Australia's Department of Infrastructure is delivering Kingston Pier through separate work packages. Land and Marine Ocean Engineering has been engaged for the rock revetment, while a second tender covers about 4,700 cubic metres of channel dredging, pier repairs, strengthening and a new navigation aid. The May 2026 government update schedules the second package for the latter half of 2026 but does not record an award or physical start.
Project signal
Tender in Norfolk Island
Current statusRock revetment contractor appointed; the separate channel-dredging and pier-repair package was released to tender on 14 May 2026Source confidenceConfirmed
Location
Norfolk Island / Global islands
Segment
Dredging and waterways
Status
Rock revetment contractor appointed; the separate channel-dredging and pier-repair package was released to tender on 14 May 2026 / Confirmed
Last checked
24 July 2026
Coverage
Related sectors
Dredging and waterways is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Australian Government Department of Infrastructure, Transport, Regional Development, Communications, Sport and the Arts
Delivery parties
Land and Marine Ocean Engineering: Kingston rock revetment repairs and extension, No dredging and pier-repair contractor identified in reviewed official sources
Contract route
Staged Australian Government procurement. The rock revetment tender has been finalised. A separate request for tender covers channel dredging and pier repair works, with the outcome to be announced after evaluation.
Execution window
Revetment works were scheduled in May 2026 to start within a month; dredging and pier repairs were anticipated for the second half of 2026. Mobilisation for either package is not confirmed.
Works package
Repair and extend the western rock revetment, deepen the navigation channel to about 3.2 m below mean sea level, widen the channel and turning area, dredge about 4,700 m3, screen material for archaeological artefacts, transport suitable material to Cascade Quarry for beneficial reuse, repair steel sheet piles, replace timber fenders, strengthen concrete and install a navigation aid
Marine interfaces
Open-ocean wave exposure, a live island cargo and passenger pier, shallow reef and marine-park waters, heritage-sensitive seabed, revetment-to-channel sequencing, pier structural limits, real-time water-quality monitoring and the road haul from dredging to Cascade Quarry
Commercial evidence boundary
The named revetment contractor does not hold the dredging and pier-repair scope. The roughly 4,700 m3 quantity and 3.2 m design level define the planned marine works, not measured output or accepted depth. Environmental and planning approvals clear a route for delivery but do not prove contract award, mobilisation or completion.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Revetment contractor appointed and dredging tender released
Land and Marine Ocean Engineering was engaged for the revetment package, while dredging and pier repairs moved into a separate tender with no award recorded.
The controlled action received approval under the EPBC Act, establishing environmental conditions and water-quality monitoring obligations without advancing the procurement or works status.
Option 3A design and pier condition entered detailed development
The Department recorded archaeological test trenches, sheet-pile degradation and additional plume investigations as inputs to final design and approvals.