Port Delivery

Kneppeskjaer moves from seabed works into 99 piles

Published 1 August 2026 Publisher IMWO Region Europe Confidence Confirmed
Aerial view of Oslo's Kneppeskjaer East quay with the project work area outlined

Oslo Havn; exact Kneppeskjaer East work-area image used for the 2025 mobilisation notice

Oslo Port reported that demolition, dredging and underwater blasting at Kneppeskjaer East had progressed into a 99-steel-pile foundation programme in March 2026. Repstad Anlegg holds the approximately NOK 250 million design-build contract, with independent and contractor environmental-control roles split between Multiconsult and Norconsult.

The workfront has shifted from basin preparation to quay foundations

Oslo Port controls the geometry, mobilisation, environmental roles and foundation-stage update. Endur controls the award value and Repstad scope. Repstad's official capability page corroborates marine-work capability but does not identify downstream parties on this project.

Foundation mobilisation leaves handover gates open

The transition exposes the actual acceptance sequence: seabed preparation, pile completion, concrete deck and ship ramps, post-dredge hydrography, environmental close-out and owner handover. It also resolves who controls design-build delivery and who monitors environmental compliance.

Evidence conclusion

Geometry and downstream packages remain open

Repstad's main contract is confirmed, but downstream piling, dredging, blasting and concrete subcontractors are not public. The owner's 284-metre quay length and contractor's rounded 300-metre description remain intentionally unreconciled. No source yet proves final depth, accepted quantities or completion of all 99 piles.

Outstanding evidence

  • Completion of the 99-pile programme
  • 284-metre versus 300-metre quay geometry
  • Post-dredge bathymetry to at least 12.5 metres
  • Concrete deck and two ship ramps
  • Environmental monitoring close-out
  • Owner handover and CO2-logistics readiness