Bidding has closed on the New Haven Harbor improvement contract. The work deepens the main channel, manoeuvring area and turning basin from 35 to 40 feet MLLW, widens the entrance and inner channel, and routes nearly 4.5 million cubic yards of material among open-water and local beneficial-use sites. PIEE posted amendment 0007 on 16 July and held the bid close at 17 July 2026.
Project signal
Tender in United States
Treat the package as closed for bids, not awarded. PIEE update 0007 fixes the 17 July response deadline. USACE's launch release and Industry Day material define the channel geometry and material system. No public source reviewed by 19 July identifies an apparent low bidder, contract value, contractor, notice to proceed, accepted baseline quantity or mobilisation.
Current statusIFB amendment 0007 posted 16 July 2026; bids closed 17 July; no award or notice to proceed postedSource confidenceConfirmed
Location
United States / Americas
Segment
Dredging and waterways
Status
IFB amendment 0007 posted 16 July 2026; bids closed 17 July; no award or notice to proceed posted / Confirmed
Evidence reviewed
19 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
U.S. Army Corps of Engineers, New England District, with Connecticut Port Authority as non-federal sponsor
Delivery parties
No contractor identified in the reviewed post-close procurement record
Contract route
Unrestricted invitation for bids through PIEE; set-aside code N/A; seven posted updates through 16 July 2026
Execution window
USACE expects construction from fall 2026 through spring 2028. The Industry Day record describes seasonal environmental windows, but award, notice to proceed and the contractor's accepted programme remain unpublished.
Works package
Deepen the channel, manoeuvring area and turning basin from -35 to -40 feet MLLW; widen the entrance channel from 500 to 600 feet, the inner main channel from 400 to 500 feet and the bend near the East Breakwater from 560 to 800 feet; lengthen the turning basin; remove ordinary material and rock; transport material by scow to defined placement and beneficial-use sites
Marine interfaces
Mechanical dredging and scow transport in Connecticut's busiest port, hard-rock removal, shallow access to local placement sites, Cross Sound Cable coordination, active terminal traffic, seasonal environmental windows and multibeam acceptance surveys
Commercial read
Bidding closed after seven solicitation updates, but PIEE has not published a bid abstract or award. The nearly 4.5 million-cubic-yard programme figure describes the wider improvement effort; it is not a measured contract quantity, paid quantity or completion result.
Next milestone
Public bid abstract or apparent low bidder, responsibility determination, contract award and value, followed by notice to proceed, final pre-dredge survey and identifiable plant mobilisation
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The amended IFB closed for bids
PIEE update 0007 retained the 17 July response deadline. The procurement moved into post-bid review without a public bidder, award, contract value or notice to proceed.
Industry Day exposed the delivery and placement constraints
USACE set out the channel geometry, seasonal windows, material classes, placement routes, rock and survey requirements while retaining quantity change risk after maintenance dredging.
Public bid abstract or apparent low bidder, responsibility determination, contract award and value, followed by notice to proceed, final pre-dredge survey and identifiable plant mobilisation
Decision watchpoints
Bid abstract and apparent low bidder
Responsibility determination, award value and named contractor
Notice to proceed and accepted seasonal programme
Final pre-dredge hydrography and contract quantities
Mechanical dredge, scows, rock plant and actual mobilisation
Cross Sound Cable coordination and blasting controls
Material acceptance at the two borrow pits, shellfish site, rock reef and CLDS
Production by acceptance section and environmental window
Multibeam surveys, grade acceptance and operating release
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed19 July 2026Sources in this record5
Source record
PIEE Notice W912WJ26BA012 controls the current procurement state: IFB, update 0007 posted 16 July 2026, response deadline 17 July at 13:00 EDT, and no public award. The April USACE release confirms the project partnership and the nearly 4.5 million-cubic-yard programme, including shellfish habitat, borrow-pit and rock-reef reuse. The Industry Day page defines channel widening, material character and placement routes but warns that its quantities were subject to change after the 2025-26 maintenance campaign. The long-standing navigation page and final feasibility report provide asset and design context, not current construction evidence.