Project record
The Port of Bellingham awarded Contract PW 23-10 to American Construction Co. Inc. after its USD 22,472,328.83 base bid ranked first of four. The wider USD 27.5 million modernization combines removal of about 22,000 cubic yards of contaminated sediment, deepening from about -26 to -35 feet MLLW, a new 140-foot steel-pile-supported heavy-lift wharf, South Terminal repairs, stormwater treatment and shore-power-enabling utilities. Washington Labor & Industries now exposes 37 intent filings, 35 affidavit filings and 30 unique named downstream companies across first-, second- and third-tier relationships. Those filings make the commercial chain unusually visible, but they do not by themselves prove each party's performed scope, owner acceptance or final account.
United States / Americas
Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities
Port reporting confirms key dock and stormwater upgrades were completed in 2025 and navigation and environmental work advanced; Washington L&I records American Construction's contractor-reported 8 April 2026 work-completed date, but no filed Notice of Completion, owner acceptance, final hydrographic survey, final dredged quantity or final account is evidenced / Confirmed
12 August 2026
Coverage
Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe filing records a USD 25,966,774.06 contractor amount and 8 April work-completed date, while leaving owner acceptance and final account unconfirmed.
SourceThe Port says key dock and stormwater upgrades were completed while environmental cleanup and navigation improvements advanced; it does not publish full PW 23-10 acceptance.
SourceThe release establishes the active modernization workfront, scope, grant and baseline completion expectation without replacing later closeout evidence.
SourceThe Port selected American Construction after its USD 22,472,328.83 bid ranked first of four, establishing the prime commercial baseline for PW 23-10.
SourceEvidence gap