complete source list.
Coastal infrastructure / Construction
Great Lakes Dredge & Dock's USD 19.5 million nourishment contract is in construction; dredge mobilisation is evidenced, but placed volume, accepted beach template and completion remain open
6 structured project sourcesCoastal infrastructure / Approval
The West Point revetment has an approved ESIA and March 2026 environmental permit; construction award, notice to proceed and physical start are not established
5 structured project sourcesCoastal infrastructure / Construction
Marine logistics and construction are established; completion and owner acceptance are not confirmed, while the latest programme update forecasts completion by the end of 2026
7 structured project sourcesCoastal infrastructure / Construction
Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed
6 structured project sourcesPorts and coastal protection / Construction
24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active
10 structured project sourcesDeep-water ports, dredging and reclamation / Tender
The approximately 200-hectare nearshore reclamation and shore-protection EPC package is awarded; as of 15 July 2026, the owner tender page lists the offshore dredging, reclamation and protection-bund HAM package closing on 17 July and the Daman marine-sand investigation closing on 15 July, while no award or AOC is published for either package or for the 10.14-kilometre offshore breakwater
11 structured project sourcesMethod
The July edition follows six public IMWO records with identifiable coastal protection scope and current delivery evidence at the 16 July 2026 cutoff. Qualification depends on a named package, a physical shoreline, breakwater, nourishment, revetment, dike, wall, reclamation or marine-material interface, and structured support from an accountable source. One project contributes one latest evidenced phase. The WACA ResIP 1 regional programme is excluded from the denominator because the included Gorée project is one of its country work fronts; counting both would duplicate the same physical package. Vadhvan is included as a bounded port-coastal interface and remains at tender because its nearshore shore-protection package is awarded while the defining offshore breakwater and dredging-reclamation packages remain without official award evidence in the reviewed record. Ocean City's formal programme baseline, completed 2022-23 cycle and active 2026 contract are retained as separate dated layers so historical placed quantities cannot enter the current production ledger.
Current construction start, dredge mobilisation, contract quantity, placement reach, design template and forecast completion boundary.
Project Partnership Agreement, 1992 initial construction, initial-fill quantity, periodic-nourishment baseline and design geometry.
Prior-cycle completion, placed quantity and stockpile boundary; these figures do not measure the 2026 campaign.
Permit and coordinate boundary for the West Point revetment; the permit does not establish award, notice to proceed or mobilisation.
Programme status, finance, implementation period and coastal-defence objective for West Point.
Contract, first riprap arrival and protected-coast indicator basis for Ebeye.
Armourstone source, supply quantity, ocean voyage and deep-water transfer basis for Ebeye's quarry-to-shore chain.
Current Gorée scope, cost-pressure causes and proposed 2027 completion path.
Current caisson, foundation and first-kilometre construction evidence for Genoa.
Owner-side package boundaries and reviewed award or evaluation state for nearshore, breakwater and offshore works.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
This report is a dated research snapshot, not an investment forecast, procurement recommendation, legal opinion, or delivery commitment. Review the linked project records and current briefings before acting on any individual project signal.