Shore-power contract chain

Igoumenitsa OPS award names a prime and three subcontractors

Published 9 August 2026 Updated 16 August 2026 Publisher IMWO Region Europe Confidence Confirmed
Paralos control room capability image with multiple monitoring screens and electrical systems interfaces

Paralos Systems; control and energy-system capability context, not evidence of Igoumenitsa OPS installation progress

TED result 104641-2026 records a EUR 6.82 million Igoumenitsa shore-power contract to Paralos Systems Industry and names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors. HEDNO confirms two 3 MVA systems and one 0.5 MVA system under an 18-month design-to-commissioning package. The award identifies the chain but not each party's workshare, while the 18-month contract window extends beyond the published 31 December 2026 ALFION-INFRA programme end date.

A signed EUR 6.82m contract replaces the tender estimate

TED reports the result value, conclusion date, prime legal identifier, named subcontractors and duration. HEDNO states the installed ratings and turnkey scope. Programme pages provide the grant boundary and broader dates; Paralos identifies itself as prime contractor. Participation records do not disclose subcontract workshare or field progress.

The award identifies parties below prime-contract level

TED identifies Paralos Systems Industry as prime and names Paralos Energy, Controls Vasiloglou and Siemens A.G. as subcontractors. It does not allocate switchgear, protection, controls, cable management, civil works or commissioning among them, and no subcontract value is published. The named chain is therefore more specific than the workshare evidence.

Evidence conclusion

The 18-month contract window extends beyond the CEF programme date

HEDNO concluded the turnkey contract on 11 February 2026. TED reports EUR 6.82 million against the EUR 7.14 million procedure estimate and an 18-month duration. HEDNO defines two 3 MVA and one 0.5 MVA positions for Ro-Pax vessels; ALFION-INFRA separately includes a cruise-position study, so the latter should not be counted as a fourth installed system. Igoumenitsa Port Authority publishes EUR 8.925 million for the wider 85%-CEF-funded programme and describes completion by 2026, while the programme page ends on 31 December 2026. Those broader values and dates do not override the executed contract. Until an accepted baseline or phased handover plan appears, the defensible status is signed award, not installed or operational shore power.

Outstanding evidence

  • Accepted baseline and reconciliation of 2026 programme and 18-month contract dates
  • Subcontract workshare and values for Paralos Energy, Controls Vasiloglou and Siemens
  • Berth allocation and vessel-interface standards
  • Cable-management, transformer, conversion, switchgear and protection packages
  • Grid, civil-route and electrical-room mobilisation
  • Factory acceptance and on-site commissioning tests
  • First Ro-Pax connection and phased operational handover
  • Final acceptance, availability, variations and final account