USACE awarded the USD 2.852 million contract to American Construction on 24 September 2026; dredging is scheduled no sooner than 1 December and mobilisation remains unreported
Seattle District awarded contract W912DW26CA038 to American Construction Co., Inc. for USD 2,851,950 on 24 September 2026. The announced mechanical campaign covers up to 140,000 cubic yards from shoaled areas in the Duwamish Waterway turning basin, section A and section B between stations 242+00 and 275+56. USACE expects continuous clamshell dredging no sooner than 1 December, with material routed to the Elliott Bay open-water disposal site. The award and planned scope are public, but mobilisation, plant assignment, measured production, disposal receipts, post-dredge hydrography and acceptance remain unreported.
Navigation channel maintenance dredging is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, Seattle District
Delivery parties
American Construction Co., Inc.
Contract route
USACE awarded definitive contract W912DW26CA038, following solicitation W912DW26BA011, to American Construction Co., Inc. on 24 September 2026. SAM.gov reports a USD 2,851,950 base-and-options value, a total small-business set-aside, NAICS 237990 and PSC Y1KF. The public award notice does not disclose the bid count, line-item prices, option split, modification history or final account.
Execution window
The Seattle District release says dredging will begin no sooner than 1 December 2026, operate continuously 24 hours per day and conclude all in-water work no later than 1 March 2027. The earlier SAM.gov solicitation described a 1 December 2026 to 15 February 2027 dredging window. The later release controls the current public operating statement, but the difference requires contract-document or owner clarification.
Works package
Mechanical clamshell dredging of up to 140,000 cubic yards from shoaled areas of the federal turning basin, section A and section B between stations 242+00 and 275+56, followed by transport to and open-water placement at the Elliott Bay disposal site. The published map distinguishes base and option work areas but does not assign public quantities or prices to each line item.
Marine interfaces
The work combines clamshell excavation, barge loading and a transit from the Duwamish federal channel to the Elliott Bay open-water site while the channel remains open. USACE calls for 24/7 operations and asks fishing, crabbing and recreational users to keep boats and gear at least 300 feet from the channel and placement boundaries. Navigation separation, debris, water quality, tribal fishing coordination, salmonid and forage-fish restrictions, weather and disposal-site controls are therefore part of the delivery boundary.
Commercial evidence boundary
The USD 2,851,950 figure is the SAM.gov base-and-options value and the amount shown in the USACE DQM award register. This figure does not represent a certified final cost, paid quantity or unit-rate basis. The 140,000-cubic-yard figure is an upper planned quantity, and the public map's base-and-option labels should not be converted into exercised scope without the contract schedule or later USACE confirmation.
Contract and delivery chain
Work packages and named roles
Published scope, named parties and supporting evidence for each workstream.
Award
W912DW26CA038
Named party
American Construction Co., Inc.
Evidence status
Confirmed
Source position
SAM.gov and the USACE DQM register report a 24 September 2026 award with a USD 2,851,950 base-and-options value. Source
Dredging scope
Turning basin, section A and section B
Named party
American Construction Co., Inc.
Evidence status
Confirmed
Source position
Seattle District announces mechanical clamshell dredging of up to 140,000 cubic yards between the identified federal channel work areas. Source
Material placement
Elliott Bay open-water disposal site
Named party
USACE and campaign delivery parties
Evidence status
Confirmed
Source position
The release and map establish Elliott Bay as the planned route; no delivered loads or disposal receipts are yet published. Source
Field delivery and close-out
W912DW26CA038
Named party
U.S. Army Corps of Engineers, Seattle District and American Construction Co., Inc.
Evidence status
Not evidenced
Source position
The reviewed public chain does not establish mobilisation, assigned plant, measured production, disposal loads, post-dredge surveys, demobilisation, acceptance or final account.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Seattle District published the field and placement plan
The release connects the awarded contractor to an upper 140,000-cubic-yard clamshell scope, 24/7 operations and Elliott Bay placement while leaving actual mobilisation and production open.