Project record

Oslo Kneppeskjaer East quay replacement and expansion

Foundation barge working alongside the existing Kneppeskjaer East quay in Oslo during the 2026 pile programme

Oslo Havn; exact Kneppeskjaer East foundation-work update published in February 2026

Port of Oslo awarded Repstad Anlegg an approximately NOK 250 million design-build contract to replace and extend Kneppeskjaer East. The owner describes a continuous 284-metre quay front, two ship ramps and at least 12.5 metres of depth, while the contractor uses a rounded 300-metre description. Demolition, dredging and subsea blasting moved into a 99-steel-pile foundation stage in 2026. Multiconsult and Norconsult hold distinct environmental-control roles.

Project signal

Construction in Norway

Current status Repstad Anlegg began works in August 2025; demolition, dredging and subsea blasting preceded a 99-pile quay-foundation programme scheduled from March to July 2026 Source confidence Confirmed

Location

Norway / Europe

Segment

Multipurpose quays, dredging and carbon-logistics infrastructure

Status

Repstad Anlegg began works in August 2025; demolition, dredging and subsea blasting preceded a 99-pile quay-foundation programme scheduled from March to July 2026 / Confirmed

Last checked

1 August 2026

Coverage

Related sectors

Multipurpose quays, dredging and carbon-logistics infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Oslo Havn KF, the Port of Oslo municipal port authority
Delivery parties
Repstad Anlegg AS - design-build main contractor for demolition, subsea blasting, dredging, concrete works and quay construction, Multiconsult - independent ecological and chemical monitoring and control before, during and after the works for the port authority, Norconsult - environmental adviser to Repstad for turbidity, noise, pollution and biodiversity planning and control, No reviewed primary source names downstream piling, dredging, blasting, concrete or marine-plant subcontractors
Contract route
Oslo Port awarded a design-build contract to Repstad Anlegg, an Endur subsidiary, in June 2025 for approximately NOK 250 million. The main contractor integrates demolition, seabed work, structures and quay delivery while environmental control is split between the owner's independent adviser and the contractor's adviser.
Execution window
Repstad mobilised in late July and early August 2025 for an approximately 20-month programme. Oslo Port reported foundation work beginning in March 2026 after demolition, dredging and subsea blasting, with the 99-pile driving programme targeted for completion in week 29 of 2026.
Works package
Demolish and replace the northern quay, extend the southern quay, create a continuous quay front stated as 284 metres by the owner and 300 metres by the contractor, install two ship ramps, deepen the basin to at least 12.5 metres and complete associated concrete and marine works. The quay is intended to support general cargo and future liquid-CO2 logistics.
Marine interfaces
Dredging and underwater blasting establish the basin and foundation workfront before 99 steel tubular piles, concrete deck works and ship ramps can be completed. Turbidity, underwater noise, contaminated sediment and biodiversity controls form explicit release conditions throughout the sequence.
Commercial evidence boundary
The top-tier contract, value and environmental roles are unusually clear. The downstream plant and subcontract chain is not public. The owner has published a construction-stage transition into piling but no as-built depths, accepted dredging quantities, final pile completion or quay handover.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

The quay moved into its 99-pile foundation stage

Oslo Port placed the project after demolition, dredging and underwater blasting but before concrete quay completion and handover.

Source

Repstad mobilised under active environmental controls

Oslo Port identified both environmental advisers and the monitoring measures governing demolition, dredging, noise, turbidity and contaminated sediment.

Source

Repstad received the design-build contract

The approximately NOK 250 million award placed demolition, dredging, blasting, concrete and quay works under one main contractor.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Completion of 99 steel tubular piles
  • Owner 284-metre versus contractor 300-metre geometry
  • Post-dredge bathymetry and minimum 12.5-metre depth
  • Concrete deck and two ship-ramp completion
  • Turbidity, noise and contaminated-sediment compliance
  • Downstream marine-plant and subcontract allocation
  • Quay handover and liquid-CO2 logistics readiness

Reporting status

Construction, confirmed confidence

Last checked 1 August 2026 across 6 cited sources. The dated timeline above carries the project events.

Last checked 1 August 2026 Cited sources 6