Dredging Award
London Gateway selects Jan De Nul for the GBP 57m C2526 package
DP World; London Gateway operating-terminal context, not evidence of C2526 mobilisation
London Gateway's latest UK6 publishes the 18 December 2025 decision selecting Jan De Nul for C2526 at GBP 57 million excluding VAT, GBP 68.4 million including VAT. It estimates a 6 January 2026 to 30 December 2027 period. Both compiled awards retain pending status and scheduled signature milestones; an actual signed-contract object and C2526 mobilisation, plant and production records remain unconfirmed.
December award decision and revised estimated period
The official complete history fixes the 18 December decision and 19 December publication, Jan De Nul, values, pending award objects and estimated periods. DP World infrastructure information supplies operating-port context. Signed terms and C2526 execution remain outstanding.
One procurement with two award notices
The July tender's GBP 10 million excluding-VAT estimate and six-month programme changed substantially at selection. October and December notices name the same supplier and value under one OCID while publishing different estimated periods. The priced scope and work instructions are needed to compare those programmes and understand the final commercial boundary.
Evidence conclusion
Selected supplier and outstanding executed scope
The UK6 decision establishes supplier selection for the advertised competition. Contract 1 and Contract 2 remain within ocds-h6vhtk-056674; their shared GBP 57 million value is one procurement result. The reason for the numbering sequence, executed scope and physical start remain unconfirmed. C2526 requires its own quantities, depths, sediment route, licences and hydrography. The separate 2023-24 NewWaves contract's 1.5 million m3, -14.50 mCD target and disposal assumptions retain their historical scope.
Outstanding evidence
- UK7 contract-details notice or project-specific signature confirmation
- Owner explanation for the two UK6 award notices
- Issued work order and final contract period
- Dredger and support-spread mobilisation
- Channel- and berth-specific ordered quantities and depths
- Sediment testing, licence and placement route
- Pre- and post-dredge hydrographic surveys
- Named downstream delivery parties
- Certified payments, changes and final account
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- C2526 Maintenance Dredging procurement record UK Find a Tender, Current procurement chain reviewed 3 August 2026
- C2526 contract award notice 084669-2025 UK Find a Tender, 19 December 2025
- C2526 contract award notice 065302-2025 UK Find a Tender, 14 October 2025
- C2526 tender notice 043208-2025 UK Find a Tender, 25 July 2025
- London Gateway infrastructure and terminal facts DP World, Current operating page reviewed 3 August 2026
- Complete official London Gateway C2526 maintenance dredging procurement history UK Find a Tender API, Complete procurement record checked 14 October 2026