Project record
Fox Island River Small Craft Harbour has two separately awarded marine packages in the current evidence chain. Marine Contractors Inc received the 2023 entrance-improvement contract for excavation or dredging and a rubble-mound breakwater or groyne. R.J.G Construction Limited then received a distinct 2024 channel re-dredging contract. Published contract dates have elapsed, while physical completion and acceptance remain unverified.
Canada / North America
Small-craft-harbour entrance dredging and breakwater works
Marine Contractors' CAD 1.499m entrance-improvement contract and R.J.G Construction's separate CAD 1.133m channel re-dredging contract have both reached their published administrative end dates, but no completion certificate, accepted hydrography, final dredged quantity or causal link between the packages is public / Confirmed
9 August 2026
Coverage
Small-craft-harbour entrance dredging and breakwater works is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe new marginal-wharf and wall proposal is a distinct pre-procurement workfront and does not evidence completion or defects on either earlier contract.
SourceThe CanadaBuys period ended on 23 April 2025 at CAD 1,133,000 without a published completion certificate or accepted hydrography.
SourceContract 4500077474 established a new CAD 1.133 million delivery package rather than an amendment to Marine Contractors' entrance works.
SourceA CAD 14,375 reduction brought CW2330925 to CAD 1,499,255 while physical completion, accepted quantities, owner handover and the final account remained unreported.
SourceMarine Contractors became the confirmed prime for the excavation or dredging and rubble-mound package, while lower tiers and acceptance evidence remained undisclosed.
SourceEvidence gap