Location
Norway / Europe
Project record
Repstad Anlegg began works in August 2025; demolition, dredging and subsea blasting preceded a 99-pile quay-foundation programme scheduled from March to July 2026
Port of Oslo awarded Repstad Anlegg an approximately NOK 250 million design-build contract to replace and extend Kneppeskjaer East. The owner describes a continuous 284-metre quay front, two ship ramps and at least 12.5 metres of depth, while the contractor uses a rounded 300-metre description. Demolition, dredging and subsea blasting moved into a 99-steel-pile foundation stage in 2026. Multiconsult and Norconsult hold distinct environmental-control roles.
Oslo Havn; exact Kneppeskjaer East foundation-work update published in February 2026
Norway / Europe
Multipurpose quays, dredging and carbon-logistics infrastructure
Construction / Confirmed
1 August 2026
Coverage
Multipurpose quays, dredging and carbon-logistics infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogOslo Port placed the project after demolition, dredging and underwater blasting but before concrete quay completion and handover.
SourceOslo Port identified both environmental advisers and the monitoring measures governing demolition, dredging, noise, turbidity and contaminated sediment.
SourceThe approximately NOK 250 million award placed demolition, dredging, blasting, concrete and quay works under one main contractor.
SourceEvidence gap