Australia's Department of Infrastructure is delivering Kingston Pier through separate work packages. Land and Marine Ocean Engineering has been engaged for the rock revetment, while a second tender covers about 4,700 cubic metres of channel dredging, pier repairs, strengthening and a new navigation aid. The May 2026 government update schedules the second package for the latter half of 2026 but does not record an award or physical start.
Project signal
Tender in Norfolk Island
Keep the revetment contract and the dredging-and-repair tender on separate commercial records. The revetment must precede channel deepening because the Department expects the deeper channel to change wave action at the western wall. The dredging package still depends on a tender outcome, construction baseline and environmental controls before delivery can be treated as active.
Current statusRock revetment contractor appointed; the separate channel-dredging and pier-repair package was released to tender on 14 May 2026Source confidenceConfirmed
Location
Norfolk Island / Global islands
Segment
Dredging and waterways
Status
Rock revetment contractor appointed; the separate channel-dredging and pier-repair package was released to tender on 14 May 2026 / Confirmed
Evidence reviewed
19 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
Australian Government Department of Infrastructure, Transport, Regional Development, Communications, Sport and the Arts
Delivery parties
Land and Marine Ocean Engineering: Kingston rock revetment repairs and extension, No dredging and pier-repair contractor identified in reviewed official sources
Contract route
Staged Australian Government procurement. The rock revetment tender has been finalised. A separate request for tender covers channel dredging and pier repair works, with the outcome to be announced after evaluation.
Execution window
Revetment works were scheduled in May 2026 to start within a month; dredging and pier repairs were anticipated for the second half of 2026. Mobilisation for either package is not confirmed.
Works package
Repair and extend the western rock revetment, deepen the navigation channel to about 3.2 m below mean sea level, widen the channel and turning area, dredge about 4,700 m3, screen material for archaeological artefacts, transport suitable material to Cascade Quarry for beneficial reuse, repair steel sheet piles, replace timber fenders, strengthen concrete and install a navigation aid
Marine interfaces
Open-ocean wave exposure, a live island cargo and passenger pier, shallow reef and marine-park waters, heritage-sensitive seabed, revetment-to-channel sequencing, pier structural limits, real-time water-quality monitoring and the road haul from dredging to Cascade Quarry
Commercial read
The named revetment contractor does not hold the dredging and pier-repair scope. The roughly 4,700 m3 quantity and 3.2 m design level define the planned marine works, not measured output or accepted depth. Environmental and planning approvals clear a route for delivery but do not prove contract award, mobilisation or completion.
Next milestone
Official award of the dredging and pier-repair package, followed by notice to proceed, pre-dredge hydrography, agreed water-quality thresholds and identifiable mobilisation
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Revetment contractor appointed and dredging tender released
Land and Marine Ocean Engineering was engaged for the revetment package, while dredging and pier repairs moved into a separate tender with no award recorded.
The controlled action received approval under the EPBC Act, establishing environmental conditions and water-quality monitoring obligations without advancing the procurement or works status.
Option 3A design and pier condition entered detailed development
The Department recorded archaeological test trenches, sheet-pile degradation and additional plume investigations as inputs to final design and approvals.
Official award of the dredging and pier-repair package, followed by notice to proceed, pre-dredge hydrography, agreed water-quality thresholds and identifiable mobilisation
Decision watchpoints
Award and executed scope for the dredging and pier-repair package
Notice to proceed and contractor mobilisation evidence
Pre-dredge bathymetry and agreed channel geometry
Plant selection for the confined, exposed channel and turning area
Revetment completion and handover before channel deepening
Pier sheet-pile, fender and concrete repair sequence
Archaeological screening and artefact protocol
Real-time water-quality trigger levels and response actions
Cascade Quarry transport, placement and beneficial-reuse records
Post-dredge survey, navigation-aid commissioning and access release
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed19 July 2026Sources in this record5
Source record
The Department's project page defines the channel, turning-area, pier and navigation-aid scope and records environmental approval on 7 April 2025. Its 14 May 2026 update names Land and Marine Ocean Engineering for the separate revetment works and says the dredging and pier-repair request for tender has been released. The Public Environment Report and earlier design record establish the heritage, plume, structural and material-reuse constraints. Calendar expectations are retained as plans until an accountable source confirms the relevant event.