Project record
Carmarthenshire County Council signed a GBP 425,000 excluding VAT emergency dredging contract with Kaymac Marine & Civil Engineering on 29 June 2026 for a 13 July to 31 October delivery window; the council has published no mobilisation, dredger, production, survey, completion or acceptance update
Carmarthenshire County Council directly awarded Kaymac Marine & Civil Engineering the emergency sand-dredging works at Burry Port Harbour. The contract covers the outer harbour and approach channel and moves recovered sand to a deposition site on East Beach. The UK7 contract-details notice records GBP 425,000 excluding VAT, GBP 510,000 including VAT, signature on 29 June 2026 and a planned 13 July to 31 October 2026 period. A separate GBP 48,848 excluding VAT consultancy contract with Anthony D. Bates Partnership runs to 25 November 2026 and covers mechanical and water-injection dredging advice plus a 5-10 year maintenance strategy. Neither notice proves physical mobilisation or accepted output.
IMWO artist's impression of the published Burry Port Harbour emergency sand dredging scope
United Kingdom / Europe
Maintenance dredging, approach-channel access and beach placement
Award / Confirmed
14 October 2026
Coverage
Maintenance dredging, approach-channel access and beach placement is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe notice fixes the contractor, direct procurement route, GBP 425,000 excluding VAT baseline, planned period and East Beach destination while leaving field delivery open.
SourceThe start date is a contractual baseline and must not be treated as proof that equipment mobilised or dredging began.
SourceThe signed contract establishes the delivery party and commercial baseline, while mobilisation, production, survey acceptance and completed output remain undisclosed.
SourceThe capital programme strengthens owner-side investment context but does not allocate the full amount to either dredging contract.
SourceThe advisory package adds mechanical and water-injection method review plus a 5-10 year maintenance horizon, separate from Kaymac's later works contract.
SourceEvidence gap