Location
Republic of the Congo / Africa
Project record
Congo Terminal; exact East Mole construction progress published 6 July 2026
Congo Terminal is extending its existing Pointe-Noire container concession with a separate 750-metre East Mole quay, a deepened berth line and an electrically operated terminal platform. CRBC is the confirmed construction contractor and Ingerop is the named engineering consultant for dredging, navigation, wave and reclamation studies. By July 2026 the owner reported 400 metres of quay delivered, all 558 steel piles driven and active dredging adapted to bituminous sands.
Republic of the Congo / Africa
Deep-water ports, dredging and multipurpose terminals
Congo Terminal reported 400 metres of the planned 750-metre quay complete by 6 July 2026 after all 558 steel piles were driven; dredging and electric-terminal integration remain active toward the 2027 delivery target / Confirmed
1 August 2026
Coverage
Deep-water ports, dredging and multipurpose terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogCongo Terminal identified five electric STS cranes, 15 eRTGs and 30 electric tractors for a 2.5 million TEU configuration without naming the equipment suppliers or confirming commissioning.
SourceThe owner placed the live works beyond pile mobilisation but short of the full 750-metre quay and terminal handover.
SourceCompletion of the marine foundation programme removed a major structural gate while deck, dredging and terminal integration continued.
SourceThe financing supported a EUR 361 million works programme and strengthened delivery visibility beyond the initial CRBC award.
SourceEvidence gap