Zeevonk has awarded DEME the foundation transport and installation package for the 1,062.6 MW wind component of its first permitted phase. The contract covers intermediate monopile transport, marshalling of primary and secondary steel, transport and installation of 69 monopile foundations, and placement of a filter layer for scour protection. The owner plans phase 1 for 2029, but has not published the marshalling port, fabrication split, installation vessel or offshore start date.
Project signal
Award in Netherlands
Current statusDEME holds the transport and installation contract for 69 monopile foundations; offshore mobilisation has not been announcedSource confidenceConfirmed
Location
Netherlands / Europe
Segment
Offshore wind foundations
Status
DEME holds the transport and installation contract for 69 monopile foundations; offshore mobilisation has not been announced / Confirmed
Last checked
20 July 2026
Coverage
Related sectors
Offshore wind foundations is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Zeevonk Phase 1 C.V., a Vattenfall and Copenhagen Infrastructure Partners project
Delivery parties
DEME - intermediate monopile transport, marshalling services, transport and installation of 69 monopile foundations, and filter-layer placement, TKF - separate supply contract for approximately 162 km of 66 kV inter-array cable, Fugro - geotechnical and geophysical investigation partner identified by Vattenfall
Contract route
Zeevonk awarded DEME a substantial transport and installation contract for the phase 1 foundations. DEME uses 'substantial' as a value category but did not disclose the price. Zeevonk separately awarded TKF the design, manufacture, testing and delivery of the 66 kV inter-array cables; that announcement does not name the cable installation contractor.
Execution window
The amended permit defines phase 1 as 1,062.6 MW of wind capacity plus 6 MWp of offshore solar. Vattenfall schedules this phase for completion in 2029. Phase 2 adds 1,001 MW of wind, 50 MWp of offshore solar and 500 MW of system-integration capacity, with owner delivery planned for 2032. The DEME release does not publish foundation fabrication, marshalling, mobilisation or offshore installation dates.
Works package
Intermediate transport of monopiles, marshalling services for primary and secondary steel, transport and installation of 69 monopile foundations, and installation of a filter layer for scour protection. The package sits within the 1,062.6 MW wind component of phase 1, located 63 to 84 km off Bergen aan Zee. It does not, on the published evidence, include monopile fabrication, turbine installation, inter-array cable installation, the TenneT platform, offshore solar or the onshore hydrogen facilities.
Marine interfaces
The foundation sequence must join fabrication delivery, a still-unannounced marshalling base, intermediate transport, offshore lifting and piling, secondary-steel handling and filter-layer placement. Site investigations found strong currents, large sand formations and artificial seabed obstacles; Vattenfall also planned a 2026 unexploded-ordnance survey. The 69 turbine positions then need to connect through approximately 162 km of 66 kV inter-array cable to the TenneT offshore substation.
Commercial evidence boundary
The core foundation installation opportunity is no longer open at owner level. Remaining visible interfaces include fabrication and port logistics disclosures, vessel and feeder strategy, survey and UXO work, noise and ecological controls, cable installation, remaining scour-protection layers, as-built survey and acceptance. No source reviewed for this record publishes package value, installation productivity, port allocation or subcontract awards.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
DEME won the 69-foundation transport and installation package
The award fixes the principal offshore foundation contractor and includes marshalling, intermediate transport and filter-layer placement. Port, vessel, fabrication and mobilisation details remain unpublished.
TKF received the phase 1 inter-array cable supply contract
The separate award covers about 162 km of 66 kV cable and accessories. It establishes the cable supply chain but does not identify the offshore installer.
The amended permit separated Zeevonk into two licensed phases
The permit assigns phase 1 and phase 2 to separate Zeevonk entities and fixes their capacities at 1,062.6 MW plus 6 MWp offshore solar, and 1,001 MW plus 50 MWp offshore solar and 500 MW system integration, respectively.