Shoreline protection, waterfront resilience, coastal access, reclamation interfaces, public realm edges, and climate adaptation works.

Projects retain their detailed work segment and may appear in more than one sector when the scope crosses delivery disciplines.

Last checked 55 public projects 63 related publications 45 connected organizations

Coverage focus

Shoreline protection, resilience and reclamation interfaces

Tracker coverage

55 project records connected to this sector.

Publication coverage

63 current analyses and briefs connect through governed project relationships.

Organization coverage

45 public profiles connect through documented project roles.

Project coverage

All current Coastal infrastructure project records

55 records
Confirmed

Langstone Coastal Defence Scheme

United Kingdom / Continuous tidal flood and coastal erosion defence with early contractor involvement / Havant Borough Council selected Jackson Civil Engineering for a GBP 14 million excluding-VAT NEC4 coastal-defence contract; the 1 May 2026 award notice still marked the contract pending, while planning officers recommended conditional permission on 25 June and the owner continues to target two April-November construction windows in 2027 and 2028

award / Last checked
Confirmed

Centreville small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Kerr Limited's CAD 18.86 million contract reached its amended 31 December 2025 expiry after 11 amendments; no cited owner record confirms accepted completion, final dredged quantities or reopening

delivery / Last checked
Confirmed

Port 2000 Chatiere protected river access

France / Ports and coastal protection / Terelian and SDI/DEME are constructing the 1,800 metre protection dike; HAROPA reported nearly 800,000 m3 of foundation material placed by 1 June 2026 after a 760,000 m3 weak-silt purge, while channel dredging, dike tie-ins, completion and operating release remain pending

construction / Last checked
Confirmed

Mus seawall at Car Nicobar

India / Coastal infrastructure / Recall tender is in post-bid evaluation; no public AOC or named EPC contractor

tender / Last checked
Confirmed

Parks Victoria Bays Maintenance Dredging Program

Australia / Maintenance dredging, approach-channel access and beach placement / Buying for Victoria records Birdon Pty Ltd on a current AUD 31.9 million contract starting 1 November 2021; Birdon describes a 2021-2030 term and names dredge Ballina with support craft Willie Tell and Bella, while site-level quantities and owner acceptance remain campaign-specific

delivery / Last checked
Confirmed

Wesleyville and Brookfield floating-dock reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Granite Management received DFO contract 4500013526 on 23 December 2021 for a two-site floating-dock package; the 2021-22 Public Accounts mark the contract completed, while physical acceptance records remain unpublished

completed / Last checked
Confirmed

Port de Grave marginal wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210731/001/PWD on 15 November 2021; CanadaBuys records a CAD 1,763,368 cumulative contract after amendments, and the 2022-23 Public Accounts mark the Port de Grave contract completed

completed / Last checked
Confirmed

Winterton small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed

completed / Last checked
Confirmed

Snapper Creek State Boat Harbour shoreline protection works

Australia / Port revetment repair and armour-rock placement / Queensland Transport and Main Roads disclosed Contract MSQ25017 with Hunter Contractors Pty Ltd at AUD 1,981,207 on 10 July 2025, and Maritime Safety Queensland announced a 2 September 2025 construction start; no cited official source confirms installed quantities, completion, acceptance or final account

construction / Last checked
Confirmed

Skinners Pond wharf 401 copewall rehabilitation

Canada / Fishing harbour wharf, dredging and shore protection / Kildare Construction Ltd. received CAD 1.10 million contract 4500013345 on 23 December 2021 for structure 401; the 15 June 2022 target date is published, but completion and owner acceptance remain unverified

award / Last checked
Confirmed

Saint-Edouard-de-Kent containment-cell reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Christian Larocque Services LTEE received the CAD 347,878.45 construction contract in November 2021; Harbourside Engineering reports the rebuilt dredge-spoil containment cell completed in March 2022

completed / Last checked
Confirmed

Port of Durban North Bank revetment repairs

South Africa / Port revetment repair and armour-rock placement / South Africa's official procurement release records an active ZAR 5,466,159 award to KATLANTIC for the Port of Durban North Bank revetment repairs; the public record does not provide an award date, executed contract, notice to proceed, physical progress or completion

award / Last checked
Confirmed

Le Goulet Harbour 2026 maintenance dredging

Canada / Fishing harbour wharf, dredging and shore protection / CanadaBuys solicitation WS5822483507 is open for Le Goulet harbour-basin maintenance dredging and closes 1 September 2026 at 14:00 EDT; no current winner, contract value, quantity, depth, disposal site, plant or delivery contractor is publicly established

tender / Last checked
Confirmed

Norfolk Island Cascade Pier emergency remediation works

Norfolk Island / Pier remediation and island freight access / GP Services' AUD 183,041 emergency-remediation period has elapsed without accepted completion evidence; the separate AUD 10 million apron project is in detailed design with Consult Marine, with no construction award or mobilisation published

award / Last checked
Confirmed

NOC Southampton quayside wall and pontoon repairs

United Kingdom / Seawall, quayside and pontoon repair / National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT; the contract period ran from 13 August to 12 September 2025, but no dated completion, acceptance or final-account record has been located

award / Last checked
Confirmed

Cheticamp Jobs Wharf floating-dock reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Superior Contracting's CAD 1.264 million contract ran from 14 October 2022 to 31 March 2023 for an integrated timber-wharf, dredging, breakwater, floating-dock and electrical package; the reviewed federal record does not publish accepted completion, measured quantities or final account

delivery / Last checked
Confirmed

Menzel Abderrahmane fishing-port extension and coastal esplanade

Tunisia / Fishing-port expansion, dredging, breakwater, quay and coastal esplanade / ETEP signed the TND 20,018,762.19 works contract on 28 April 2025, but Tunisia's parliament still described the port and esplanade project as delayed during a February 2026 site visit; physical start, achieved quantities and supervision award remain unverified

award / Last checked
Confirmed

Apollo Bay Harbour seawall construction

Australia / Harbour seawall renewal and coastal asset protection / Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation

award / Last checked
Confirmed

Meteghan floating wharf and pile rehabilitation

Canada / Fishing harbour wharf, dredging and shore protection / Dexter holds CAD 4.29 million CW2462474 for floating-dock and pipe-pile replacement, while Connors Diving holds CAD 1.27 million 4500109325 for Wharf 403 pile jackets and concrete repairs; both awards are active but mobilisation and progress are unverified

award / Last checked
Confirmed

Glace Bay small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified

award / Last checked
Confirmed

Larrys River small craft harbour breakwater reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds active CAD 2.75 million contract CW2455209 through 27 November 2026 for rubble-mound breakwater construction at Larrys River; award and scope are confirmed but mobilisation and physical progress are not

delivery / Last checked
Confirmed

Grande-Anse harbour-basin dredging and containment-cell works

Canada / Fishing harbour wharf, dredging and shore protection / Les Entreprises P E C inc holds active CAD 862,270 contract CW2452382 through 31 December 2026 for barge-excavator dredging and containment-cell reconfiguration; earliest site start was 6 July and field progress remains unverified

delivery / Last checked
Confirmed

Sainte-Marie-Sur-Mer structure 401 wharf and breakwater works

Canada / Fishing harbour wharf, dredging and shore protection / L Breau and Sons Ltd holds active CAD 8.75 million contract CW2440554 through 24 August 2027 for structure 401 wharf reconstruction and a new breakwater; mobilisation, measured work and acceptance remain unconfirmed

delivery / Last checked
Confirmed

Granville Herel main breakwater and sill-wall repair

France / Breakwater and reinforced-concrete marine-structure rehabilitation / The owner-confirmed nine-month repair started on 25 August 2025; its planned end-May 2026 acceptance window has passed without a published completion certificate, handover or final account

construction / Last checked
Confirmed

Kustlijnzorg South Holland nourishment (31205037)

Netherlands / Beach and foreshore nourishment / Van den Herik signed the EUR 16.302 million contract on 10 March 2026; Rijkswaterstaat schedules Maasvlakte 2 nourishment for September and names Van den Herik with Van der Kamp there, while mobilisation and the parties' commercial relationship remain unverified

award / Last checked
Confirmed

Kustlijnzorg Walcheren beach nourishment (31205036)

Netherlands / Beach and foreshore nourishment / Fa. Gebr. Van der Lee signed the EUR 8.199 million contract on 31 March 2026; the contract is live through 2027, while no public evidence of physical mobilisation, vessel assignment or accepted production was identified by the 7 August 2026 review

award / Last checked
Confirmed

Kustlijnzorg North Holland and Texel nourishment (31205035)

Netherlands / Beach and foreshore nourishment / Boskalis signed the EUR 26.098 million contract on 12 May 2026; Rijkswaterstaat announced Den Helder tidal-channel nourishment from 14 July to mid-October and Julianadorp sinker-pipe removal from 20 July, while measured production and acceptance remain unpublished

construction / Last checked
Confirmed

Soubise/Marquis coastal protection: Soubise Lots 1 and 2

Grenada / Coastal infrastructure / Two Soubise works lots were signed on 27 April 2026 for a combined USD 5.747 million; Marquis Lot 3, notice to proceed, mobilisation and physical works remain publicly unconfirmed

award / Last checked
Confirmed

Bridgetown Fisheries Complex breakwater repair

Barbados / Coastal infrastructure / C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished

construction / Last checked
Confirmed

Petit-Cap structure 403 wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Landco Construction's CAD 3.08 million contract ran from 2 November 2023 to 4 July 2024 for a Berlin-wall marginal wharf, harbour dredging and electrical reinstatement; CanadaBuys does not publish accepted completion or final quantities

delivery / Last checked
Confirmed

Harbour Grace small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Bulldog Contracting received the CAD 7.05 million award on 1 April 2022 for timber-crib wharf, finger-pier, dredging and utility works; the reviewed federal record does not establish the delivery end date, accepted completion or final account

delivery / Last checked
Confirmed

Pugwash small craft harbour floating-dock works

Canada / Fishing harbour wharf, dredging and shore protection / Brian MacGillivary Construction's CAD 516,100 contract ran from 22 November 2023 to 29 March 2024; CanadaBuys confirms the award and amended term but publishes no accepted dredging quantity, dock handover or completion certificate

delivery / Last checked
Confirmed

Ebeye Coastal Protection Works

Marshall Islands / Coastal infrastructure / USD 52,635,577.03 contract in construction; 1,421 m of 1,800 m built by 28 November 2025; rock supply, completion and owner acceptance unresolved

construction / Last checked
Confirmed

Burry Port Harbour emergency sand dredging

United Kingdom / Maintenance dredging, approach-channel access and beach placement / Carmarthenshire County Council signed a GBP 425,000 excluding VAT emergency dredging contract with Kaymac Marine & Civil Engineering on 29 June 2026 for a 13 July to 31 October delivery window; the council has published no mobilisation, dredger, production, survey, completion or acceptance update

award / Last checked
Confirmed

Nanumaga and Nanumea climate-resilient small-boat harbors

Tuvalu / Ports and coastal protection / Hall Civil Contracting signed the USD 62.552 million design-build contract on 21 July 2025; the latest cited mission set August 2027 and January 2028 completion targets for Nanumaga and Nanumea, but no cited source confirms physical mobilisation or current progress

award / Last checked
Confirmed

Moss Landing Harbor jetty repair and maintenance dredging

United States / Breakwater armour repair, access dredging and nearshore placement / Ahtna Infrastructure & Technologies held the USD 16,037,425 current-obligation contract for Moss Landing Harbor dredging and jetty repair; the US Coast Guard published 2025 field-work windows and USACE published August-September post-dredge surveys, but the 23 January 2026 contract end does not establish final quantity, jetty acceptance, completion or final account

construction / Last checked
Confirmed

Warrawong Parklands Kully Bay seawall reconstruction

Australia / Foreshore seawall and rip-rap protection / Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence

construction / Last checked
Confirmed

Cap-des-Caissie small craft harbour upgrade

Canada / Fishing harbour wharf, dredging and shore protection / Mskikue'j Enterprises holds the CAD 5.09 million wharf and shore-protection contract through March 2027; the separate 2025 dredging and containment-cell contract reached its stated expiry without a public completion or measured-quantity record

award / Last checked
Confirmed

Dunkirk Braek submerged sand-discharge pipeline replacement

France / Coastal protection and dredged-sand reuse / Baggerbedrijf de Boer holds the EUR 1.720365 million replacement contract concluded on 13 January 2025; the planned 31 May 2025 in-service deadline has passed, while physical completion, acceptance and downstream packages remain unverified

award / Last checked
Confirmed

Dana Point Harbor breakwater repair and access dredging

United States / Breakwater armour repair, access dredging and nearshore placement / Curtin Maritime holds the USD 4.89 million USACE award for breakwater repair and approximately 45,000 yd3 of access dredging; owner and award sources reviewed do not confirm mobilisation or construction progress

award / Last checked
Confirmed

Folkestone to Hythe beach management works 2025-2030

United Kingdom / Shingle recycling, beach regrading and coastal flood defence / Chunnel holds the signed beach-management contract; the council reported a 100,000-tonne spring 2026 campaign under way and an April purchase order names Chunnel, while measured completion and profile acceptance remain unpublished

delivery / Last checked
Confirmed

Raysut Fishery Harbour rehabilitation and sedimentation works

Oman / Fishing-port dredging, breakwater, groyne, quay and reclamation / The Ministry reported 100% completion in May 2026 after an 81% owner update in January; final hydrography, formal acceptance, operating release and most downstream marine packages remain undisclosed

completed / Last checked
Confirmed

Sidmouth and East Beach coastal defence scheme

United Kingdom / Two-stage coastal flood and erosion defence, beach recharge and offshore rock works / East Devon selected Boskalis Westminster on 30 June 2026 for a GBP 18.911242 million two-stage NEC4 Option C contract; the 6 July notice still marked the award and contract pending, with standstill to 16 July and future signature scheduled for 17 July, and no later contract-details notice, Stage 1 start or construction commitment is yet published

award / Last checked
Confirmed

Frioul East breakwater rehabilitation and rock spur

France / Historic rubble-mound breakwater rehabilitation and island-port protection / Contract Z250608F00 was concluded on 2 February 2026 with an Océlian-led five-company group for EUR 19.589919 million; the owner reports that the overall rehabilitation programme continues in 2026, while main-contract mobilisation, placed rock, accepted sections and downstream subcontract awards remain unpublished

award / Last checked
Confirmed

Gdynia Outer Port protective breakwaters

Poland / Caisson breakwaters and port access infrastructure / The May 2026 building permit has moved the design-build contract into principal in-water works; the first reinforced-concrete caisson was launched and towed toward its placement position in July 2026, with the remaining 48 caissons and breakwater systems still to be delivered

construction / Last checked
Confirmed

San Antonio Puerto Exterior common marine works

Chile / Deep-water ports, dredging and reclamation / Environmental approval was granted on 26 May 2026; six bidders or consortia are prequalified for the common marine-works tender, but no construction award has been announced

tender / Last checked
Confirmed

Niagara River Emerald Shiner Fish Passage

United States / Coastal infrastructure / USACE reports the 700-foot full phase completed in May 2026 and the combined 778-foot fish passage opened with a ribbon-cutting on 23 July 2026

completed / Last checked
Confirmed

Snow's Cut AIWW shoreline stabilization

United States / Coastal infrastructure / USD 7.016 million contract awarded; mobilization and the awarded reach split remain unpublished

award / Last checked
Confirmed

Isle of Palms Breach Inlet beneficial-use dredging

United States / Coastal infrastructure / Two dredging packages completed on 27 February 2026; clay cleanup followed in April and staging was cleared in May

completed / Last checked
Confirmed

West Point Coastal Defence Revetment

Liberia / Coastal infrastructure / The West Point revetment has an approved ESIA and March 2026 environmental permit; construction award, notice to proceed and physical start are not established

approval / Last checked
Confirmed

WACA ResIP 1 coastal protection works programme

Benin / Côte d'Ivoire / Mauritania / São Tomé and Príncipe / Senegal / Togo / Coastal infrastructure / ResIP 1 in finalisation; country work fronts and closing dates remain separate

construction / Last checked
Confirmed

Ocean City and Peck Beach 2026 Periodic Nourishment

United States / Coastal infrastructure / Great Lakes Dredge & Dock's USD 19.5 million nourishment contract is in construction; dredge mobilisation is evidenced, but placed volume, accepted beach template and completion remain open

construction / Last checked
Confirmed

Vadhvan Greenfield Deep-draft Port

India / Deep-water ports, dredging and reclamation / The approximately 200-hectare nearshore reclamation and shore-protection EPC package is awarded; as of 15 July 2026, the owner tender page lists the offshore dredging, reclamation and protection-bund HAM package closing on 17 July and the Daman marine-sand investigation closing on 15 July, while no award or AOC is published for either package or for the 10.14-kilometre offshore breakwater

tender / Last checked
Confirmed

Genoa New Breakwater

Italy / Ports and coastal protection / 24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active

construction / Last checked

Current research

Latest publications connected to this sector

6 shown / 63 current
Official Port of Durban North Bank revetment cross-section showing armour, 50-100 kg rock and filter layers
Brief / Confirmed

Durban's ZAR 5.47m revetment award leaves delivery unverified

National Treasury's active award record names KATLANTIC at ZAR 5,466,159, while TNPA's RFP fixes the workfront at a damaged entrance-channel section requiring approximately 1,000 m3 of 50-100 kg rock. Neither source confirms contract signature, notice to proceed, installed quantities or completion.

Updated
Visualization for Le Goulet maintenance dredging, showing dredged material transport from a harbour basin by excavator barge and scow
Brief / Confirmed

Le Goulet opens basin dredging without naming quantity or disposal site

CanadaBuys has opened WS5822483507 for maintenance dredging in Le Goulet's harbour basin, transport and approved disposal. Bids close 1 September 2026, but the public notice names no quantity, depth, disposal site, method, value, bidder or contractor.

Updated
Cutter-suction dredger performing maintenance dredging at Portarlington Harbour with navigation day shapes displayed
Brief / Confirmed

Birdon's AUD31.9m Parks Victoria contract leaves campaign allocation open

Buying for Victoria names Birdon on a current AUD 31.9 million maintenance-dredging contract. Parks Victoria separately reports a 2018-2027 owner programme and 206,201 m3 removed in 2022-23; neither record attributes every campaign or cubic metre to Birdon.

Updated
Owner-published visualization of a proposed flood-defence treatment along the Langstone waterfront at the Royal Oak
Brief / Confirmed

Langstone's Jackson award opens ECI, not the construction site

Havant Borough Council selected Jackson Civil Engineering at GBP 14 million excluding VAT for Langstone's one-kilometre coastal-defence scheme. The UK6 release still marked the contract pending and estimated a later signature. Planning officers subsequently recommended conditional permission, while Coastal Partners targets April 2027 for physical works. Selection identifies the preferred contractor; it does not establish contract execution, consent, mobilisation or installed progress.

Updated
Kerr Limited marine works and wharf construction capability image showing pile installation, lifting equipment and an active waterside interface
Brief / Confirmed

Centreville contract expired without published acceptance records

Centreville's integrated wharf, dredging and breakwater contract moved from an 84-week requirement ending 31 August 2024 to a 31 December 2025 expiry. CanadaBuys reports CAD 18,864,176.72 after 11 amendments, while Public Accounts publishes different fiscal snapshots. None of the cited records supplies the physical and commercial close-out evidence needed to call the harbour work complete.

Updated
Long-reach excavator placing the first concrete Accropode units on the active Port 2000 Chatiere dike workfront at Le Havre
Brief / Confirmed

Port 2000 dike foundation identifies the main delivery firms

HAROPA's 2026 records identify the firms and measured quantities behind the Chatiere works. Terelian leads the EUR 183.128 million works group with SDI/DEME, GTM OA is the named Accropode subcontractor, Lafarge Gonfreville supplies concrete, and I-SEA with HOZRO support turbidity monitoring. Nearly 800,000 m3 of foundation had been placed by 1 June; channel completion and operating release remain unconfirmed.

Updated

Delivery network

Organizations connected to this collection

6 shown / 45 profiled
Port of Apollo Bay harbour with its commercial fishing fleet, marina berths, wharf and breakwater
Victorian statutory coastal and local-port authority

Great Ocean Road Coast and Parks Authority

Statutory coast-and-parks manager / Port manager for Apollo Bay, Port Campbell and Lorne / Apollo Bay waterway manager and harbour-master function holder

Last checked
USACE hopper dredge Essayons operating in the Columbia River near Cathlamet, Washington
Federal water-resources agency and navigation-project owner

U.S. Army Corps of Engineers, Civil Works

Federal navigation project owner / Coastal and inland navigation asset manager / Planning, design, construction and operations-and-maintenance authority

Last checked
Concrete spillway and reservoir edge at Tenterfield Creek Dam in New South Wales
NSW state-government infrastructure advisory, procurement and delivery agency

NSW Public Works

Whole-of-government construction procurement system custodian / Infrastructure advisory and project assurance / Project and programme management

Last checked
Upstream view of the Yarra River, where Parks Victoria serves as waterway manager
Victorian statutory park, local-port and waterway management authority

Parks Victoria

Local-port manager for Port Phillip and Western Port / Yarra and Maribyrnong statutory waterway manager / Navigation-aid and vessel-activity manager

Last checked
TNPA pilot boats and tugboats berthed for marine services at a South African commercial port
South African national port authority, landlord and marine-services provider

Transnet National Ports Authority (TNPA)

National commercial-port landlord and infrastructure owner / Port master planning, capital works and asset maintenance / Navigation control, Harbour Master and vessel-traffic oversight

Last checked
Rows of large white process pressure vessels at an ACCIONA reverse-osmosis desalination facility
Integrated infrastructure, water, port and concession developer-contractor

ACCIONA

Integrated infrastructure developer and contractor / Water design and construction contractor / Desalination EPC and commissioning lead

Last checked

Continue the sector evidence review