Project record

London Gateway C2526 maintenance dredging

Aerial view of DP World London Gateway's container berths, berth pockets and Thames Estuary approach setting

DP World; London Gateway operating-port context, not evidence of C2526 mobilisation

London Gateway Port Limited selected Jan De Nul for maintenance dredging across parts of the Thames Estuary navigation route and the port's berth pockets. The latest award notice values the package at GBP 57 million excluding VAT and estimates a 6 January 2026 to 30 December 2027 period. The reviewed public chain stops at award and publishes no signed contract, mobilisation, assigned dredger, measured quantity, sediment route, post-dredge survey or accepted depth.

Project signal

Award in United Kingdom

Current status Jan De Nul is the selected supplier under a GBP 57 million award decision; the latest notice estimates a 6 January 2026 to 30 December 2027 contract period, while signature, mobilisation and physical production remain unconfirmed Source confidence Confirmed

Location

United Kingdom / Europe

Segment

Maintenance dredging and operating-port access

Status

Jan De Nul is the selected supplier under a GBP 57 million award decision; the latest notice estimates a 6 January 2026 to 30 December 2027 contract period, while signature, mobilisation and physical production remain unconfirmed / Confirmed

Last checked

3 August 2026

Coverage

Related sectors

Maintenance dredging and operating-port access is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
London Gateway Port Limited, the DP World port company and statutory harbour authority
Delivery parties
Jan De Nul nv - selected dredging supplier under the latest UK6 award notice, No lower-tier subcontractor, survey provider, disposal operator or support-vessel provider is identified in the reviewed public record
Contract route
Utilities competitive flexible procedure under the Procurement Act 2023. The tender allowed up to four suppliers into the tender stage and weighted commercial evaluation at 70% and technical quality at 30%. It estimated GBP 10 million excluding VAT for a 1 October 2025 to 2 March 2026 period, with a possible one-month extension. A 14 October award notice selected Jan De Nul at GBP 57 million for an estimated 3 November 2025 to 1 November 2027 period with a possible extension to November 2028. The 19 December notice retained the same supplier and value but labelled the result Contract 2 and revised the estimated period to 6 January 2026 through 30 December 2027. No UK7 contract-details notice was located in the reviewed procurement chain by 3 August 2026.
Execution window
The latest public award notice gives an estimated 6 January 2026 start and 30 December 2027 end. Those dates are not treated as proof of signature or field execution. Earlier notice dates remain procurement history: the original tender expected a six-month 2025-26 campaign, while the first award expected a November 2025 start and allowed extension into November 2028.
Works package
Maintain deep-draft access by dredging designated areas within the Yantlet, including Sea Reach and the manoeuvring area, the Sunk and Knock John Channel, and by removing high spots from berth pockets. London Gateway may also instruct dredging at Yantlet/West Oaze and Black Deep. The works include mobilisation and demobilisation of dredging equipment. The C2526 notices do not publish a bill quantity, target depth, dredging method, vessel, sediment classification, disposal or beneficial-use route, survey specification or acceptance criterion.
Marine interfaces
The works sit inside a live Thames Estuary navigation system serving an operating deep-water terminal. DP World currently lists four berths, 1,690 metres of quay, 16.5 metres chart-datum depth alongside and a tidal approach range of 14.5 to 21 metres, while Berths 5 and 6 are being developed separately. Dredging must therefore protect deep-draft access and berth availability without conflating this maintenance award with the separate quay and yard expansion packages.
Commercial evidence boundary
The latest GBP 57 million award value is 5.7 times the tender estimate, but the public notices also lengthen the period and the first award mentions possible maintenance and capital dredging. Without the priced scope, contract-details notice, instructed quantities, rate schedule, change record and final account, the difference is not evidence of overrun, final spend or a unit-rate benchmark. The same value in two award notices is one procurement result, not two contracts to be added together.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Latest award notice retained Jan De Nul and GBP 57 million

The second UK6 notice labels the result Contract 2 and estimates 6 January 2026 to 30 December 2027. It is an award decision, not a contract-details, mobilisation or completion notice.

Source

First award notice selected Jan De Nul

The first UK6 notice named the same supplier and value but estimated a 3 November 2025 to 1 November 2027 period with a possible extension to November 2028.

Source

London Gateway opened the C2526 competition

The tender established the named channel and berth-pocket workfronts, a GBP 10 million estimate, a short initial campaign window and a 70:30 commercial-to-technical evaluation split.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • UK7 contract-details notice or another project-specific signature record
  • Reason for the Contract 1 to Contract 2 award-notice sequence
  • Issued work orders and any capital-dredging option
  • Named dredger, support vessels and survey team
  • Ordered, measured and accepted dredging quantities
  • Target and post-dredge depths by channel reach and berth pocket
  • Sediment classification, marine licence and disposal or beneficial-use route
  • Hydrographic acceptance and navigation release
  • Named lower-tier subcontractors and suppliers
  • Certified payments, changes and final account

Reporting status

Award, confirmed confidence

Last checked 3 August 2026 across 6 cited sources. The dated timeline above carries the project events.

Last checked 3 August 2026 Cited sources 6