Project record

Port-Vendres Quai Dezoums shore-power electrification

Cameroun Express cargo vessel alongside the operating commercial quay at Port-Vendres

Departement des Pyrenees-Orientales; operating-port context photo, not evidence of Quai Dezoums electrification works

The Conseil departemental des Pyrenees-Orientales awarded contract M2500432 for electrical works at Quai Dezoums after an open procedure that received one tender. The published scope combines shore power for commercial vessels, an EDF grid connection for a port crane, reefer-container supplies, low-voltage connections for smaller vessels, provision for future lighting and a technical room. The award notice names SPIE CityNetworks as consortium lead, Nidec ASI and T.A.E.H. as consortium members and Guintoli as a subcontractor, but does not allocate project-specific work packages among them. The Department's March 2026 procurement presentation confirms construction is in progress; it does not evidence energisation or acceptance.

Project signal

Construction in France

Current status BOAMP notice 25-50611 records a EUR 5,436,212 contract issued on 3 April 2025 to the SPIE CityNetworks-led consortium with Nidec ASI and T.A.E.H., plus subcontractor Guintoli. A 24 March 2026 Department presentation classifies the work as in progress; energisation, vessel connection, commissioning, acceptance and completion remain unconfirmed Source confidence Confirmed

Location

France / Europe

Segment

Commercial-port shore power and electrical utility integration

Status

BOAMP notice 25-50611 records a EUR 5,436,212 contract issued on 3 April 2025 to the SPIE CityNetworks-led consortium with Nidec ASI and T.A.E.H., plus subcontractor Guintoli. A 24 March 2026 Department presentation classifies the work as in progress; energisation, vessel connection, commissioning, acceptance and completion remain unconfirmed / Confirmed

Last checked

8 August 2026

Coverage

Related sectors

Commercial-port shore power and electrical utility integration is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Conseil departemental des Pyrenees-Orientales
Delivery parties
SPIE CityNetworks - consortium lead (mandataire), Nidec ASI - consortium member; project-specific work package not published, T.A.E.H. - consortium member; project-specific work package not published, Guintoli - named subcontractor; project-specific work package not published
Contract route
BOAMP procedure 2024-TX-SDET-0251 was run as an open procedure with a mandatory site visit. The notice chain comprises 24-138672, 25-8590, 25-12874 and award notice 25-50611. One electronic tender was received. Contract M2500432 was issued on 3 April 2025 for EUR 5,436,212 to the SPIE CityNetworks-led grouping with Nidec ASI and T.A.E.H.; Guintoli is identified as a subcontractor.
Execution window
The tender documents used 17 March 2025 as a provisional start and required bidders to propose a 9-to-12-month period including two months of preparation, with execution beginning from contract notification. The contract was issued on 3 April 2025, and the Department still classified the work as in progress on 24 March 2026. The accepted baseline programme, actual site possession, energisation sequence and completion date are not published in the cited records.
Works package
Electrical works cover shore-side power for commercial vessels, EDF network connection for a port crane, electrical connections for refrigerated containers, low-voltage shore connections for smaller vessels, power provision for future port-lighting works and construction or fit-out of a technical room. Published notices do not disclose equipment quantities, berth connection ratings, cable-management arrangement, OEM package allocation or executed subcontract values.
Marine interfaces
Delivery must integrate shore-side electrical infrastructure with an operating commercial quay, vessel connection points, a port crane, reefer operations, smaller-vessel supplies and future lighting. Key interfaces include grid availability, shutdown and switching plans, cable routing, quay penetrations, saltwater exposure, berth access, vessel-call windows, electrical protection, earthing, testing and safe handover to port operations.
Commercial evidence boundary
The award notice publishes EUR 5,436,212 for the electrical contract and records one tender. This amount is distinct from the wider Quai Dezoums requalification, described by the Department at approximately EUR 29 million, and from the EUR 1.5 million fishing-pontoon procurement shown separately in the March 2026 presentation. No cited source publishes consortium workshare, subcontract amount, approved variations, payments, forecast final cost or final account.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Electrical construction award

Contract M2500432, procedure 2024-TX-SDET-0251

Named party
SPIE CityNetworks-led grouping with Nidec ASI and T.A.E.H.; Guintoli named subcontractor
Status
Confirmed
Source position
BOAMP award notice 25-50611 publishes the EUR 5,436,212 contract, 3 April 2025 issue date, one tender and the four-party delivery chain. Source
Shore power and port electrical utilities

Commercial-vessel shore power, crane grid connection, reefer and smaller-vessel supplies

Named party
Awarded consortium; individual package allocation undisclosed
Status
Confirmed
Source position
The BOAMP tender notice defines the electrical scope but does not divide it among the consortium members or subcontractor. Source
Current delivery status

Quai Dezoums electrification

Named party
Department and awarded delivery chain
Status
Confirmed
Source position
The Department's 24 March 2026 procurement presentation places the electrification project under works in progress. Source
Commissioning and handover

Energisation, vessel connection, testing, acceptance and operational performance

Named party
Department and awarded delivery chain
Status
Not evidenced
Source position
No cited record confirms energisation, a connected vessel, completed testing, owner acceptance, installed quantities, measured CO2 savings or completion.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Department classifies electrification as works in progress

The current official procurement presentation moves the evidence base beyond award and supports a construction phase, without proving commissioning or completion.

Source

BOAMP publishes electrical works award

Award notice 25-50611 publishes the EUR 5.436 million contract, one-tender outcome and named consortium and subcontractor chain for delivery.

Source

Contract M2500432 is issued

The award record identifies 3 April 2025 as the contract issue date; the cited sources do not publish the accepted programme or actual site-possession date.

Source

Final amended tender deadline closes

The notice chain establishes the final tender deadline and bidder-proposed 9-to-12-month delivery window, replacing the earlier provisional notice dates.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Executed Contract M2500432 and accepted baseline programme
  • Project-specific workshare for SPIE CityNetworks, Nidec ASI, T.A.E.H. and Guintoli
  • Grid-connection, transformer, switchgear and cable-management specifications
  • Actual site possession, construction progress and berth-access constraints
  • Shore-power energisation and first commercial-vessel connection
  • Crane, reefer-container and smaller-vessel electrical interfaces
  • Protection, earthing, load and interoperability testing
  • Operational handover, acceptance and measured environmental performance
  • Variations, forecast final cost, final account and completion

Reporting status

Construction, confirmed confidence

Last checked 8 August 2026 across 8 cited sources. The dated timeline above carries the project events.

Last checked 8 August 2026 Cited sources 8

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 8