Project record

Boskalis SEAWAY 31,000 m³ TSHD

Aerial view of Boskalis SEAWAY, a 31,000 m³ trailing suction hopper dredger, manoeuvring during sea trials before its July 2026 handover

Royal IHC

Boskalis ordered the 31,000 m³ trailing suction hopper dredger SEAWAY from Royal IHC in October 2023 and launched the vessel at Krimpen aan den IJssel on 3 October 2025. Boskalis still described construction as ongoing in its 5 March 2026 results. Royal IHC then reported that SEAWAY was handed over to Boskalis on 20 July 2026 after a successful sea trial, closing the public shipbuilding and delivery sequence. A first project, operating fuel and measured dredging, discharge, fuel, emissions and reliability results have not been published.

Project signal

Completed in Netherlands

Current status Delivered 20 July 2026; deployment unpublished Source confidence Confirmed

Location

Netherlands / Europe

Segment

Dredging

Status

Delivered 20 July 2026; deployment unpublished / Confirmed

Last checked

14 August 2026

Coverage

Related sectors

Dredging is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Boskalis
Delivery parties
Royal IHC
Contract route
Contractor-funded custom fleet investment. Royal IHC and Boskalis signed a letter of intent on 5 June 2023 after a co-design and engineering phase, and Boskalis announced the construction contract on 27 October 2023. Boskalis' 2025 results report EUR 564 million of group property, plant, and equipment investment and EUR 237 million of year-end capital commitments relating predominantly to completion of SEAWAY, Windpiper, and four Smit Lamnalco vessels; those aggregate figures do not disclose a SEAWAY contract value.
Execution window
The 2023 owner and shipyard releases expected delivery or service entry in mid-2026. SEAWAY was named and launched on 3 October 2025, remained under construction in Boskalis' 5 March 2026 results and was handed over on 20 July 2026 after what Royal IHC describes as a successful sea trial. The delivery announcement does not publish the trial programme, class or flag particulars, first commercial mobilisation or first project.
Works package
One 178-metre-long, 38-metre-wide TSHD with a 31,000 m³ hopper, two trailing suction pipes with underwater pumps, two discharge pumps with a combined 15,000 kW, full diesel-electric installation, Azipods propulsion, an optimised hull, and advanced automation. Boskalis says the dual-fuel main engines, methanol plant, and storage tanks prepare the vessel to use biodiesel or methanol as alternatives to conventional fuel. The sources do not prove which fuel will be used at entry into service or publish achieved fuel, emissions, production, or discharge performance.
Marine interfaces
The vessel is designed for high-volume dredging, long sailing distances and long-distance pump-ashore discharge to reclamation sites. The 20 July handover confirms delivery to Boskalis after sea trial, but project readiness still depends on crew deployment, project-specific equipment configuration, bunkering and fuel selection, mobilisation and the operating limits required by the first assignment.
Commercial evidence boundary
Royal IHC delivered SEAWAY within the mid-2026 period stated at order and launch. The unresolved commercial questions are its first deployment, supported material and discharge envelope, operating-fuel baseline, utilisation and whether measured productivity and emissions support the design claims.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

SEAWAY delivered to Boskalis

The shipyard's dated delivery record closes the construction and handover sequence. The record omits the first project, operating fuel and measured production and environmental performance.

Source

Boskalis still reported SEAWAY under construction

The owner identified SEAWAY as one of its largest 2025 investments and said year-end capital commitments related predominantly to its completion and other named fleet investments. This is a current construction and capital-completion signal, not delivery or service entry.

Source

SEAWAY was christened and launched at Royal IHC

The physical launch closed the hull-launch gate and exposed the named vessel, but Royal IHC explicitly placed final outfitting and extensive testing afterward and retained a future mid-2026 service-entry expectation.

Source

Boskalis converted the design phase into a construction contract

The owner confirmed Royal IHC, a 31,000 m³ hopper, the dredging and discharge arrangement, propulsion and fuel-preparation concept, build location, and intended mid-2026 service entry. The announcement did not disclose contract value or acceptance terms.

Source

Royal IHC and Boskalis signed the construction letter of intent

The letter of intent followed joint design and engineering and established the intended 31,000 m³ custom-build route at Krimpen aan den IJssel. It preceded the later construction contract and was not itself delivery evidence.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • First named overseas deployment and mobilisation date
  • Boskalis fleet listing, classification and flag particulars
  • Published scope and results of dredging and discharge trials
  • Operating fuel, methanol bunkering pathway, and emissions baseline
  • Representative production, pump-ashore, sailing-cycle, reliability, and utilisation evidence

Reporting status

Completed, confirmed confidence

Last checked 14 August 2026 across 5 cited sources. The dated timeline above carries the project events.

Last checked 14 August 2026 Cited sources 5

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 5