Project record

Kamarajar Port AECTPL Phase I Stage II capital dredging

Aerial view of Kamarajar Port harbour with operating bulk berths, ships, tugs, basin and breakwaters

Kamarajar Port Limited

Kamarajar Port tendered 668,855 m3 of capital dredging for the proposed AECTPL Phase I Stage II berth pocket and adjacent operating areas. The INR 738.16 million package also carries 41,643 m3 of dry excavation, separate land and offshore placement routes, survey obligations and a 120-day work period.

Project signal

Tender in India

Use the BOQ as the scope baseline, not as evidence that a contractor is appointed or any quantity is complete. The proposed berth pocket and the existing berth and approach areas have different target levels and different material destinations, so progress must be measured against the correct survey and placement ledger.

Current status The open tender closed on 16 March 2026; no award, work order or mobilisation is identified Source confidence Confirmed

Location

India / Asia Pacific

Segment

Dredging

Status

The open tender closed on 16 March 2026; no award, work order or mobilisation is identified / Confirmed

Evidence reviewed

18 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Kamarajar Port Limited
Delivery parties
No dredging contractor awarded
Contract route
Kamarajar Port issued an open, two-cover works tender under reference KPL/PPD/CD(AECTPL)/2025 and CPPP tender ID 2026_MoS_899932_1. The official notice gives an estimated value of INR 738,163,458, an EMD of INR 9,381,635, 180-day bid validity and a 120-day work period. Bids were scheduled to close on 16 March and open on 17 March 2026; the reviewed official page does not publish an award.
Execution window
The tender allows 120 days for the works. That is a proposed contractual period and does not start until an award, work order or notice to proceed establishes the delivery clock.
Works package
Excavate 41,643 m3 of dry material in the proposed AECTPL Phase I Stage II berth pocket down to 0.00 m CD and place it within port land. Dredge 299,859 m3 in the proposed berth pocket to -16.0 m CD for placement within port land up to 5 km away. Dredge a further 368,996 m3 in the existing AECTPL, EBTPL and GCB-II berth pockets to -16.0 m CD and in the approaches and Phase VI excluded area to -16.5 m CD for disposal at Kamarajar Port's designated offshore ground. The BOQ permits TSHD, CSD, backhoe or other suitable plant and includes pre-, interim, post- and third-party surveys plus isolated submerged boulder removal.
Marine interfaces
The package joins a new container-terminal berth pocket to live AECTPL, Ennore Bulk Terminal and GCB-II waters and their approaches. Kamarajar lists the operating AECTPL berth at 400 metres long and 16.70 metres deep, EBTPL at 270 metres and 16.00 metres, and GCB-II at 330 metres and 16.00 metres. Dredging therefore has to be sequenced with active berth access, traffic control, hydrographic verification and two distinct material routes rather than treated as one undifferentiated quantity.
Commercial read
The main procurement question is still who receives the work and on what final terms. Once awarded, the package will require production dredging, near-berth plant, survey launch and third-party hydrography, land transport and spreading, offshore placement control, boulder handling, environmental monitoring and coordination with operating terminals. The BOQ names acceptable plant families but does not select a dredger or prove plant availability.
Next milestone
Confirm the official award and work order, then follow the accepted baseline survey, plant mobilisation, route-by-route production, depth acceptance and release of the affected berth and approach areas.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

The published bid window closed

The CPPP schedule reached its submission deadline with a 17 March bid-opening date. This closes the advertised bid window but does not establish technical admission, financial opening, award or a work order.

Read controlling source

Kamarajar published the capital-dredging tender

The open tender fixed the INR 738.16 million estimate, 120-day period and separate proposed-berth and associated-dredging scope lines.

Read controlling source

Delivery watch

Evidence needed next

Confirm the official award and work order, then follow the accepted baseline survey, plant mobilisation, route-by-route production, depth acceptance and release of the affected berth and approach areas.

Decision watchpoints

  • Official award, work order, contractor identity and accepted contract value
  • Baseline multibeam, side-scan, sub-bottom and topographic survey acceptance
  • Dredger and support-fleet selection for mixed soil, cobbles and isolated boulders
  • 299,859 m3 proposed-berth volume routed to port land within 5 km
  • 368,996 m3 existing-berth and approach volume routed to the approved offshore ground
  • Accepted -16.0 m CD berth pockets and -16.5 m CD approach and Phase VI areas
  • Post-dredge hydrography, quantity certification and release of usable navigation depth

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 18 July 2026 Sources in this record 4

Source record

CPPP controls the tender identity, estimated value, dates, EMD and 120-day period. The BOQ controls the 41,643 m3 dry excavation, 299,859 m3 land-placement dredging and 368,996 m3 offshore-placement dredging lines. Kamarajar Port's current Survey & Dredging page establishes the berth depths, survey standard and environmental controls; its terminal page establishes AECTPL's operating geometry. An awarded dredging contractor, mobilisation, completed production and accepted depth are not identified.

Phase: tender. Evidence reviewed: 18 July 2026.