Offshore Foundations
Zeevonk has named the installer for its first 69 foundations
DEME Group; image published with the Zeevonk foundation-installation contract release
DEME will transport and install the 69 monopile foundations for Zeevonk's first 1 GW phase. Its contract also covers steel marshalling, intermediate monopile transport and a filter layer for scour protection. The owner still has to disclose the port, vessel spread and offshore start.
What changed
DEME's 20 July 2026 release confirms intermediate monopile transport, marshalling of primary and secondary steel, transport and installation of 69 monopile foundations, and a filter layer for scour protection. Vattenfall's project page places phase 1 at 1 GW with delivery planned for 2029. The separate TKF award covers cable design, manufacture, testing and delivery, not installation. RVO confirms the permit holder and amended permit status. The foundation marshalling port, installation vessel, fabricators, offshore start and acceptance regime remain unpublished.
Why it matters
The award ties four jobs into one installation chain: receive the steel, marshal it, move the monopiles offshore and put the foundations and filter layer in place. That makes the eventual port and vessel plan more than a logistics footnote. It will determine how 69 very large components move from fabrication yards into a North Sea installation campaign scheduled to support 2029 delivery.
Decision read
What remains open
This is a contract award, not evidence of offshore progress. DEME has the foundation installation scope, but the release does not assign a vessel or name a marshalling base. The cable picture is also incomplete: TKF will supply about 162 km of 66 kV inter-array cable, while the installer remains unnamed. Fabrication allocation, port selection, vessel mobilisation and the first foundation will mark the move from contract award to offshore campaign.
Next watchpoints
- Foundation fabrication and secondary-steel awards
- Marshalling port and delivery sequence
- Installation vessel and feeder strategy
- UXO survey and clearance
- Underwater-noise and ecological controls
- First monopile and filter-layer installation
- Inter-array cable installation contractor
- As-built and acceptance evidence
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Sources used 6
- DEME awarded contract for foundation installation at Zeevonk DEME Group, 20 July 2026
- Zeevonk foundation installation contract release DEME Group, 20 July 2026
- Zeevonk offshore energy park overview Vattenfall Nederland, Current page reviewed 20 July 2026
- Zeevonk phase 1 inter-array cable award to TKF Vattenfall, 11 May 2026
- IJmuiden Ver Alpha and Beta wind-farm permits Netherlands Enterprise Agency (RVO), Current page reviewed 20 July 2026
- Zeevonk seabed investigation Vattenfall Nederland, Current page reviewed 20 July 2026
Corrections and methodology
Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.
Review methodology Open intelligence archive Submit a correction