Project record
Sangam Thathi Reddy via Dredging Today; historical operating context
Mumbai Port Authority is procuring one contract for three annual maintenance-dredging campaigns across approach channels, turning circles, outside berths, Indira Dock, bunder areas, anchorages, ferry and fish-jetty areas, and other live-port locations from 2026-27 through 2028-29.
India / Asia Pacific
Dredging
Tender E.47/2026 remains open; bids due 6 August 2026 after two corrigenda / Confirmed
21 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Mumbai Port's second due-date extension moves the E.47/2026 bid close from 23 July to 6 August at 15:00 India time. It changes the procurement calendar only; it does not disclose bidders, evaluate technical offers, open prices or award the contract.
Read controlling sourceE.47/2026 packages three annual campaigns at an estimated INR 281.70 crore. The opening establishes the scope and procurement route; later deadline extensions do not establish bidders, award, mobilisation, quantity or accepted depth.
Read controlling sourceMumbai Port's budget records INR 86.02 crore actual expenditure for 2024-25, INR 70 crore revised estimate for 2025-26, and INR 65 crore budget estimate for 2026-27. These are annual accounting figures and are not the E.47/2026 contract value or dredged quantity.
Read controlling sourceThe October 2024 register records a INR 216.40 crore item-rate contract with Van Oord India, scheduled from 19 January 2024 to 30 April 2026 and then described as work in progress. It is historical incumbent context, not evidence of an E.47/2026 bid or award.
Read controlling sourceThe SOP sets one-month permission, vessel-certificate, VTS, AIS, logbook, 15-day reporting, designated-ground, and unauthorized-dumping controls. It is a general compliance baseline and does not prove permission for the new contract.
Read controlling sourceThe historical register records a INR 91.87 crore Van Oord contract covering left-over 2017-18 work and the 2018-19 and 2019-20 cycles. This confirms recurring multi-cycle procurement history without carrying old prices, performance, or contractor identity into 2026.
Read controlling sourceDelivery watch
Track the 6 August bid close, any further corrigendum, technical qualification, disclosed bidders, financial opening, award, performance security, each annual notice to commence, TSHD nomination and 45-day mobilisation, pre-dredge surveys, DS1 permissions and vessel logs, fortnightly dredging reports, and accepted post-dredge surveys for all three cycles.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerThe live authority listing and CPPP status establish an open tender, not an award. The technical and financial bids define the INR 281.70 crore three-year estimate, INR 5.64 crore bid security, three 24-week annual cycles, 45-day TSHD mobilisation, minimum 9,000 cubic metres combined hopper capacity, assured-depth and in-situ payment split, supplementary near-wall plant, hydrographic acceptance, and DS1 route. The 2026-27 budget's INR 65 crore maintenance line is an annual accounting provision. The January 2024 SOP is a general permission and monitoring baseline, not project-specific permission. Registers show Van Oord on earlier E.47 packages, including E.47/2023 at INR 216.40 crore through 30 April 2026; those records and the lead photograph are history only and do not identify a bidder or contractor for E.47/2026.
Phase: tender. Evidence reviewed: 21 July 2026.