Project record

Igoumenitsa Port three-berth OPS shore-power systems

Aerial view of Igoumenitsa Port showing the ferry berths, terminal aprons and Ro-Pax vessels

Igoumenitsa Port Authority; exact operating-port context image, not evidence of OPS installation progress

HEDNO signed an 18-month turnkey contract for three onshore-power-supply systems at Igoumenitsa Port. The official release defines two 3 MVA positions and one 0.5 MVA position for Ro-Pax vessels, covering design, supply, installation, testing and commissioning. TED reports a EUR 6,820,000 contract to Paralos Systems Industry and names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors without publishing their workshare or subcontract values. Igoumenitsa Port Authority coordinates the wider CEF-backed ALFION-INFRA programme, while HEDNO is the client for this electrical package. The programme's 31 December 2026 end date and the contract's 18-month delivery period do not form one reconciled public completion baseline.

Project signal

Award in Greece

Current status HEDNO signed the EUR 6.82 million turnkey contract with Paralos on 11 February 2026 for two 3 MVA OPS positions and one 0.5 MVA position. TED names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors; mobilisation, installation, energisation, vessel connection and acceptance remain unconfirmed Source confidence Confirmed

Location

Greece / Europe

Segment

Commercial-port shore power and electrical utility integration

Status

HEDNO signed the EUR 6.82 million turnkey contract with Paralos on 11 February 2026 for two 3 MVA OPS positions and one 0.5 MVA position. TED names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors; mobilisation, installation, energisation, vessel connection and acceptance remain unconfirmed / Confirmed

Last checked

16 August 2026

Coverage

Related sectors

Commercial-port shore power and electrical utility integration is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Hellenic Electricity Distribution Network Operator S.A. (HEDNO), within the Igoumenitsa Port Authority-coordinated ALFION-INFRA programme
Delivery parties
Paralos Systems Industry / Paralos S.A. - prime turnkey contractor; TED identifier EL-800712539, Paralos Energy - named subcontractor; project-specific scope and value not published, Controls Vasiloglou - named subcontractor; project-specific scope and value not published, Siemens A.G. - named subcontractor; project-specific scope and value not published
Contract route
HEDNO open procedure 5124163, also referenced by TED contract identifier 51241631. TED notice 352742-2025 opened the procurement and result notice 104641-2026 records contract conclusion on 11 February 2026, EUR 6.82 million total value, an earlier EUR 7.14 million estimate, an 18-month duration and the named prime and subcontractors.
Execution window
HEDNO's 12 February 2026 release says the three systems will be delivered within the following 18 months, implying a contract window extending into 2027 if measured from signature. ALFION-INFRA's published programme period ends on 31 December 2026, while Igoumenitsa Port Authority separately describes infrastructure completion by 2026. No official record reconciles those dates or publishes an accepted baseline programme, site-possession date or phased commissioning sequence.
Works package
Design, supply, install, test and commission three turnkey OPS/Cold Ironing systems for passenger and cargo ferry operations: two positions rated at 3 MVA and one at 0.5 MVA. The systems are intended to let berthed Ro-Pax vessels shut down auxiliary engines and draw electricity from the distribution network. ALFION-INFRA separately includes an energy-management system and studies and tender documentation for one additional cruise-vessel OPS position; that study position is not presented as a fourth installed system under this contract.
Marine interfaces
The package joins HEDNO's distribution network to three live ferry berths through shore-side switchgear, protection, earthing, transformers or conversion equipment, cable management and vessel interfaces. Ro-Pax calls, apron traffic, salt exposure, berth access, electrical shutdowns, harbour safety and vessel compatibility all affect delivery. Under FuelEU Maritime, in-scope passenger ships must use OPS from 2030 in ports covered by Article 9 of AFIR and from 2035 in any port that develops OPS, subject to stated exceptions. The European Commission separately identifies berth-equipment availability, grid stability and ship-shore compatibility, so installed equipment, available power, a compatible vessel connection and accepted service are distinct milestones. The cited project records do not identify berth numbers, cable-management OEM, frequency-conversion arrangement, civil routes, planned outage windows, first compatible vessels or which calls fall within the AFIR denominator.
Commercial evidence boundary
TED reports EUR 6.82 million for the executed contract against a EUR 7.14 million procedure estimate. Igoumenitsa Port Authority reports EUR 8.925 million for the wider ALFION-INFRA programme, funded 85% through CEF grant 101122898. These are different cost bases. Subcontract values, payment milestones, package allocation, variations, forecast final cost and final account remain unpublished in the cited record.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Turnkey OPS prime contract

HEDNO procedure 5124163 / TED contract 51241631

Named party
Paralos Systems Industry / Paralos S.A.
Status
Confirmed
Source position
TED result 104641-2026 records EUR 6.82 million and contract conclusion on 11 February 2026; HEDNO confirms the signed turnkey contract. Source
Named subcontract chain

Subcontracted elements within the three-system OPS contract

Named party
Paralos Energy; Controls Vasiloglou; Siemens A.G.
Status
Confirmed
Source position
The TED result names all three as subcontractors but publishes no workshare, scope, percentage or value for any of them. Source
Installed system configuration

Two 3 MVA positions and one 0.5 MVA position for Ro-Pax vessels

Named party
HEDNO, Igoumenitsa Port Authority and awarded delivery chain
Status
Confirmed
Source position
HEDNO's signed-contract release defines the three ratings and full design-to-commissioning scope. Source
Installation, commissioning and operation

Mobilisation, energisation, vessel connection, acceptance and measured performance

Named party
HEDNO, port operator and awarded delivery chain
Status
Not evidenced
Source position
No cited official record confirms site mobilisation, installed equipment, an energised berth, a connected vessel, accepted testing or commercial operation.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Paralos confirms the Igoumenitsa turnkey award

The contractor confirms design, procurement, installation and commissioning for the same two 3 MVA and one 0.5 MVA configuration, without adding field-progress evidence.

Source

TED publishes the contract result and subcontract chain

The result fixes the EUR 6.82 million value, prime identity, three named subcontractors and 18-month duration, while leaving party workshare and delivery milestones undisclosed.

Source

HEDNO concludes the three-system OPS contract

Contract conclusion moves the package beyond tender into an 18-month delivery obligation, but does not itself prove mobilisation or energisation.

Source

TED opens the European procurement record

The tender notice records the open procedure, turnkey scope and EUR 7.14 million estimate that preceded the February 2026 award.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Accepted contract programme versus the 31 December 2026 CEF programme end date
  • Berth numbers and the allocation of the two 3 MVA and one 0.5 MVA systems
  • Project-specific scopes and values for Paralos Energy, Controls Vasiloglou and Siemens
  • Cable-management, transformer, converter, switchgear and protection suppliers
  • Civil routes, electrical rooms, grid works and planned outages
  • Equipment manufacture, site mobilisation and installation progress
  • Earthing, protection, load, frequency and vessel-interoperability testing
  • First connected Ro-Pax vessel and operational handover
  • Acceptance, availability, measured emissions effect, variations and final account

Reporting status

Award, confirmed confidence

Last checked 16 August 2026 across 10 cited sources. The dated timeline above carries the project events.

Last checked 16 August 2026 Cited sources 10

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 10