Bullo holds the signed GBP 392,500 excluding-VAT contract; July and August navigation windows are historical, with the post-term instruction and accepted output unconfirmed
Bristol City Council signed Bullo Limited on 24 March 2026 for GBP 392,500 excluding VAT, GBP 471,000 including VAT, to remove silt within and adjacent to the Floating Harbour. The original period was 30 March to 26 June. Notices 35/26 and 36/26, consulted in August, scheduled western Baltic Wharf windows on 27-31 July and 10-17 August with a floating pipeline and Bullo call sign. They are absent from the current October listing and remain historical schedule references. The contractual basis for later work, actual production, accepted quantity and depth, payment and handover remain unconfirmed.
IMWO artist's impression of the published Bristol Floating Harbour 2026 maintenance dredging scope
United Kingdom / Europe
Maintenance dredging, floating-harbour navigation and marina access
Award / Confirmed
14 October 2026
Coverage
Maintenance dredging, floating-harbour navigation and marina access is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe current listing was checked on 14 October and no longer contains 35/26 or 36/26. This records source availability, not the date work stopped, a contract extension or completed dredging.
SourceNotice 36/26 schedules about seven days at western Baltic Wharf through 17 August, identifies the floating pipeline and Bullo call sign, but does not publish the contractual basis or prove that the scheduled move has occurred.
SourceNotice 35/26 scheduled a five-day western Baltic Wharf period after the 26 June contract end. It remains a navigation notice rather than a contract variation or completion record.
SourceFind a Tender fixes Bullo Limited, GBP 392,500 excluding VAT, limited competition and an original 30 March-26 June term.
SourceEvidence gap