Location
India / Asia Pacific
Project record
Sangam Thathi Reddy via Dredging Today; historical operating context
Mumbai Port Authority is procuring one contract for three annual maintenance-dredging campaigns across approach channels, turning circles, outside berths, Indira Dock, bunder areas, anchorages, ferry and fish-jetty areas, and other live-port locations from 2026-27 through 2028-29.
India / Asia Pacific
Dredging
Tender E.47/2026 remains open; bids due 24 August 2026 under Corrigendum VI / Confirmed
16 August 2026
Coverage
Dredging is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogMumbai Port extended E.47/2026 bid submission to 24 August at 15:00 India time and scheduled technical-bid opening for 25 August at 15:00. The extension keeps the competition open and does not identify bidders, award the contract or start mobilisation.
SourceMumbai Port's second due-date extension moves the E.47/2026 bid close from 23 July to 6 August at 15:00 India time. It changes the procurement calendar only; it does not disclose bidders, evaluate technical offers, open prices or award the contract.
SourceE.47/2026 packages three annual campaigns at an estimated INR 281.70 crore. The opening establishes the scope and procurement route; later deadline extensions do not establish bidders, award, mobilisation, quantity or accepted depth.
SourceMumbai Port's budget records INR 86.02 crore actual expenditure for 2024-25, INR 70 crore revised estimate for 2025-26, and INR 65 crore budget estimate for 2026-27. These are annual accounting figures and are not the E.47/2026 contract value or dredged quantity.
SourceThe October 2024 register records a INR 216.40 crore item-rate contract with Van Oord India, scheduled from 19 January 2024 to 30 April 2026 and then described as work in progress. It is historical incumbent context, not evidence of an E.47/2026 bid or award.
SourceThe SOP sets one-month permission, vessel-certificate, VTS, AIS, logbook, 15-day reporting, designated-ground, and unauthorized-dumping controls. It is a general compliance baseline and does not prove permission for the new contract.
SourceThe historical register records a INR 91.87 crore Van Oord contract covering left-over 2017-18 work and the 2018-19 and 2019-20 cycles. This confirms recurring multi-cycle procurement history without carrying old prices, performance, or contractor identity into 2026.
SourceEvidence gap