ABP names GEOXYZ UK for the first geophysical and shallow-subsurface survey supporting Future Port Talbot. The phased scope uses broad reconnaissance to refine the later investigation area and cable corridor.
Offshore energy is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Associated British Ports
Procurement references
ABP-FPT-2601; ocds-h6vhtk-06ada5
Delivery parties
GEOXYZ UK: named survey supplier in the intended-award notice.
Contract route
Procurement references: ABP-FPT-2601; ocds-h6vhtk-06ada5. Official intended-award notice names GEOXYZ UK at GBP 832,236 excluding VAT. The published award and contract status fields remain pending, with a scheduled signature date of 26 October 2026.
Execution window
Notice contract window 30 October 2026-26 February 2027. Phase 1 expected November-December 2026; optional Phase 2 during 2027.
Works package
Approximately 60km2 reconnaissance with high-resolution bathymetry, side-scan sonar and shallow sub-bottom profiling below 10m beneath the seabed. Optional later survey refines the area and cable corridor with seismic work to about 30m below seabed.
Marine interfaces
The broad first-phase area lies about 10-15km offshore in water 25-35m below LAT. Interpretation is intended to focus subsequent survey lines and corridor development; magnetometer results identify follow-up targets.
Commercial evidence boundary
Firm first-phase acquisition and optional deeper work require different line plans and vessel time. The decision to exercise the option depends on route selection and remaining investigation questions after reconnaissance.
Evidence gap
What remains unverified
Outstanding evidence
Actual contract signature and phase-one mobilisation record
Usable survey coverage and interpretation across route alternatives
Optional 2027 corridor, deeper lines and UXO follow-up requirements