Dredging and specialist marine works intelligence

Navigation-channel dredging, marine pipelines, tunnels, specialist plant, access systems, and other technically constrained waterside packages.

Projects retain their detailed work segment and may appear in more than one sector when the scope crosses delivery disciplines.

Latest item update 122 public projects 144 related publications 89 connected organizations
On this page

Coverage focus

Dredging, material handling and specialist installation interfaces

Tracker coverage

122 project records connected to this sector.

Publication coverage

144 current analyses and briefs connect through governed project relationships.

Organization coverage

89 public profiles connect through documented project roles.

Project coverage

All current Dredging and specialist marine works project records

122 records
Confirmed

Gulfport Harbor deep-draft navigation improvements

United States / Navigation-channel deepening and sedimentation basin / Signed Chief's recommendation dated 23 June 2026; Gulfport included in the House-passed September WRDA bill

planning / Last checked
Confirmed

Sizewell C Marine Bulk Import Facility

United Kingdom / Bulk-import jetty, conveyor and berthing pocket / Owner reports offshore construction progress and expects bulk-import operation in Q2 2027

construction / Last checked
Confirmed

Vietnam Southern Waterway Corridors: A1 Canals and A2 Rivers

Vietnam / Inland-waterway channel improvement and bank protection / A1 formal works invitation issued 28 September 2026; latest A1 amendments and the separate A2 participation position remain under review.

tender / Last checked
Confirmed

FY27 Galveston-area Scope Dredge to Budget

United States / Navigation channel maintenance dredging / 3 November presolicitation plans unrestricted firm-fixed-price maintenance dredging

planning / Last checked
Confirmed

Salcombe-Kingsbridge estuary 2026 maintenance dredging

United Kingdom / Maintenance dredging and operating-port access / The Harbour Master's 22 June 2026 report confirms Van Oord completed dredging at Batson, Lincombe and Kingsbridge, with pontoons reopened by April; published draft meeting minutes record subsequent receipt of the post-dredge survey

award / Last checked
Confirmed

Port of Progreso expansion dredging and north-platform procurement

Mexico / Dredging / ASIPONA records dredger arrival for third-phase stage 1 on 26 October 2026; estimated stage scope 3,076,370 m3. The July north-platform tender remains a separate historical procurement record.

construction / Last checked
Confirmed

Itajai 2026 channel maintenance dredging

Brazil / Navigation channel maintenance dredging / Daily Njord water injection reported; Utrecht return planned for November

construction / Last checked
Confirmed

Holt Lock permanent monolith repair

United States / Inland navigation lock rehabilitation and hydraulic steel structures / Permanent monolith repairs with revised navigation closures

construction / Last checked
Confirmed

Weipa 2026 maintenance dredging campaign

Australia / Dredging / NQBP reported campaign completion on 1 September 2026: 63 days and about 1.16 million m³ removed

completed / Last checked
Confirmed

New Haven Harbor improvement dredging

United States / Dredging and waterways / USACE DQM lists W912WJ26CA017 as active from 24 October 2026, naming Great Lakes and GL 58, GL 67 and GL 68.

construction / Last checked
Confirmed

Malaga Port Quay 4 facing rehabilitation

Spain / Submerged masonry quay repair and structural concrete rehabilitation / Malaga Port Authority declared Quay 4 procedure 26exma-033 unsuccessful on 7 September 2026 after receiving no bids; the 15 September notice retains the seven-zone repair design and EUR 78,739.06 excluding-VAT tender budget, with no works award under this procedure

tender / Last checked
Confirmed

Dunkirk port cathodic-protection replacement framework

France / Port structures and underwater asset maintenance / The published 4 September 2026 bid deadline has passed; the latest buyer-profile result and framework holder remain unverified

tender / Last checked
Confirmed

Port of Aberdeen 2026-2028 maintenance dredging

United Kingdom / Maintenance dredging and operating-port access / Three-year Boskalis award covers annual 2026-2028 campaigns; dated navigation notices add operational evidence, with 2026 contractual acceptance unconfirmed in the appointment and navigation notices

award / Last checked
Confirmed

Newark Bay FY26 federal navigation maintenance dredging

United States / Dredging and waterways / IFB W912DS26BA027 closed after the extended 6 August 2026 deadline; SAM lists the opportunity as inactive and publishes the bid abstract

tender / Last checked
Confirmed

Southampton Channel Deepening capital dredge

United Kingdom / Dredging / ABP selected Boskalis Westminster on 11 August 2026; the UK6 award remains pending and signature is unconfirmed. MMO case MLA/2026/00178 shows Submitted / (In progress) / [On Hold], with no current consultation, as reviewed on 15 October

award / Last checked
Confirmed

Bristol Floating Harbour 2026 maintenance dredging

United Kingdom / Maintenance dredging, floating-harbour navigation and marina access / Bullo holds the signed GBP 392,500 excluding-VAT contract; July and August navigation windows are historical, with the post-term instruction and accepted output unconfirmed

award / Last checked
Confirmed

Burry Port Harbour emergency sand dredging

United Kingdom / Maintenance dredging, approach-channel access and beach placement / Carmarthenshire County Council signed a GBP 425,000 excluding VAT emergency dredging contract with Kaymac Marine & Civil Engineering on 29 June 2026 for a 13 July to 31 October delivery window; the council has published no mobilisation, dredger, production, survey, completion or acceptance update

award / Last checked
Confirmed

Harwich Haven five-year maintenance dredging

United Kingdom / Maintenance dredging, beneficial use and dredging technology / HHA confirmed Suffolk Dredging LLP's five-year maintenance award in July; the March procurement family was withdrawn for a scope-description correction, with current value and exact commencement unconfirmed

award / Last checked
Confirmed

London Gateway C2526 maintenance dredging

United Kingdom / Maintenance dredging and operating-port access / Jan De Nul was selected at GBP 57 million excluding VAT under the 18 December 2025 decision; the UK6 award remains pending for signature and C2526 field execution is unconfirmed

award / Last checked
Confirmed

UK Navy Future Dredging Contract

United Kingdom / Dredging / Contract signed; individual campaign delivery and accepted depths remain unverified

award / Last checked
Confirmed

Duwamish Waterway FY2026 maintenance dredging

United States / Navigation channel maintenance dredging / USACE awarded the USD 2.852 million contract to American Construction on 24 September 2026; dredging is scheduled no sooner than 1 December and mobilisation remains unreported

award / Last checked
Confirmed

Sandusky Harbor 2026 maintenance dredging and nearshore placement

United States / Navigation channel maintenance dredging / USACE scheduled Morrish-Wallace's 109,000-cubic-yard campaign to start on 6 October 2026 and finish by 1 November; actual mobilisation remains unverified

construction / Last checked
Confirmed

Anaklia marine infrastructure and terminal-delivery interface

Georgia / Capital dredging and navigation-channel deepening / Initial breakwater-channel dredging reported; main basin campaign and private terminal milestones follow separate delivery stages

construction / Last checked
Confirmed

Paradip 18.5m capital dredging and terminal-readiness interface

India / Capital dredging and navigation-channel deepening / Owner reports channel completion and inaugurated 18.5m capability; earlier berth-specific admissible drafts require their own operating amendment

completed / Last checked
Confirmed

Boskalis SEAWAY 31,000 m³ TSHD

Netherlands / Dredging / In service; first project off Den Helder reported

completed / Last checked
Confirmed

Brazos Island Harbor Phase 2 channel deepening

United States / Capital dredging and navigation-channel deepening / USACE lists Phase 2 in construction with new-work dredging continuing toward an FY2026 scheduled completion; final accepted depth, certified quantity and contract completion are unpublished

delivery / Last checked
Confirmed

Igoumenitsa Port three-berth OPS shore-power systems

Greece / Commercial-port shore power and electrical utility integration / HEDNO signed the EUR 6.82 million turnkey contract with Paralos on 11 February 2026 for two 3 MVA OPS positions and one 0.5 MVA position. TED names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors; mobilisation, installation, energisation, vessel connection and acceptance remain unconfirmed

award / Last checked
Confirmed

Molo Sali Phase B sheet-pile restoration and quay completion

Italy / Sheet-pile rehabilitation and port-yard conversion / TED notice 514687-2026 records a EUR 8,295,571.84 contract concluded on 23 July 2026 with the Rossi Renzo Costruzioni-led four-member RTI; notice to proceed, mobilisation, named subcontractors and installed work remain unverified

award / Last checked
Confirmed

Dundee Beach boat-ramp maintenance

Australia / Public boat-launch infrastructure, maintenance dredging and fixed access / Northern Territory Tenders Online records T25-1462 as a 12-month awarded period contract to Polaris Marine Constructions at AUD 676,047.56 on an estimated-unit-rate basis

award / Last checked
Confirmed

Libertad Outfall dredging works

Philippines / Dredging / Group completion reported; Libertad closeout remains unpublished.

construction / Last checked
Confirmed

Parks Victoria Bays Maintenance Dredging Program

Australia / Maintenance dredging, approach-channel access and beach placement / Buying for Victoria records Birdon Pty Ltd on a current AUD 31.9 million contract starting 1 November 2021; Birdon describes a 2021-2030 term and names dredge Ballina with support craft Willie Tell and Bella, while site-level quantities and owner acceptance remain campaign-specific

delivery / Last checked
Confirmed

Cap-aux-Meules access-channel dredging

Canada / Capital and maintenance dredging for a remote ferry, cargo and fishing port / PSPC awarded contract CW2402077 to Dragage Ocean DS on 1 September 2025; a CNESST filing places the contractor at the Cap-aux-Meules dredging site from a planned 13 October to 12 November 2025, while a 13 May 2026 amendment lifted the published contract total to CAD 6,724,266.72 without disclosing its scope

construction / Last checked
Confirmed

Bellingham Shipping Terminal marine infrastructure and dredging

United States / Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities / Port reporting confirms key dock and stormwater upgrades were completed in 2025 and navigation and environmental work advanced; Washington L&I records American Construction's contractor-reported 8 April 2026 work-completed date, but no filed Notice of Completion, owner acceptance, final hydrographic survey, final dredged quantity or final account is evidenced

delivery / Last checked
Confirmed

San Francisco Pier 80 mooring and berthing improvements

United States / Wharf maintenance, fender piles and marine asset renewal / The San Francisco Port Commission adopted Resolution 25-25 on 13 May 2025, authorizing award of Contract 2871 to Manson Construction Co. for USD 5,518,500 plus a USD 551,850 contingency; the cited official record does not confirm the planned notice to proceed, physical progress, substantial completion or acceptance

award / Last checked
Confirmed

Upper Mississippi Lock and Dam 9 miter-gate replacement

United States / Inland navigation lock rehabilitation and hydraulic steel structures / USACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublished

completed / Last checked
Confirmed

Los Angeles Berths 238-239 Marine Oil Terminal Improvements

United States / MOTEMS wharf replacement, dolphins, fenders and maintenance dredging / The Port of Los Angeles January 2026 CIP report classifies the project in construction and, using actuals through November 2025, records 22% construction completion, a 31 March 2027 forecast finish, USD 39,288,466 projected project cost and USD 6,315,074 spent to date

construction / Last checked
Confirmed

Bapco wharf and pipeline repair term services

Bahrain / Liquid-cargo terminal maintenance / Bahrain Tender Board's May 2026 report records a BHD 340,000 extension under tender T17600(65), following the May 2021 BHD 2,489,690 five-year award to Bahrain Maintenance and Diving Services; the extension duration and work orders remain undisclosed

award / Last checked
Confirmed

CVM Congo River Easydredge 2700XL fleet renewal

Democratic Republic of the Congo / Dredging / Easydredge 2700XL building contract signed; no yard, trial, delivery, acceptance, or Congo River deployment milestone published

delivery / Last checked
Confirmed

Lower Yarra River Maintenance Dredging Program

Australia / Urban waterway maintenance dredging, navigation access and in-river material placement / Buying for Victoria records Australasian Marine Associates on a current AUD 1.93985 million contract starting 8 September 2021; Parks Victoria confirms AMA delivered Campaign C in 2024, while the owner programme was reported complete and the next funding cycle remained open

delivery / Last checked
Confirmed

Tinian seaport P-940, P-1001 and P-1002 design

United States / Naval and civil seaport wharf, breakwater and harbor-dredging design / MDPAC JV holds a USD 12.616m architect-engineer task order through 31 December 2026 for P-940 wharf improvements, P-1001 breakwater restoration and P-1002 harbor dredging and Finger Pier A removal; 13 named design-chain subaward records total USD 4.055m, while no construction award or mobilisation is evidenced

design / Last checked
Confirmed

Ringvaart 2 dredging

Netherlands / Dredging / Award signed; start unverified.

award / Last checked
Confirmed

Fox Island River harbour entrance improvement and re-dredging

Canada / Small-craft-harbour entrance dredging and breakwater works / Marine Contractors' CAD 1.499m entrance-improvement contract and R.J.G Construction's separate CAD 1.133m channel re-dredging contract have both reached their published administrative end dates, but no completion certificate, accepted hydrography, final dredged quantity or causal link between the packages is public

delivery / Last checked
Confirmed

P-835 Lima Wharf and Inner Apra Harbor dredging

United States / Naval-wharf and inner-harbor dredging design / MDPAC JV holds the USD 3.335m P-835 design task order, expanded in August 2025 from DD1391 and 15% design into a design-bid-build package and extended in March 2026 to September 2028; no construction award or physical dredging is evidenced

design / Last checked
Confirmed

Tarifa fishing-wharf electrical utility upgrade

Spain / Fishing-wharf electrical distribution and utility connection / APBA awarded the EUR 273,030 works to VES Renewable; contract formalization and setting-out remain unpublished

award / Last checked
Confirmed

La Pozona harbour upgrade

Spain / Dredging, pontoons, piles and utilities / Cantabria awarded the EUR 2.647m works to a three-member UTE; contract and mobilisation remain unpublished

award / Last checked
Confirmed

Menzel Abderrahmane fishing-port extension and coastal esplanade

Tunisia / Fishing-port expansion, dredging, breakwater, quay and coastal esplanade / ETEP signed the TND 20,018,762.19 works contract on 28 April 2025, but Tunisia's parliament still described the port and esplanade project as delayed during a February 2026 site visit; physical start, achieved quantities and supervision award remain unverified

award / Last checked
Confirmed

Port-Vendres Quai Dezoums shore-power electrification

France / Commercial-port shore power and electrical utility integration / BOAMP notice 25-50611 records a EUR 5,436,212 contract issued on 3 April 2025 to the SPIE CityNetworks-led consortium with Nidec ASI and T.A.E.H., plus subcontractor Guintoli. A 24 March 2026 Department presentation classifies the work as in progress; energisation, vessel connection, commissioning, acceptance and completion remain unconfirmed

construction / Last checked
Confirmed

Liwa Fishery Harbour maintenance dredging procurement 2023

Oman / Operating fishing-port maintenance dredging / Oman eTender 441/2023/MAFWR/HQ-36 reached financial evaluation in Q3 2023, then a Recall-1 procedure closed on 19 December 2023; an awardee, value and mobilisation remain undisclosed

tender / Last checked
Confirmed

Liwa (Nabur) Fishery Harbour construction

Oman / Fishing-port breakwaters, dredging, quay and marine infrastructure / Liwa harbour was operating by 2023 after the original Galfar award and 2015-2017 downstream marine works; formal completion, acceptance and final-account records remain unrecovered

completed / Last checked
Confirmed

Bukha Fishery Harbour maintenance, rehabilitation and dredging

Oman / Fishing-port maintenance, rehabilitation and dredging / Masirah Island International identifies active harbour maintenance, rehabilitation and dredging; a 2025 Oman News Agency owner-side report says the port remained under maintenance, with no public completion or acceptance record

construction / Last checked
Confirmed

Granville Herel main breakwater and sill-wall repair

France / Breakwater and reinforced-concrete marine-structure rehabilitation / The owner-confirmed nine-month repair started on 25 August 2025; its planned end-May 2026 acceptance window has passed without a published completion certificate, handover or final account

construction / Last checked
Confirmed

Kustlijnzorg South Holland nourishment (31205037)

Netherlands / Beach and foreshore nourishment / Van den Herik signed the EUR 16.302 million contract on 10 March 2026; Rijkswaterstaat schedules Maasvlakte 2 nourishment for September and names Van den Herik with Van der Kamp there, while mobilisation and the parties' commercial relationship remain unverified

award / Last checked
Confirmed

Kustlijnzorg Walcheren beach nourishment (31205036)

Netherlands / Beach and foreshore nourishment / Fa. Gebr. Van der Lee signed the EUR 8.199 million contract on 31 March 2026; the contract is live through 2027, while no public evidence of physical mobilisation, vessel assignment or accepted production was identified by the 7 August 2026 review

award / Last checked
Confirmed

Kustlijnzorg North Holland and Texel nourishment (31205035)

Netherlands / Beach and foreshore nourishment / Boskalis signed the EUR 26.098 million contract on 12 May 2026; Rijkswaterstaat announced Den Helder tidal-channel nourishment from 14 July to mid-October and Julianadorp sinker-pipe removal from 20 July, while measured production and acceptance remain unpublished

construction / Last checked
Confirmed

Yukonhaven Jetty 4 LNG bunker-loading berth

Netherlands / LNG jetty, combi-wall, mooring structures, dredging and shore works / Gate took FID in January 2026, Port of Rotterdam signed the Hakkers Waterbouw-De Klerk combination on 6 February, and April works notices support early construction; start-up is planned around the end of 2028

construction / Last checked
Confirmed

Tumaco port access-channel deepening, Phase I

Colombia / Capital dredging and navigation-channel deepening / SECOP II records contract GN2862-2026 signed with Consorcio Puerto Tumaco II for COP 26.826 billion and eight months, but the public ledger has no start date, invoicing or payment and the separate supervision procurement remains unawarded

award / Last checked
Confirmed

Barranquilla access-channel maintenance dredging

Colombia / Navigation channel maintenance dredging / SECOP II shows contract 0-525-2024 modified to COP 241.685 billion and 31 December 2026 after a 365-day extension; Cormagdalena reported 80.7% execution at 31 March before the later ledger update, while completion and acceptance remain unconfirmed

delivery / Last checked
Confirmed

Townsville MSQ Base wharf fender-pile replacement

Australia / Wharf maintenance, fender piles and marine asset renewal / Queensland TMR awarded MSQ26005 to Pacific Marine Group on 11 May 2026 for AUD 423,687; no public milestone establishes mobilisation, pile quantities, installation method, completion or acceptance

award / Last checked
Confirmed

Dar es Salaam channel deepening and berth concrete repairs

Tanzania / Capital dredging, berth reconstruction and concrete remediation / Channel and berth civil packages were reported complete in 2024 and the port publishes operational depths; CHEC's separate USD 15.70 million 2025 concrete-repair contract has no cited completion or acceptance evidence

construction / Last checked
Confirmed

Brazos Island Harbor FY24 entrance and jetty maintenance dredging

United States / Maintenance dredging and operating-port access / Great Lakes' Padre Island campaign was publicly scheduled from 20 October to 16 November 2024; an April 2025 final-quantity modification reduced the current federal obligation from USD 8.799 million to USD 7.456 million, while accepted quantities and formal closeout remain unpublished

delivery / Last checked
Confirmed

Sabine-Neches Contract 6 offshore channel deepening

United States / Dredging and waterways / Great Lakes holds the USD 219.108 million Contract 6 obligation; its USD 235.423 million potential value, April 2027 owner finish, production, assigned fleet and lower tiers remain to be confirmed

delivery / Last checked
Confirmed

Poona boat ramp and access-channel upgrade

Australia / Public boat-launch infrastructure, capital dredging and fixed access / Australian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026

construction / Last checked
Confirmed

Newell Beach all-tide boat ramp upgrade

Australia / Public boat-launch infrastructure, capital dredging and fixed access / Queensland TMR completed the upgraded all-tide facility in May 2022 after Australian Marine & Civil delivered the main works under CN-17011; the published contract disclosure rose from AUD 2,560,154 to AUD 2,603,835 after a variation

completed / Last checked
Confirmed

Boulogne-sur-Mer-Calais maintenance dredging framework

France / Dredging / Region Hauts-de-France concluded contract 202613951 with SODRANORD on 24 February 2026 for a purchase-order maintenance dredging framework; the EUR 23 million figure is the four-year maximum ceiling, while the first call-off, 2026 quantity and mobilisation remain unconfirmed

award / Last checked
Confirmed

Callao access-channel and inner-roadstead maintenance dredging

Peru / Maintenance dredging and operating-port access / APN started the access-channel and inner-roadstead campaign on 20 December 2025; a Jan De Nul post-dredging environmental report covers January 2026 monitoring, while owner acceptance, as-built hydrography and final account remain unverified

commissioning / Last checked
Confirmed

Tanzania five-MCA demarcation and mooring-buoy installation

Tanzania / Specialist marine works / Zanzibar Marine and Diving Services signed the USD 266,878 supply-and-installation contract on 12 March 2026; the procurement plan's 24 May 2026 completion target has passed without cited installation or acceptance evidence

delivery / Last checked
Confirmed

Santoña North Basin fishing-quay structural repair

Spain / Piled fishing-quay concrete rehabilitation and metal fender renewal / Cantabria formalized the EUR 2,486,545.15 excluding-VAT works contract with the Cuevas Gestión de Obras-COMSA UTE on 9 July 2026; the signed contract requires a viable setting-out check before the 24-month execution period starts, while the setting-out act, site mobilisation, monthly production and lower-tier appointments remain unpublished

award / Last checked
Confirmed

Moss Landing Harbor jetty repair and maintenance dredging

United States / Breakwater armour repair, access dredging and nearshore placement / Ahtna Infrastructure & Technologies held the USD 16,037,425 current-obligation contract for Moss Landing Harbor dredging and jetty repair; the US Coast Guard published 2025 field-work windows and USACE published August-September post-dredge surveys, but the 23 January 2026 contract end does not establish final quantity, jetty acceptance, completion or final account

construction / Last checked
Confirmed

Mopti boat-quay access dredging and sediment clearance

Mali / Inland river-port access dredging and sediment clearance / The package was officially launched on 13 February 2025 and a project team inspected progress on 6 March 2025; the latest disclosed procurement plan, dated 13 April 2026, still records the contract only as signed, and no official completion, accepted bathymetry or operating release has been published

construction / Last checked
Confirmed

Dunkirk Braek submerged sand-discharge pipeline replacement

France / Coastal protection and dredged-sand reuse / Baggerbedrijf de Boer holds the EUR 1.720365 million replacement contract concluded on 13 January 2025; the planned 31 May 2025 in-service deadline has passed, while physical completion, acceptance and downstream packages remain unverified

award / Last checked
Confirmed

Dana Point Harbor breakwater repair and access dredging

United States / Breakwater armour repair, access dredging and nearshore placement / Curtin Maritime holds the USD 4.89 million USACE award for breakwater repair and approximately 45,000 yd3 of access dredging; owner and award sources reviewed do not confirm mobilisation or construction progress

award / Last checked
Confirmed

Elizabeth Harbour marine redevelopment

Jersey / Ferry-terminal marine works, dredging and demolition / Final design and planning-condition discharge are evidenced; construction was scheduled for autumn 2026, while Stage Two authorization, dredger or piling mobilisation and physical works start remain unpublished

design / Last checked
Confirmed

Raysut Fishery Harbour rehabilitation and sedimentation works

Oman / Fishing-port dredging, breakwater, groyne, quay and reclamation / The Ministry reported 100% completion in May 2026 after an 81% owner update in January; final hydrography, formal acceptance, operating release and most downstream marine packages remain undisclosed

completed / Last checked
Confirmed

Port of Workington maintenance dredging framework 2026-2030

United Kingdom / Maintenance dredging and operating-port access / Four-year framework awarded to Boskalis Westminster, Dutch Dredging and Van den Herik; the first mini-competition, call-off, assigned vessel, dredged quantity and acceptance remain unconfirmed

award / Last checked
Confirmed

Normandy ports maintenance dredging framework 2026-2029

France / Maintenance dredging and operating-port access / Eight call-off lots were concluded on 12 November 2025 for a four-year maximum framework beginning in 2026; the award chain is confirmed, while the first 2026 call-off, vessel mobilisation, measured quantity and port acceptance remain unpublished

award / Last checked
Confirmed

Marsaxlokk fishing-port fairway dredging

Malta / Fishing-port fairway dredging and beneficial reuse / Transport Malta described the Marsaxlokk works as ongoing on 26 June 2026; the original navigation notice ran to 31 July, but no public final hydrographic survey, accepted quantity, completion certificate or final account was located by 2 August

construction / Last checked
Confirmed

Saint-Malo Terminal du Naye Lot 2 marine works

France / Ferry-terminal marine works, dredging and demolition / Région Bretagne reported one of the two old lock-guide structures under demolition on 1 April 2026 after the 270-tonne Ro-Ro ramp was removed in December 2025; the new reinforced-concrete guide caissons and maintenance dredging remain inside the two-year Lot 2 mission, with no owner acceptance published

construction / Last checked
Confirmed

Höfn Grynnslin 2025 maintenance dredging

Iceland / Maintenance dredging and operating-port access / Jan De Nul confirms that trailing suction hopper dredger Tristão da Cunha deepened the Höfn access channel between January and February 2025; the measured quantity and post-dredge acceptance remain unpublished, and a separate Boskalis contract now covers 2026-2028

completed / Last checked
Confirmed

Husøy Fishing Port Deepening

Norway / Dredging / Kystverket's latest dated update records blasting complete and about 26,000 solid cubic metres of clean material dredged by 21 April 2026; the owner page says work remains in progress toward December 2026 completion

construction / Last checked
Confirmed

Fehmarnbelt Fixed Link Immersed Tunnel

Denmark / Germany / Immersed tunnels and marine crossings / Third tunnel element immersed and connected on 1 August 2026; protection, serial immersion, systems integration, and a two-stage road-then-rail opening remain active

construction / Last checked
Confirmed

Oslo Kneppeskjaer East quay replacement and expansion

Norway / Multipurpose quays, dredging and carbon-logistics infrastructure / Repstad Anlegg began works in August 2025; demolition, dredging and subsea blasting preceded a 99-pile quay-foundation programme scheduled from March to July 2026

construction / Last checked
Confirmed

Congo Terminal East Mole expansion

Republic of the Congo / Deep-water ports, dredging and multipurpose terminals / Congo Terminal reported 400 metres of the planned 750-metre quay complete by 6 July 2026 after all 558 steel piles were driven; dredging and electric-terminal integration remain active toward the 2027 delivery target

construction / Last checked
Confirmed

Puerto Antioquia multipurpose deep-water terminal

Colombia / Deep-water ports, dredging and multipurpose terminals / Commercial operations began on 5 February 2026 after four controlled vessel trials; the operator's current port-status ledger shows repeat container, breakbulk and refrigerated calls through July 2026

completed / Last checked
Confirmed

NOAA Newport MOC-P maintenance dredging

United States / Dredging / Six timely bids are publicly tabulated; no award, permit issuance, notice to proceed or mobilisation has been announced

evaluation / Last checked
Confirmed

Norfolk Island Kingston Pier channel and repair works

Norfolk Island / Dredging and waterways / Rock revetment contractor appointed; the separate channel-dredging and pier-repair package was released to tender on 14 May 2026

tender / Last checked
Confirmed

New Zealand regional-port dredging barge

New Zealand / Dredging / NZD 8 million of government co-funding confirmed; designer, shipyard, build contract and first port assignment not disclosed

planning / Last checked
Confirmed

Redwood City Channel FY26 maintenance dredging

United States / Dredging and waterways / HME Construction under contract; 24/7 clamshell dredging and dump-scow operations notified for July 2026

construction / Last checked
Confirmed

Zeevonk phase 1 foundation installation

Netherlands / Offshore wind foundations / DEME holds the transport and installation contract for 69 monopile foundations; offshore mobilisation has not been announced

award / Last checked
Confirmed

Itajaí-Mirim flood-channel widening and dredging

Brazil / Dredging and waterways / World Bank project is Active and Board Approved; the April 2026 procurement plan omits the Itajaí-Mirim main works package

approval / Last checked
Confirmed

Port Mansfield Channel 2026 maintenance dredging

United States / Dredging and waterways / Callan Marine dredging has reached the Gulf Intracoastal Waterway junction; the Navigation District says the next work front is the harbor and turning basin

construction / Last checked
Confirmed

Kamarajar Port Capital Dredging Phase VI

India / Dredging / The Government of India reports Phase VI complete and Kamarajar operating at 18.0 metres draft; the post-dredge survey sheet and a first fully laden Capesize call are not published

completed / Last checked
Confirmed

DEME next-generation 22,000 m³ TSHD

Belgium / Dredging / 22,000 m³ TSHD ordered; China hull build, Singapore completion, trials, and 2029 delivery remain pending

delivery / Last checked
Confirmed

Sabine-Neches Waterway Channel Improvement Project

United States / Dredging and waterways / Callan Marine 44-foot package awarded; Great Lakes offshore Contract 6 in delivery; final 48-foot inland cut remains separate

construction / Last checked

Current research

Latest publications connected to this sector

6 shown / 144 current
IVY 1 and IVY 2 supporting a standard Fehmarnbelt tunnel element during mooring trials at Rødbyhavn, in the owner's 2026 image-library record
Brief / Confirmed

Fehmarnbelt: IVY's 1,600-Tonne Load Test

Fehmarnbelt's September load test addressed a change in transport geometry. The first special tunnel element has a basement and must travel higher in the water than a standard element. Raising it reduces buoyancy and transfers more load to the immersion vessel IVY. Sund & Bælt reported on 11 September 2026 that the fourth standard element had been loaded with an additional 1,600 tonnes, distributed between water bags on its roof and tanks inside it, and lifted to the height required for transporting the special element. [1]

Updated
Historical Cho Lach canal view with boats, bank paths and a steel bridge; 2010 according to source metadata.
Brief / Confirmed

Cho Lach: Dredging and the A3 Bridge Construction Interface

Vietnam's A1 invitation combines improvements to Cho Lach, Rach Ky Hon and Rach La canals in a 24-month works contract. The signed 28 September 2026 notice specifies dredging, embankments, drainage and local roads, with rated technical and non-price factors weighted at 50% and the financial bid at 50% [1]. The 13 August procurement table places Cho Lach 2 Bridge and its access roads in a separate A3 package [2]. The canal programme therefore interfaces with the separately planned A3 bridge and access-road works.

Updated
Melaka mud-removal diagram shows the four boundary points in Port Circular 52/2026 and the two named anchor-handling tugs and two barges
Brief / Confirmed

Melaka sets a buoyed work area for power-plant mud removal

Malaysia's Marine Department has published a mud-removal work area for the Melaka 2,242 MW combined-cycle power plant, with a stated period from 7 October 2026 to 15 June 2027. Port Circular 52/2026, dated 12 October, identifies four boundary points and names anchor-handling tugs JETTA 35 and JETTA 37 and barges JETTA 39 and LIGHT SABER. It advises other vessels to keep clear of the work area and navigate cautiously nearby. [1]

Updated
Sizewell bulk-import diagram connects the planned Wind jetty-head work and Canti-travel trestle to the berth, conveyor and shore receiving route
Brief / Confirmed

Sizewell targets Q2 2027 bulk imports as jetty works advance offshore

Sizewell C expects its Marine Bulk Import Facility to become operational in the second quarter of 2027. The owner's works tracker reports that construction has advanced from the beach into the sea, with platform works continuing through the end of 2026. The facility will transfer bulk materials from vessels to the main construction site. April's site forum recorded Canti-travel piling in progress; the harbour's subsequent phase-two plan paired offshore jetty-head construction with an approach trestle advancing seaward from the mainland. [1][2][4]

Updated
Gulfport funding diagram separates initial shares, later GNF repayment, local facilities and the estimated $17 million annual federal OMRR&R account, including maintenance dredging
Brief / Confirmed

Gulfport's deepening plan includes a later sponsor payment

Gulfport's recommended navigation improvements carry two different sponsor payments. The signed 23 June 2026 Chief's Report assigns $137.102 million of the $548.216 million initial project cost to the Mississippi State Port Authority. It also estimates an additional General Navigation Features payment at $50.8 million, before eligible credits. Paragraph 9(d) places that additional payment after construction, with interest, over a period of up to 30 years. A sponsor's funding forecast therefore needs a construction contribution and a separate post-completion repayment schedule. Annual federal operation, maintenance, repair, replacement and rehabilitation (OMRR&R) is estimated at $17 million, including anticipated maintenance dredging. [1]

Updated
Progreso payment-clock diagram: an illustrative 31 October cutoff reaches 11 December through 6 plus 15 plus 20 calendar days, or 17 December through 41 days after the 6 November submission.
Analysis / Dredging Economics

Progreso Dredging Finance: The 15% Advance and the First Progress Payment

Progreso's north-platform tender combines a 15% annual advance, a first-estimate receipt in the third month and a front-loaded fiscal spending requirement. The financing allowance needs the same workfronts, surveys and dates as the dredging programme.

Updated

Delivery network

Organizations connected to this collection

6 shown / 89 profiled
Harwich Haven waters and Port of Felixstowe cranes in the operating context of HHA's Tiamat launch
UK dredging joint-venture LLP

Suffolk Dredging LLP

Maintenance-dredging contract supplier / Tiamat licensee / Harwich dredging joint venture

Last checked
American Construction Company floating crane, tug and marine construction plant working on a Seattle waterfront
Pacific Northwest marine construction and dredging contractor

American Construction Company

Navigational maintenance-dredging contractor / Environmental and contaminated-sediment dredging contractor / Open-water and contained material-placement contractor

Last checked
USACE hopper dredge Essayons operating in the Columbia River near Cathlamet, Washington
Federal water-resources agency and navigation-project owner

U.S. Army Corps of Engineers, Civil Works

Federal navigation project owner / Coastal and inland navigation asset manager / Planning, design, construction and operations-and-maintenance authority

Last checked
IMWO illustrated guide to Boskalis' Dredging and Inland Infra, Offshore Energy, and Towage and Salvage businesses, separating corporate capabilities from individual project assignments
Dredging, marine infrastructure and offshore-energy contractor

Boskalis

Capital and maintenance dredging contractor / Port, waterway and reclamation contractor / Coastal defence, riverbank and hydraulic-infrastructure contractor

Corporate facts reviewed Procurement checked
Royal IHC-built cutter suction dredger Hussein Tantawy in Rotterdam before delivery to the Suez Canal Authority
Marine equipment provider

Royal IHC

Dredging vessel designer / Marine equipment manufacturer / Shipbuilder

Last checked
Official execution drawing comparing Tarifa fishing wharf's existing 20 kV route with the proposed 20 kV route to the new transformation centre
Spanish state-port authority and marine-infrastructure owner

Algeciras Bay Port Authority (APBA)

State-port authority / Port infrastructure owner and landlord / Marine and utility works client

Last checked

Continue the sector evidence review