Project record
Completed seawall and footpath handed over on 17 September 2026; final account and post-storm performance unverified
The completed Ebeye Seawall and Footpath was handed over on 17 September 2026, according to the Marshall Islands President's Office. Hall Contracting reports delivery of a 1.81-kilometre seawall, an illuminated footpath and connections to the island's road drainage scheme. The contractor describes transporting 84,000 tonnes of armour rock and fill, including specialised rock sourced from the United Arab Emirates. Haskoning led the design and construction supervision. World Bank contract 1786103 records Hall Civil Contracting Pty Ltd, a 9 May 2024 signature date and USD 52,635,577.03 value. The earlier November 2025 rock shortfall remains part of the construction history; its agreed remedy, final quantities and financial settlement have not been established from the completion announcements. Post-storm protection performance remains to be measured.
Marshall Islands / Global islands
Coastal infrastructure
Completed / Confirmed
21 October 2026
Coverage
Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe President's Office confirms the physical handover, replacing the earlier incomplete-work position; Hall separately reports a 1.81-kilometre seawall and drainage integration. Final certified quantities, financial settlement and measured post-storm performance remain unverified.
SourceThe latest World Bank report records nearly 80% of the 1,800 metres of new seawall built, but says the contractor identified an unexpected rock shortfall and solutions were still being developed. The remaining 379 metres and southern-end asset protection stay on the critical path.
SourceThe World Bank report moved the job from site preparation into marine material delivery. The rock still had to be transferred to barges, landed on Ebeye, placed to the design profile, surveyed, and accepted.
SourceThe team began the unloading facility, access works, and other preparations needed for the 1.81-kilometre seawall. It was the start of delivery, with armour placement and acceptance still ahead.
SourceContract 1786103 identifies Hall Civil Contracting Pty Ltd under Request for Bids reference MH-PREP II-PIU-364075-CW-RFB at an exact value of USD 52,635,577.03. The final bill of quantities and contract risk allocation are not disclosed in the public record.
SourceEvidence gap