Project record

New Haven Harbor improvement dredging

Aerial view across New Haven Harbor's commercial waterfront and federal navigation channel

U.S. Army Corps of Engineers, New England District archive aerial; location context, not 2026 dredging

USACE opened four bids for the New Haven Harbor improvement contract. Great Lakes Dredge & Dock submitted the lowest total at USD 69,469,200, compared with the USD 63,642,050.63 government estimate. The package deepens the main channel, manoeuvring area and turning basin from 35 to 40 feet MLLW and routes nearly 4.5 million cubic yards among open-water and local beneficial-use sites.

Project signal

Evaluation in United States

Current status Bid abstract posted 20 July 2026; four bids opened and Great Lakes submitted the lowest total at USD 69.469 million; no award or notice to proceed posted Source confidence Confirmed

Location

United States / Americas

Segment

Dredging and waterways

Status

Bid abstract posted 20 July 2026; four bids opened and Great Lakes submitted the lowest total at USD 69.469 million; no award or notice to proceed posted / Confirmed

Last checked

26 July 2026

Coverage

Related sectors

Dredging and waterways is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
U.S. Army Corps of Engineers, New England District, with Connecticut Port Authority as non-federal sponsor
Delivery parties
No awarded contractor; Great Lakes Dredge & Dock Company, LLC submitted the lowest total bid
Contract route
Unrestricted invitation for bids through SAM.gov and PIEE; four bids opened 17 July 2026; official bid abstract posted 20 July
Execution window
USACE expects construction from fall 2026 through spring 2028. The Industry Day record describes seasonal environmental windows, but award, notice to proceed and the contractor's accepted programme remain unpublished.
Works package
Deepen the channel, manoeuvring area and turning basin from -35 to -40 feet MLLW; widen the entrance channel from 500 to 600 feet, the inner main channel from 400 to 500 feet and the bend near the East Breakwater from 560 to 800 feet; lengthen the turning basin; remove ordinary material and rock; transport material by scow to defined placement and beneficial-use sites
Marine interfaces
Mechanical dredging and scow transport in Connecticut's busiest port, hard-rock removal, shallow access to local placement sites, Cross Sound Cable coordination, active terminal traffic, seasonal environmental windows and multibeam acceptance surveys
Commercial evidence boundary
The lowest submitted total, USD 69,469,200 from Great Lakes, is USD 5,827,149.37 or 9.2% above the USD 63,642,050.63 government estimate. Curtin submitted USD 83,951,953.28, Cashman USD 97,276,500 and Dutra USD 97,417,700. These are bid totals, not evaluated award values. The nearly 4.5 million-cubic-yard programme figure is also not a measured contract quantity, paid quantity or completion result.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

USACE published four opened bids

The official abstract records Great Lakes at the lowest submitted total of USD 69,469,200 against a USD 63,642,050.63 government estimate. The result moves the package into evaluation but does not identify an awarded contractor or accepted contract value.

Source

The amended IFB closed for bids

Amendment 0007 retained the 17 July response deadline. The procurement moved into post-bid review without an award, accepted contract value or notice to proceed.

Source

USACE and Connecticut executed the project partnership

The construction phase was formally launched and the owner set a fall 2026 to spring 2028 expectation, without naming a works contractor.

Source

Industry Day exposed the delivery and placement constraints

USACE set out the channel geometry, seasonal windows, material classes, placement routes, rock and survey requirements while retaining quantity change risk after maintenance dredging.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Responsibility determination, award value and named contractor
  • Notice to proceed and accepted seasonal programme
  • Final pre-dredge hydrography and contract quantities
  • Mechanical dredge, scows, rock plant and actual mobilisation
  • Cross Sound Cable coordination and blasting controls
  • Material acceptance at the two borrow pits, shellfish site, rock reef and CLDS
  • Production by acceptance section and environmental window
  • Multibeam surveys, grade acceptance and operating release

Reporting status

Evaluation, confirmed confidence

Last checked 26 July 2026 across 5 cited sources. The dated timeline above carries the project events.