Location
Greece / Europe
Project record
HEDNO signed the EUR 6.82 million turnkey contract with Paralos on 11 February 2026 for two 3 MVA OPS positions and one 0.5 MVA position. TED names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors; mobilisation, installation, energisation, vessel connection and acceptance remain unconfirmed
HEDNO signed an 18-month turnkey contract for three onshore-power-supply systems at Igoumenitsa Port. The official release defines two 3 MVA positions and one 0.5 MVA position for Ro-Pax vessels, covering design, supply, installation, testing and commissioning. TED reports a EUR 6,820,000 contract to Paralos Systems Industry and names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors without publishing their workshare or subcontract values. Igoumenitsa Port Authority coordinates the wider CEF-backed ALFION-INFRA programme, while HEDNO is the client for this electrical package. The programme's 31 December 2026 end date and the contract's 18-month delivery period do not form one reconciled public completion baseline.
Greece / Europe
Commercial-port shore power and electrical utility integration
Award / Confirmed
16 August 2026
Coverage
Commercial-port shore power and electrical utility integration is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe contractor confirms design, procurement, installation and commissioning for the same two 3 MVA and one 0.5 MVA configuration, without adding field-progress evidence.
SourceThe result fixes the EUR 6.82 million value, prime identity, three named subcontractors and 18-month duration, while leaving party workshare and delivery milestones undisclosed.
SourceContract conclusion moves the package beyond tender into an 18-month delivery obligation, but does not itself prove mobilisation or energisation.
SourceThe tender notice records the open procedure, turnkey scope and EUR 7.14 million estimate that preceded the February 2026 award.
SourceEvidence gap