Project record

Fehmarnbelt Fixed Link Immersed Tunnel

Aerial view of the two IVY immersion pontoons positioned in the Fehmarnbelt work area during the second-element operation in June 2026

Femern A/S

Femern A/S and its delivery consortia have moved the 18-kilometre Denmark-Germany fixed link from first-of-kind immersion into an early repeat cycle. The second 73,500-tonne standard element was installed and connected on 29 June 2026, after the first was joined to the Danish portal in May. The owner reports more than 500 metres of the tunnel installed, but 87 of 89 elements, protective backfill, portal and systems interfaces, commissioning, and separate road and railway opening paths remain ahead.

Project signal

Construction in Denmark / Germany

Treat the second successful immersion as evidence that the marine method can be repeated, not as a proportional completion percentage. Track accepted element production, tow and immersion cadence, joint closure, gravel and stone protection, special-element learning, German-water work constraints, systems handover, and the owner's dated road and rail opening programme as separate gates.

Current status Second tunnel element immersed and connected; serial immersion, backfill, systems integration, and a two-stage road-then-rail opening remain active Source confidence Confirmed

Location

Denmark / Germany / Europe

Segment

Immersed tunnels and marine crossings

Status

Second tunnel element immersed and connected; serial immersion, backfill, systems integration, and a two-stage road-then-rail opening remain active / Confirmed

Evidence reviewed

15 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Femern A/S
Delivery parties
Femern Link Contractors (FLC), Fehmarn Belt Contractors (FBC), Femern SICE Cobra (FSC), Elecnor
Contract route
Femern A/S is the Danish state-owned client under Sund & Bælt. FBC, a Boskalis-Van Oord consortium, is responsible for marine dredging, work harbours, reclamation, and preparatory portal works. FLC's contracts for the element factory, immersed tunnel, portals, and ramps became effective on 1 January 2021. FSC holds the electro-mechanical systems package, while Elecnor is delivering the transformer station. The project is financed through Danish state-guaranteed loans repaid by road tolls and railway charges, with EU support. A replacement overall programme and final cost outcome have not been published after the immersion delay.
Execution window
The Danish site works began in 2020 and the principal tunnel contracts became effective in 2021. The 18-kilometre trench was declared fully excavated in April 2024. The first standard element was immersed and connected in May 2026 and the second in June. Sund & Bælt has stated that the former 2029 opening is no longer realistic and is developing a staged opening in which road traffic starts first and railway service follows after the German land connections are ready. Replacement opening dates have not been set.
Works package
The crossing comprises approximately 18 kilometres of immersed tunnel carrying a four-lane motorway and two electrified railway tracks in separate tubes, plus a service tube. The marine system uses 79 standard elements, each 217 metres long and about 73,500 tonnes, and 10 shorter special elements with lower-level technical spaces. The completed trench averages about 12 metres deep and 100 metres wide and required excavation of about 15 million cubic metres. Elements are serially cast at Rødbyhavn, floated through purpose-built basins and harbour, towed roughly two kilometres to the trench, lowered onto a prepared gravel bed, joined, secured with gravel and sand, and covered with stone.
Marine interfaces
Each immersion joins industrial element production to ballast control, harbour release, tug coordination, the IVY immersion pontoons, wire-guided positioning, survey and laser confirmation, seabed bedding, water-pressure-assisted joint closure, side backfill, and stone cover. Standard and special elements have different handling requirements. The sequence must also respect weather and metocean windows, navigation safety, German plan-approval limits on underwater noise and the location and timing of work, portal readiness, and the handover boundary from civil works to ventilation, lighting, safety, power, road, and railway systems.
Commercial read
The second operation materially reduces first-of-kind uncertainty, but it does not establish mature series productivity. The owner expects pace to improve as crews gain experience, while also stating that the specialized immersion-vessel delay put Danish construction about two years behind the former programme. A road-first opening reduces final-stage interface complexity but does not close the German railway, systems, safety, or commissioning obligations. Cost and repayment effects should remain owner-controlled until a revised schedule and financial frame are published.
Next milestone
Track the third standard-element operation, accepted cadence across subsequent elements, side backfill and stone cover, production and immersion of the first special element, work in German waters, portal and civil continuity, systems installation and test readiness, German road and railway land connections, and publication of dated road-opening and later railway-opening milestones.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

Second standard element immersed and connected

The owner record demonstrates an early repeat of the 73,500-tonne tow, positioning, immersion, and joint sequence and reports more than 500 metres installed; it does not establish mature series cadence, completed protection, or overall tunnel completion.

Read controlling source

Owner adopted separate road-first and rail-later opening paths

The decision changes the operating-release sequence and makes German railway landworks a separate service dependency, while replacement road and rail opening dates, final systems acceptance, and cost effects remain unpublished.

Read controlling source

First standard element immersed and joined to the Danish portal

The first-of-kind operation proves the initial 217-metre element could be towed, lowered, positioned, laser-confirmed, and hydraulically connected, without proving repeat productivity or acceptance of the remaining 88 elements and systems.

Read controlling source

Owner withdrew the former 2029 opening baseline

The preparation update establishes that the immersion-vessel delay made a 2029 opening unrealistic and that a new overall schedule would follow early immersion experience; it does not publish replacement dates or a revised final cost.

Read controlling source

Eighteen-kilometre tunnel trench excavation completed

The owner record closes the main dredging phase at about 15 million cubic metres and identifies FBC's Boskalis-Van Oord delivery role, while bedding, immersion, backfill, protection, portals, systems, and opening remain separate packages and gates.

Read controlling source

Delivery watch

Evidence needed next

Track the third standard-element operation, accepted cadence across subsequent elements, side backfill and stone cover, production and immersion of the first special element, work in German waters, portal and civil continuity, systems installation and test readiness, German road and railway land connections, and publication of dated road-opening and later railway-opening milestones.

Decision watchpoints

  • Repeat standard-element tow, immersion, joint, and protection cadence
  • First special-element production and immersion learning
  • Gravel-bed acceptance, survey evidence, side backfill, and stone cover
  • German-water environmental and underwater-noise work windows
  • Portal, road, railway, power, ventilation, lighting, and safety-system interfaces
  • Published road-opening programme and later railway-opening programme
  • Owner-approved cost, repayment, and schedule revisions

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 15 July 2026 Sources in this record 10

Source record

Femern's 29 June 2026 release controls the second-element status, 73,500-tonne unit weight, five-tug tow, wire-guided placement, more-than-500-metre owner statement, and immediate protection works. The 7 and 4 May records establish first-element connection and tow/immersion method. The 17 May owner statement controls the road-first and rail-later strategy and explicitly says a new schedule will follow operating experience with standard and special elements. The January 2026 update controls the old-2029 boundary and delay context. The April 2026 factsheet controls the current physical scope; the April 2024 record controls completed trench excavation. Contractor and ownership pages control role attribution. Two immersed elements do not establish a completion percentage, replacement dates or final costs that the owner has not published.

Phase: construction. Evidence reviewed: 15 July 2026.

Project sources 10