Peru's SEACE adjudications dataset identifies Jan De Nul N.V. Sucursal del Peru as award recipient for maintenance dredging in Callao's access channel and inner roadstead, with a source-reported awarded amount of USD 59,694,989.93. APN announced physical works from 20 December 2025 to an estimated 7 February 2026 and a safe-depth objective of up to -16.50 m. APN later published Jan De Nul's post-dredging environmental report, revised 9 March 2026 and based on January monitoring, establishing that the campaign reached a post-dredging evidence stage without proving formal owner acceptance or final commercial closeout.
Project signal
Commissioning in Peru
Current statusAPN started the access-channel and inner-roadstead campaign on 20 December 2025; a Jan De Nul post-dredging environmental report covers January 2026 monitoring, while owner acceptance, as-built hydrography and final account remain unverifiedSource confidenceConfirmed
Location
Peru / Americas
Segment
Maintenance dredging and operating-port access
Status
APN started the access-channel and inner-roadstead campaign on 20 December 2025; a Jan De Nul post-dredging environmental report covers January 2026 monitoring, while owner acceptance, as-built hydrography and final account remain unverified / Confirmed
Last checked
5 August 2026
Coverage
Related sectors
Maintenance dredging and operating-port access is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Autoridad Portuaria Nacional under Peru's Ministry of Transport and Communications
Delivery parties
Jan De Nul N.V. Sucursal del Peru - SEACE award recipient and author of the published post-dredging environmental report, Hydrographic surveyor, disposal-site operator, environmental laboratories, marine support craft and other lower-tier providers - not identified in the cited public records
Contract route
The 2025 SEACE adjudications workbook classifies the specialized maintenance-dredging service as Contratado, names APN as buyer and Jan De Nul N.V. Sucursal del Peru as award recipient, and reports USD 59,694,989.93. The open-data row does not expose the executed instrument, variation history, payment certificates, taxes or final account.
Execution window
APN announced a 20 December 2025 start and an estimated 7 February 2026 finish without interrupting commercial vessel operations. The published post-dredging report records January 2026 monitoring and a 9 March 2026 document revision. These dates support a post-dredging phase but do not establish the owner's final completion certificate or commercial closeout.
Works package
The public package covers maintenance dredging in Callao's common port areas: the access channel and inner roadstead. APN's stated objective was to recover safe operating depths of up to -16.50 m. Public sources reviewed do not disclose the final measured volume, dredging limits by reach, over-dredge tolerance, vessel spread, disposal quantities, accepted depth surfaces or payment measurement.
Marine interfaces
The campaign interfaces with continuous commercial navigation, fisheries and mariculture activity, dredging and disposal controls, turbidity and water-quality monitoring, bathymetric survey, port traffic management and safe-depth release. PRODUCE recorded stakeholder concern and permanent environmental monitoring during works, making environmental closeout and transparent survey evidence material to acceptance.
Commercial evidence boundary
The USD 59.695 million SEACE awarded-item total is a procurement record, not a certified final account. Without the signed instrument and bill of quantities, it does not reveal the commercial split among dredging production, disposal, surveys, monitoring, standby, variation and support services.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
APN published the pre- and post-dredging environmental reports
The Jan De Nul report records January 2026 post-dredging monitoring and moves the evidence chain beyond award and mobilisation, while formal acceptance and final hydrography remain open.
Physical work was scheduled to begin at 19:00 in the access channel and inner roadstead, targeting safe depths up to -16.50 m and an estimated 7 February 2026 finish.
SEACE published the contracted dredging service record
The open dataset names Jan De Nul N.V. Sucursal del Peru as award recipient and reports USD 59,694,989.93 for the specialized maintenance-dredging service.